MONTHYEARML24206A1062024-07-30030 July 2024 2024 Brunswick Requal Inspection Corporate Notification Letter ML24066A0132024-03-0505 March 2024 Bru 2024-002 Radiation Safety Baseline Inspection Information Request IR 05000324/20230062024-02-28028 February 2024 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2023006 and 05000325/2023006 IR 05000324/20244032024-02-14014 February 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perm Inspection 05000325/2024403; 05000324/2024403 IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2022006 and 05000325/2022006 ML22307A1762022-11-0707 November 2022 Notification of an NRC Fire Protection Team Inspection (FPTI) IR 05000324/20220052022-08-24024 August 2022 Updated Inspection Plan for Brunswick Steam Electric Plant (Report 05000324/2022005 and 05000325/2022005) ML22192A0862022-07-12012 July 2022 RQ Inspection Notification Letter IR 05000324/20224032022-05-0909 May 2022 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000325/2022403; 05000324/2022403 IR 05000324/20210062022-03-0202 March 2022 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 (Reports No. 05000324/2021006 and 05000325/2021006) IR 05000324/20210052021-08-26026 August 2021 Updated Inspection Plan for Brunswick Steam Electric Plant (Report 05000324/2021005 and 05000325/2021005) ML21113A0762021-04-23023 April 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000324/20200062021-03-0303 March 2021 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Reports 05000325/2020006 and 05000324/2020006 ML20310A3342020-11-0505 November 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000324/20200052020-08-24024 August 2020 Updated Inspection Plan for Brunswick Steam Electric Plant Units 1 and 2, NRC Inspection Report 05000325/2020005 and 05000324/2020005 ML20198M5742020-07-16016 July 2020 Requalification Program Inspection - Brunswick Steam Electric Plant IR 05000324/20190062020-03-0303 March 2020 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Reports 05000325/2019006 and 05000324/2019006 ML19296A7712019-10-23023 October 2019 Notification of an NRC Fire Protection Team Inspection - NRC Inspection Report 05000324/2020010 and 05000325/2020010) and Request for Information IR 05000324/20180062019-03-0404 March 2019 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2018006 and 05000324/2018006 ML18352B0192018-12-18018 December 2018 U2 ISI 2019001 RFI Notification IR 05000324/20180052018-08-23023 August 2018 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2, NRC Report 05000325/2018005 and 05000324/2018005 IR 05000324/20170062018-02-28028 February 2018 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Reports 05000325/2017006 and 05000324/2017006, 05000325/2017402 and 05000324/2017402, 05000325/2017501 and 05000324/2017501 ML18026A6242018-01-25025 January 2018 U1 ISI 2018001 RFI Bcc IR 05000324/20170052017-08-28028 August 2017 Updated Inspection Plan NRC Inspection Report 05000325/2017005 and 05000324/2017005 ML17153A0712017-06-0101 June 2017 Notification of Inspection and Request for Information ML17115A4742017-04-17017 April 2017 Emergency Preparedness Inspection and Request for Information IR 05000324/20160062017-03-0101 March 2017 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 & 2 - NRC Inspection Report 05000325/2016006 and 05000324/2016006 ML17021A0032017-01-20020 January 2017 Notification of Inspection and Request for Information IR 05000324/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2016005 and 05000324/2016005 ML16027A1652016-01-27027 January 2016 Notification of Inspection and Request for Information IR 05000324/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2015005 and 05000324/2015005 ML15085A1392015-03-26026 March 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000324/20140012015-03-0404 March 2015 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2014001 and 05000324/2014001 IR 05000324/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Brunswick, Units 1 & 2, Inspection Report 05000325/2014006 and 05000324/2014006 IR 05000324/20130012014-03-0404 March 2014 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2013001 and 05000324/2013001 ML13254A0402013-09-10010 September 2013 Notification of Inspection and Request for Information ML13246A0592013-09-0303 September 2013 Mid Cycle Assessment Letter ML13123A3252013-05-0101 May 2013 Emergency Preparedness Inspection and Request for Information ML13080A3912013-03-21021 March 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000324/20120012013-03-0404 March 2013 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 & 2, (IR 05000325-12-001 and 05000324-12-001,) on 02/13/2013, ML12304A0702012-10-30030 October 2012 Requalification Program Inspection ML12248A1812012-09-0404 September 2012 Mid Cycle Assessment Letter Brunswuck 2012 ML1206504102012-03-0505 March 2012 EOC Report 22 ML1124401522011-09-0101 September 2011 Report 22 Inspection/Activity Plan ML1106304362011-03-0404 March 2011 EOC Report 22, Inspection/Activity Plan, 03/01/2011 - 06/30/2012 ML1006210132010-03-0303 March 2010 ISFSI Report 22 - 2010-001 ML1006210102010-03-0303 March 2010 Report 22 - 2010001 ML0924405252009-09-0101 September 2009 Report 22, Inspection/Activity Plan 09/01/2009 - 12/31/2010 2024-07-30
[Table view] Category:Letter
MONTHYEARIR 05000324/20240032024-11-13013 November 2024 Integrated Inspection Report 05000324/2024003 and 05000325/2024003 IR 05000324/20253012024-10-17017 October 2024 Notification of Licensed Operator Initial Examination 05000325/2025301 and 05000324/2025301 IR 05000324/20244012024-10-15015 October 2024 Security Baseline Inspection Report 05000324/2024401 and 05000325/2024401 ML24297A6262024-10-11011 October 2024 PCA Letter to NRC Brunswick Potential Tropical Storm Eight IR 05000324/20240102024-09-10010 September 2024 Focused Engineering Inspection Commercial Grade Dedication Report 05000324-2024010 and 05000325-2024010 ML24218A0862024-09-0909 September 2024 NRC to NMFS, Designation of Duke Energy Progress LLC as the Non-Federal Representative for Brunswick Steam Electric Plant, Units 1 and 2 ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24242A0322024-08-29029 August 2024 Submittal of Updated Final Safety Analysis Report (UFSAR) Revision 29, 10 CFR 54.37 Update, Technical Requirements Manuals, Technical Specification Bases, 10 CFR 50.59 and 10 CFR 72.48 Evaluation Summaries, and Commitment Change IR 05000324/20240052024-08-23023 August 2024 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2024005 and 05000325/2024005) IR 05000324/20240022024-08-0505 August 2024 Integrated Inspection Report 05000324/2024002 and 05000325/2024002 and 07200006/2024001 ML24206A1062024-07-30030 July 2024 2024 Brunswick Requal Inspection Corporate Notification Letter ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000324/20244202024-07-0202 July 2024 – Security Baseline Inspection Report 05000324/2024420 and 05000325/2024420 ML24108A0702024-06-0505 June 2024 – Issuance of License Amendments to Revise the 10 CFR 50.69 Categorization Process to Reflect an Alternative Seismic Approach IR 05000324/20244022024-05-17017 May 2024 Plan Material Control and Accounting Program Inspection Report 05000324/2024402 and 05000325/2024402 - Cover Letter IR 05000324/20240012024-05-0909 May 2024 Integrated Inspection Report 05000324/2024001 and 05000325/2024001 05000325/LER-2024-001, Primary Containment Penetration Local Leak Rate Testing Failure2024-04-10010 April 2024 Primary Containment Penetration Local Leak Rate Testing Failure 05000325/LER-2024-002, Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization2024-04-10010 April 2024 Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization ML24066A0132024-03-0505 March 2024 Bru 2024-002 Radiation Safety Baseline Inspection Information Request ML24026A0982024-03-0101 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0057 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000324/20230062024-02-28028 February 2024 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2023006 and 05000325/2023006 IR 05000324/20244032024-02-14014 February 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perm Inspection 05000325/2024403; 05000324/2024403 ML24032A1392024-02-12012 February 2024 Correction of Errors within Authorized Alternative Request RA-22-0308 IR 05000324/20230042024-02-0606 February 2024 Integrated Inspection Report 05000324/2023004 and 05000325/2023004 IR 05000324/20230112023-12-26026 December 2023 NRC Fire Protection Team Inspection - FPTI Report 05000324/2023011 and 05000325/2023011 IR 05000324/20234022023-12-14014 December 2023 Security Baseline Inspection Report 05000324-2023402 and 05000325-2023402 ML23297A0262023-11-27027 November 2023 – Proposed Alternatives to ASME Code Section XI Subsection IWE Requirements for Torus Metallic Liner Inspections ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230032023-11-0101 November 2023 Integrated Inspection Report 05000324/2023003 and 05000325/2023003 IR 05000324/20230102023-10-17017 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000324/2023010 and 05000325/2023010 IR 05000325/20234012023-10-16016 October 2023 Security Baseline Inspection Report 05000324 and 05000325 2023401 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20230022023-08-0404 August 2023 Integrated Inspection Report 05000324/2023002 and 05000325/2023002 ML23201A2042023-07-28028 July 2023 Summary of Regulatory Audit in Support of Alternative Request RA-22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20243012023-07-25025 July 2023 – Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 05000324/LER-2023-001, Two Main Steam Line Safety Relief Valves Inoperable2023-07-17017 July 2023 Two Main Steam Line Safety Relief Valves Inoperable 05000325/LER-2023-001, Loss of Redundant Power Supply Operation Causes Turbine Trip and Subsequent Reactor Scram2023-06-15015 June 2023 Loss of Redundant Power Supply Operation Causes Turbine Trip and Subsequent Reactor Scram ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML23146A0012023-05-24024 May 2023 EN 56538 - Engine Systems Inc and Brunswick ML23130A3902023-05-12012 May 2023 – Regulatory Audit Plan in Support of Alternative Request RA 22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000324 2023001 and 05000325 2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2022006 and 05000325/2022006 IR 05000324/20220042023-02-0808 February 2023 Integrated Inspection Report 05000324/2022004 and 05000325/2022004 IR 05000324/20223012023-02-0303 February 2023 NRC Operator License Examination Report 05000325/2022301 and 05000324/2022301 IR 05000324/20224022022-11-23023 November 2022 Security Baseline Inspection Report 05000324 2022402 and 05000325 2022402 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 May 1, 2013 Mr. Michael J. Annacone Vice President Brunswick Steam Electric Plant P.O. Box 10429 Southport, NC 28461-0429
SUBJECT:
BRUNSWICK STEAM ELECTRIC PLANT - EMERGENCY PREPAREDNESS INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Annacone:
From August 19-23, 2013, the U.S. Nuclear Regulatory Commission (NRC) will perform a baseline Emergency Preparedness inspection at the Brunswick Steam Electric Plant. The inspection will evaluate activities in the Emergency Preparedness cornerstone using NRC Inspection Procedures 71114.02 - Alert and Notification System (ANS) Evaluation, 71114.03 - Emergency Response Organization (ERO) Staffing and Augmentation System, 71114.05 - Maintenance of Emergency Preparedness, and the Emergency Preparedness Sections of 71151, Performance Indicator Verification.
Experience has shown that this inspection is resource-intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Tom Sherrill of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Mark E. Speck at (404) 997-4759 (Mark.Speck@nrc.gov) or the Chief, Plant Support Branch 1, Brian Bonser at (404) 997-4653.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, under control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system
M. Annacone 2 (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Brian Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket No.: 50-325, 50-324 License No.: DPR-71, DPR-62
Enclosure:
Pre-Inspection Document Request List cc: (See page 3)
ML13123A325 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE /RA by B. /RA/
Bonser for/
NAME SPECK BONSER DATE 5/1/2013 5/1/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO M. Annacone 3 cc:
Plant General Manager Randy C. Ivey Brunswick Steam Electric Plant Manager, Nuclear Oversight Progress Energy Brunswick Steam Electric Plant Electronic Mail Distribution Progress Energy Carolinas, Inc.
Electronic Mail Distribution Edward L. Wills, Jr.
Director Site Operations Paul E. Dubrouillet Brunswick Steam Electric Plant Manager, Training Electronic Mail Distribution Brunswick Steam Electric Plant Electronic Mail Distribution J. W. (Bill) Pitesa Senior Vice President Joseph W. Donahue Nuclear Operations Vice President Duke Energy Corporation Nuclear Oversight Electronic Mail Distribution Progress Energy Electronic Mail Distribution John A. Krakuszeski Plant Manager Senior Resident Inspector Brunswick Steam Electric Plant U.S. Nuclear Regulatory Commission Electronic Mail Distribution Brunswick Steam Electric Plant U.S. NRC Lara S. Nichols 8470 River Road, SE Deputy General Counsel Southport, NC 28461 Duke Energy Corporation Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge M. Christopher Nolan 2300 N. Street, NW Director - Regulatory Affairs Washington, DC 20037-1128 General Office Duke Energy Corporation Peggy Force Electronic Mail Distribution Assistant Attorney General State of North Carolina Michael J. Annacone P.O. Box 629 Vice President Raleigh, NC 27602 Brunswick Steam Electric Plant Electronic Mail Distribution Chairman North Carolina Utilities Commission Annette H. Pope Electronic Mail Distribution Manager-Organizational Effectiveness Brunswick Steam Electric Plant Robert P. Gruber Electronic Mail Distribution Executive Director Public Staff - NCUC Lee Grzeck 4326 Mail Service Center Regulatory Affairs Manager Raleigh, NC 27699-4326 Brunswick Steam Electric Plant Progress Energy Carolinas, Inc. (cc contd - See page 4)
Electronic Mail Distribution
M. Annacone 4 (cc contd)
Anthony Marzano Director Brunswick County Emergency Services Electronic Mail Distribution Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 W. Lee Cox, III Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Warren Lee Emergency Management Director New Hanover County Department of Emergency Management 230 Government Center Drive Suite 115 Wilmington, NC 28403
Pre-Inspection Document Request List Inspection Dates: August 19-23, 2013 Inspection Procedures: IP 71114.02 Alert and Notification System Evaluation IP 71114.03 ERO Staffing and Augmentation System IP 71114.05 Maintenance of Emergency Preparedness IP 71151 Performance Indicator Verification Note: This is a list of the documents to be provided to the inspectors upon arrival onsite. The current version of these documents is expected unless specified otherwise. Electronic media is preferred, if readily available (the preferred file format is Word or searchable .pdf files on CDROM or thumb drive). Please organize the information as it is arranged below (e.g. a folder labeled Miscellaneous). It is not the intent that large or burdensome data be scanned for this purpose. This data will be inspected using original documentation. Material can be provided prior to the inspection to the U.S. Nuclear Regulatory Commission (NRC) Region II Office (Attention: Mark Speck, 245 Peachtree Center Avenue, NE, Suite 1200, Atlanta, GA 30303-1257). If there are questions regarding the documents requested, please do not hesitate to contact the lead inspector.
EP2 Alert and Notification System (ANS) Evaluation Department of Homeland Security (DHS) approved Alert Notification System (ANS) report Alert Notification System Testing Procedure ANS equipment technical manual ANS equipment testing results (raw data) for two year inspection period ANS equipment maintenance records for two year inspection period Changes to the ANS system, implementing procedures, testing procedures and the maintenance program including any supporting DHS approval letters for the past 2 years Corrective action program entries related to the Alert and Notification System for the two year inspection period Information provided to the public inside the 10 mile plume exposure pathway EP3 Emergency Response Organization (ERO) Staffing and Augmentation System Current ERO roster ERO and Augmentation implementing procedures and changes made over the past 2 years NUREG 0654 Table B1 site equivalent ERO training program procedure EP staff training program and qualification records ERO augmentation ERF activation, including backup, equipment initiation procedure ERO augmentation testing results Corrective action program entries related to the ERO staffing and augmentation for the two year inspection period EP5 Maintenance of Emergency Preparedness Governing documents for the assessment process All EP program assessments, not including INPO performed assessments, for the two year inspection period 10 CFR 50.54(t) audits and subsequent state/local correspondence for the two year inspection period Drill and exercise critiques for the past two year period Enclosure
2 Critiques of actual events resulting in implementation of the emergency plan for past two years Corrective action program entries relating to emergency preparedness (abbreviated, i.e.
identifier and brief description), for the two year inspection period with the risk significant related entries separated Governing documents for 10 CFR 50.54(q) evaluation process Corrective Action Program procedures Maintenance records and availability-tracking information for equipment important to emergency preparedness EP01/EP02/EP03 Performance Indicators (PI) Verification Governing document for the performance indicator process Drill and Exercise Performance (DEP), Emergency Response Organization (ERO), and Alert and Notification System (ANS) PI data submitted for the two year inspection period DEP documentation and evaluations for the two year inspection period Current ERO roster Corrective action program entries related to performance indicators, that is DEP, ERO training and participation, and ANS for the two year inspection period Miscellaneous Procedures Current Emergency Plan Safety Evaluation Report approved Emergency Plan Current Emergency Action Levels Safety Evaluation Report approved Emergency Action Levels Current Emergency Plan implementing procedures Departmental processes or procedures for Emergency Preparedness staff Corporate processes or procedures for Emergency Preparedness staff Lead Inspector Contact Information:
Mark Speck (404) 997-4759 Mark.Speck@nrc.gov