Part 52 Lessons Learned Construction Initiative
Two Products Document lessons learned for a broad review of internal processes Publicly available summary report focused on construction inspection, ITAAC, and licensing insights 2
SCHEDULE The staffs lessons learned charter (ADAMS Accession No. ML21160A031) contains the milestones for this effort.
Framework for Discussion ITAAC LICENSING INSPECTION 4
What are your observations regarding the licensing process for the changing combined licenses under Part 52? Specifically, what could be improved on the license amendment, and exemption, and preliminary amendment review (PAR) processes? How beneficial and effective were the practices of maximizing the use of pre-submittal meetings and the processes for identifying and reviewing high complexity licensing actions?
How can the scope, interpretation, and overall use of ITAAC in combined licenses be improved for future Part 52 applications? How can ITAAC be upgraded to reduce any experienced administrative burden?
How can the NRC improve the construction inspection program?
Regarding construction and ITAAC findings, were the results of the issue screening process appropriately risk-informed? How can the process be improved? If future designs rely on increased vendor and manufacturer fabrication of reactor plant SSCs, how could the current inspection process be optimized to meet those needs?
Days to complete Vogtle 3 and 4 LARs 5
ICN average days in review 6
Total cumulative direct inspection hours 7
0 5000 10000 15000 20000 25000 30000 35000 40000 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Vogtle, Unit 3, Cumulative Data Vogtle, Unit 4, Cumulative Data
Inspection Procedures ranked by hours 8
Questions and Discussions