IR 05000269/2024002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002
ML24201A090
Person / Time
Site: Oconee  
(DPR-038, DPR-047, DPR-055)
Issue date: 07/25/2024
From: Eric Stamm
NRC/RGN-II/DRP/RPB1
To: Snider S
Duke Energy Carolinas
References
IR 2024002
Download: ML24201A090 (27)


Text

SUBJECT:

OCONEE NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000269/2024002 AND 05000270/2024002 AND 05000287/2024002

Dear Steven Snider:

On June 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Oconee Nuclear Station. On July 24, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Oconee Nuclear Station.

July 25, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Eric J. Stamm, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 05000269 and 05000270 and 05000287 License Nos. DPR-38 and DPR-47 and DPR-55

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000269, 05000270 and 05000287

License Numbers:

DPR-38, DPR-47 and DPR-55

Report Numbers:

05000269/2024002, 05000270/2024002 and 05000287/2024002

Enterprise Identifier:

I-2024-002-0022

Licensee:

Duke Energy Carolinas, LLC

Facility:

Oconee Nuclear Station

Location:

Seneca, South Carolina

Inspection Dates:

April 1, 2024, to June 30, 2024

Inspectors:

N. Smalley, Senior Resident Inspector

E. Robinson, Resident Inspector

D. Dang, Resident Inspector, Acting

B. Bowker, Reactor Inspector

A. Hutto, Senior Project Engineer

J. Nadel, Reactor Inspector

E. Riggs, Senior Technical Training Program Specialist

A. Ruh, Senior Reactor Inspector

J. Vasquez, Reactor Inspector

Approved By:

Eric J. Stamm, Chief

Reactor Projects Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Oconee Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Maintain Fire Penetration in Accordance with Fire Protection Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000269/2024002-01 Open/Closed None (NPP)71111.05 The inspectors identified a Green finding and associated non-cited violation (NCV) of Oconee Nuclear Station Units 1, 2, and 3, Renewed Facility Operating License Condition 3.D for the licensees failure to maintain in effect all provisions of the approved fire protection program.

Specifically, the licensee failed to ensure that the fire resistive penetration seal assembly in fire penetration 1-M-N-5 was installed to the correct seal thickness per plant design drawings.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000270/2023-001-00 Oconee Nuclear Station Unit 2,

Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition that Could Have Prevented Fulfillment of a Safety Function 71153 Closed LER 05000287/2023-002-00 Oconee Nuclear Station, Unit 3,

Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications 71153 Closed

PLANT STATUS

Unit 1 operated at or near 100 percent rated thermal power (RTP) for the entire inspection period.

Unit 2 operated at or near 100 percent RTP for the entire inspection period, with the exception of a temporary power reduction to 96 percent RTP on May 1, 2024, as required to implement a measurement uncertainty recapture power uprate from 2568 megawatts to 2608 megawatts core thermal power.

Unit 3 began the inspection period at or near 100 percent RTP. On May 4, 2024, Unit 3 was shut down for a scheduled refueling outage (O3R32). During startup, on May 29, 2024, Unit 3 was limited to 74 percent RTP following unexpected measured high assembly power for assembly location H-05. On June 2, 2024, Unit 3 was shut down for a maintenance outage (O3F32A) to replace two burnable poison rod assemblies (BPRAs) that had incorrect boron concentrations. During O3F32A, indications of a leaking fuel assembly were discovered, independent of the faulty BPRAs. The leaking assembly was isolated and replaced, with no indications of significant fuel damage. The unit was returned to 100 percent RTP on June 20, 2024, and operated at or near 100 percent RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Standby shutdown facility, protected service water and alternate reactor building cooling portable submersible pump equipment on April 15, 19, and 25, 2024
(2) Unit 1 motor driven emergency feedwater (MDEFW) pumps and valves on April 17, 2024
(3) Unit 3 low pressure injection system during O3R32 refueling outage on May 21, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire zone 105: Unit 2 cable room on April 16, 2024
(2) Fire zone 108: Unit 1 east penetration room on April 30, 2024
(3) Fire zone 89: Unit 3 equipment room on May 22, 2024
(4) Fire zone 124: Unit 3 containment on May 24, 2024
(5) Fire zone 112: Unit 3 control room on May 28, 2024
(6) Fire zone 85: Unit 1 auxiliary building 200 level hallway on June 10, 2024

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 1 reactor building cooling units following performance testing per PT/0/A/0160/006, Reactor Building Cooling Units Performance Test, on April 23 and April 24, 2024

===71111.08P - Inservice Inspection Activities (PWR) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities in Unit 3 during refueling outage O3R32 from May 6 to May 17, 2024.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)===

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1) Ultrasonic Examination (UT)
  • 3-GRID-001, UT thickness on containment liner, ASME Class CC

Radiographic Examination

  • 3-LP-0182-10, low pressure injection (LPI) pipe to valve, ASME Class 2 (associated with work order (WO) 20397347)

Dye Penetrant Examination

Magnetic Particle Examination

Visual Examination

WO 20397347-13, 3A LPI HDR test line, 3" gate valve, ASME Class 2 o

WO 20547399, new 18" valve 3LPSW-1236 and piping, ASME Class 3 PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection

Activities (IP Section 03.02) (1 Sample)

The inspectors verified that the licensee conducted the following vessel upper head penetration inspections and addressed any identified defects appropriately:

(1) Bare metal visual examination of the reactor pressure vessel upper head, ASME Class 1 PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:

(1)

Action request (AR) 02477429 o

AR 02483940 o

AR 02491702

  • Review of corrective actions performed for evidence of boric acid leaks that were identified o

AR 02515422 o

Work request (WR) 20268607 o

WR 20268611

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed power ascension for Unit 2 due to the power uprate from the main control room on May 1, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated simulator just in time training for power escalation using lesson plan OP-OC-20JT-06 on June 12, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) C low pressure service water pump (LPSW) pump lubricating oil sampling and addition using commercial grade dedicated oil, WO 20645573
(2) Nuclear condition report (NCR) 2473173, Unit 1/2 C LPSW pump tripped after maintenance on May 17, 2023
(3) NCR 2501851, Keowee hydro unit air circuit breaker, ACB-1, failed to open on shutdown on January 22, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Units 1, 2, and 3 green risk due to planned maintenance on the primary instrument air compressor, on April 9, 2024
(2) Units 1 and 2 green risk due to maintenance for the C train of LPSW, on April 18, 2024
(3) Units 1, 2, and 3 green risk due to maintenance for protected service water primary and booster pump, on April 26, 2024
(4) Unit 3 yellow risk due to reactor coolant system draining and lowered inventory operations, on May 5 and May 6, 2024
(5) Units 1, 2, and 3 green risk following issuance of a tornado watch, on May 8, 2024
(6) Unit 3 yellow risk due to reactor coolant system draining and lowered inventory operations, on June 4 and June 5, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) NCR 2511097, 3LPSW-125 and 3LPSW-132 not through bolted
(2) NCR 2511743, KHU-2 exciter warning alarm locked in
(3) NCR 2512430, unexpected bearing cooling water alarms during KHU-2 starts
(4) NCR 2517136, debris discovered in Unit 3 borated water storage tank
(5) NCR 2517412, Unit 3 core high assembly power at H-05 on power escalation following O3R32 refueling outage
(6) NCR 2515786, 3A2 HPI makeup nozzle indications observed during UT examinations

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modification:

(1) AR 2403542, replacement of axial power shaping rod assemblies for all 3 units

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (2 Samples)

(1) The inspectors evaluated refueling outage O3R32 activities from May 4 to May 29, 2024
(2) The inspectors evaluated forced outage O3F32A activities from June 2 to June 20, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (8 Samples)

(1) PT/1/A/0251/001, "C Low Pressure Service Water Pump Test," following oil sampling and seal regulator maintenance, on April 19, 2024
(2) TT/2/A/0261/021, "CCW Pump Flange Seal Data Collection Test," of 2D condenser circulating water pump, on May 1, 2024, following installation of engineering change

===422106

(3) PT/3/A/0600/012, "Turbine Driven Emergency Feedwater Pump Test," following outage maintenance, on May 22, 2024
(4) PT/3/A/0151/019, "Penetration 19 Leak Rate Test," following preventive maintenance on reactor building purge valves, on May 22, 2024
(5) PT/0/A/0711/001, "Zero Power Physics Test," on May 25, 2024
(6) PT/3/A/0811/001, "Power Imbalance Correlation Test," on Unit 3 following refueling outage, on May 28, 2024
(7) PT/2/A/2200/011, "KHU-2 Turbine Guide Bearing Oil System Retest," following motor contact inspection, on June 8, 2024
(8) PT/1/A/0600/13, "1A MDEFW Pump Test," following maintenance, on June 11, 2024 Surveillance Testing (IP Section 03.01)===
(1) PT/3/A/0261/010, "Essential Siphon Vacuum System Pump Tests," on Unit 3, on April 11 and April 15, 2024
(2) PT/3/A/0610/001, "J Emergency Power Switching Logic (EPSL) Loadshed Test," on May 17, 2024

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (2 Samples)

(1) PT/3/A/0151/029, "Penetration 29 Leak Rate Test," on Unit 3, on May 15, 2024
(2) PT/3/A/0151/019, "Penetration 19 Leak Rate Test," on Unit 3, on June 12, 2024

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) The inspectors observed and evaluated a simulator drill and exercise performance examination using lesson plan ASE-13 on June 25,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2023, through March 31, 2024)
(2) Unit 2 (April 1, 2023, through March 31, 2024)
(3) Unit 3 (April 1, 2023, through March 31, 2024)

MS08: Heat Removal Systems (IP Section 02.07) (3 Samples)

(1) Unit 1 (April 1, 2023, through March 31, 2024)
(2) Unit 2 (April 1, 2023, through March 31, 2024)
(3) Unit 3 (April 1, 2023, through March 31, 2024)

MS10: Cooling Water Support Systems (IP Section 02.09) (3 Samples)

(1) Unit 1 (April 1, 2023, through March 31, 2024)
(2) Unit 2 (April 1, 2023, through March 31, 2024)
(3) Unit 3 (April 1, 2023, through March 31, 2024)

BI02: RCS Leak Rate Sample (IP Section 02.11) (3 Samples)

(1) Unit 1 (April 1, 2023, through March 31, 2024)
(2) Unit 2 (April 1, 2023, through March 31, 2024)
(3) Unit 3 (April 1, 2023, through March 31, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) NCR 2516804, Part 21 notification for potential defect of AMETEK oil filled aluminum case capacitors - 07-020139-10

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in foreign material issues and foreign material exclusion controls during refueling outages that might be indicative of a more significant safety issue.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1) LER 05000270/2023-001-00, Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition that Could Have Prevented Fulfillment of a Safety Function (ADAMS Accession No. ML24060A312). The inspection conclusions associated with this LER are documented in Inspection Report 05000269, 05000270, 05000287/2023011 (ADAMS Accession No. ML23236A615)under Inspection Results Section 71111.21M. This LER is Closed.
(2) LER 05000287/2023-002-00, Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications (ADAMS Accession No. ML24060A311). The inspection conclusions associated with this LER are documented in Inspection Report 05000269, 05000270, 05000287/2023004 (ADAMS Accession No. ML24038A367) under Inspection Results Section 71152A.

This LER is Closed.

INSPECTION RESULTS

Failure to Maintain Fire Penetration in Accordance with Fire Protection Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000269/2024002-01 Open/Closed None (NPP)71111.05 The inspectors identified a Green finding and associated NCV of Oconee Nuclear Station Units 1, 2, and 3, Renewed Facility Operating License Condition 3.D for the licensees failure to maintain in effect all provisions of the approved fire protection program. Specifically, the licensee failed to ensure that the fire resistive penetration seal assembly in fire penetration 1-M-N-5 was installed to the correct seal thickness per plant design drawings.

Description:

On March 14, 2024, during a fire protection walkdown of the Unit 1 east penetration room, the inspectors identified a potentially degraded fire barrier penetration, 1-M-N-5, a 5-inch pipe passing through the wall above door 401B between the Unit 1 cable room and the Unit 1 east penetration room. Although the penetration seal was flush with the wall, inspectors noted possible degradation with signs of potential loss of foam insulation in the seal assembly. The inspectors informed the licensee operations staff and the fire protection engineer, who determined that the penetration seal was non-functional. The licensee established an hourly fire watch and documented the condition in the corrective action program as NCR 2508926.

The licensee determined through a destructive examination that the wall containing penetration 1-M-N-5 had a thickness of only eight inches. This was contrary to the dimensional data listed in the equipment database (EDB), the established method of design control for plant equipment. The EDB had listed 1-M-N-5 as a penetration of 12 inches thick.

Additionally, the penetration was installed with foam insulation seal, but the EDB incorrectly listed a grout seal design. Procedure MP/1/A/1705/018, Fire Protection - Penetration - Fire and Flood Barrier - Inspection and Minor Repair, is used for periodic external visual inspection and repair of fire penetrations such as 1-M-N-5. The licensee identified that this procedure had listed the wall containing this penetration as being 12 inches thick as far back as 1998. Around this time, an effort was undertaken by the licensee to re-inspect and repair many fire penetrations as well as implement the EDB as the method of design control. The engineering change (EC) implemented in 1999, established EDB entries and issued drawings for maintenance and inspection of penetration seals. This information was then used to update inspection procedure MP/1/A/1705/018.

The licensee concluded that the most likely cause of the dimensional design discrepancies was an improper interpretation of plant drawings during the establishment of the EDB and implementation of the EC in 1999. The licensee completed inspections of penetration 1-M-N-5 several times since 1999 per MP/1/A/1705/018. The licensee used drawing O-0310-KM-001 to verify correct penetration seal design. Based on the wall thickness of the penetration in question, the licensee would refer to either Detail M-1 or M-2 for a barrier thickness of less than 12 inches or equal to or greater than 12 inches, respectively. Based on the flawed penetration thickness listed as 12 inches in MP/1/A/1705/018, the visual condition of the penetration would have been acceptable per Detail M-2 as 12 inches of seal material would have been present. However, with the current plant configuration of the penetration being only 8 inches in thickness and the penetration seal being flush with the wall surface, the penetration would not have been acceptable in accordance with Detail M-1 of O-0310-KM-001. Specifically, penetration 1-M-N-5 would be required to have a minimum of 12 inches of foam insulation, extending beyond the barrier plane to achieve the required seal depth. The maintenance procedures consist of external visual inspections, which allowed the as-built configuration being different from the procedure stated wall thickness to go unrecognized since 1999.

Corrective Actions: The licensee declared the penetration non-functional and set an hourly fire watch. Additionally, the correct penetration depth and seal design was determined, and the fire penetration seal was repaired and restored to a functional condition (12-inch foam insulation thickness). The equipment database and associated maintenance procedures for inspection and repair were corrected to reflect actual plant conditions.

Corrective Action References: NCRs 2508926, 2509983

Performance Assessment:

Performance Deficiency: The inspectors determined that the failure to maintain fire penetration 1-M-N-5 in accordance with drawing O-0310-KM-001, Penetration Seal Configuration Mechanical Fire Penetration Seal Designs Details M-1 & M-2, was a performance deficiency. Specifically, the licensee failed to ensure that penetration 1-M-N-5 was maintained with a minimum of 12 inches of foam insulation per Detail M-1 to ensure that the 3-hour rated fire boundary was functional as required by the fire protection program.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, fire penetration 1-M-N-5 separates two high risk fire zones in the auxiliary building and was declared non-functional, adversely impacting the 3-hour fire boundary. Additionally, this performance deficiency is similar to the more than minor Example 2.d in Inspection Manual Chapter (IMC) 0612 Appendix E, Examples of Minor Issues.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. The finding was assigned to category 1.4.4 Fire Confinement with a High Degradation rating because greater than 10 percent of the required foam seal depth was missing. Using IMC 0609, Appendix F, 1, Step 1.4.4-E, the inspectors determined that if a fire were to spread from one fire area to another due to the degraded fire barrier, no additional targets would be damaged in the exposed fire area that could impact the credited safe shutdown strategy for the exposing fire area. Therefore, the inspectors determined that the finding was of very low safety significance (Green).

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Oconee Nuclear Station Units 1, 2, and 3, Renewed Facility Operating License Condition 3.D required, in part, Duke Energy Carolinas, LLC shall implement and maintain in effect all provisions of the approved fire protection program that comply with 10 CFR 50.48(a)and 10 CFR 50.48(c) and NFPA 805. NFPA 805, Section 3.11.4, requires, in part, that through penetration fire stops shall be protected such that the annular space between the penetrating item and the through opening in the fire barrier shall be filled with a qualified fire resistive penetration seal assembly capable of maintaining the fire resistance of the fire barrier. Oconee implemented this requirement through drawing O-0310-KM-001, Penetration Seal Configuration Mechanical Fire Penetration Seal Designs Details M-1 & M-2, via the licensee's design control equipment database. Fire Penetration 1-M-N-5 is a pipe penetration with a foam seal assembly through an 8-inch fire barrier and is required to be maintained in accordance with Detail M-1 (12-inch foam insulation thickness) of drawing O-0310-KM-001.

Contrary to the above, from at least 1999 until March 15, 2024, the licensee failed to implement and maintain in effect, all provisions of the approved fire protection program as required by drawing O-0310-KM-001. Specifically, the licensee failed to maintain fire penetration 1-M-N-5 in accordance with Detail M-1 of drawing O-0310-KM-001.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On May 9, 2024, the inspectors presented the inservice inspection results to Steven Snider and other members of the licensee staff.
  • On July 24, 2024, the inspectors presented the integrated inspection results to Steven Snider and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

2512968

OFD-102A-3.1

Flow Diagram of Low Pressure Injection System (Borated

Water Supply and LPI Pump Suction)

065

OFD-102A-3.2

Flow Diagram of Low Pressure Injection System (LPI Pump

Discharge)

049

OFD-102A-3.3

Flow Diagram of Low Pressure Injection System (Core

Flood)

25

Drawings

OFD-121D-1.1

Flow Diagram of Emergency Feedwater System

038

71111.04

Miscellaneous

Clearance PRT-3 -24-3A LPI TRAIN-0109

OSC-9293

NFPA 805 Transition Radioactive Release G-1 Table

004

OSC-9314

NFPA 805 Transition Risk-Informed Performance-Based

Fire Risk Evaluation

006

Calculations

OSC-9659

Oconee Nuclear Safety Capability Assessment for Units 1,

2, and 3

011

Corrective Action

Documents

2508926

CSD-ONS-PFP-

1AB-0783

Pre-Fire Plan for U1 Auxiliary Building Elevation 783

000

CSD-ONS-PFP-

1AB-0809

Pre-Fire Plan for U1 Auxiliary Building Elevation 809

000

CSD-ONS-PFP-

2AB-0809

Pre-Fire Plan for U2 Auxiliary Building Elevation 809

000

CSD-ONS-PFP-

3AB-0796

Pre-Fire Plan for Unit 3 Auxiliary Building Elevation 796

001

CSD-ONS-PFP-

3AB-0822

Pre-Fire Plan for Unit 3 Auxiliary Building Elevation 822

000

Fire Plans

CSD-ONS-PFP-

3RB

Pre-Fire Plan for U3 Reactor Building All Elevations

000

O-0310-FZ-006

Auxiliary Building - Units 1 Fire Protection Plan Fire Area &

Fire Zone Boundaries Plan at EL 783 + 9

003

71111.05

Miscellaneous

O-0310-FZ-011

Auxiliary Building - Unit 3 Fire Protection Plan Fire Area &

000

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Fire Zone Boundaries Plan at EL 796+6 & 797+6

O-0310-FZ-017

Auxiliary & Reactor Building - Unit 3 Fire Protection Plan

Fire Area & Fire Zone Boundaries Plan at EL 822+0 & EL

25+0

003

O-0310-FZ-023

Reactor Building - Units 3 Fire Protection Plan Fire Area &

Fire Zone Boundaries Plan at EL 861 + 6

001

O-0310-K-004

Fire Protection Auxiliary Building Unit 1 EL 783 + 9

009

O-0310-K-009

Fire Protection Auxiliary Building Unit 3 EL 796+6

015

O-0310-K-010

Auxiliary Building Unit 1 Fire Protection Plan & Fire Barrier,

Flood & Pressure Boundaries Plan at EL 809+3

O-0310-K-015

Fire Protect Auxiliary Building Unit 3 EL 822+0

017

O-0310-K-018

Auxiliary & Reactor Building Unit 3 Fire Protection Plant &

Fire Barrier, Flood, & Pressure Boundaries Plant at EL 838 +

0, EL 844 + 6, Below EL 876 + 0 and Below EL 886 +5

O-0310-K-021

Reactor Building - Unit 3 Fire Protection Plan & Fire Barrier,

Flood & Pressure Boundaries Plan at EL 861 + 6

O-0310-KM-001

Penetration Seal Configuration Mechanical Fire Penetration

Seal Designs Details M-1 & M-2

AD-FP-ALL-1520

Transient Combustible Control

001

MP/0/A/1705/027

Fire Protection - Fire Barrier Penetrations - Installation and

Repair Using Silicone Foam and Damming Material

047

Procedures

MP/1/A/1705/018

Fire Protection - Penetration - Fire and Flood Barrier -

Inspection and Minor Repair

2

Work Orders

265272

Calculations

OSC-11956

Reactor Building Cooling Units Performance Test

Corrective Action

Documents

2510287, 2438405, 2479288, 2507201, 2515539

Miscellaneous

ONEI-0400-400

Revised Reactor Building Cooling Unit (RBCU)

Requirements in Support of 1-Year Mission Times

71111.07A

Work Orders

20653985

EC 105524

Miscellaneous

Power Escalation JITT, OP-OC-20JT-06

AD-OP-All-0106

Conduct Of Infrequently Performed Tests Or Evolutions

71111.11Q

Procedures

AD-OP-ALL-1000

Conduct of Operations

23

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AD-OP-ALL-1001

Abnormal Conduct of Operations

006

AD-OP-ONS-

0002

Oconee Specific Abnormal Operations Guidance

007

AP/0/A/1700/047

External Flood Mitigation

29

OP/2/A/1102/004

Operation at Power

134

Corrective Action

Documents

2473173, 2466960, 2501851, 2355727, 2357958, 2365144,

2446131, 2356835, 2356873, 2503151, 2453446

Drawings

KEE-114

Elementary Diagram Generator Control ACB-1 Control

Circuit

Engineering

Changes

403225

Lubrication Datasheet for ON0LPSPU000C

04/18/2024

Miscellaneous

OSS-0254.00-

2005

(ELECT) Keowee Emergency Power Design Basis

Document

035

AD-EG-ALL-1103

Procurement Engineering Products

Procedures

PT/0/A/0251/029

Siphon Seal Water System Test

71111.12

Work Orders

262241, 20433314, 20643793, 20447425, 20654745

Corrective Action

Documents

2490772, 2490763

Drawings

OFD-137B-1.1

Flow Diagram of Instrument Air System (Air Compressors,

After Coolers, Receivers, Air Dryers)

Phoenix ONS Risk Profile for all Units on the week of April

2, 2024

Phoenix ONS Risk Profile for Unit 3 on the week of June 3,

24

Miscellaneous

OSS-0254.00-00-

25

Design Basis Specification for the Instrument Air System

018

AD-OP-ALL-0106

Conduct of Infrequently Performed Tests or Evolutions

AD-WC-ALL-0240

On-line Risk Management Process

AD-WC-ALL-0410

Work Activity Integrated Risk Management

AD-WC-ALL-0420

Shutdown Risk Management

Rev 8

AD-WC-ALL-0420

Shutdown Risk Management

71111.13

Procedures

AD-WC-ALL-0430

Outage Risk Review

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AD-WC-ONS-

20

ONS Shutdown Risk Management

AD-WC-ONS-

20

ONS Shutdown Risk Management

Rev 5

AP/0/A/1700/006

Natural Disaster

Rev 35

AP/3/A/1700/022

Loss of Instrument Air

29

MP/0/B/3007/049

Compressors - Primary Instrument Air - Sullair - Model 32-

25-400 - Preventive Maintenance

29

OP/0/A/1102/026

Operations IPTE Pre-Job Briefings

033

OP/0/A/1106/027

Instrument Air System

28

PT/0/A/0500/001

Protected Service Water Primary and Booster Pump Test

007

Work Orders

20599978, 20647911

OSC-7220.81

Supporting Design Analyses for ONS 3 EC 424255

Evaluation for Acceptability of Existing Indications on the

3A2 HPI Safe End and DMBW

000

Calculations

OSC-9033

Risk Significance Evaluation of Sump Outlet Pipe Foreign

Material

Corrective Action

Documents

2511743, 2503915, PIP-O-05-05720, PIP-O-11-09953,

2511097, 2487656, 2512045, 2441303, 2483549, 2511097,

2517412, 2517443, 2517450, 2517461, 2517929, 2515886,

2354522, 2517136, 1761227, 2317886, 2517379, 2515786

KEE-213-2

Elementary Diagram Master Control System Gen.

Miscellaneous Relaying

KFD-100A-2.1

Flow Diagram of Turbine Generator Cooling Water System

Drawings

OFD-124A-3.1

Flow Diagram of Low Pressure Service Water System

Turbine BLDG. (Low Pressure Service Water Pumps)

Engineering Change 424255

000

ONEI-0400-592

Oconee 3 Cycle 33 Final Core Load Map

000

ONEI-0400-598

Oconee 3 Cycle 33 Core Operating Limits Report

000

OSS-0254.00-00-

2005

(Elect) Keowee Emergency Power Design Basis Document

034

Miscellaneous

PT/0/A/0811/001

Power Escalation Test

059

AD-EG-ALL-1110

Design Review Requirements

71111.15

Procedures

AD-EG-ALL-1708

Development of Relief Requests and Alternatives Pursuant

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

to 10 CFR 50.55A

AD-MN-ALL-0002

Foreign Material Exclusion

AD-NE-ALL-1107

Evaluation of Indications and Relevant Conditions

AD-PI-ALL-0100

Corrective Action Program

IP/0/A/2005/006

Maintenance Of Keowee Hydro Station General Electric

EX2100 Digital Exciter

21

OP/0/A/1106/019

Keowee Hydro At Oconee

114

OP/2/A/2000/102

KHU-2 Alarm Response Guide 2SA-2

2

TE-MN-ALL-0002

Foreign Material Exclusion Level and Controls Screening

Work Orders

266554, 20651767, 20255683, 20651767, 20658316,

266313, 20266013, 20661235, 20537999

Corrective Action

Documents

2403506, 2403542, 2423658

71111.18

Miscellaneous

OSC -11971

Oconee Replacement Axial Power Shaping Rod Assembly

(APSRA) Mechanical Design Evaluation

Corrective Action

Documents

2515019, 2515022, 2515090, 2515091, 2517306, 2518069,

2518189, 2518172, 2518685, 2517443, 2517450

OFD-101A-3.1

Flow Diagram of High Pressure Injection System (Letdown

Section)

044

OFD-101A-3.2

Flow Diagram of High Pressure Injection System (Storage

Section)

044

OFD-102A-3.1

Flow Diagram of Low Pressure Injection System (Borated

Water Supply and LPI Pump Suction)

065

OFD-102A-3.2

Flow Diagram of Low Pressure Injection System (LPI Pump

Discharge)

049

OFD-102A-3.3

Flow Diagram of Low Pressure Injection System (Core

Flood)

25

OFD-104A-3.1

Flow Diagram of Spent Fuel Cooling System

061

OFD-109A-3.1

Flow Diagram of Purification Demineralizers

016

OFD-116-3.1

Flow Diagram of Reactor Building Purge System

Drawings

OFD-121D-1.1

Flow Diagram of Emergency Feedwater System

Engineering

Changes

24347

Disposition for Re-use of Fuel Assembly UDPK01 and

UDPK03

71111.20

Miscellaneous

Clearance OPS-3-24-HP-LTOP S/U-0667

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Clearance OPS-3-24-LPI-LPI Sys Fill-0680

Pheonix Online Risk profile for Unit 3 for the week of April

28, 2024

O3R32 - Outage Schedule by Early Start, Current

Active/Working Version

Clearance OPS-3-24-RC-PZR Cooldown-0409

Clearance OPS-3-24-HPI-HPI Fill-0678

ONEI-0400-267

Oconee 3 Cycle 32 Spent Fuel Pool Decay Heat

Engineering Instruction

013

ONEI-0400-301

Communication of Requirements for Oconee Technical Specification 3.7.13: Definitions, Boundary Conditions, and

Spent Fuel Pool Storage Qualifications

001

ONEI-0400-349

Core Alignment Verification

001

ONEI-0400-371

Oconee Nuclear Station Unit 3 Loss of Spent Fuel Cooling

Heat Up Times Due to Decay Heat

003

ONEI-0400-592

Oconee 3 Cycle 33 Final Core Load Map

2

OSC-11714

Oconee Nuclear Station Cycle Specific Decay Heat

Calculations

019

OSC-1594

NUREG-0612 - Control of Heavy Loads - Load Drop

Analysis

2

OSC-6051

Verification of Alternate Method Used to Fill Spent Fuel

Pools Following Operation of SSF RC Makeup System

011

OSS-0254.00-00-

1004

(Mech) Design Basis Specification for Standby Shutdown

Facility Reactor Coolant Makeup System

064

OSS-0254.00-00-

1006

(Mech) Design Basis Specification for the Spent Fuel

Cooling System

034

OSS-0254.00-00-

4001

(Mech) Design Basis Specification for Reactor Building

Containment Isolation

046

AD-MN-ALL-0002

Foreign Material Exclusion

AD-MN-ALL-0009

Nuclear Rigging and Lifting

AD-OP-ALL-0201

Protected Equipment

AD-OP-ALL-0203

Reactivity Management

AD-SY-ALL-0460

Managing Fatigue and Work Hour Limits

Procedures

AM/0/A/3009/012

Emergency Plan for Refilling Spent Fuel Pools

013

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

A

AP/3/A/1700/002

Excessive RCS Leakage

016

AP/3/A/1700/026

Loss of Decay Heat Removal

29

AP/3/A/1700/035

Loss of SFP Cooling and/or Level

25

FG/0/A/1900/011

Alternative Spent Fuel Pool Cooling

2

IP/0/B/0200/027 A

Reactor Level Instrumentation and Calibration

033

IP/0/B/0200/027 B

Ultrasonic Level Instrument Installation and Calibration

25

IP/0/B/0200/027

C

Reactor Vessel Level Transmitters Return to Service and

Removal from Service

013

IP/0/B/3002/002 A

Polar Crane Inspection and Preventive Maintenance

015

MP/0/A/1150/002

A

Reactor Vessel - Closure Head - Installation

059

MP/0/A/1400/002

A

Equipment Hatch - Reactor Building - Temporary Opening

and

Closing

2

MP/0/A/1500/009

Defueling/Refueling Procedure

078

MP/0/A/1710/017

B

Crane - Whiting - Polar - Inspection

018

MP/0/A/1800/105

A

RBES - LPI Suction Line Flange Installation and Removal,

Drain Line and Sump Inspections

23

MP/0/A/3005/012

Containment Inspection/Close Out Procedure

2

MP/0/B/1710/022

Operation of Reactor Building Polar Crane and Auxiliary

Hoist (CRD Crane)

039

OP/0/A/1108/001

Curves and General Information

119

OP/0/A/1108/001

A

Reactor Core and SFP Loss of Cooling Heatup Tables

008

OP/0/A/1108/001

B

Spent Fuel Pool Level vs. Temperature Curves

018

OP/3/A/1102/001

Controlling Procedure for Unit Startup

285

OP/3/A/1102/001

Controlling Procedure for Unit Startup

285

OP/3/A/1102/004

Operation at Power

143

OP/3/A/1102/004

Operation at Power

2

OP/3/A/1102/010

Controlling Procedure for Unit Shutdown

256

OP/3/A/1102/015

Filling and Draining FTC

088

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP/3/A/1102/028

Reactor Building Tour and Containment Material Controls

2

OP/3/A/1103/011

Draining and Nitrogen Purging RCS

100

OP/3/A/1104/004

Low Pressure Injection System

171

OP/3/A/1104/006

SF Cooling System

2

OP/3/A/1104/010

Low Pressure Service Water

2

OP/3/A/1104/049

Low Temperature Overpressure Protection (LTOP)

061

OP/3/A/1105/019

Control Rod Drive System

035

OP/3/A/1106/001

Turbine Generator

29

OP/3/A/1106/006

Emergency FDW System

116

OP/3/A/1502/001

Operations Defueling/Refueling Responsibilities

093

OP/3/A/1502/007

Operations Defueling/Refueling Responsibilities

093

OP/3/A/1502/009

Containment Closure Control

050

PT/0/A/0711/001

Zero Power Physics Testing

081

PT/0/A/0750/002

Core Inspections Procedure

031

PT/0/A/0750/012

Development of Fuel Movement Instructions Procedure

054

PT/0/A/0750/012

Development of Fuel Movement Instructions Procedure

054

PT/0/A/0750/018

Refueling Activities

26

PT/0/A/0775/015

Core Alignment Verification

015

PT/3/A/0115/008

Reactor Building Containment Isolation and Verification

043

PT/3/A/0115/012

Unborated Water Source Isolation Verification

005

PT/3/A/0150/029

Performance Containment Verification

015

PT/3/A/0150/030

Containment Verification

004

PT/3/A/0150/034

Leak Rate History Record and Reactor Building Leak Rate

Verification

2

PT/3/A/0200/046

Reactor Coolant System Leak Test

011

PT/3/A/0600/001

B

Instrument Surveillance Prior to Mode Change

PT/3/A/0600/015

Control Rod Movement

030

PT/3/A/0630/001

Mode Change Verification

037

Work Orders

20541411, 20541412, 20268299, 20612211, 20612035,

20612355, 20612627, 20612628

71111.24

Corrective Action

Documents

2476102, 2473099, 2471437, 2426308, 2426301, 2516589,

2518189, 2515022, 2517412, 2517443, 2505843, 2469093,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2401644, 2327394, 2401085, 2327585, 2401253, 2518116

OFD-102A-3.1

Flow Diagram of Low Pressure Injection System (Borated

Water Supply and LPI Pump Suction)

065

OFD-102A-3.2

Flow Diagram of Low Pressure Injection System (LPI Pump

Discharge)

049

OFD-116A-3.1

Flow Diagram of Reactor Building Purge System

014

Drawings

OFD-121D-1.1

Flow Diagram of Emergency Feedwater System

039

Engineering

Changes

2106, 424347

ONEI-0400-352

Oconee Mast Sipping Limits and Precautions

001

ONEI-0400-477

Oconee Core Power Distribution Comparison Criteria

000

Miscellaneous

OSS-0254.00-00-

1049

(MECH) Design Basis Spec for the Essential Siphon

Vacuum System

015

AD-NF-ALL-0806

Nuclear Fuel Integrity

AD-OP-ALL-0106

Conduct of Infrequently Performed Tests or Evolutions

AP/3/A/1700/026

Loss of Decay Heat Removal

29

AP/3/A/1700/035

Loss of SFP Cooling and/or Level

25

EP/3/A/1800/001

0P

Unit 3 EOP Enclosures 5.31-5.40

MP/0/A/1200/045

Valve - Henry Pratt Type RIA11 - Reactor Building Purge -

Seat to Disc Adjustment

25

MP/0/A/1200/088

Valves - Henry Pratt - Reactor Building Purge Isolation -

Preventive Maintenance

28

MP/0/A/1840/040

A

Pumps - Motors - Miscellaneous Components - Lubrication

Post Maintenance Testing

004

MP/0/A/3009/020

A

DC Motor - Up to 50 HP - Visual Inspection and Preventive

Maintenance

010

PT/0/A/0711/001

Zero Power Physics Test

081

PT/0/A/0750/023

Fuel Assembly Inspection by In-Mast Sipping

009

PT/0/A/0750/025

Fuel Assembly Inspection by Canned Sipping

001

PT/0/A/0800/030

Core Power Distribution Comparison

063

PT/0/A/0811/011

Power Escalation Test

058

Procedures

PT/1/A/0600/013

Motor Driven Emergency Feedwater Pump Test

078

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PT/2/A/2200/011

KHU-2 Turbine Guide Bearing Oil System Surveillance

014

PT/3/A/0150/006

Mechanical Penetration Leak Rate Data

076

PT/3/A/0151/019

Penetration 19 Leak Rate Test

019

PT/3/A/0151/029

Penetration 29 Leak Rate Test

013

PT/3/A/0152/016

Purge System Valve Stroke Test

20

PT/3/A/0261/010

Essential Siphon Vacuum System Test

PT/3/A/0600/012

Turbine Driven Emergency Feedwater Pump Test

096

PT/3/A/0610/001

A

EPSL Normal Source Voltage Sensing Circuit

036

PT/3/A/0610/001

B

EPSL Startup Source Voltage Sensing Circuit

036

PT/3/A/0610/001

C

EPSL Standby Bus 1 And 2 Voltage Sensing Circuits

21

PT/3/A/0610/001

J

Emergency Power Switching Logic Test

056

Work Orders

20647905, 20523776, 20563143, 20645573, 20561397,

20666997, 20611772, 20612606, 20612630, 20612607,

20476249, 20648458, 20469789, 20669079, 20609616,

20655172

71114.06

Miscellaneous

ASE-13

Corrective Action

Documents

2506370

MSPI Derivation and Margin Reports for Heat Removal for

Oconee Nuclear Station

Mitigating Systems Performance Index (MSPI) Basis

Document

LER 270-2023-001

LER 287-2023-001

LER 287-2023-002

RCS Leak rate data for Oconee Nuclear Station

MSPI Derivation and Margin Reports for Cooling Water

System for Units 1, 2, and 3 from June 2023 to March 2024

AD-PI-ALL-0700

Performance Indicators

71151

Miscellaneous

OSS-0254.00-00-

(Mech) Design Basis Spec for Keowee Turbine Generator

018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1046

Cooling Water (WL) System

PT/X/A/0201/007

RCS Leakage Calculation Test

Corrective Action

Documents

2516908, 2516782

71152A

Miscellaneous

Interim Report of a Deviation Associated with an Oil Filled

Capacitors in Aluminum Case Part Number 07-020139-10,

Final Report of a Deviation Associated with an Oil Filled

Capacitors in Aluminum Case Part Number 07-020139-10

Corrective Action

Documents

2504661, 2508057, 2517041, 2517136, 2515865, 2518663,

2494275

71152S

Work Orders

263850, 20263851, 20263865, 20263849, 20537999,

20670317

71153

Corrective Action

Documents

2477145, 2477208, 2477210, 2477611, 2489821, 2477886,

2477925, 2480047, 2480068, 2503208