April 22, 2015, Meeting with Southern Nuclear Company, Slide Presentation
ML15106A204
Person / Time
Site: Hatch, Vogtle, Farley  Southern Nuclear icon.png
Issue date: 04/22/2015
From:
Southern Co, Southern Nuclear Operating Co
To:
Division of Operating Reactor Licensing
Williams S
Shared Package
ML15106A195 List:
References
Download: ML15106A204 (11)


Text

Southern Nuclear Operating Company (SNC) Standard Emergency Plan (SEP)

SNC/Nuclear Regulatory Commission (NRC) Pre-submittal Interaction April, 22, 2015

Agenda

  • July 2014 Interaction Recap
  • Change in Submittal Scope
  • Status of Fleet SEP
  • Construction/Testing Schedule Milestones Update
  • License Amendment Scope and Schedule
  • Key Features of the Submittal
  • Effect on EP Inspection Tests Analyses and Acceptance Criteria (ITAAC)
  • Licensing Considerations
  • Questions/Feedback 2

July 2014 Interaction Recap

  • Discussed options for combining the two Vogtle emergency plans into a single plan
  • Agreed that the option of adopting the fleet SEP on a limited basis to include Vogtle only was the option of choice
  • Agreed that future interactions would be desirable 3

Change in Submittal Scope

  • Initial submittal to include SNC SEP base for all SNC plants, and annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
  • Vogtle 3-4 will be submitted using the Vogtle common TSC and OSC
  • When approved and SNC personnel trained on new SNC Fleet SEP then Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 will implement
  • Impacts to Emergency Operations Facility (EOF) and EOF staffing require all SNC plants to implement concurrently, with exception of Vogtle 3-4
  • A separate License Amendment Request (LAR) will be submitted for Vogtle 1-2 to transition to the common TSC and OSC

Status of Fleet SEP

  • Fleet SEP drafted

- Includes all emergency plan information common to SNC plants (Farley, Hatch and Vogtle)

  • Communication plan
  • Annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 drafted

- Include EP information unique to each site

- Much information for each Vogtle annex identical, but separate information for treatment of Emergency Action Level (EALs) and associated technical bases 5

VEGP 3 and 4 EP Related Construction/Testing Schedule Milestones

  • Final EALs submitted for approval - 180 days before fuel load -

License Condition (Following SCANA approach)

  • Staffing assessment submitted - 180 days before fuel load - License Condition (Staffing analysis completed December 2014)
  • Implementing procedures submitted - 180 days before fuel load -

ITAAC 6

License Amendment Scope and Schedule

  • Amend all eight licenses to incorporate a SNC SEP with site specific annexes
  • Applies the common TSC and OSC to Vogtle 3-4
  • Includes conforming changes to affected EP ITAAC
  • Submittal planned for June 2015
  • Requesting approval by June 2016
  • Submit LAR for Vogtle site common TSC and OSC in June 2016 immediately following approval of SNC SEP
  • Implement SNC SEP for entire SNC Fleet (except Vogtle 3-4) in June 2017
  • Implement Common TSC and OSC for Vogtle site at or near the 103(g) for Unit 3 7

Key Features of the Submittal

  • Removes unnecessary detail
  • Leverages fleet standard procedures and processes
  • Requests a 90 minute augmentation time
  • Revises EOF organization to include Emergency Director
  • Standardizes on-shift and augmented ERO for the SNC fleet with minor exceptions for Vogtle 3-4 8

Effect on EP ITAAC

  • Some conforming changes to EP ITAAC required

- 90 minute augmentation time

- Use of tone alert radio as back-up notification method

  • Existing emergency plan uses the term Emergency Implementing Procedure (EIP)
  • EP ITAAC will retain the EIP nomenclature 9

Licensing Considerations Submittal contents

  • LAR Considerations

- One letter with separate enclosures for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4

- Separate enclosures with change justification matrices for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4

- Separate enclosures with ERO Augmentation Technical Document for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4

  • Separate LAR for Vogtle site common TSC and OSC submitted after NRC approval of SNC SEP 10

Questions/Feedback 11