{{#Wiki_filter: UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA  30303-1257  May 4, 2011  Mr. T. Preston Gillespie, Jr. Site Vice President
[[Issue date::May 4, 2011]]
Duke Energy Carolinas, LLC
Oconee Nuclear Station
7800 Rochester Highway
Seneca, SC 29672
SUBJECT: NOTIFICATION OCONEE NUCLEAR PLANT - COMPONENT DESIGN BASES INSPECTION - NRC INSPECTION REPORT 05000269,270,287/2011010  Dear Mr. Gillespie:  The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a component design bases inspection at your Oconee Nuclear Power Plant reactor facility during the period of August 15 - September 30, 2011.  The inspection team will be led by Mr. Patrick Higgins, a Senior Reactor Inspector from the NRC's Region II Office.  This inspection will be conducted in accordance with the baseline inspection procedure, Procedure 71111.21, Component Design Bases Inspection, issued August 19, 2008.
The inspection will evaluate the capability of risk significant / low margin components to function as designed and to support proper system operation.  The inspection will also include a review of selected operator actions, operating experience, and modifications. 
During a discussion on April 26, 2011, Mr. Higgins confirmed, with Ms. Judy Smith of your staff,
arrangements for an information gathering site visit and the three-week onsite inspection. The
schedule is as follows:
* Information gathering visit:  July 11 - July 15, 2011 * Week 1 of onsite inspection: August 29 - September 2, 2011 * Week 2 of onsite inspection:  September 12 - September 16, 2011 * Week 3 of onsite inspection:  September 26 - September 30, 2011 
The purpose of the information gathering visit is to meet with members of your staff to identify
risk-significant components and operator actions.  Information and documentation needed to
support the inspection will also be identified and gathered or requested.  Mr. Rudolph Bernhard, Region II Senior Reactor Analyst, may accompany Mr. Higgins during the information gathering
visit to review probabilistic risk assessment data and identify risk significant components which will be examined during the inspection. 
 
DEC 2  The enclosure lists documents that will be needed prior to the information gathering visit.  Please contact Mr. Higgins with any questions prior to preparing materials listed in the enclosure and provide the referenced information to the Region II office by June 10, 2011, unless otherwise noted.  The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for the inspection preparation.
During the information gathering visit, the team leader will also discuss the following inspection support administrative details: office space; site, plant and information system access; required
resources; and information exchange protocol.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for
information or an information collection requirement unless the requesting document displays a
currently valid Office of Management and Budget control number.
Thank you for your cooperation in this matter.  If you have any questions regarding the
information requested or the inspection, please contact Mr. Higgins at (404) 997-4615 or me at
(404) 997-4519.
      Sincerely,
      /RA/  Binoy B. Desai, Chief 
Engineering Branch 1
Division of Reactor Safety 
Docket Nos.:  50-269,270,287
License Nos.:  DPR-38,47,55
Enclosure: Information Request for Oconee Nuclear Power Plant Component Design Bases Inspection 
cc w/encl:  (See page 3)
 
DEC 3  cc w/encl: Division of Radiological Health
TN Dept. of Environment & Conservation
401 Church Street
Nashville, TN  37243-1532
David A. Baxter
Vice President, Nuclear Engineering
Duke Energy Carolinas, LLC
Electronic Mail Distribution
Kent Alter
Regulatory Compliance Manager
Oconee Nuclear Station
Duke Energy Carolinas, LLC
Electronic Mail Distribution
Sandra Threatt, Manager
Nuclear Response and Emergency
Environmental Surveillance
Bureau of Land and Waste Management
Department of Health and Environmental 
Control
Electronic Mail Distribution
Scott L. Batson
Station Manager
Oconee Nuclear Station
Duke Energy Carolinas, LLC
Electronic Mail Distribution
Senior Resident Inspector
U.S. Nuclear Regulatory Commission
Oconee Nuclear Station
U.S. Nuclear Regulatory Commission
7812B Rochester Hwy
Seneca, SC  29672
Terry L. Patterson
Safety Assurance Manager
Duke Energy Carolinas, LLC
Electronic Mail Distribution
Charles Brinkman
Director
Washington Operations
Westinghouse Electric Company, LLC
Electronic Mail Distribution
Tom D. Ray Engineering Manager
Oconee Nuclear Station
Duke Energy Carolinas, LLC
Electronic Mail Distribution
County Supervisor of Oconee County
415 S. Pine Street
Walhalla, SC  29691-2145
W. Lee Cox, III
Section Chief
Radiation Protection Section
N.C. Department of Environmental
Commerce & Natural Resources
Electronic Mail Distribution
 
DEC 2  The enclosure lists documents that will be needed prior to the information gathering visit.  Please contact Mr. Higgins with any questions prior to preparing materials listed in the enclosure and provide the referenced information to the Region II office by June 10, 2011, unless otherwise noted.  The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for the inspection preparation.
During the information gathering visit, the team leader will also discuss the following inspection support administrative details: office space; site, plant and information system access; required
resources; and information exchange protocol.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for
information or an information collection requirement unless the requesting document displays a
currently valid Office of Management and Budget control number.
Thank you for your cooperation in this matter.  If you have any questions regarding the
information requested or the inspection, please contact Mr. Higgins at (404) 997-4615 or me at
(404) 997-4519.
      Sincerely,
      /RA/  Binoy B. Desai, Chief 
Engineering Branch 1
Division of Reactor Safety 
Docket Nos.: 50-269,270,287
License Nos.:  DPR-38,47,55
Enclosure: Information Request for Oconee Nuclear Power Plant Component Design Bases Inspection 
cc w/encl:  (See page 3)
X  PUBLICLY AVAILABLE  G  NON-PUBLICLY AVAILABLE  G  SENSITIVE        X  NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:_ML111250617________________________  X  SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS      SIGNATURE RA RA      NAME P. Higgins B. Desai      DATE 5/4/2011 5/4/2011      E-MAIL COPY?    YES      NO      YES      NO      YES        NO      YES        NO      YES        NO      YES      NO      YES        NO    OFFICIAL RECORD COPY          DOCUMENT NAME:  S:\DRS\ENG BRANCH 1\BRANCH INSPECTION FILES\2011-2012-2013 CYCLE EB1 INSPECTION FOLDERS FOR ALL SITES\OCONEE\OCO
CDBI NOTIFICATION 2011 (SAW).DOC 
  Letter to Preston Gillespie from Binoy Desai dated May 4, 2011
SUBJECT: NOTIFICATION OF OCONEE NUCLEAR POWER PLANT - COMPONENT  DESIGN BASES INSPECTION - NRC INSPECTION REPORT
05000269,270,287/2011010 
Distribution w/encl: RIDSNRRDIRS
PUBLIC
RidsNrrPMOconee Resource 
  Enclosure REQUEST FOR OCONEE NUCLEAR POWER PLANT COMPONENT  DESIGN BASES INSPECTION 
Please provide the information electronically in ".pdf" files, Excel, or other searchable format on
CD/DVD-ROM.  The CD/DVD-ROM should be indexed and possibly hyperlinked to facilitate ease of use.  Information in "lists" should contain enough information to be easily understood to
someone who has knowledge of pressurized water reactor technology.
1. From your most recent probabilistic safety analysis (PSA) excluding external events and fires, please provide: a. Two risk rankings of components from your site-specific probabilistic safety analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other
sorted by Birnbaum Importance. b. A list of the top 500 cutsets.  2. From your most recent probabilistic safety analysis (PSA) including external events and fires, please provide: a. Two risk rankings of components from your site-specific probabilistic safety analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other
sorted by Birnbaum Importance. b. A list of the top 500 cutsets. 
3. Risk ranking of operator actions from your site specific PSA sorted by RAW.  Provide copies of your human reliability worksheets for these items. 4. Any pre-existing evaluation or list of components and calculations with low design margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator close
to design required output, heat exchangers close to rated design heat removal, MOV risk-
margin rankings, etc.). 5. A list of station applicability evaluations/reviews performed and documented in the station corrective action program in the past two years for industry events, critical equipment
failures, and safety related equipment vulnerabilities (as communicated by NRC generic communications, industry communications, 10 CFR Part 21 notifications, etc.). 6. A list of operability evaluations completed within the last two years, sorted by associated component or system. 7. A list of common-cause failures of components that have occurred at Oconee Nuclear Power Plant and have been identified within the last five years. 8. A list of equipment currently planned for upgrade/improvement by the site (e.g. "ONE" List), including a description of the reason(s) why each component (i.e. not a programmatic or system level concern) is on that list and summaries (if available) of your
plans to address those reasons. 9. A list of equipment currently in RIS 05-020 (formerly GL 91-18) status, or in MR (a)(1) status. 10. Contact information for a person to discuss PRA information prior to the information gathering trip: name, title, phone number, and e-mail address.
2  Enclosure 11. Provide two sets of PI&D drawings (11x17) for safety-related systems and two sets of one line electrical drawings ( 11X17) for safety related systems  (for onsite week of July 11-
July 15, 2011) 12. Provide six copies of FSAR (CD/DVD-ROM only) (for onsite week of July 11- July 15, 2011) 13. Provide six copies of Technical Specifications and Bases (CD/DVD-ROM only) (for onsite week of July 11- July 15, 2011)   


Mr. T. Preston Gillespie, Jr. Site Vice President Duke Energy Carolinas, LLC Oconee Nuclear Station 7800 Rochester Highway Seneca, SC 29672
SUBJECT: NOTIFICATION OCONEE NUCLEAR PLANT - COMPONENT DESIGN BASES INSPECTION - NRC INSPECTION REPORT 05000269,270,287/2011010
==Dear Mr. Gillespie:==
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a component design bases inspection at your Oconee Nuclear Power Plant reactor facility during the period of August 15 - September 30, 2011. The inspection team will be led by Mr. Patrick Higgins, a Senior Reactor Inspector from the NRC's Region II Office. This inspection will be conducted in accordance with the baseline inspection procedure, Procedure 71111.21, Component Design Bases Inspection, issued August 19, 2008.
The inspection will evaluate the capability of risk significant / low margin components to function as designed and to support proper system operation. The inspection will also include a review of selected operator actions, operating experience, and modifications.
During a discussion on April 26, 2011, Mr. Higgins confirmed, with Ms. Judy Smith of your staff, arrangements for an information gathering site visit and the three-week onsite inspection. The schedule is as follows:
* Information gathering visit: July 11 - July 15, 2011 * Week 1 of onsite inspection: August 29 - September 2, 2011 * Week 2 of onsite inspection: September 12 - September 16, 2011 * Week 3 of onsite inspection: September 26 - September 30, 2011 The purpose of the information gathering visit is to meet with members of your staff to identify risk-significant components and operator actions. Information and documentation needed to support the inspection will also be identified and gathered or requested. Mr. Rudolph Bernhard, Region II Senior Reactor Analyst, may accompany Mr. Higgins during the information gathering visit to review probabilistic risk assessment data and identify risk significant components which will be examined during the inspection.
DEC 2 The enclosure lists documents that will be needed prior to the information gathering visit. Please contact Mr. Higgins with any questions prior to preparing materials listed in the enclosure and provide the referenced information to the Region II office by June 10, 2011, unless otherwise noted. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for the inspection preparation.
During the information gathering visit, the team leader will also discuss the following inspection support administrative details: office space; site, plant and information system access; required resources; and information exchange protocol.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-
0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
Thank you for your cooperation in this matter. If you have any questions regarding the information requested or the inspection, please contact Mr. Higgins at (404) 997-4615 or me at (404) 997-4519.
Sincerely,/RA/ Binoy B. Desai, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos.: 50-269,270,287 License Nos.: DPR-38,47,55
===Enclosure:===
Information Request for Oconee Nuclear Power Plant Component Design Bases Inspection cc w/encl: (See page 3)
DEC 3 cc w/encl: Division of Radiological Health TN Dept. of Environment & Conservation 401 Church Street Nashville, TN 37243-1532
David A. Baxter Vice President, Nuclear Engineering Duke Energy Carolinas, LLC Electronic Mail Distribution
Kent Alter Regulatory Compliance Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution
Sandra Threatt, Manager Nuclear Response and Emergency Environmental Surveillance Bureau of Land and Waste Management Department of Health and Environmental Control Electronic Mail Distribution
Scott L. Batson Station Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution
Senior Resident Inspector U.S. Nuclear Regulatory Commission Oconee Nuclear Station U.S. Nuclear Regulatory Commission 7812B Rochester Hwy Seneca, SC 29672
Terry L. Patterson Safety Assurance Manager Duke Energy Carolinas, LLC Electronic Mail Distribution
Charles Brinkman Director Washington Operations Westinghouse Electric Company, LLC Electronic Mail Distribution
Tom D. Ray Engineering Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Electronic Mail Distribution
County Supervisor of Oconee County 415 S. Pine Street Walhalla, SC 29691-2145
W. Lee Cox, III Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution
DEC 2 The enclosure lists documents that will be needed prior to the information gathering visit. Please contact Mr. Higgins with any questions prior to preparing materials listed in the enclosure and provide the referenced information to the Region II office by June 10, 2011, unless otherwise noted. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for the inspection preparation.
During the information gathering visit, the team leader will also discuss the following inspection support administrative details: office space; site, plant and information system access; required resources; and information exchange protocol.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-
0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
Thank you for your cooperation in this matter. If you have any questions regarding the information requested or the inspection, please contact Mr. Higgins at (404) 997-4615 or me at (404) 997-4519.
Sincerely,/RA/ Binoy B. Desai, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos.: 50-269,270,287 License Nos.: DPR-38,47,55
===Enclosure:===
Information Request for Oconee Nuclear Power Plant Component Design Bases Inspection cc w/encl: (See page 3)
X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:_ML111250617________________________ X SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS SIGNATURE RA RA NAME P. Higgins B. Desai DATE 5/4/2011 5/4/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: S:\DRS\ENG BRANCH 1\BRANCH INSPECTION FILES\2011-2012-2013 CYCLE EB1 INSPECTION FOLDERS FOR ALL SITES\OCONEE\OCO CDBI NOTIFICATION 2011 (SAW).DOC Letter to Preston Gillespie from Binoy Desai dated May 4, 2011.
SUBJECT: NOTIFICATION OF OCONEE NUCLEAR POWER PLANT - COMPONENT DESIGN BASES INSPECTION - NRC INSPECTION REPORT 05000269,270,287/2011010 Distribution w/encl: RIDSNRRDIRS PUBLIC RidsNrrPMOconee Resource Enclosure REQUEST FOR OCONEE NUCLEAR POWER PLANT COMPONENT DESIGN BASES INSPECTION Please provide the information electronically in ".pdf" files, Excel, or other searchable format on CD/DVD-ROM. The CD/DVD-ROM should be indexed and possibly hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood to someone who has knowledge of pressurized water reactor technology.
1. From your most recent probabilistic safety analysis (PSA) excluding external events and fires, please provide: a. Two risk rankings of components from your site-specific probabilistic safety analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other sorted by Birnbaum Importance. b. A list of the top 500 cutsets. 2. From your most recent probabilistic safety analysis (PSA) including external events and fires, please provide: a. Two risk rankings of components from your site-specific probabilistic safety analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other sorted by Birnbaum Importance. b. A list of the top 500 cutsets.
3. Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide copies of your human reliability worksheets for these items. 4. Any pre-existing evaluation or list of components and calculations with low design margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design required output, heat exchangers close to rated design heat removal, MOV risk-
margin rankings, etc.). 5. A list of station applicability evaluations/reviews performed and documented in the station corrective action program in the past two years for industry events, critical equipment failures, and safety related equipment vulnerabilities (as communicated by NRC generic communications, industry communications, 10 CFR Part 21 notifications, etc.). 6. A list of operability evaluations completed within the last two years, sorted by associated component or system. 7. A list of common-cause failures of components that have occurred at Oconee Nuclear Power Plant and have been identified within the last five years. 8. A list of equipment currently planned for upgrade/improvement by the site (e.g. "ONE" List), including a description of the reason(s) why each component (i.e. not a programmatic or system level concern) is on that list and summaries (if available) of your plans to address those reasons. 9. A list of equipment currently in RIS 05-020 (formerly GL 91-18) status, or in MR (a)(1) status. 10. Contact information for a person to discuss PRA information prior to the information gathering trip: name, title, phone number, and e-mail address.
2 Enclosure 11. Provide two sets of PI&D drawings (11x17) for safety-related systems and two sets of one line electrical drawings ( 11X17) for safety related systems (for onsite week of July 11-
July 15, 2011) 12. Provide six copies of FSAR (CD/DVD-ROM only) (for onsite week of July 11- July 15, 2011) 13. Provide six copies of Technical Specifications and Bases (CD/DVD-ROM only) (for onsite week of July 11- July 15, 2011)
}}
}}

Revision as of 13:22, 6 April 2018

IR 05000269-11-010, IR 05550270-11-010, IR 05000287-11-010, on 08/15 - 09/2011, Notification Oconee Nuclear Report
ML111250617
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 05/04/2011
From: Desai B B
NRC/RGN-II/DRS/EB1
To: Gillespie T P
Duke Energy Carolinas
References
IR-11-010
Download: ML111250617 (7)


See also: IR 05000269/2011010

Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 May 4, 2011 Mr. T. Preston Gillespie, Jr. Site Vice President

Duke Energy Carolinas, LLC

Oconee Nuclear Station

7800 Rochester Highway

Seneca, SC 29672

SUBJECT: NOTIFICATION OCONEE NUCLEAR PLANT - COMPONENT DESIGN BASES INSPECTION - NRC INSPECTION REPORT 05000269,270,287/2011010 Dear Mr. Gillespie: The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II staff will conduct a component design bases inspection at your Oconee Nuclear Power Plant reactor facility during the period of August 15 - September 30, 2011. The inspection team will be led by Mr. Patrick Higgins, a Senior Reactor Inspector from the NRC's Region II Office. This inspection will be conducted in accordance with the baseline inspection procedure, Procedure 71111.21, Component Design Bases Inspection, issued August 19, 2008.

The inspection will evaluate the capability of risk significant / low margin components to function as designed and to support proper system operation. The inspection will also include a review of selected operator actions, operating experience, and modifications.

During a discussion on April 26, 2011, Mr. Higgins confirmed, with Ms. Judy Smith of your staff,

arrangements for an information gathering site visit and the three-week onsite inspection. The

schedule is as follows:

  • Information gathering visit: July 11 - July 15, 2011 * Week 1 of onsite inspection: August 29 - September 2, 2011 * Week 2 of onsite inspection: September 12 - September 16, 2011 * Week 3 of onsite inspection: September 26 - September 30, 2011

The purpose of the information gathering visit is to meet with members of your staff to identify

risk-significant components and operator actions. Information and documentation needed to

support the inspection will also be identified and gathered or requested. Mr. Rudolph Bernhard, Region II Senior Reactor Analyst, may accompany Mr. Higgins during the information gathering

visit to review probabilistic risk assessment data and identify risk significant components which will be examined during the inspection.

DEC 2 The enclosure lists documents that will be needed prior to the information gathering visit. Please contact Mr. Higgins with any questions prior to preparing materials listed in the enclosure and provide the referenced information to the Region II office by June 10, 2011, unless otherwise noted. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for the inspection preparation.

During the information gathering visit, the team leader will also discuss the following inspection support administrative details: office space; site, plant and information system access; required

resources; and information exchange protocol.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-

0011.

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for

information or an information collection requirement unless the requesting document displays a

currently valid Office of Management and Budget control number.

Thank you for your cooperation in this matter. If you have any questions regarding the

information requested or the inspection, please contact Mr. Higgins at (404) 997-4615 or me at

(404) 997-4519.

Sincerely,

/RA/ Binoy B. Desai, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-269,270,287

License Nos.: DPR-38,47,55

Enclosure: Information Request for Oconee Nuclear Power Plant Component Design Bases Inspection

cc w/encl: (See page 3)

DEC 3 cc w/encl: Division of Radiological Health

TN Dept. of Environment & Conservation

401 Church Street

Nashville, TN 37243-1532

David A. Baxter

Vice President, Nuclear Engineering

Duke Energy Carolinas, LLC

Electronic Mail Distribution

Kent Alter

Regulatory Compliance Manager

Oconee Nuclear Station

Duke Energy Carolinas, LLC

Electronic Mail Distribution

Sandra Threatt, Manager

Nuclear Response and Emergency

Environmental Surveillance

Bureau of Land and Waste Management

Department of Health and Environmental

Control

Electronic Mail Distribution

Scott L. Batson

Station Manager

Oconee Nuclear Station

Duke Energy Carolinas, LLC

Electronic Mail Distribution

Senior Resident Inspector

U.S. Nuclear Regulatory Commission

Oconee Nuclear Station

U.S. Nuclear Regulatory Commission

7812B Rochester Hwy

Seneca, SC 29672

Terry L. Patterson

Safety Assurance Manager

Duke Energy Carolinas, LLC

Electronic Mail Distribution

Charles Brinkman

Director

Washington Operations

Westinghouse Electric Company, LLC

Electronic Mail Distribution

Tom D. Ray Engineering Manager

Oconee Nuclear Station

Duke Energy Carolinas, LLC

Electronic Mail Distribution

County Supervisor of Oconee County

415 S. Pine Street

Walhalla, SC 29691-2145

W. Lee Cox, III

Section Chief

Radiation Protection Section

N.C. Department of Environmental

Commerce & Natural Resources

Electronic Mail Distribution

DEC 2 The enclosure lists documents that will be needed prior to the information gathering visit. Please contact Mr. Higgins with any questions prior to preparing materials listed in the enclosure and provide the referenced information to the Region II office by June 10, 2011, unless otherwise noted. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for the inspection preparation.

During the information gathering visit, the team leader will also discuss the following inspection support administrative details: office space; site, plant and information system access; required

resources; and information exchange protocol.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-

0011.

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for

information or an information collection requirement unless the requesting document displays a

currently valid Office of Management and Budget control number.

Thank you for your cooperation in this matter. If you have any questions regarding the

information requested or the inspection, please contact Mr. Higgins at (404) 997-4615 or me at

(404) 997-4519.

Sincerely,

/RA/ Binoy B. Desai, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-269,270,287

License Nos.: DPR-38,47,55

Enclosure: Information Request for Oconee Nuclear Power Plant Component Design Bases Inspection

cc w/encl: (See page 3)

X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:_ML111250617________________________ X SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS SIGNATURE RA RA NAME P. Higgins B. Desai DATE 5/4/2011 5/4/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: S:\DRS\ENG BRANCH 1\BRANCH INSPECTION FILES\2011-2012-2013 CYCLE EB1 INSPECTION FOLDERS FOR ALL SITES\OCONEE\OCO

CDBI NOTIFICATION 2011 (SAW).DOC

Letter to Preston Gillespie from Binoy Desai dated May 4, 2011.

SUBJECT: NOTIFICATION OF OCONEE NUCLEAR POWER PLANT - COMPONENT DESIGN BASES INSPECTION - NRC INSPECTION REPORT

05000269,270,287/2011010

Distribution w/encl: RIDSNRRDIRS

PUBLIC

RidsNrrPMOconee Resource

Enclosure REQUEST FOR OCONEE NUCLEAR POWER PLANT COMPONENT DESIGN BASES INSPECTION

Please provide the information electronically in ".pdf" files, Excel, or other searchable format on

CD/DVD-ROM. The CD/DVD-ROM should be indexed and possibly hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood to

someone who has knowledge of pressurized water reactor technology.

1. From your most recent probabilistic safety analysis (PSA) excluding external events and fires, please provide: a. Two risk rankings of components from your site-specific probabilistic safety analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other

sorted by Birnbaum Importance. b. A list of the top 500 cutsets. 2. From your most recent probabilistic safety analysis (PSA) including external events and fires, please provide: a. Two risk rankings of components from your site-specific probabilistic safety analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other

sorted by Birnbaum Importance. b. A list of the top 500 cutsets.

3. Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide copies of your human reliability worksheets for these items. 4. Any pre-existing evaluation or list of components and calculations with low design margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator close

to design required output, heat exchangers close to rated design heat removal, MOV risk-

margin rankings, etc.). 5. A list of station applicability evaluations/reviews performed and documented in the station corrective action program in the past two years for industry events, critical equipment

failures, and safety related equipment vulnerabilities (as communicated by NRC generic communications, industry communications, 10 CFR Part 21 notifications, etc.). 6. A list of operability evaluations completed within the last two years, sorted by associated component or system. 7. A list of common-cause failures of components that have occurred at Oconee Nuclear Power Plant and have been identified within the last five years. 8. A list of equipment currently planned for upgrade/improvement by the site (e.g. "ONE" List), including a description of the reason(s) why each component (i.e. not a programmatic or system level concern) is on that list and summaries (if available) of your

plans to address those reasons. 9. A list of equipment currently in RIS 05-020 (formerly GL 91-18) status, or in MR (a)(1) status. 10. Contact information for a person to discuss PRA information prior to the information gathering trip: name, title, phone number, and e-mail address.

2 Enclosure 11. Provide two sets of PI&D drawings (11x17) for safety-related systems and two sets of one line electrical drawings ( 11X17) for safety related systems (for onsite week of July 11-

July 15, 2011) 12. Provide six copies of FSAR (CD/DVD-ROM only) (for onsite week of July 11- July 15, 2011) 13. Provide six copies of Technical Specifications and Bases (CD/DVD-ROM only) (for onsite week of July 11- July 15, 2011)