MONTHYEARML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure IR 05000269/20243012024-09-23023 September 2024 NRC Operator License Examination Report 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) ML24220A1092024-08-0808 August 2024 – Operator Licensing Examination Approval 05000269/2024301, 05000270/2024301, and 05000287/2024301 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000269/20240102024-08-0101 August 2024 Focused Engineering Inspection - Age-Related Degradation Report 05000269/2024010 and 05000270/2024010 and 05000287/2024010 IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24088A3052024-03-25025 March 2024 Fws to NRC, Agreement with Nlaa Determination for Tricolored Bat for Oconee Lr IR 05000269/20230062024-02-28028 February 2024 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 - (NRC Inspection Report 05000269/2023006, 05000270/2023006, and 05000287/2023006) ML24045A3062024-02-16016 February 2024 Ltr. to Michell Hicks, Principal Chief Eastern Band of Cherokee Re Oconee Nuclear Station Units 1,2, and 3 Section 106 ML24045A2962024-02-16016 February 2024 Ltr. to David Hill Principal Chief Muscogee Creek Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2972024-02-16016 February 2024 Ltr. to Dexter Sharp Chief Piedmont American Indian Assoc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3012024-02-16016 February 2024 Ltr. to Harold Hatcher Chief the Waccamaw Indian People Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3052024-02-16016 February 2024 Ltr. to Louis Chavis Chief Beaver Creek Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3042024-02-16016 February 2024 Ltr. to Lisa M. Collins Chief the Wassamasaw Tribe of Varnertown Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3022024-02-16016 February 2024 Ltr. to Joe Bunch United Keetoowah Band of Cherokee Indians in Ok Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3032024-02-16016 February 2024 Ltr. to John Creel Chief Edisto Natchez-Kusso Tribe of Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24030A0052024-02-16016 February 2024 Ltr. to Brian Harris, Chief, Catawba Indian Nation; Re., Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2952024-02-16016 February 2024 Ltr. to Chuck Hoskin, Jr, Principal Chief Cherokee Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2942024-02-16016 February 2024 Ltr. to Carolyn Chavis Bolton Chief Pee Dee Indian Nation of Upper Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2992024-02-16016 February 2024 Ltr. to Eric Pratt Chief the Santee Indian Organization Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3082024-02-16016 February 2024 Ltr. to Ralph Oxendine Chief Sumter Tribe of Cheraw Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3072024-02-16016 February 2024 Ltr. to Pete Parr Chief Pee Dee Indian Tribe Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24011A1482024-02-13013 February 2024 Letter to Steven M. Snider-Oconee Nuclear Sta, Unites 1,2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants ML24011A1532024-02-13013 February 2024 Letter to Tracy Watson EPA-Oconee Nuclear Sta, Unites 1, 2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants IR 05000269/20230042024-02-13013 February 2024 Integrated Inspection Report 05000269/2023004, 05000270/2023004, and 05000287/2023004; and Inspection Report 07200040/2023001 ML24019A1442024-02-13013 February 2024 Letter to Reid Nelson, Executive Director, Achp; Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24030A5212024-02-13013 February 2024 Letter to Elizabeth Johnson, Director, SHPO; Re Oconee Nuclear Stations Units 1, 2, and 3 Section 106 ML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staffs Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 2024-09-23
[Table view] Category:Inspection Plan
MONTHYEARML24257A0212024-09-11011 September 2024 Document Request for Oconee Nuclear Station - Radiation Protection Inspection - Inspection Report 2024-04 IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) IR 05000269/20230062024-02-28028 February 2024 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 - (NRC Inspection Report 05000269/2023006, 05000270/2023006, and 05000287/2023006) ML23267A0032023-09-21021 September 2023 RP Inspection Document Request IR 05000269/20230052023-08-25025 August 2023 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2 and 3 (Report 05000269/2023005, 05000270/2023005, and 05000287/2023005) ML23069A1102023-03-10010 March 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML23061A1772023-03-0303 March 2023 Notification of Oconee Nuclear Station Comprehensive Engineering Team Inspection - NRC Inspection Report 05000269/2023011, 05000270/2023011 and 05000287/2023011 IR 05000269/20220062023-03-0101 March 2023 Annual Assessment Letter for Oconee Nuclear Nuclear Station, Units 1, 2 and 3 (NRC Inspection Report 05000269/2022006, 05000270/2022006, and 05000287/2022006) ML23039A1632023-02-0808 February 2023 Requalification Program Inspection IR 05000269/20220052022-08-26026 August 2022 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 - NRC Inspection Report 05000269/2022005, 05000270/2022005, and 05000287/2022005 ML22157A0042022-06-0606 June 2022 10 CFR 50.59 Inspection Initial Information Request ML22088A0452022-03-28028 March 2022 Radiation Safety Baseline Inspection Initial Information Request Inspection Report 2022002 IR 05000269/20210062022-03-0202 March 2022 Annual Assessment Letter for Oconee Nuclear Station, Units 1, 2, and 3 (Report 05000269/2021006, 05000270/2021006, and 05000287/2021006) ML22019A2442022-01-18018 January 2022 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000269/2022010, 05000270/2022010, 05000287/2022010) and Request for Information (RFI) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21070A2982021-03-11011 March 2021 Upcoming Oconee POV Inspection (IP71111.21N.02) Information Request IR 05000269/20200062021-03-0303 March 2021 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2, & 3 NRC Inspection Report 05000269/2020006, 05000270/2020006, & 05000287/2020006 ML21043A1402021-02-11011 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000269/20200052020-08-17017 August 2020 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2, and 3 (NRC Inspection Report 05000269/2020005, 05000270/2020005, and 05000287/2020005) ML20175A6462020-06-23023 June 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000269/20190062020-03-0303 March 2020 Annual Assessment Letter or Oconee Nuclear Station, Units 1, 2, and 3 - NRC Inspection Report 05000269/2019006, 05000270/2019006, and 05000287/2019006 ML20056E7362020-02-25025 February 2020 U3 2020002 ISI RFI IR 05000269/20190052019-08-26026 August 2019 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2, and 3 (NRC Inspection Report 05000269/2019005, 05000270/2019005, and 05000287/2019005) ML19120A4592019-04-30030 April 2019 Triennial Fire Protection Inspection Plan IR 05000269/20180062019-03-0404 March 2019 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2, and 3 - NRC Inspection Report 05000269/2018006, 05000270/2018006, and 05000287/2018006 ML18264A0242018-09-21021 September 2018 Emailed RFI Notification IR 05000269/20180052018-08-20020 August 2018 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2, and 3 (NRC Inspection Report 05000269/2018005, 05000270/2018005, and 05000287/2018005) ML18074A1082018-03-15015 March 2018 Emailed RP RFI Request 2018002 ML18068A0292018-03-0808 March 2018 Emailed Notification of Inspection and Request for Information ML17115A4642017-04-17017 April 2017 Emergency Preparedness Inspection and Request for Information IR 05000269/20160062017-03-0101 March 2017 Annual Assessment Letter for Oconee Nuclear Station, Units 1, 2, and 3 - NRC Inspection Report 05000269/2016006, 05000270/2016006 and 05000287/2016006 ML17055B2572017-02-23023 February 2017 PIR Notification Letter 2017 ML16309A2772016-11-0303 November 2016 Notification of Oconee Nuclear Station Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000269/2017007, 05000270/2017007 and 05000287/2017007 IR 05000269/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 (NRC Inspection Report 05000269/2016005, 5000270/2016005 and 05000287/2016005) ML16075A0222016-03-14014 March 2016 Oconee Nuclear Station - Notification of Inspection and Request for Documents IR 05000269/20150062016-03-0202 March 2016 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 (NRC Inspection Report 05000269/2015006, 05000270/2015006 and 05000287/2015006) IR 05000269/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 (NRC Inspection Report 05000269/2015005, 05000270/2015005 and 05000287/2015005) ML15231A1922015-08-19019 August 2015 NRC June 9 2009 Memo Revision ML15202A0352015-07-15015 July 2015 Relief Request Serial #15-ON-002: Limited Volume Examinations Per 10 CFR 50.55a(g)(5)(iii) for Unit 1 and 2, Fourth Inservice Inspection Interval. Part 2 of 3 ONS-2015-086, Relief Request Serial 15-ON-002: Limited Volume Examinations Per 10 CFR 50.55a(g)(5)(iii) for Unit 1 and 2, Fourth Inservice Inspection Interval. Part 3 of 32015-07-15015 July 2015 Relief Request Serial #15-ON-002: Limited Volume Examinations Per 10 CFR 50.55a(g)(5)(iii) for Unit 1 and 2, Fourth Inservice Inspection Interval. Part 3 of 3 ML15202A0342015-07-15015 July 2015 Relief Request Serial #15-ON-002: Limited Volume Examinations Per 10 CFR 50.55a(g)(5)(iii) for Unit 1 and 2, Fourth Inservice Inspection Interval. Part 1 of 3 IR 05000269/20140012015-03-0404 March 2015 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3, (NRC Inspection Report 05000269/2014001, 05000270/2014001 and 05000287/2014001) ML15061A3352015-03-0202 March 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML14245A1272014-09-0202 September 2014 Mid-Cycle 2014 Letter ML14063A1752014-03-0404 March 2014 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 (NRC Inspection Report 05000269/2014001, 05000270/2014001 and 05000287/2014001) ML13246A1492013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000269/20120012013-03-0404 March 2013 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 (NRC Inspection Report 05000269/2012001 and 05000270/2012001) ML12248A0852012-09-0404 September 2012 Mid Cycle Assessment Letter Oconee 2012 ML12066A0552012-03-0505 March 2012 Inspection/Activity Plan, 03/01/2012 - 06/30/2013, Report 22 ML1124403672011-09-0101 September 2011 Report 22 - Oconee 2024-09-11
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 4, 2012
Mr. T. Preston Gillespie, Jr.
Site Vice President
Duke Energy Carolinas, LLC Oconee Nuclear Station 7800 Rochester Highway Seneca, SC 29672
SUBJECT:
MID-CYCLE LETTER FOR OCONEE NUCLEAR STATION UNITS 1, 2, AND 3 (NRC INSPECTION REPORT 05000369/2012006 AND 05000370/2012006)
Dear Mr. Gillespie:
On August 14, 2012, the NRC completed its mid-cycle performance review of Oconee Nuclear Station Unit 1, Unit 2, and Unit 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This assessment reflects the integration of the Security Cornerstone into the IMC 0305, "Reactor Oversight Process."ROP
performance assessment program governed by IMC 0305, "Operating Reactor Assessment Program."
The NRC determined the performance at Oconee Units 1, 2, and 3 during the previous four quarters was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix. The NRC issued a Yellow Finding on December 6, 2011, for failing to ensure that the Standby Shutdown Facility (SSF) pressurizer heater breakers would function during all credited SSF events. All other inspection findings had very low (i.e. Green) safety significance, and all PIs indicated that your performance was within the nominal expected range. The NRC determined that this Yellow Finding met the requirements of Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, for treatment as an "old design issue," and therefore, the finding did not aggregate in the NRC's Action Matrix. In addition to ROP baseline inspections, the NRC will conduct a supplemental inspection using Inspection Procedure 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area, to review the actions taken to address this finding the week of August 27, 2012.
The enclosed inspection plan lists the inspections scheduled through December 31, 2013.
Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the ROP baseline inspections, we will conduct license renewal inspections, initial reactor operator examinations, and, consistent with the Agency's actions related to Fukushima, TI-187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-188, Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The T. Gillespie, Jr. 2
inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of- cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice" a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4607 with any questions you have regarding this letter.
Sincerely, /RA/
Jonathan H. Bartley, Chief Reactor Projects Branch 1
Division of Reactor Projects Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55
Enclosure:
Oconee Inspection/Activity Plan (09/01/2012 - 12/31/2013) cc w/Encl: (See page 3)
_________________________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP SIGNATURE JHB /RA/ NAME JBartley DATE 09/04/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO T. Gillespie, Jr. 3
cc w/encl:
Division of Radiological Health TN Dept. of Environment & Conservation
401 Church Street
Nashville, TN 37243-1532
Thomas D. Ray Plant Manger Oconee Nuclear Station
Duke Energy Carolinas, LLC Electronic Mail Distribution James A. Kammer
Design Engineering Manager Oconee Nuclear Station
Duke Energy Carolinas, LLC Electronic Mail Distribution
David A. Cummings Fleet Regulatory Compliance and Licensing Manager Duke Energy Corporation Electronic Mail Distribution
Judy E. Smith Licensing Administrator Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution
Kent Alter
Regulatory Compliance Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution
Lara S. Nichols Deputy General Counsel Duke Energy Corporation Electronic Mail Distribution
Luellen B. Jones Fleet Licensing Engineer
Duke Energy Carolinas, LLC Electronic Mail Distribution
Joseph Michael Frisco, Jr.
Vice President Nuclear Design Eng
Duke Energy Carolinas, LLC Electronic Mail Distribution M. Christopher Nolan Director, Regulatory Affairs Duke Energy Carolinas, LLC Electronic Mail Distribution
Sandra Threatt, Manager Nuclear Response and Emergency Environmental Surveillance Bureau of Land and Waste Management Department of Health and Environmental
Control Electronic Mail Distribution Robert H. Guy Organizational Effectiveness Manager Oconee Nuclear Station
Duke Energy Carolinas, LLC Electronic Mail Distribution
Alicia Richardson Licensing Administrative Assistant Duke Energy Corporation Electronic Mail Distribution Terry L. Patterson
Safety Assurance Manager
Duke Energy Carolinas, LLC Electronic Mail Distribution Charles Brinkman
Director Washington Operations Westinghouse Electric Company, LLC Electronic Mail Distribution County Supervisor of Oconee County
415 S. Pine Street Walhalla, SC 29691-2145
W. Lee Cox, III Section Chief
Radiation Protection Section N.C. Department of Environmental
Commerce & Natural Resources Electronic Mail Distribution T. Gillespie, Jr. 4
Letter to T. Preston Gillespie, Jr. from Jonathan H. Bartley dated September 4, 2012
SUBJECT:
MID-CYCLE LETTER FOR OCONEE NUCLEAR STATION UNITS 1, 2, AND 3 (NRC INSPECTION REPORT 05000369/2012006 AND 05000370/2012006)
Distribution w/encl
- C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS
PUBLIC RidsNrrPMOconee Resource INPO ROP Reports Oconee Inspection / Activity Plan 09/01/2012
-12/31/2013 Unit Number Page 1 of 2 09/04/2012 08:19:50 Report 22 No. of Staff on Site Planned Dates Start End Inspection Activity Title 5 TI-177-TI-177 1, 2, 3 09/10/2012 09/14/2012 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 6 PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 1, 2, 3 09/17/2012 09/21/2012 IP 7111401 Exercise Evaluation 1, 2, 3 09/17/2012 09/21/2012 IP 71151 Performance Indicator Verification 1 TI-188-TI-188 P2 - NTTF 2.3 - SEISMIC WALKDOWNS 1, 2, 3 10/15/2012 10/17/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns 2 EB3 ISI-UNIT 1 INSERVICE INSPECTION & RPVH EXAMS 1 11/05/2012 11/09/2012 IP 7111108P Inservice Inspection Activities - PWR 2 EB3 LR-UNIT 1 POST APPROVAL LR - PHASE 1 1, 2, 3 11/05/2012 11/09/2012 IP 71003 Post-Approval Site Inspection for License Renewal 1 EB3SGISI-UNIT 1 SG INSERVICE INSPECTION 1 11/05/2012 11/09/2012 IP 7111108P Inservice Inspection Activities - PWR 3 OL EXAM-INITIAL EXAM PREP 1 11/26/2012 11/30/2012 V23391 OCONEE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES 3 OL EXAM-INITIAL EXAM - WEEK 1 1 12/17/2012 12/21/2012 V23391 OCONEE/DECEMBER 2012 INITIAL EXAM AT POWER FACILITIES 6 OCO TFPI-OCO - TRIENNIAL FIRE PROTECTION INSP 1, 2, 3 01/08/2013 01/10/2013 IP 7111105x Fire Protection - NFPA 805 (Triennial) 1, 2, 3 01/28/2013 02/01/2013 IP 7111105x Fire Protection - NFPA 805 (Triennial) 1, 2, 3 02/11/2013 02/15/2013 IP 7111105x Fire Protection - NFPA 805 (Triennial) 2 OL RQ-REQUAL INSPECTION 1, 2, 3 02/11/2013 02/14/2013 IP 7111111B Licensed Operator Requalification Program 5 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 1, 2, 3 04/01/2013 04/05/2013 IP 71152B Problem Identification and Resolution 1, 2, 3 04/15/2013 04/19/2013 IP 71152B Problem Identification and Resolution 3 OL EXAM-INITIAL EXAM PREP 1 05/20/2013 05/24/2013 V23406 OCONEE/JUNE 2013 EXAM AT POWER FACILITIES 3 OL EXAM-INITIAL EXAM - WEEK 1 1 06/10/2013 06/14/2013 V23406 OCONEE/JUNE 2013 EXAM AT POWER FACILITIES 4 MODS-PERM MODS 50.59 INSPECTION 1, 2, 3 08/26/2013 08/30/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 1, 2, 3 09/09/2013 09/13/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Oconee Inspection / Activity Plan 09/01/2012
-12/31/2013 Unit Number Page 2 of 2 09/04/2012 08:19:50 Report 22 No. of Staff on Site Planned Dates Start End Inspection Activity Title 1 EP-EMERGENCY PREPAREDNESS INSPECTION 1, 2, 3 09/16/2013 09/20/2013 IP 7111402 A lert and Notification System Testing 1, 2, 3 09/16/2013 09/20/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2, 3 09/16/2013 09/20/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2, 3 09/16/2013 09/20/2013 IP 71151 Performance Indicator Verification 2 ISI-UNIT 2 IN-SERVICE INSPECTION 2 10/21/2013 10/25/2013 IP 7111108P Inservice Inspection Activities - PWR 3 PSB1-RP-RP OCCUPATIONAL BASELINE WEEK2 1, 2, 3 10/21/2013 10/25/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 10/21/2013 10/25/2013 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 10/21/2013 10/25/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 10/21/2013 10/25/2013 IP 71124.04 Occupational Dose Assessment 1, 2, 3 10/21/2013 10/25/2013 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 10/21/2013 10/25/2013 IP 71151 Performance Indicator Verification 1 SGISI-UNIT 2 SG INSERVICE INSPECTION 2 10/21/2013 10/25/2013 IP 7111108P Inservice Inspection Activities - PWR 3 PSB1-RP-RP-OCCUPATIONAL BASELINE 1, 2, 3 11/18/2013 11/22/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 11/18/2013 11/22/2013 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 11/18/2013 11/22/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 11/18/2013 11/22/2013 IP 71124.04 Occupational Dose Assessment 1, 2, 3 11/18/2013 11/22/2013 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 11/18/2013 11/22/2013 IP 71151 Performance Indicator Verification Comments: This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.