| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 4, 2009 | | {{#Wiki_filter:UNITED STATES rch 4, 2009 |
|
| |
|
| Mr. Timothy Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362-9637
| | ==SUBJECT:== |
| | ANNUAL ASSESSMENT LETTER - MONTICELLO NUCLEAR GENERATING PLANT (05000263/2009001) |
|
| |
|
| SUBJECT: ANNUAL ASSESSMENT LETTER - MONTICELLO NUCLEAR GENERATING PLANT (05000263/2009001)
| | ==Dear Mr. OConnor:== |
| | On February 11, 2009, the NRC staff completed its performance review of Monticello Nuclear Generating Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2008. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility. |
|
| |
|
| ==Dear Mr. O'Connor:==
| | This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the Security Cornerstone review and resultant inspection plan. |
| On February 11, 2009, the NRC staff completed its performance review of Monticello Nuclear Generating Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2008. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the Security Cornerstone review and resultant inspection plan. Overall, Monticello Nuclear Generating Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. The staff identified that there were two areas in which there were more than three green inspection findings for the current 12-mont h assessment period, both with documented human performance (HP) cross-cutting aspects. The first group of findings had a cross-cutting theme in the aspect associated with oversight of work practices [H.4(c)]. The second group of findings had a cross-cutting theme in the aspect associated with correct and accurate procedures [H.2(c)]. The findings involved the Initiating Events, Mitigating Systems, and Barrier Integrity cornerstones. There were 19 findings documented with cross-cutting aspects in the HP area.
| |
|
| |
|
| In evaluating the licensee's scope of efforts and progress in addressing these cross-cutting themes, the staff determined that the licensee has not yet resolved the issues associated with these cross-cutting area performance deficiencies. Because of the decline in the area of HP, the NRC has concluded that a substantive cross-cu tting issue exists in th is area. Therefore, a new substantive cross-cutting issue with a theme in the aspect of [H.2(c)] and with a theme of [H.4(C)] will be opened. This substantive cross-cutting issue will remain open until the NRC gains confidence in your efforts and progress in addressing this issue. The enclosed inspection plan details the inspections, including baseline and other infrequently conducted inspections, less those related to security, scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
| | Overall, Monticello Nuclear Generating Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. |
|
| |
|
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
| | The staff identified that there were two areas in which there were more than three green inspection findings for the current 12-month assessment period, both with documented human performance (HP) cross-cutting aspects. The first group of findings had a cross-cutting theme in the aspect associated with oversight of work practices [H.4(c)]. The second group of findings had a cross-cutting theme in the aspect associated with correct and accurate procedures |
| | [H.2(c)]. The findings involved the Initiating Events, Mitigating Systems, and Barrier Integrity cornerstones. There were 19 findings documented with cross-cutting aspects in the HP area. |
|
| |
|
| enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Kenneth Riemer at 630-829-9628 with any questions you may have regarding this letter or the inspection plan. | | In evaluating the licensees scope of efforts and progress in addressing these cross-cutting themes, the staff determined that the licensee has not yet resolved the issues associated with these cross-cutting area performance deficiencies. Because of the decline in the area of HP, the NRC has concluded that a substantive cross-cutting issue exists in this area. Therefore, a new substantive cross-cutting issue with a theme in the aspect of [H.2(c)] and with a theme of |
| | [H.4(C)] will be opened. This substantive cross-cutting issue will remain open until the NRC gains confidence in your efforts and progress in addressing this issue. The enclosed inspection plan details the inspections, including baseline and other infrequently conducted inspections, less those related to security, scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review. |
| | |
| | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| | |
| | If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Kenneth Riemer at 630-829-9628 with any questions you may have regarding this letter or the inspection plan. |
|
| |
|
| Sincerely, | | Sincerely, |
| /RA/ | | /RA/ |
| Cynthia D. Pederson, Director | | Cynthia D. Pederson, Director Division of Reactor Projects Docket No. 50-263 License No. DPR-22 Enclosure: Monticello Inspection/Activity Plan cc w/encl: D. Koehl, Chief Nuclear Officer Manager, Nuclear Safety Assessment P. Glass, Assistant General Counsel Nuclear Asset Manager, Xcel Energy, Inc. |
| | |
| Division of Reactor Projects Docket No. 50-263 License No. DPR-22 | |
| | |
| Enclosure: Monticello Inspection/Activity Plan cc w/encl: D. Koehl, Chief Nuclear Officer Manager, Nuclear Safety Assessment P. Glass, Assistant General Counsel Nuclear Asset Manager, Xcel Energy, Inc. | |
|
| |
|
| J. Stine, State Liaison Officer, Minnesota Department of Health R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA) | | J. Stine, State Liaison Officer, Minnesota Department of Health R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA) |
| Commissioner, Minnesota Pollution Control Agency R. Hiivala, Auditor/Treasurer, Wright County Government Center Commissioner, Minnesota Department of Commerce Manager - Environmental Protection Division Minnesota Attorney General's Office Chairman, Wright County Board Mayor of Monticello Chairperson, Sherburne County Administrator, City of Monticello G. Mortensen, INPO Inspection / Activity Plan Page 1 of 2 02/25/2009 Report 22 03/01/2009-06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Monticello OL EXAM-MONTICELLO INITIAL LICENSE EXAMINATION 3 1 OL - INITIAL EXAM - JAN 2009 - MONT W90198 02/23/2009 03/06/2009 RENEWAL-POST-APPROVAL SITE INSP. FOR LR 4 1 IP Post-Approval Site Inspection for License Renewal 71003 03/23/2009 04/03/2009 BI ENG-ENGINEERING INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - BWR 7111108G 03/23/2009 04/03/2009 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP A ccess Control to Radiologically Significant Areas 7112101 04/13/2009 04/17/2009 1 IP A LARA Planning and Controls 7112102 04/13/2009 04/17/2009 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 05/18/2009 05/22/2009 1 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 7112203 05/18/2009 05/22/2009 1 IP RETS/ODCM Radiological Effluent 71151-PR01 05/18/2009 05/22/2009 PWR UPR-EROSION/CORROSION PORTION OF IP 71004 1 1 IP Inservice Inspection Activities - BWR 7111108G 06/22/2009 06/26/2009 BI EP-EP EXERCISE INSPECTION / PI VERIFICATION 4 1 IP Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 2515/175 08/17/2009 08/21/2009 1 IP Exercise Evaluation 7111401 08/17/2009 08/21/2009 1 IP Drill/Exercise Performance 71151-EP01 08/17/2009 08/21/2009 1 IP ERO Drill Participation 71151-EP02 08/17/2009 08/21/2009 1 IP A lert & Notification System 71151-EP03 08/17/2009 08/21/2009 BI ENG-COMPONENT DESIGN BASES INSPECTION 6 1 IP Component Design Bases Inspection 7111121 08/31/2009 10/02/2009 BI OL-LIC. OPERATOR REQUAL. PROGRAM EVALUATION 2 1 IP Licensed Operator Requalification Program 7111111B 09/28/2009 10/02/2009 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 10/19/2009 10/23/2009 1 IP Reactor Coolant System Activity 71151-BI01 10/19/2009 10/23/2009 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP A ccess Control to Radiologically Significant Areas 7112101 12/14/2009 12/18/2009 1 IP A LARA Planning and Controls 7112102 12/14/2009 12/18/2009 1 IP Occupational Exposure Control Effectiveness 71151-OR01 12/14/2009 12/18/2009 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP A ccess Control to Radiologically Significant Areas 7112101 01/04/2010 01/08/2010 1 IP A LARA Planning and Controls 7112102 01/04/2010 01/08/2010 This report does not include INPO and OUTAGE activities. | | Commissioner, Minnesota Pollution Control Agency R. Hiivala, Auditor/Treasurer, Wright County Government Center Commissioner, Minnesota Department of Commerce Manager - Environmental Protection Division Minnesota Attorney Generals Office Chairman, Wright County Board Mayor of Monticello Chairperson, Sherburne County Administrator, City of Monticello G. Mortensen, INPO |
| | |
| This report shows only on-site and announced inspection procedures.
| |
|
| |
|
| Inspection / Activity Plan Page 2 of 2 02/25/2009 Report 22 03/01/2009-06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Monticello BI ENG-HEAD DROP ANALYSES 1 1 IP Refueling and Other Outage Activities 7111120 01/25/2010 02/12/2010 BI ENG-ENGINEERING MODIFICATIONS / 50.59 3 1 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 03/08/2010 03/26/2010 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 7112201 03/15/2010 03/19/2010 1 IP Reactor Coolant System Activity 71151-BI01 03/15/2010 03/19/2010 1 IP RETS/ODCM Radiological Effluent 71151-PR01 03/15/2010 03/19/2010 BI ENG-TRIENNIAL HEAT SINK INSPECTION 1 1 IP Heat Sink Performance 7111107T 04/12/2010 04/16/2010 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radioactive Material Processing and Transportation 7112202 05/24/2010 05/28/2010 RENEWAL-LICENSE RENEWAL PHASE 2 2 1 IP Post-Approval Site Inspection for License Renewal 71003 06/14/2010 07/02/2010 BI EP-EP ROUTINE INSPECTION / PI VERIFICATION 1 1 IP A lert and Notification System Testing 7111402 06/28/2010 07/02/2010 1 IP Emergency Response Organization Augmentation Testing 7111403 06/28/2010 07/02/2010 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 06/28/2010 07/02/2010 1 IP Drill/Exercise Performance 71151-EP01 06/28/2010 07/02/2010 1 IP ERO Drill Participation 71151-EP02 06/28/2010 07/02/2010 1 IP A lert & Notification System 71151-EP03 06/28/2010 07/02/2010 This report does not include INPO and OUTAGE activities. | | Monticello Inspection / Activity Plan 03/01/2009 - 06/30/2010 Planned Dates No. of Staff Start End Inspection Activity Title on Site OL EXAM - MONTICELLO INITIAL LICENSE EXAMINATION 3 2/23/2009 03/06/2009 W90198 OL - INITIAL EXAM - JAN 2009 - MONT RENEWAL - POST-APPROVAL SITE INSP. FOR LR 4 3/23/2009 04/03/2009 IP 71003 Post-Approval Site Inspection for License Renewal BI ENG - ENGINEERING INSERVICE INSPECTION 1 3/23/2009 04/03/2009 IP 7111108G Inservice Inspection Activities - BWR BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 4/13/2009 04/17/2009 IP 7112101 Access Control to Radiologically Significant Areas 4/13/2009 04/17/2009 IP 7112102 ALARA Planning and Controls BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 5/18/2009 05/22/2009 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 5/18/2009 05/22/2009 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 5/18/2009 05/22/2009 IP 71151-PR01 RETS/ODCM Radiological Effluent PWR UPR - EROSION/CORROSION PORTION OF IP 71004 1 6/22/2009 06/26/2009 IP 7111108G Inservice Inspection Activities - BWR BI EP - EP EXERCISE INSPECTION / PI VERIFICATION 4 8/17/2009 08/21/2009 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 8/17/2009 08/21/2009 IP 7111401 Exercise Evaluation 8/17/2009 08/21/2009 IP 71151-EP01 Drill/Exercise Performance 8/17/2009 08/21/2009 IP 71151-EP02 ERO Drill Participation 8/17/2009 08/21/2009 IP 71151-EP03 Alert & Notification System BI ENG - COMPONENT DESIGN BASES INSPECTION 6 8/31/2009 10/02/2009 IP 7111121 Component Design Bases Inspection BI OL - LIC. OPERATOR REQUAL. PROGRAM EVALUATION 2 9/28/2009 10/02/2009 IP 7111111B Licensed Operator Requalification Program BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 0/19/2009 10/23/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 0/19/2009 10/23/2009 IP 71151-BI01 Reactor Coolant System Activity BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2/14/2009 12/18/2009 IP 7112101 Access Control to Radiologically Significant Areas 2/14/2009 12/18/2009 IP 7112102 ALARA Planning and Controls 2/14/2009 12/18/2009 IP 71151-OR01 Occupational Exposure Control Effectiveness BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1/04/2010 01/08/2010 IP 7112101 Access Control to Radiologically Significant Areas 1/04/2010 01/08/2010 IP 7112102 ALARA Planning and Controls |
|
| |
|
| This report shows only on-site and announced inspection procedures.
| | Monticello Inspection / Activity Plan 03/01/2009 - 06/30/2010 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI ENG - HEAD DROP ANALYSES 1 1/25/2010 02/12/2010 IP 7111120 Refueling and Other Outage Activities BI ENG - ENGINEERING MODIFICATIONS / 50.59 3 3/08/2010 03/26/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 3/15/2010 03/19/2010 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 3/15/2010 03/19/2010 IP 71151-BI01 Reactor Coolant System Activity 3/15/2010 03/19/2010 IP 71151-PR01 RETS/ODCM Radiological Effluent BI ENG - TRIENNIAL HEAT SINK INSPECTION 1 4/12/2010 04/16/2010 IP 7111107T Heat Sink Performance BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 5/24/2010 05/28/2010 IP 7112202 Radioactive Material Processing and Transportation RENEWAL - LICENSE RENEWAL PHASE 2 2 6/14/2010 07/02/2010 IP 71003 Post-Approval Site Inspection for License Renewal BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 1 6/28/2010 07/02/2010 IP 7111402 Alert and Notification System Testing 6/28/2010 07/02/2010 IP 7111403 Emergency Response Organization Augmentation Testing 6/28/2010 07/02/2010 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 6/28/2010 07/02/2010 IP 71151-EP01 Drill/Exercise Performance 6/28/2010 07/02/2010 IP 71151-EP02 ERO Drill Participation 6/28/2010 07/02/2010 IP 71151-EP03 Alert & Notification System |
| }} | | }} |
|
---|
Category:Inspection Plan
MONTHYEARIR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) IR 05000263/20230062024-02-28028 February 2024 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2023006) IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) IR 05000263/20220062023-03-0101 March 2023 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2022006) ML23058A1522023-02-27027 February 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2023002 IR 05000263/20220052022-08-29029 August 2022 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2022005) IR 05000263/20210062022-03-0202 March 2022 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2021006) ML21322A2362021-11-18018 November 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2022401 IR 05000263/20210052021-09-0101 September 2021 Updated Inspection Plan for Monticello Nuclear Generating Plant 2 (Report 05000263/2021005) ML21215A2172021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21147A5082021-06-0303 June 2021 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21099A0902021-04-0808 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000263/2021011 ML21085A8582021-03-26026 March 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000263/2021010 IR 05000263/20200062021-03-0404 March 2021 Annual Assessment Letter for the Monticello Nuclear Generating Plant (Report 05000263/2020006) ML21029A2982021-01-29029 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2021002 ML20275A3942020-10-0101 October 2020 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at the Monticello Nuclear Generating Plant IR 05000263/20200052020-09-0101 September 2020 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2020005) ML20134H9282020-05-12012 May 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000263/2020013 IR 05000263/20190062020-03-0303 March 2020 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2019006 and 07200058/2019006) ML19324F8512019-11-20020 November 2019 Long-Term Replacement Steam Dryer Inspection Plan ML19322C0512019-11-14014 November 2019 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000263/2020011 IR 05000263/20190052019-08-28028 August 2019 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2019005) ML19136A0202019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19065A0832019-03-0505 March 2019 Ltr. 03/05/19 Monticello Nuclear Generating Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2019002 (DRS-E.Fernandez) IR 05000263/20180062019-03-0404 March 2019 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2018006 and 07200058/2018006) IR 05000263/20180052018-08-28028 August 2018 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2018005) IR 05000263/20170062018-03-0202 March 2018 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2017006) ML17345A8402017-12-11011 December 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Monticello Nuclear Generating Plant IR 05000263/20170052017-08-28028 August 2017 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2017005) ML17159A6992017-06-0808 June 2017 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2017409 ML17094A4352017-04-0303 April 2017 Monticello - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000263/20160062017-03-0101 March 2017 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016006) ML17026A4302017-01-26026 January 2017 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000263/2017007 IR 05000263/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016005) IR 05000263/20150062016-03-0202 March 2016 Annual Assessment Letter for Monticello Nuclear Generating Plant (Inspection Report 05000263/2015006) ML16041A0482016-02-0909 February 2016 Ltr. 02/09/16 Monticello Nuclear Generating Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000263/2016002 IR 05000263/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2015005) IR 05000263/20140012015-03-0404 March 2015 Annual Assessment Letter for the Monticello Nuclear Generating Plant, (Report 05000263/2014001) ML15027A0412015-01-26026 January 2015 ISI Request for Information ML14245A1442014-09-0202 September 2014 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant ML14216A5132014-08-0404 August 2014 Information Request to Support Upcoming Biennial Problem Identification and Resolution Inspection at the Monticello Nuclear Generating Plant IR 05000263/20130012014-03-0404 March 2014 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2013001) ML13246A2312013-09-0303 September 2013 2013 Monticello MOC Letter Combined ML13221A5712013-08-0909 August 2013 Ltr 8/9/13 Monticello MOD 50.59 Request for Information IR 05000263/20120012013-03-0404 March 2013 Annual Assessment Letter for Monticello Nuclear Generating Plant, (Report 05000263-12-001) ML12249A4222012-09-0404 September 2012 Mid-Cycle Assessment Letter for Monticello Generating Plant IR 05000263/20110072012-03-0505 March 2012 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2011007) IR 05000263/20110062011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plant for Monticello Nuclear Plant 05000263-11-006 IR 05000263/20110012011-03-0404 March 2011 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263-11-001) ML1104705722011-02-16016 February 2011 Request Notification of NRC Inspection and Request for Information ISI 2024-08-30
[Table view] Category:Letter
MONTHYEARML24283A1192024-10-28028 October 2024 Letter to Shawn Hafen, Re Monticello Subsequent License Renewal Schedule Change L-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 ML24199A1752024-10-0101 October 2024 Issuance of Amendment No. 212 Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 IR 05000263/20244012024-05-30030 May 2024 Public - Monticello Nuclear Generating Plant - Cyber Security Inspection Report 05000263/2024401 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin ML24115A2902024-04-25025 April 2024 Sec106 Tribal, Jackson-Street, Lonna-Spirit Lake Nation ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A2992024-04-25025 April 2024 Sec106 Tribal, Renville, J. Garret-Sisseton Wahpeton Oyate of the Lake Travers Reservation ML24115A2932024-04-25025 April 2024 Sec106 Tribal, Johnson, Grant-Prairie Island Indian Community ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa ML24115A3002024-04-25025 April 2024 Sec106 Tribal, Rhodd, Timothy-Iowa Tribe of Kansas and Nebraska ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe 05000263/LER-2024-001, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A2942024-04-25025 April 2024 Sec106 Tribal, Johnson, John-Lac Du Flambeau Band of Lake Superior Chippewa Indians 2024-09-26
[Table view] |
Text
UNITED STATES rch 4, 2009
SUBJECT:
ANNUAL ASSESSMENT LETTER - MONTICELLO NUCLEAR GENERATING PLANT (05000263/2009001)
Dear Mr. OConnor:
On February 11, 2009, the NRC staff completed its performance review of Monticello Nuclear Generating Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2008. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the Security Cornerstone review and resultant inspection plan.
Overall, Monticello Nuclear Generating Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The staff identified that there were two areas in which there were more than three green inspection findings for the current 12-month assessment period, both with documented human performance (HP) cross-cutting aspects. The first group of findings had a cross-cutting theme in the aspect associated with oversight of work practices H.4(c). The second group of findings had a cross-cutting theme in the aspect associated with correct and accurate procedures
H.2(c). The findings involved the Initiating Events, Mitigating Systems, and Barrier Integrity cornerstones. There were 19 findings documented with cross-cutting aspects in the HP area.
In evaluating the licensees scope of efforts and progress in addressing these cross-cutting themes, the staff determined that the licensee has not yet resolved the issues associated with these cross-cutting area performance deficiencies. Because of the decline in the area of HP, the NRC has concluded that a substantive cross-cutting issue exists in this area. Therefore, a new substantive cross-cutting issue with a theme in the aspect of H.2(c) and with a theme of
[H.4(C)] will be opened. This substantive cross-cutting issue will remain open until the NRC gains confidence in your efforts and progress in addressing this issue. The enclosed inspection plan details the inspections, including baseline and other infrequently conducted inspections, less those related to security, scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Kenneth Riemer at 630-829-9628 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Cynthia D. Pederson, Director Division of Reactor Projects Docket No. 50-263 License No. DPR-22 Enclosure: Monticello Inspection/Activity Plan cc w/encl: D. Koehl, Chief Nuclear Officer Manager, Nuclear Safety Assessment P. Glass, Assistant General Counsel Nuclear Asset Manager, Xcel Energy, Inc.
J. Stine, State Liaison Officer, Minnesota Department of Health R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA)
Commissioner, Minnesota Pollution Control Agency R. Hiivala, Auditor/Treasurer, Wright County Government Center Commissioner, Minnesota Department of Commerce Manager - Environmental Protection Division Minnesota Attorney Generals Office Chairman, Wright County Board Mayor of Monticello Chairperson, Sherburne County Administrator, City of Monticello G. Mortensen, INPO
Monticello Inspection / Activity Plan 03/01/2009 - 06/30/2010 Planned Dates No. of Staff Start End Inspection Activity Title on Site OL EXAM - MONTICELLO INITIAL LICENSE EXAMINATION 3 2/23/2009 03/06/2009 W90198 OL - INITIAL EXAM - JAN 2009 - MONT RENEWAL - POST-APPROVAL SITE INSP. FOR LR 4 3/23/2009 04/03/2009 IP 71003 Post-Approval Site Inspection for License Renewal BI ENG - ENGINEERING INSERVICE INSPECTION 1 3/23/2009 04/03/2009 IP 7111108G Inservice Inspection Activities - BWR BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 4/13/2009 04/17/2009 IP 7112101 Access Control to Radiologically Significant Areas 4/13/2009 04/17/2009 IP 7112102 ALARA Planning and Controls BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 5/18/2009 05/22/2009 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 5/18/2009 05/22/2009 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 5/18/2009 05/22/2009 IP 71151-PR01 RETS/ODCM Radiological Effluent PWR UPR - EROSION/CORROSION PORTION OF IP 71004 1 6/22/2009 06/26/2009 IP 7111108G Inservice Inspection Activities - BWR BI EP - EP EXERCISE INSPECTION / PI VERIFICATION 4 8/17/2009 08/21/2009 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 8/17/2009 08/21/2009 IP 7111401 Exercise Evaluation 8/17/2009 08/21/2009 IP 71151-EP01 Drill/Exercise Performance 8/17/2009 08/21/2009 IP 71151-EP02 ERO Drill Participation 8/17/2009 08/21/2009 IP 71151-EP03 Alert & Notification System BI ENG - COMPONENT DESIGN BASES INSPECTION 6 8/31/2009 10/02/2009 IP 7111121 Component Design Bases Inspection BI OL - LIC. OPERATOR REQUAL. PROGRAM EVALUATION 2 9/28/2009 10/02/2009 IP 7111111B Licensed Operator Requalification Program BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 0/19/2009 10/23/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 0/19/2009 10/23/2009 IP 71151-BI01 Reactor Coolant System Activity BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2/14/2009 12/18/2009 IP 7112101 Access Control to Radiologically Significant Areas 2/14/2009 12/18/2009 IP 7112102 ALARA Planning and Controls 2/14/2009 12/18/2009 IP 71151-OR01 Occupational Exposure Control Effectiveness BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1/04/2010 01/08/2010 IP 7112101 Access Control to Radiologically Significant Areas 1/04/2010 01/08/2010 IP 7112102 ALARA Planning and Controls
Monticello Inspection / Activity Plan 03/01/2009 - 06/30/2010 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI ENG - HEAD DROP ANALYSES 1 1/25/2010 02/12/2010 IP 7111120 Refueling and Other Outage Activities BI ENG - ENGINEERING MODIFICATIONS / 50.59 3 3/08/2010 03/26/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 3/15/2010 03/19/2010 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 3/15/2010 03/19/2010 IP 71151-BI01 Reactor Coolant System Activity 3/15/2010 03/19/2010 IP 71151-PR01 RETS/ODCM Radiological Effluent BI ENG - TRIENNIAL HEAT SINK INSPECTION 1 4/12/2010 04/16/2010 IP 7111107T Heat Sink Performance BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 5/24/2010 05/28/2010 IP 7112202 Radioactive Material Processing and Transportation RENEWAL - LICENSE RENEWAL PHASE 2 2 6/14/2010 07/02/2010 IP 71003 Post-Approval Site Inspection for License Renewal BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 1 6/28/2010 07/02/2010 IP 7111402 Alert and Notification System Testing 6/28/2010 07/02/2010 IP 7111403 Emergency Response Organization Augmentation Testing 6/28/2010 07/02/2010 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 6/28/2010 07/02/2010 IP 71151-EP01 Drill/Exercise Performance 6/28/2010 07/02/2010 IP 71151-EP02 ERO Drill Participation 6/28/2010 07/02/2010 IP 71151-EP03 Alert & Notification System