ML20078B673

From kanterella
Revision as of 04:03, 25 April 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Requests 30-day Extension to Respond to NRC 830815 Ltr Re Violations Noted in IE Insp Rept 50-461/83-09
ML20078B673
Person / Time
Site: Clinton Constellation icon.png
Issue date: 09/16/1983
From: Hall D
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20078B651 List:
References
0981-L, 981-L, NUDOCS 8309270192
Download: ML20078B673 (1)


Text

. . .

.J 0981-L ILLIN0/S POWER 00MPANY U-10094 CLINTON POWER STATION. P.O. BOX 678, CLINTON. ILLINOIS 61727 September 16, 1983 Docket No. 50-461 Mr. James G. Keppler Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Subject:

Response to Notice of Violation dated August 15, 1983; NRC IE Inspection Report 83-09

Dear Mr. Keppler:

Illinois Power Company is evaluating the two issues addressed in the Notice of Violation dated August 15, 1983. In order to complete a proper review of these issues, Illinois Power requests a thirty-day extension to provide a corporate response. Illinois Power regrets the administrative delay in requesting this extension.

Your consideration of this matter would be appreciated.

. Sincerely yours, I

i . . Hall l Vice President RDW/j f cc: W. S. Little (Chief Engineering Branch 2, Region III)

Director, Office of I&E, Washington, D.C. 20555 Illinois Department of Nuclear Safety NRC Resident Office 8309270192 830923 PDR ADOCK 05000461 SEP 21 t983 G PDR

, - . . .--.. - _-, . _ - -__ .-__. .-, - --_. .,..,,,- ,.-._ - . . - _ - . . - - . - ...- - ,- -