4 OPERATING DATA REPORT | |||
~ | |||
. DOCKET NO. 50 298 DATE nnuarv 4, 1982 COMPLETED BY P_ T.. Mn11inger TELEPHONE 407-825-1811 3 | |||
OPERATING STATUS N ''5' | |||
: 1. Unit Name: cooner Nurlear station | |||
: 2. Reporting Period: | |||
December 1981 2381 | |||
: 3. Licensed Thennal Power (MWt): | |||
836 | |||
: 4. Nameplate Rating (Gross MWe): | |||
778 S. Design Electrical Rating (Net MWe): | |||
: 6. Maxi num Dependable Capacity (Gross MWe): 787 764 | |||
: 7. Maximum Dependable Capacity (Net MWe): | |||
; . 8. If Changes Occur in Capacity Ratings (!tems Number 3 Through 7) Since Last Report. Give Reasons: | |||
{ 9. Power Level To Which Restricted,if Any(Net MWe): Nona | |||
: 10. Reasons For Restrictions. If Any: None This Month Yr..to Date Cumulative 744.0 8,760.0 65,785.0 | |||
: 11. Hours in Reporting Period | |||
: 12. Number Of Hours Reactor Was Critical 744.0 6,297.0 53,886.4 - | |||
: 13. Reactor Reserve Shutdown Hours 0.0 0.0- | |||
* 0.0 | |||
: 14. Hours Generator On.Line 744.0 6,239.7 52,957.5 0.0 0.0 0.0 | |||
: 15. Unit Reserve Shutdown Hours | |||
: 16. Cross Thermal Energy Generated (MWH) 1,744,464.0 13,906,368.0 103,688,478.0 . | |||
, 17. Gross Electrical Energy Generated (MWH) 585.656.0 4.003.773.0 32.480,787.0 | |||
: 18. Net Electrical EnerEy Generated (MWH) 566.202.0 3.851.048.0 31.297,378.0 | |||
: 19. Unit Senice Factor 100.0 71.2 80.5 | |||
: 20. Unit Availability Factor 100.0 71.2 80.5 | |||
: 21. Unit Capacity Factor (Using MDC Net) 99.6 57.5 62.3 | |||
: 22. Unit Capacity Factor (Using DER Net) 97.8 56.5 61.2 | |||
: 23. Unit Forced Outage Rate O_0 2.0 4.0 | |||
: 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each t: | |||
Refuelinc Mey 22, 1982, 4 weeks | |||
: 25. If Shut Down At End Of Report Period. Estimated Date of Startup: | |||
: 26. Units in Test Status (Prior o Commercial Operation): Forecast Achiesed INITIA L CRITICALITY INITIA L ELECTRICITY COMMERCIAL OPERATION . | |||
8211110336 820104 gg , | |||
PDR ADOCK 05000298 PM R _ , _ , _ _ | |||
H 2O. nO14CD c2q m=Ca =Ct2* 2 w ,C*m3 g0wCOdO2m L. | |||
} | |||
7* | |||
C2 H 2>Zm "(O3331 f)e.301 pTDr. | |||
r t | |||
e , | |||
O>wm a 1. ~\ a 1' : s0DJ | |||
' u i5<I OOw.mtmW Cw mM 4' | |||
* 3D1 | |||
?731y31 = a. J 4 3. C ' 1 mm,. oMH gC24 qmF =o2M >ONIONu D | |||
@ww | |||
't 3ro t | |||
n n s- oEt c e l | |||
io )s n ma .. | |||
t.R=g' m4 n$e q = G 5 q= E:.<n e r os d e e op d | |||
: 2. Oi. e. | |||
. p a u t | |||
ot e t . | |||
Wn = tsd o >C3= 0 y r o a e h uR yo mC T uH D( R tehS n xn2:24 Sc o 7a n=" fe.=5=ei r M w C o | |||
D ZOnN vcMrom %a3O1- 't P | |||
M$moMWOo t m | |||
- Ed 2 | |||
gun = . | |||
r 2= =c. -- m:=YE* O . p ~ =Er.;=# | |||
: m. m: e.n - | |||
1 | |||
/. | |||
C. | |||
~ | |||
mn... n"==.a C | |||
?m=.= m5n= mu=C n mu' .=., | |||
- Ku=ce. m4 S " u F 5 :' Ou~u | |||
: ?u~= 2G=nq C. d0-3 : yIu= ce. mOu 5' m=:M Mgn~ .~" fen =$S | |||
* y>=e==".n mn u5 m<S1 %n' 5 ~' 3 mk _ E %" 7* | |||
O %n ~'C: n.5''" | |||
p7nse=" m Mn 0E= =. | |||
*- C=g m!.j e2 .. | |||
o O~ | |||
e . | |||
m Cmn u ; d e. .3.=" > r.3 s 9:,u E=u= 5 n | |||
- >c. ===* | |||
*a 9o n,uc. | |||
m u E0 C= | |||
u s: ; ...... x ,~ =- | |||
m e=@% ~ * [5.' a@==e.#" | |||
= a =n. | |||
~ | |||
dau ~ | |||
mx Lu*= ~ | |||
i | |||
? ,,.. 1s AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-298. | |||
UNIT Cooper Nuclear Station DATE .Tanuarv 4. 1982 COMPLETED BY P. L. En11inger TELEPHONE 402-825-3811 MONTH December DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) | |||
. I 779 17 779 2 | |||
777 gg 777 3 777 39 773 4 777 20 731 5 | |||
776 21 775 6 740 22 776 7 777 23 768 3 777 24 676 I | |||
9 775 25 702 ~ | |||
10 780 26 721 11 780 27 734 780 ;g 776 12 13 736 29 774 14 780 30 774 15 /80 33 761 16 780 . | |||
INSTRUCTIONS 1 | |||
On this format. list the average daily unit power level in MWe. Net for each day in the reporting month. Compute to the nearest whole megawatt. | |||
(9/77) | |||
- A OPERATIONS NARRATIVE Cooper Nuclear Station - | |||
December 1981 Operated the month of December at a capacity factor of 97.8%. There were no scheduled or unscheduled power reductions or shutdowns during the month. A Refueling and Maintenance Outage is tentatively scheduled for May 22, 1982. | |||
6 0 | |||
'S}} |
Latest revision as of 16:39, 21 December 2020
ML20066D434 | |
Person / Time | |
---|---|
Site: | Cooper |
Issue date: | 01/04/1982 |
From: | Ballinger P NEBRASKA PUBLIC POWER DISTRICT |
To: | |
Shared Package | |
ML20066D424 | List: |
References | |
NUDOCS 8211110336 | |
Download: ML20066D434 (4) | |
Text
'
. j o, ..~.
4 OPERATING DATA REPORT
~
. DOCKET NO. 50 298 DATE nnuarv 4, 1982 COMPLETED BY P_ T.. Mn11inger TELEPHONE 407-825-1811 3
OPERATING STATUS N 5'
- 1. Unit Name: cooner Nurlear station
- 2. Reporting Period:
December 1981 2381
- 3. Licensed Thennal Power (MWt):
836
- 4. Nameplate Rating (Gross MWe):
778 S. Design Electrical Rating (Net MWe):
- 6. Maxi num Dependable Capacity (Gross MWe): 787 764
- 7. Maximum Dependable Capacity (Net MWe):
- . 8. If Changes Occur in Capacity Ratings (!tems Number 3 Through 7) Since Last Report. Give Reasons
{ 9. Power Level To Which Restricted,if Any(Net MWe): Nona
- 10. Reasons For Restrictions. If Any: None This Month Yr..to Date Cumulative 744.0 8,760.0 65,785.0
- 11. Hours in Reporting Period
- 12. Number Of Hours Reactor Was Critical 744.0 6,297.0 53,886.4 -
- 13. Reactor Reserve Shutdown Hours 0.0 0.0-
- 0.0
- 14. Hours Generator On.Line 744.0 6,239.7 52,957.5 0.0 0.0 0.0
- 15. Unit Reserve Shutdown Hours
- 16. Cross Thermal Energy Generated (MWH) 1,744,464.0 13,906,368.0 103,688,478.0 .
, 17. Gross Electrical Energy Generated (MWH) 585.656.0 4.003.773.0 32.480,787.0
- 18. Net Electrical EnerEy Generated (MWH) 566.202.0 3.851.048.0 31.297,378.0
- 19. Unit Senice Factor 100.0 71.2 80.5
- 20. Unit Availability Factor 100.0 71.2 80.5
- 21. Unit Capacity Factor (Using MDC Net) 99.6 57.5 62.3
- 22. Unit Capacity Factor (Using DER Net) 97.8 56.5 61.2
- 23. Unit Forced Outage Rate O_0 2.0 4.0
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each t:
Refuelinc Mey 22, 1982, 4 weeks
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status (Prior o Commercial Operation): Forecast Achiesed INITIA L CRITICALITY INITIA L ELECTRICITY COMMERCIAL OPERATION .
8211110336 820104 gg ,
PDR ADOCK 05000298 PM R _ , _ , _ _
H 2O. nO14CD c2q m=Ca =Ct2* 2 w ,C*m3 g0wCOdO2m L.
}
7*
C2 H 2>Zm "(O3331 f)e.301 pTDr.
r t
e ,
O>wm a 1. ~\ a 1' : s0DJ
' u i5ONIONu D
@ww
't 3ro t
n n s- oEt c e l
io )s n ma ..
t.R=g' m4 n$e q = G 5 q= E:.<n e r os d e e op d
- 2. Oi. e.
. p a u t
ot e t .
Wn = tsd o >C3= 0 y r o a e h uR yo mC T uH D( R tehS n xn2:24 Sc o 7a n=" fe.=5=ei r M w C o
D ZOnN vcMrom %a3O1- 't P
M$moMWOo t m
- Ed 2
gun = .
r 2= =c. -- m:=YE* O . p ~ =Er.;=#
- m. m: e.n -
1
/.
C.
~
mn... n"==.a C
?m=.= m5n= mu=C n mu' .=.,
- Ku=ce. m4 S " u F 5 :' Ou~u
- ?u~= 2G=nq C. d0-3 : yIu= ce. mOu 5' m=:M Mgn~ .~" fen =$S
- y>=e==".n mn u5 m<S1 %n' 5 ~' 3 mk _ E %" 7*
O %n ~'C: n.5"
p7nse=" m Mn 0E= =.
- - C=g m!.j e2 ..
o O~
e .
m Cmn u ; d e. .3.=" > r.3 s 9:,u E=u= 5 n
- >c. ===*
- a 9o n,uc.
m u E0 C=
u s: ; ...... x ,~ =-
m e=@% ~ * [5.' a@==e.#"
= a =n.
~
dau ~
mx Lu*= ~
i
? ,,.. 1s AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-298.
UNIT Cooper Nuclear Station DATE .Tanuarv 4. 1982 COMPLETED BY P. L. En11inger TELEPHONE 402-825-3811 MONTH December DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net)
. I 779 17 779 2
777 gg 777 3 777 39 773 4 777 20 731 5
776 21 775 6 740 22 776 7 777 23 768 3 777 24 676 I
9 775 25 702 ~
10 780 26 721 11 780 27 734 780 ;g 776 12 13 736 29 774 14 780 30 774 15 /80 33 761 16 780 .
INSTRUCTIONS 1
On this format. list the average daily unit power level in MWe. Net for each day in the reporting month. Compute to the nearest whole megawatt.
(9/77)
- A OPERATIONS NARRATIVE Cooper Nuclear Station -
December 1981 Operated the month of December at a capacity factor of 97.8%. There were no scheduled or unscheduled power reductions or shutdowns during the month. A Refueling and Maintenance Outage is tentatively scheduled for May 22, 1982.