ML21165A114: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 1: Line 1:
#REDIRECT [[IR 07200036/2021001]]
{{Adams
| number = ML21165A114
| issue date = 06/14/2021
| title = Operation of an Independent Spent Fuel Storage Installation Report 07200036/2021001
| author name = Desai B
| author affiliation = NRC/RGN-II/DRS/EB3
| addressee name = Gayheart C
| addressee affiliation = Southern Nuclear Operating Co, Inc
| docket = 05000321, 05000366, 07200036
| license number = DPR-057, NPF-005
| contact person =
| document report number = IR 2021001
| document type = Inspection Report, Letter
| page count = 5
}}
See also: [[see also::IR 07200036/2021001]]
 
=Text=
{{#Wiki_filter:June 14, 2021
Ms. Cheryl A. Gayheart
Regulatory Affairs Director
Southern Nuclear Operating Co. Inc.
3535 Colonnade Parkway
Birmingham, AL 35243
SUBJECT: EDWIN I. HATCH NUCLEAR PLANT -- OPERATION OF AN INDEPENDENT
              SPENT FUEL STORAGE INSTALLATION REPORT 07200036/2021001
Dear Ms. Gayheart:
On May 10, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an
inspection at Edwin I. Hatch Nuclear Plant and discussed the results of this inspection with you
and other members of your staff. The results of this inspection are documented in the enclosed
report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
                                          Sincerely,
                                          /RA/
                                          Binoy B. Desai, Chief
                                          Engineering Branch 3
                                          Division of Reactor Safety
Docket No. 07200036
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
 
 
ML21165A114
                              x    Non-Sensitive            x Publicly Available
  x    SUNSI Review
                                  Sensitive                Non-Publicly Available
OFFICE RII/DRS            NMSS/IOB              RII/DRS
NAME    P. Cooper        M. Learn              B. Desai
DATE    6/10/2021        6/10/2021              6/11/2021
                                   
                          U.S. NUCLEAR REGULATORY COMMISSION
                                      Inspection Report
Docket Number:        07200036
License Number:        DPR-57 and NPF-5
Report Number:        07200036/2021001
Enterprise Identifier: I-2021-001-0153
Licensee:              Southern Nuclear Operating Co. Inc.
Facility:              Edwin I. Hatch Nuclear Plant
Location:              Baxley, GA 31513
Inspection Dates:      May 3, 2021 to May 10, 2021
Inspectors:            P. Cooper, Senior Reactor Inspector
                      M. Learn, Transportation and Storage Inspector
Approved By:          Binoy B. Desai, Chief
                      Engineering Branch 3
                      Division of Reactor Safety
                                                                      Enclosure
 
                                            SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting inspections of activities related to Edwin I. Hatch Nuclear Plant
operational activities of dry cask storage of spent fuel from May 3, 2021 to May 10, 2021. The
NRCs program for overseeing the safe operation of dry storage of spent fuel at an Independent
Spent Fuel Storage Installations (ISFSI) is described in Inspection Manual Chapter 2690,
Inspection Program for Dry Storage of Spent Reactor Fuel at Independent Spent Fuel Storage
Installations and for 10 CFR Part 71 Transportation Packagings.
                                  List of Findings and Violations
No findings or violations of more than minor significance were identified.
                                    Additional Tracking Items
None.
                                                2
 
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with
their attached revision histories are located on the public website at http://www.nrc.gov/reading-
rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared
complete when the IP requirements most appropriate to the inspection activity were met
consistent with Inspection Manual Chapter (IMC) 2690, Inspection Program for Storage of
Spent Reactor Fuel and Reactor-Related Greater-than-Class C Waste at Independent Spent
Fuel Storage Installations (ISFSI) and for 10 CFR Part 71 Transportation Packagings."
60855 - OPERATION OF AN INDEPENDENT SPENT FUEL STORAGE INSTALLATION
Operation of an Independent Spent Fuel Storage Installation (1 Sample)
From May 3 through 10, 2021, the inspectors performed a review of the licensees ISFSI
activities to verify compliance with regulatory requirements. During the on-site inspection, the
inspectors observed and reviewed licensee activities in each of the five safety focus areas
including occupational exposure, public exposure, fuel damage, confinement, and impact to
plant operations.
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel to assess licensee performance and compliance with Commission rules and
regulations, license conditions, site procedures, and standards. Additionally, the inspectors
performed independent walkdowns of the heavy load lifting equipment and the ISFSI haul path.
The inspector also performed an independent radiation survey of the ISFSI pad.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On May 10, 2021, the inspectors presented the results to Sonny Dean, Site Vice President and
other members of the licensee staff.
                                                  3
}}

Latest revision as of 14:55, 20 January 2022

Operation of an Independent Spent Fuel Storage Installation Report 07200036/2021001
ML21165A114
Person / Time
Site: Hatch, 07200036  Southern Nuclear icon.png
Issue date: 06/14/2021
From: Binoy Desai
NRC/RGN-II/DRS/EB3
To: Gayheart C
Southern Nuclear Operating Co
References
IR 2021001
Download: ML21165A114 (5)


See also: IR 07200036/2021001

Text

June 14, 2021

Ms. Cheryl A. Gayheart

Regulatory Affairs Director

Southern Nuclear Operating Co. Inc.

3535 Colonnade Parkway

Birmingham, AL 35243

SUBJECT: EDWIN I. HATCH NUCLEAR PLANT -- OPERATION OF AN INDEPENDENT

SPENT FUEL STORAGE INSTALLATION REPORT 07200036/2021001

Dear Ms. Gayheart:

On May 10, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at Edwin I. Hatch Nuclear Plant and discussed the results of this inspection with you

and other members of your staff. The results of this inspection are documented in the enclosed

report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Binoy B. Desai, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 07200036

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML21165A114

x Non-Sensitive x Publicly Available

x SUNSI Review

Sensitive Non-Publicly Available

OFFICE RII/DRS NMSS/IOB RII/DRS

NAME P. Cooper M. Learn B. Desai

DATE 6/10/2021 6/10/2021 6/11/2021

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 07200036

License Number: DPR-57 and NPF-5

Report Number: 07200036/2021001

Enterprise Identifier: I-2021-001-0153

Licensee: Southern Nuclear Operating Co. Inc.

Facility: Edwin I. Hatch Nuclear Plant

Location: Baxley, GA 31513

Inspection Dates: May 3, 2021 to May 10, 2021

Inspectors: P. Cooper, Senior Reactor Inspector

M. Learn, Transportation and Storage Inspector

Approved By: Binoy B. Desai, Chief

Engineering Branch 3

Division of Reactor Safety

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting inspections of activities related to Edwin I. Hatch Nuclear Plant

operational activities of dry cask storage of spent fuel from May 3, 2021 to May 10, 2021. The

NRCs program for overseeing the safe operation of dry storage of spent fuel at an Independent

Spent Fuel Storage Installations (ISFSI) is described in Inspection Manual Chapter 2690,

Inspection Program for Dry Storage of Spent Reactor Fuel at Independent Spent Fuel Storage

Installations and for 10 CFR Part 71 Transportation Packagings.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

2

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2690, Inspection Program for Storage of

Spent Reactor Fuel and Reactor-Related Greater-than-Class C Waste at Independent Spent

Fuel Storage Installations (ISFSI) and for 10 CFR Part 71 Transportation Packagings."

60855 - OPERATION OF AN INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Operation of an Independent Spent Fuel Storage Installation (1 Sample)

From May 3 through 10, 2021, the inspectors performed a review of the licensees ISFSI

activities to verify compliance with regulatory requirements. During the on-site inspection, the

inspectors observed and reviewed licensee activities in each of the five safety focus areas

including occupational exposure, public exposure, fuel damage, confinement, and impact to

plant operations.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel to assess licensee performance and compliance with Commission rules and

regulations, license conditions, site procedures, and standards. Additionally, the inspectors

performed independent walkdowns of the heavy load lifting equipment and the ISFSI haul path.

The inspector also performed an independent radiation survey of the ISFSI pad.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On May 10, 2021, the inspectors presented the results to Sonny Dean, Site Vice President and

other members of the licensee staff.

3