MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20244032024-05-0202 May 2024 Public Lasalle County Station - Security Baseline Inspection Report 05000373/2024403 and 05000374/2024403; NRC Investigation Report No. 3-2023-006 IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 IR 05000373/20234022023-12-20020 December 2023 County Station - Security Baseline Inspection Report 05000373/2023402 and 05000374/2023402 IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 IR 05000373/20224042022-12-21021 December 2022 County Station - Material Control and Accounting Program Inspection Report 05000373/2022404 and 05000374/2022404 IR 05000373/20225012022-12-0505 December 2022 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2022501 and 05000374/2022501 IR 05000373/20224022022-11-17017 November 2022 County Station - Security Baseline Inspection Report 05000373/2022402 and 05000374/2022402 IR 05000373/20220032022-11-0101 November 2022 County Station - Integrated Inspection Report 05000373/2022003 and 05000374/2022003 IR 05000373/20220112022-11-0101 November 2022 County Station Design Basis Assurance Inspection (Teams) Inspection Report 05000373/2022011 and 05000374/2022011 IR 05000373/20224032022-09-15015 September 2022 County Station - Cyber Security Inspection Report 05000373/2022403 and 05000374/2022403 IR 05000373/20220052022-08-22022 August 2022 Updated Inspection Plan for Lasalle County Station (Report 05000373/2022005; 05000374/2022005) IR 05000373/20220022022-08-10010 August 2022 County Station - Integrated Inspection Report 05000373/2022002 and 05000374/2022002 IR 05000373/20224012022-05-18018 May 2022 County Station - Security Baseline Inspection Report 05000373/2022401 and 05000374/2022401 IR 05000373/20220012022-04-26026 April 2022 County Station - Integrated Inspection Report 05000373/2022001 and 05000374/2022001 ML22108A2802022-04-19019 April 2022 Information Request for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000373/2022011 05000374/20220 IR 05000373/20220102022-03-15015 March 2022 County Station License Renewal Phase 2 Report 05000373/2022010 IR 05000373/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000373/2021006 and 05000374/2021006) IR 05000373/20210042022-02-0707 February 2022 County Station Integrated Inspection Report 05000373/2021004 and 05000374/2021004 IR 05000373/20210132022-01-20020 January 2022 County Station Biennial Problem Identification and Resolution Inspection Report 05000373/2021013 and 05000374/2021013 IR 05000373/20214022021-12-15015 December 2021 County Station - Security Baseline Inspection Report 05000373/2021402 and 05000374/2021402 IR 05000373/20210032021-11-0808 November 2021 County Station Integrated Inspection Report 05000373/2021003; 05000374/2021003 and 07200070/2021001 IR 05000373/20210022021-11-0101 November 2021 County Station Integrated Inspection Report 05000373/2021002 and 05000374/2021002 IR 05000373/20210122021-10-28028 October 2021 County Station- 50.59 Team Inspection Report 05000373/2021012 and 05000374/2021012 IR 05000373/20210052021-09-0101 September 2021 Updated Inspection Plan for Lasalle County Station, Units 1 and 2; Report 05000373/2021005 and 05000374/2021005 IR 05000373/20210112021-08-23023 August 2021 County Station - Design Basis Assurance Inspection (Programs) Inspection Report 05000373/2021011 and 05000374/2021011 IR 05000373/20215012021-06-16016 June 2021 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2021501 and 05000374/2021501 IR 05000373/20214012021-05-18018 May 2021 County Station - Security Baseline Inspection Report 05000373/2021401 and 05000374/2021401 IR 05000373/20210012021-05-0404 May 2021 Lssalle County Station - Integrated Inspection Report 05000373/2021001 and 05000374/2021001 IR 05000374/20210102021-04-0505 April 2021 County Station - Post-Approval Site Inspection for License Renewal (Phase I) Report 05000374/2021010 IR 05000373/20200042021-03-0505 March 2021 Reissue - Lasalle County Station - Integrated Inspection Report 05000373/2020004; 05000374/2020004; 05000373/2020501; 05000374/2020501; 05000373/2020011 and 05000374/2020011 2024-09-27
[Table view] Category:Letter
MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2023-001-01, Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate2024-10-0909 October 2024 Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 ML24263A2062024-09-19019 September 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for LaSalle County Station - Holtec MPC-68MCBS ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 05000373/LER-2024-004-01, Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer2024-08-22022 August 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 05000373/LER-2024-003-01, Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-07-31031 July 2024 Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions ML24178A2522024-06-27027 June 2024 County Station – Acknowledgement of Response to NRC Inspection Report 05000373/2024001 and 05000374/2024001 and Disputed Non-Cited Violation 05000373/LER-2024-004, Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer2024-06-19019 June 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations 05000373/LER-2024-003, Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-06-0606 June 2024 Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes 05000373/LER-2024-002, Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip2024-05-17017 May 2024 Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2024-001, Core Operating Limits Report Thermal Limits Exceeded2024-04-26026 April 2024 Core Operating Limits Report Thermal Limits Exceeded ML24108A1562024-04-15015 April 2024 Updated Final Safety Analysis Report (Ufsar), Revision 26 and Fire Protection Report (Fpr), Revision 11 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24071A2122024-03-12012 March 2024 County Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) RS-24-014, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-02-22022 February 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24018A0682024-02-0909 February 2024 Issuance of Amendment Nos. 262 and 247 Revised Design Bases of Lower Downcomer Braces ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums 2024-09-06
[Table view] |
See also: IR 05000373/2018010
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, ILLINOIS 60532-4352
January 11, 2018
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2INFORMATION REQUEST FOR
AN NRC TRIENNIAL 10 CFR 50.59 BASELINE INSPECTION; INSPECTION
REPORT 05000373/2018010; 05000374/2018010
Dear Mr. Hanson:
On April 2, 2018, the U.S. Nuclear Regulatory Commission (NRC) will begin a Title 10 of the
Code of Federal Regulations (CFR), Part 50.59 Baseline Inspection at the LaSalle County
Station, Units 1 and 2. This inspection will be performed in accordance with the NRC Baseline
Inspection Procedure 71111.17T. The onsite portions of the inspection will take place on
April 2-6, 2018.
Experience has shown that these baseline inspections are extremely resource intensive, both
for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the
site and to ensure a productive inspection for both parties, we have enclosed a request for
documents needed for the inspection. These documents have been divided into three groups.
The first group of information is necessary to ensure that the inspection team is
adequately prepared for the inspection. This information should be made available
via compact disc and delivered to the regional office no later than February 16, 2018.
The inspection team will review this information and, by February 23, 2018, will
request specific items that should be provided for review in the regional office by
March 16, 2018.
The second group of requested documents contains additional items that the team will
review, or need access to, during the inspection. Certain documents contained within
Group II (i.e., Item (1)), will be requested for review in the regional office prior to the
inspection by March 16, 2018, as identified above. The remaining documents should be
available by the first day of the onsite inspection, April 2, 2018.
The third group lists information necessary to aid the inspection team in tracking issues
identified as a result of the inspection. It is requested that this information be provided to
the lead inspector as the information is generated during the inspection. It is important
that all of these documents are up to date and complete in order to minimize the number
of additional documents requested during the preparation and/or the onsite portions of
the inspection.
B. Hanson -2-
The lead inspector for this inspection is Mr. Alan Dahbur. We understand that our regulatory
contact for this inspection is Ms. Shakeeta Lickert of your organization. If there are any
questions about the inspection or the material requested, please contact the lead inspector at
630-829-9810 or via e-mail at Alan.Dahbur@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA Atif Shaikh Acting for/
Alan Dahbur, Senior Reactor Inspector
Engineering Branch 3
Division of Reactor Safety
Docket Nos. 50-373; 50-374
License Nos. NPF-11; NPF-18
Enclosure:
Document Request for 10 CFR 50.59 Baseline Inspection
cc: Distribution via LISTSERV
B. Hanson -3-
Letter to Bryan C. Hanson from Alan Dahbur dated January 11, 2018
SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2INFORMATION REQUEST FOR
AN NRC TRIENNIAL 10 CFR 50.59 BASELINE INSPECTION; INSPECTION
REPORT 05000373/2018010; 05000374/2018010
DISTRIBUTION:
Jeremy Bowen
RidsNrrDorlLpl3
RidsNrrPMLaSalle
RidsNrrDirsIrib Resource
Steven West
Darrell Roberts
Richard Skokowski
Allan Barker
Carole Ariano
Linda Linn
DRPIII
DRSIII
ADAMS Accession Number ML18012A585
OFFICE RIII RIII RIII RIII
NAME AShaikh for
ADahbur:cl
DATE 01/11/18
OFFICIAL RECORD COPY
DOCUMENT REQUEST FOR 10 CFR 50.59 BASELINE INSPECTION
Inspection Report: 05000373/2018010; 05000374/2018010
Onsite Inspection Dates: April 2-6, 2018
Inspection Procedures: IP 71111.17T, Evaluations of Changes, Tests and Experiments
IP 71152, Identification and Resolution of Problems
Inspectors: Alan Dahbur
Senior Reactor Inspector (Lead)
630-829-9810
Alan.Dahbur@nrc.gov
Vijay Meghani Lionel Rodriguez
Reactor Inspector Reactor Inspector
630-829-9751 630-829-9609
Vijay.Meghani@nrc.gov Lionel.Rodriguez@nrc.gov
I. Information Requested for In-Office Preparation Week
The following information is requested by February 16, 2018, or sooner, to facilitate the
selection of specific items that will be reviewed during the onsite inspection week. The
inspection team will select specific items from the information requested below and
submit a list to your staff by February 23, 2018. We will request that certain items be
made available to the regional office prior to the inspection by March 16, 2018. We
request that the remaining items selected from the lists be available and ready for review
on the first day of inspection. All requested information should identify the associated
system and cover the time frame from the receipt of information for the last MOD/50.59
inspection to the present.
The required information identified below should be provided on compact disc (CD).
Please provide three copies of each CD submitted (i.e., one for each inspector). The
preferred file format is a searchable pdf file. The CDs should be indexed and
hyper-linked to facilitate ease of use, if possible. If you have any questions regarding
this information, please call the inspection team leader as soon as possible.
1) List of all Title 10 of the Code of Federal Regulations (CFR), Part 50.59
completed evaluations involving: (a) calculations, (b) procedure revisions,
(c) changes to the facility (modifications), (d) non-routine operating
configurations, or (e) departures in methods of analyses. This list should include
50.59 evaluations for the following:
a. Changes that have been made under the provisions of 10 CFR 50.59 that
have been updated in accordance with 10 CFR 50.71(e)(4) since the last
MOD/50.59 inspection;
b. Modifications that are field work complete; and
Enclosure
DOCUMENT REQUEST FOR 10 CFR 50.59 BASELINE INSPECTION
c. Changes to calculations (or initiation of new calculations) that have been
issued. The list should contain the number and title of each document, a brief
description of the change, and the corresponding number and type of the
affected document (i.e., the modification or procedure to which the evaluation
applies). The list should NOT include any evaluations in which prior
U.S. Nuclear Regulatory Commission approval was sought and obtained.
2) A list of all 10 CFR 50.59 changes that have been screened out as not requiring
a full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes
to the facility (modifications); (d) non-routine operating configurations; or
(e) departures in methods of analyses.
The list should contain the number and title of each document, a brief description
of the change, and the corresponding number and type of the affected document
(i.e., the modification or procedure to which the evaluation applies).
3) A list of any modifications, procedure revisions, or UFSAR changes where it was
determined that 10 CFR 50.59 did not apply.
4) A list of calculation changes that have been issued for use.
5) A list of corrective action documents (open and closed) that address
10 CFR 50.59 issues, concerns, or processes. These documents should
also include the associated corrective action documents and the 50.59 change
implementation.
The list should contain the number, title and revision (or date) of each document,
the affected system and corresponding documentation (if applicable), and should
be sorted in order of significance.
6) Copies of procedures addressing the following: modifications, design changes,
set point changes, equivalency evaluations or suitability analyses, commercial
grade dedications, post-modification testing, 10 CFR 50.59 evaluations and
screenings, and UFSAR updates.
7) UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide
copies of the complete submittal.
8) Copy of the UFSAR change log or a synopsis of the changes. This should
include all of the changes made to the UFSAR that were incorporated in the last
10 CFR 50.71(e)(4) submittal.
9) Electronic copy of the UFSAR and Bases, and technical specifications, if
available.
10) Name(s) and phone numbers for the regulatory and technical contacts.
11) Current management and engineering organizational chart.
2
DOCUMENT REQUEST FOR 10 CFR 50.59 BASELINE INSPECTION
II. Information Requested to be Available Prior to Inspection. Requests will be Made
for Specific Item (1) Documents by February 16, 2018, for Availability of Requested
Item (1) Documents in Regional Office by March 16, 2018, and Items (2), (3) and (4)
Documents on First Day of Inspection (April 2, 2018)
1) Copies of all selected items from Section I. This includes copies of associated
documents such as calculations, post-modification test packages, 10 CFR 50.59
evaluations or screenings, and any corrective action documents.
2) Copies of these documents do not need to be solely available to the inspection
team as long as the inspectors have easy and unrestrained access to them.
a. UFSAR, if not previously provided;
b. Original Final Safety Analysis Report Volumes;
c. Original Safety Evaluation Report and Supplements;
d. Final Safety Analysis Report Question and Answers;
e. Quality Assurance Plan;
f. Technical Specifications, if not previously provided;
g. Latest IPE/PRA Report;
h. Vendor Manuals; and
i. The latest 10 CFR 50.59 UFSAR Update Submittal.
3) Please ensure that other supporting documents for the selected items have been
located and are readily retrievable as the inspection team will likely be requesting
these documents during the inspection. Examples of supporting documents are:
a. Drawings supporting the modifications;
b. Procedures affected by the modifications; and
c. UFSAR change papers generated due to a 10 CFR 50.59 evaluation.
4) Assessment and Corrective Actions:
a. The most recent 50.59 Quality Assurance audit and/or self-assessment; and
b. Corrective action documents (e.g., condition reports, including status of
corrective actions) generate as a result of the most recent 50.59 Quality
Assurance audit and/or self-assessment.
3
DOCUMENT REQUEST FOR 10 CFR 50.59 BASELINE INSPECTION
III. Information Requested to be provided throughout the inspection
1) Copies of any corrective action documents generated as a result of the
inspection teams questions or queries during this inspection.
2) Copies of the list of questions submitted by the inspection team members and
the status/resolution of the information requested (provided daily during the
inspection to each inspection team member).
If you have questions regarding the information requested, please contact the lead inspector.
4