MONTHYEARIR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 IR 05000315/20230062024-02-28028 February 2024 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2023006 and 05000316/2023006) IR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 IR 05000315/20224202022-10-19019 October 2022 Cover Letter - Donald C. Cook Nuclear Plant Units 1 and 2 - Security Baseline Inspection Report 05000315/2022420 and 05000316/2022420 IR 05000315/20224012022-09-21021 September 2022 Security Baseline Inspection Report 05000315 2022401 05000316 2022401 Independent Spent Fuel Storage Security Inspection Report 07200072 2022401 IR 05000315/20223012022-08-31031 August 2022 NRC Initial License Examination Report 05000315/2022301; 05000316/2022301 IR 05000315/20220052022-08-24024 August 2022 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) IR 05000315/20220022022-08-0808 August 2022 Integrated Inspection Report 05000315/2022002 and 05000316/2022002 IR 05000315/20224022022-07-0505 July 2022 Material Control and Accounting Program Inspection Report 05000315/2022402 and 05000316/2022402 ML22165A2012022-06-14014 June 2022 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2022001 and 05000316/2022001 ML22129A2052022-05-10010 May 2022 Integrated Inspection Report 05000315/2022001 and 05000316/2022001 IR 05000315/20220012022-05-10010 May 2022 Integrated Inspection Report 05000315/2022001 and 05000316/2022001 IR 05000315/20220102022-04-0505 April 2022 Triennial Fire Protection Inspection Report 05000315/2022010 and 05000316/2022010 ML22084A5812022-03-25025 March 2022 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000315/2022011 05000316/2022011 IR 05000315/20210062022-03-0202 March 2022 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) IR 05000315/20210042022-02-0707 February 2022 Integrated Inspection Report 05000315/2021004 and 05000316/2021004 and Exercise of Enforcement Discretion IR 05000315/20210132021-12-0606 December 2021 Inspection Report 05000315/2021013 and 05000316/2021013 IR 05000315/20214032021-11-17017 November 2021 Security Baseline Inspection Report 05000315/2021403 and 05000316/2021403 IR 05000315/20210112021-11-15015 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000315/2021011 and 05000316/2021011 IR 05000315/20210032021-10-26026 October 2021 Integrated Inspection Report 05000315/2021003; 05000316/2021003; and 07200072/2021001 IR 05000315/20214012021-10-21021 October 2021 Cyber Security Inspection Report 05000315/2021401 and 05000316/2021401 IR 05000315/20215012021-10-0606 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2021501 and 05000316/2021501 IR 05000315/20210102021-09-0707 September 2021 Biennial Problem Identification and Resolution Inspection Report 05000315/2021010 and 05000316/2021010 IR 05000315/20210052021-09-0101 September 2021 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) IR 05000315/20210122021-08-0202 August 2021 Donald Cook Nuclear Plant - NRC Inspection Report 05000315/2021012 and 05000316/2021012 IR 05000315/20210022021-07-22022 July 2021 Integrated Inspection Report 05000315/2021002 and 05000316/2021002 IR 05000315/20214022021-06-0909 June 2021 Donald D. C. Cook Nuclear Plant - Security Baseline Inspection Report 05000315/2021402 and 05000316/2021402 ML21158A1732021-06-0909 June 2021 Review of the Fall 2017 Steam Generator Tube Inspections Report IR 05000315/20210012021-04-28028 April 2021 Integrated Inspection Report 05000315/2021001 and 05000316/2021001 IR 05000315/20200062021-03-0404 March 2021 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) 2024-09-05
[Table view] Category:Letter
MONTHYEARAEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-19, Annual Report of Property Insurance2024-04-0101 April 2024 Annual Report of Property Insurance 2024-09-09
[Table view] |
Text
June 21, 2023
SUBJECT:
DONALD C. COOK NUCLEAR PLANT - EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION REPORT 05000315/2023501 AND 05000316/2023501
Dear Q. Shane Lies:
On May 18, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Donald C. Cook Nuclear Plant and discussed the results of this inspection with Scott Dailey, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Signed by Orth, Steven on 06/21/23 Steven K. Orth, Chief Security, Emergency Preparedness & Incident Response Branch Division of Radiological Safety and Security Docket Nos. 05000315 and 05000316 License Nos. DPR-58 and DPR-74
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000315 and 05000316 License Numbers: DPR-58 and DPR-74 Report Numbers: 05000315/2023501 and 05000316/2023501 Enterprise Identifier: I-2023-501-0005 Licensee: Indiana Michigan Power Company Facility: Donald C. Cook Nuclear Plant Location: Bridgman, Michigan Inspection Dates: May 15, 2023 to May 18, 2023 Inspectors: E. Fernandez, Senior Reactor Inspector G. Hansen, Sr. Emergency Preparedness Inspector J. Kutlesa, Emergency Preparedness Inspector R. Ng, Senior Project Engineer Approved By: Steven K. Orth, Chief Security, Emergency Preparedness & Incident Response Branch Division of Radiological Safety and Security Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness biennial exercise inspection at Donald C. Cook Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71114.01 - Exercise Evaluation
Inspection Review (IP Section 02.01-02.11) (1 Sample)
- (1) The inspectors evaluated the biennial emergency plan exercise on May 16, 2023.
The exercise scenario simulated an event at the D. C. Cook Nuclear Power Plant that initiated with the declaration and notification of an Unusual Event in response to Control Room personnel feeling an actual or potential seismic event that was confirmed through site seismic monitor indications. The scenario conditions simulated the escalation of the significance of the event, requiring the declaration of a Site Area Emergency, and then a General Emergency, as well as the development of Protective Action Recommendations that were communicated to the required state and local government agencies.
71114.08 - Exercise Evaluation - Scenario Review
Inspection Review (IP Section 02.01 - 02.04) (1 Sample)
- (1) The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on April 13,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) ===
- (1) January 1, 2022 through December 31, 2022 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13)
(1 Sample)
- (1) January 1, 2022 through December 31, 2022 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
- (1) The site is in compliance with ANS performance indicator reporting requirements. The site's primary ANS is the Integrated Public Alert Warning System (IPAWS), therefore, for the period of this inspection, no siren performance testing data was available or required. In accordance with EPFAQ 21-03, Revision 1, "Reporting ANS Data Following a Transition to IPAWS," the performance of the licensees ANS is evaluated during the site's emergency preparedness program inspection using NRC Inspection Procedure 711 and is documented in the associated inspection report.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On May 18, 2023, the inspectors presented the emergency preparedness biennial exercise inspection results to Scott Dailey, Plant Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71114.01 Corrective Action AR 2021-7359 EOF Activation Time During Drill Exceeded CEP 08/26/2021
Documents Requirements
AR 2021-7366 EMD-032A inaccuracies 08/26/2021
AR 2021-7754 Validate Dose Assessment Results from ERO Drill 09/14/2021
AR 2021-7972 KI Authorization Form Not Completed During Drill 09/23/2021
AR 2021-9078 PA and OCANS Announcement Late or Not Performed 11/04/2021
During Drill
AR 2021-9081 EOF Full Staffing Level Not Met within 1 HR. Expectation 11/03/2021
AR 2022-0327 EOF Full Staffing Level Not Met within 1 HR. Expectation 01/12/2022
AR 2022-0343 Back-Up Method Required to Notify MSP During ERO Drill 01/12/2022
AR 2022-0529 ERO Drill: Low-Level Issue Failure to Critique 01/19/2022
AR 2022-1178 EMD-032 Forms Transmit Slowly Via Mail Through 02/10/2022
Vaporstream
AR 2022-5468 Partial Failure of EMD-032A Message Transmission 06/29/2022
AR 2022-6770 Prioritizing ERO Issues 08/24/2022
AR 2022-6771 Weaknesses in KI documentation and Distribution 08/24/2022
AR 2022-6867 NRC Red Phone Does Not Work 08/29/2022
AR 2023-0298 Command and Control During Beyond-Design-Basis Event 01/11/2023
Miscellaneous Donald C. Cook Nuclear Plant Emergency Plan 47
Donald C. Cook Nuclear Plant Units 1 and 2 Emergency Plan 03/09/2023
Evaluated Exercise Scenario
PMP-2080-EPP- Emergency Response 44
100
PMP-2080-EPP- Emergency Classification 29
101
Procedures PMP-2080-EPP- Initial Dose Assessment 18
108
PMP-2081-EPP- Core Damage Assessment 9
105
RMT-2080-ENC- Activation and Operation of the ENC-JIC 2
001
RMT-2080-EOF- Activation and Operation of the EOF 38
Inspection Type Designation Description or Title Revision or
Procedure Date
001
RMT-2080-FRM- Accountability 1
005
RMT-2080-FRM- Protective Action Recommendations 2
006
RMT-2080-FRM- Instructions for Administration of KI 0
013
RMT-2080-OSC- Activation and Operation of the OSC 25
001
RMT-2080-TSC- Activation and Operation of TSC 28
001
71151 Miscellaneous NRC Performance Indicator Data; Emergency Preparedness 01/01/2022 -
- ERO Drill Participation 12/31/2022
NRC Performance Indicator Data; Emergency Preparedness 01/01/2022 -
- Drill/Exercise Performance 12/31/2022
6