IR 05000269/2020010

From kanterella
Jump to navigation Jump to search
NRC Design Bases Assurance Inspection (Team) Report 05000269/2020010 and 05000270/2020010 and 05000287/2020010 and Notice of Violation
ML21022A160
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 01/22/2021
From: James Baptist
NRC/RGN-II/DRS/EB1
To: Burchfield J
Duke Energy Carolinas
References
IR 2020010
Download: ML21022A160 (24)


Text

January 22, 2021

SUBJECT:

OCONEE NUCLEAR STATION - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000269/2020010 AND 05000270/2020010 AND 05000287/2020010 AND NOTICE OF VIOLATION

Dear Mr. Burchfield,

Jr.:

On September 24, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Oconee Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Based on the results of this inspection, the NRC has identified an issue that was evaluated under the risk significance determination process as having very low safety significance (Green). The NRC has also determined a violation is associated with this issue. This violation was evaluated in accordance with the NRC Enforcement Policy. The current Enforcement Policy is included on the NRC's Web site at (http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html).

The violation is cited in the enclosed Notice of Violation (Notice) and the circumstances surrounding it are described in detail in the subject inspection report. The violation is cited in the Notice because it did not meet the criteria to be treated as a non-cited violation because the licensee failed to restore compliance with safety-related electrical system voltage calculations associated with two previous NRC Green NCVs from 2011 and 2014 CDBI inspections. The failure to restore compliance follows guidance from NRC Enforcement Manual Chapter 2.2.2.A, Circumstances Resulting in Consideration of an NOV (vs. an NCV) for Licensees and Non-Licensees with an Approved Corrective Action Program.

You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response. If you have additional information that you believe the NRC should consider, you may provide it in your response to the Notice. The NRCs review of your response to the Notice will also determine whether further enforcement action is necessary to ensure your compliance with regulatory requirements.

Additionally, one finding of very low safety significance (Green) is documented in this report.

This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Oconee Nuclear Station. If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Oconee Nuclear Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety

Docket Nos. 05000269 and 05000270 and 05000287 License Nos. DPR-38 and DPR-47 and DPR-55

Enclosure:

As Stated

Inspection Report

Docket Numbers:

05000269, 05000270 and 05000287

License Numbers:

DPR-38, DPR-47 and DPR-55

Report Numbers:

05000269/2020010, 05000270/2020010 and 05000287/2020010

Enterprise Identifier: I-2020-010-0044

Licensee:

Duke Energy Carolinas, LLC

Facility:

Oconee Nuclear Station

Location:

Seneca, SC

Inspection Dates:

August 03, 2020 to August 21, 2020

Inspectors:

J. Brand, Reactor Inspector

P. Braxton, Reactor Inspector

M. Greenleaf, Reactor Inspector

J. Parent, Resident Inspector

R. Patterson, Senior Reactor Inspector

T. Su, Reactor Inspector

D. Edwards, Reactor Inspector (Trainee)

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Oconee Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Evaluate Design Basis Conditions for PPM Applicability for Motor Operated Valve 1LP-2 Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000270,05000287,05000269/202001 0-01 Open

[H.7] -

Documentation 71111.21M The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Appendix B, Criterion V of 10 CFR Part 50 when the licensee failed to demonstrate that MOV 1LP-2 is capable of performing its design basis safety function by failing to justify the use of the EPRI PPM in accordance with DPS-1205.19-00-0002.

Inadequate Corrective Action - Control Voltage for 4160 Breakers Closing Coil and 480V MCC control Circuits were not Assured Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NOV 05000270,05000287,05000269/202001 0-02 Open None 71111.21M The team identified a Green cited violation, with two examples, of 10 CFR 50, Appendix B,

Criterion XVI, for the licensees failure to correct a condition adverse to quality. Specifically, the licensee (1) failed to perform all corrective actions identified to correct voltage calculations for safety-related 4160V circuit breaker 125Vdc control circuits and (2) failed to perform all corrective actions to correct voltage calculations for safety-related 120Vac MCC control circuits. The above issues were previously identified in NCV-05000269,270,287/2011010-04;

NCV 05000269,270,287/2011010-0; and NCV 05000269/2014007-02; 05000270/2014007-02; 05000287/2014007-02, respectively.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (3 Samples)

(1) Lee Gas Station Transformer (CT-5)
  • Compliance with UFSAR, TS, and TS Bases
  • Conformance with manufacturer instructions for installation, maintenance, and operation
  • Adequacy of corrective action activities
  • Material condition and configuration
  • Verification that System Health Report accurately reflect current system conditions
  • Design requirements (tap settings, degraded grid and loss of voltage relays setting, load flow analysis and short circuit calculation, etc.)
(2) Instrument Air (IA) Main Compressor
  • Conformance with maintenance and operation procedures
  • Adequacy of corrective action activities
  • Material condition and configuration
  • Design requirements
  • Maintenance review
(3) Unit 3 Control Rod Drive
  • Conformance with maintenance and operating procedures
  • Adequacy of corrective action activities
  • Material condition and configuration
  • Design requirements
  • Verification that System Health Report accurately reflect current system conditions
  • Maintenance review

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) LPI-MDP-A, RHR Pump Train A LPI and LPR Functions
  • Compliance with UFSAR, TS, and TS Bases
  • Conformance with manufacturer instructions for installation, maintenance, and operation
  • Adequacy of corrective action activities
  • Material condition and configuration
  • Verification that System Health Report accurately reflect current system conditions
  • Design requirements

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) EC 107578 - Actuator Change for 1LP-2 to Increase Stroke Time
(2) EC 95361 - Keowee Main Step-up (KMSU) Transformer Replacement
(3) EC 113581-Replace the SSF RC Make-Up Pump Motor New Motor
(4) EC 112329-Install New Unit 2 LPSW Supply to the MDEFWP Motor Coolers and Separate It from Unit 1
(5) EC 405874-Modify Three Pipe Supports on Unit 3 HPI Injection Due to Thermal Stratification; 51A-0-2479A-H2D, 52A-0-2479A-H13A, and 51A-0-2479A-H16A

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1) IN 2009-10: Transformer Failures - Recent Operating Experience
(2) IN 2017-005 - Potential Binding of Masterpact and NW 480-VAC Circuit Breaker Anti-Pump Features

INSPECTION RESULTS

Failure to Evaluate Design Basis Conditions for PPM Applicability for Motor Operated Valve 1LP-2 Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green

[H.7] -

Documentation 71111.21M NCV 05000270,05000287,05000269/20200 10-01 Open

The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Appendix B, Criterion V of 10 CFR Part 50 when the licensee failed to demonstrate that MOV 1LP-2 is capable of performing its design basis safety function by failing to justify the use of the EPRI PPM in accordance with DPS-1205.19-00-0002.

Description:

In 2014, the Electric Power Research Institute (EPRI) issued an error notice informing the licensee that the Performance Prediction Methodology (PPM) software had an error that allowed 400 series martensitic stainless steel to be treated as 300 series austenitic stainless steel. This error would lead some licensees to believe that valves with 400 series steel internal sliding surfaces would meet the EPRI PPM applicability criteria. EPRI stated that if licensees could adequately justify appropriate guide rail friction coefficients, then the PPM may be considered applicable and the resulting analyses may be classified as Best Available Information.

The licensee entered the issue into its corrective action program and determined that several valves contained 400 series stainless steel in their guide rail design and performed an engineering evaluation to attempt to demonstrate that the PPM results were best available and would provide reasonable assurance, in part, of the motor operated valve's (MOVs)capability to perform their safety function(s) during design basis accidents. Part of this basis relied on the use of Joint Owners Group (JOG) valve data to establish a bounding coefficient of friction for the 400 series steel valve internal sliding surfaces. In performing this evaluation, the licensee determined that 1LP-2 was one MOV that required such justifications as described in the EPRI error notice.

MOV 1LP-2 is required to open during post-loss-of-coolant-accident (post-LOCA) and steam generator tube rupture accidents to provide an alternate boron dilution path and reactor coolant system (RCS) cooling function, respectively. The method by which the licensee attempted to demonstrate the capability of this MOV relies upon, in part, EPRIs PPM software.

The licensees use of JOG data to determine a bounding coefficient of friction without confirming that the JOG data was applicable and of quality dictated by the licensees QA program failed to justify the coefficient of friction chosen by the licensee (0.72) as an input into the PPM software.

Additionally, in April of 2020, Engineering Change EC 107578 completed the modification of Low Pressure Injection (LPI) MOV 1LP-2 via a change to its overall actuator gear ratio such that it would open slower to prevent the rapid collapse of voids in the LPI piping which had led to a previous pressure transient event in the system. The modification also changed the opening order of MOVs 1LP-1 and 1LP-2 (which are in series) such that 1LP-2 would open after 1LP-1. Specifically, OSS-0254.00-00-1028, Rev. 74, states in Section 2.4.2.22:

1/2/3LP-2 should be the last valve opened and the first valve closed when aligning and isolating the LPI DHR mode of operation. In addition, this valve should be the last valve opened when aligning the alternate boron dilution flow path following a LOCA.

This opening order of the valves was also reflected in Emergency Operating Procedure EP-1-A-1800-001-0I, Rev. 0, LOCA Cooldown, where MOV 1LP-2 would be expected to be opened after 1LP-105 and 1LP-1 to establish a safety-related flow-path between the units decay heat drop line and the emergency sump. Based on the design basis information provided in the emergency operating procedure and the system design basis document (OSS-0254.00-00-1028 Rev. 60), the design of the alternate boron dilution flow-path would indicate that the MOV would be required to be designed for flow conditions when it is required to open post-LOCA.

Based upon language also noted by the inspectors in OSS-0254.00-00-1028 Rev. 60, the inspectors questioned if the 250°F maximum fluid temperature was accurate as described in OSC-4281, OSC-5674, and OSC-5879. The licensee reviewed additional documentation and determined that based upon Babcock & Wilcox Owners Group analysis (as described in technical support center (TSC) guidance EM 5.1) that the expected fluid temperature that 1LP-2 would experience during a LOCA alternate boron dilution alignment was approximately 315°F.

Considering a design basis flow condition at a fluid temperature of 315°F, the inspectors noted that galling of the guide rails is expected (EPRI TR-1002847). Based upon this design basis review, the inspectors found that the justification for the coefficient of friction used in the licensees application of the PPM for 1LP-2 was additionally inadequate based on the expectation of galling at this high temperature under potential flow conditions.

The licensee reviewed its design basis documentation and procedures and determined that technical support center (TSC) guidance document EM 5.1 (which is not a safety-related, quality assurance (QA-1) document) contained procedural steps for placing the alternate boron dilution path into service that differed significantly from the QA emergency operating procedures. Based upon its review of those documents, the licensee asserted that the operations staff would defer to the TSC guidance and not align the alternate boron dilution flow path in such a way as to require 1LP-2 to open under a flow condition.

Inspectors additionally questioned whether voiding of piping downstream of 1LP-2 during normal, abnormal, and design basis accident conditions could occur such that the valve could be opened under flow conditions at temperatures in excess of 200°F. As a result of these questions, the licensee reviewed the potential conditions of downstream piping and determined under LOCA conditions the piping could be voided - leading to a flow condition at high temperatures.

As a result of the inadequate justification for the application of the EPRI PPM based upon the use of unverified JOG valve data, and upon several inaccuracies in the incorporation of the licensees design basis into calculations, procedures and specifications, the inspectors determined that the characterization of MOV 1LP-2 as JOG Class B was not appropriate and that the MOV should be considered as Class D. JOG Class D MOVs are subject to periodic verification of their design-basis capability to satisfy 10 CFR 50.55a(b)(3)(ii) and the licensees GL 96-05 program.

Corrective Actions: The licensee entered these issues into the corrective action program as NCR 02344871. The licensee evaluated the valves functionality considering the potential for galling and concluded that the valve could supply the necessary flow if only opened 1/16 of an inch - a stroke that would be highly likely to be successful even with galling likely to occur.

Additionally, the licensee took immediate actions to order the operations staff to defer to EM 5.1 guidance for alternate boron dilution flow-path alignment procedures until new emergency operating procedures could be written. Based on the licensees functionality assessment, its order to the operations staff and the margin available in the MOV actuator capability, the licensee asserted that the MOV can meet its safety function to open when called upon.

Corrective Action References: NCR 02344871

Performance Assessment:

Performance Deficiency: The failure to appropriately justify the use of the EPRI PPM for MOV 1LP-2 is a performance deficiency. Specifically, Attachment 20 DPS-1205.19-00-0002, requires, in part, that the licensee will be responsible for justifying the use of the EPRI model for valve designs not tested as part of the EPRI program.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the unjustified use of the EPRI PPM misclassified 1LP-2 as a JOG Class B MOV, which is excused from periodic verification testing under dynamic flow conditions with increased diagnostic testing required by 10 CFR 50.55a(b)(3)(ii). This reduced inspection to track and correct the deleterious effects of degradation over time - adversely impacted the reliability and capability of the MOV to perform its safety function when called upon in post-LOCA and steam generator tube rupture accident scenarios.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. This finding was screened to Green because the finding was a deficiency affecting the design or qualification of a mitigating structure, system or component (SSC) and the SSC maintained its operability or PRA functionality.

Cross-Cutting Aspect: H.7 - Documentation: The organization creates and maintains complete, accurate and up-to-date documentation. This aspect was assigned because the performance deficiency's most significant contributor was the change to the opening order of the MOV 1LP-2 - which was not fully evaluated in EC 107578 which was closed in April of 2020.

Enforcement:

Violation: Appendix B, Criterion V, in 10 CFR Part 50 requires that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. Contrary to this, the licensee failed to demonstrate that MOV 1LP-2 was capable of performing its design basis safety function by failing to justify the use of the EPRI PPM in accordance with DPS-1205.19-00-0002.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate Corrective Action - Control Voltage for 4160 Breakers Closing Coil and 480V MCC control Circuits were not Assured Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NOV 05000270,05000287,05000269/20200 10-02 Open

None 71111.21M The team identified a Green cited violation, with two examples, of 10 CFR 50, Appendix B, Criterion XVI, for the licensees failure to correct a condition adverse to quality. Specifically, the licensee

(1) failed to perform all corrective actions identified to correct voltage calculations for safety-related 4160V circuit breaker 125Vdc control circuits and
(2) failed to perform all corrective actions to correct voltage calculations for safety-related 120Vac MCC control circuits. The above issues were previously identified in NCV-05000269,270,287/2011010-04; NCV 05000269,270,287/2011010-0; and NCV 05000269/2014007-02; 05000270/2014007-02; 05000287/2014007-02, respectively.
Description:

During the 2020 DBAI, the team reviewed previous violations and their associated corrective actions and identified that all concerns, issues, and corrective actions from the original violations in 2011 and 2014 were not addressed.

Example 1 - Failure to Perform Corrective Actions to Correct Voltage Calculations for Safety-Related 4160V Circuit Breaker 125Vdc Control Circuits

The 2011 CDBI team identified a Green violation of Criterion III to perform adequate 125VDdc control circuit calculations, which credited the use Test Report (TR)-144, Oconee Emergency Power 5HK Switchgear Test," a one time test in 1995 at Oconee, to re-qualify the breaker close coil circuits from 100Vdc as qualified by the vendor, to 70Vdc. The testing did not consider seismic, aging or temperature concerns which were the basis of the vendor qualified rating of 100VDC. Additionally, the licensee took credit for the completion of preventative maintenance procedures which periodically tested the breakers at 85VDC. The violation also questioned whether this 70VDC tested values were used in other Oconee calculations. NCR 1904970 was written in 2011 to evaluate the use of TR-144 in only OSC-6195 that was specifically used as the violation example. As an action, EC110252 was performed to address aging and temperature effects for OSC-6195 but, an extent of condition was not performed to identify all calculations that the same condition would apply. The 2014 CDBI team identified a Criterion XVI Green violation for licensee's failure to correct all calculations for safety-related 4160V circuit breaker 125Vdc control circuits where the same issue identified in 2011 was also applicable. NCR 186283 was written to address only one of the new identified calculations, OSC-8113, but was closed stating in part, that, the condition was a legacy human performance deficiency and no additional actions were required.

After the team raised the issues during the 2020 DBAI, the licensee issued AR 02343949 and AR 02343959 to re-visit the corrective actions from the previous inspection violations and re-evaluate their review of similar fleet OE which represented an additional missed opportunity to revisit their previous actions.

Example 2 - Failure to Perform Corrective Actions to Correct Voltage Calculations for Safety-Related 120Vac Motor Control Center Control Circuits

The 2011 CDBI team identified the following five areas of concern in regard to testing, including sample sizes, ambient temperature, and aging:

  • For Sylvania TM starters only two specimens each of size 1 and 2 were tested, providing an inadequate basis for the rating.
  • For Joslyn Clark and Cutler Hammer contactors the calculation took credit for Control Power Transformer boost (approximately 2-4%) that had already been credited in tests.
  • Tests were conducted on contactors at shop ambient temperature (cold coil). Contactors may have been required to operate in service with hot coils. This could have raised the pickup voltage by approximately 4%.
  • The acceptance criteria in the calculation did not provide margin over test criteria to account for degradation over the service life of the contactors. Contactors were not periodically tested to confirm low pickup voltage capability.
  • The calculation contained incomplete or obsolete information (e.g. contactors that have been replaced and test reports missing).

The site documented these concerns in PIP 0-11-11440 and 0-11-11510. In CDBI 2014-007, the team issued a Green Violation of Criterion XVI for failure to correct the issues and concerns from the 2011 Violation, as PIP 0-11-11440 issued at that time was closed with some of the corrective actions not fully addressed and was documented in AR 01864324. During this inspection in 2020, the team determined that the original corrective actions were not fully implemented to resolve the issues identified in violations in 2011 and 2014. As a result, Oconee issued AR 02343569 to address of the original corrective actions which required the MCC PM procedure IP/0/A/3011/015 be revised to bound all contactor coil minimum design pickup voltages. This AR still did not adequately address all of the following original issues that were identified in the original 2011 and 2014 violations.

Corrective Actions: This is violation has been entered into the licensees corrective action program AR 02343949, AR 02343959 and AR 02343569.

Corrective Action References: AR 02343949, AR 02343959 and AR 02343569

Performance Assessment:

Performance Deficiency: The licensees failure to perform corrective actions to correct voltage calculations for safety-related 4160V circuit breaker 125Vdc control circuits and to correct voltage calculations for safety-related 120Vac MCC control circuits as required by 10 CFR Part 50, Appendix B, Criterion XVI, was a performance deficiency. The team determined that the performance deficiency was more than minor because it affected the Equipment Performance attribute of the Mitigating Systems Cornerstone, and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, failing to account for seismic, aging and environmental effects could negatively impact the reliability of the affected safety-related electrical components.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The team determined that the performance deficiency was more than minor because it affected the Equipment Performance attribute of the Mitigating Systems Cornerstone, and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, failing to account for aging and environmental effects could negatively impact the reliability of the affected safety-related electrical components.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, 0609.04, Initial Characterization of Findings. Because the finding impacted the Mitigating Systems cornerstone, the team screened the finding through IMC 0609 Appendix A, The Significance Determination Process for Findings At-Power, using Exhibit 2, Mitigating Systems Screening Questions. The finding screened as of very low safety significance (Green) because the incomplete corrective actions did not result in losses of operability or function for any of the examples.

Cross-Cutting Aspect: None

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, requires, in part, that, measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment and non-conformances are promptly identified and corrected. Contrary to the above, since June 27, 2014, the licensee failed to correct conditions adverse to quality. Specifically, the licensee (1)failed to correct voltage calculations for safety-related 4160V circuit breaker 125Vdc control circuits and

(2) failed to correct voltage calculations for safety-related 120VAC MCC control circuits.

This violation is of very low safety significance and has been entered into the licensees corrective action program AR 02343949, AR 02343959 and AR 02343569. The failure to restore compliance follows guidance from NRC Enforcement Manual Chapter 2.2.2.A, Circumstances Resulting in Consideration of an NOV (vs. an NCV) for Licensees and Non-Licensees with an Approved Corrective Action Program.

Enforcement Action: This violation is being cited because the licensee failed to restore compliance within a reasonable period of time after the violation was identified consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 24, 2020, the inspectors presented the design basis assurance inspection (teams) inspection results to J. Ed Burchfield, Jr. and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

OSC 1776

Problem No. 1-14-08; 3 inch Backwash Piping From LPSW

Pump to L.P. Strainers; System 14

Revised per As-Built EC112329 and per As-Designed

EC113381.000

Rev. 23

OSC 1776

Piping Analysis for 3" Strainer Backwash piping from LPSW

Pumps to 2" piping to Units 1 & 2 EFWP Motors: Piping

Analysis Problem No. 1-14-08

Rev. 26

OSC-0559

Piping Analysis from Penetrations #3 and #44 to the

Component Cooling Pumps Analysis Problem No. 3-55-02

Rev. 13

OSC-10667

Qualification of Component Coolers "3A" & "3B" Piping

Analysis Problem No. 3-55-15

Rev. 4

OSC-11071

Uncertainty Calculation for BWST Discharge Pump Header

Digital Differential Pressure Transmitter (Rosemount 3051N)

Rev. 4

OSC-11202

CRD Filter Nozzle Evaluation

Rev. 1

OSC-11210

Anchorage Evaluation for Component Cooling Coolers 3A &

3B

Rev. 002

OSC-11343

Evaluation of MOV Motors and ETAP Inputs

Rev. 3

OSC-11522

Failure Modes and Effect Analysis for EC 96548

Rev. 1

OSC-11562

ONS Unit 2 Main Generator Relay Settings for the SEL-

300G and Beckwith M-3425A Relays

Rev. 0

OSC-11563

ONS Unit 2 Unit and Auxiliary Transformers Protection for

SEL-487E and Beckwith M-3311A Relay

Rev. 3

OSC-11581

U1/2/3, Keowee EPS and 100kV APS Voltage Adequacy

Analyses

Rev. 1

OSC-2408

Determine the design parameters to adequately ventilate the

instrument air compressor in the Turbine Building

Rev. 0

OSC-3189

BWST Level Uncertainty

Rev. 8

OSC-4276

Oconee 125 Vdc Vital Instrumentation and Control Voltage

Adequacy

Rev. 13

OSC-4281

System Condition Review for LPI Valves

Rev. 18

OSC-4300

(ELEX) Protective Relay Settings

Rev. 38

OSC-5674

Generic Letter 89-10 Calculation for Unit 1 Gate and Globe

Rev. 38

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Valves

OSC-5879

Evaluation of EPRI MOV Methodology for 1LP-002

Rev. 4

OSC-5930

600/208 Vac Essential Auxiliary Power System

Rev. 15

OSC-6587

25 VDC Vital Instrumentation and Control Load Profile,

Battery Sizing and Voltage Analysis

Rev. 7

OSC-7167

Qualified Life Analysis for Limitorque Motor Operated Valves Rev. 5

OSC-7371.01

GL 96-06 Water Hammer Operability Evaluation: Operability

Criteria for Evaluation of Piping, Components and Pipe

Supports/Restraints (Type IV)

Rev. D2

OSC-7561

Differential Pressure Calculations for Valves FDW-0315 and

FDW-0316

Rev. 000

OSC-8113

25 VDC Vital Instrumentation and Control Load profile,

Battery Sizing, and Voltage Analysis

Rev. 0

OSC-8941

Power Conversion Systems (CCW, C, FDW, MS)

Rev. 0

OSC-9239

JOG Classification for Oconee's GL 96-05 MOV Population

Rev. 6

OSC-9610

Evaluation of LPI, CF, RBS & HPI Systems for Generic Letter 2008-01

Rev. 2

OSC-9855

LPI Drop Line Pressure Transient Analyses

Rev. 0

OSC-9855

LPI Drop Line Pressure Transient Analyses

Rev. 0

Corrective Action

Documents

01546807

01709578

01794387

01808457

01816298

01822353

01829206

01864306

01864324

01905117

01905946

01905980

2055781

2055781

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2114967

2119055

2142563

2154009

219546

226564

261444

297905

2304474

2306767

2307601

2310958

2337450

2341043

2341080

2342932

Corrective Action

Documents

Resulting from

Inspection

2341473

ISA Document Revision Incorrect in OSC-11071

2342913

NRC DBAI, 1LP-2 Max DP to Open

2342914

NRC DBAI, LP-17/LP-18 Capability to Open Under Max DP

2342932

NRC DBAI LPI Operation During HI DP from Check Valve

Leakage

2342941

Missing Extension Due Date for AR

2343201

Revision Needed to Clarify OSC-4281 LPI System

Conditions

2343368

Thermal Conduction Impact on Actuator Temperature

2343569

SSF RCMUP Contactors and MCC PM Procedure

2343949

Breaker Close Coil DC Voltage Evaluation

2343959

Review of Previous Corrective Actions

2344570

TS 3.4.14 Allowed Leakage Not Evaluated

2344570

NRC DBAI, TS 3.4.14 Allowed Leakage not Evaluated

2344805

20 NRC DBAI: Inadequate Limitorque Documentation

OSC-7161

2344864

Discovered Air Leak Near 2FDW-316

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2344871

OSC-4281 Does Not Provide Bounding Parameters for 1LP-

2344877

Housekeeping Items Identified

2346192

Question on Step Sequence for Alt Boron Dilution.

Drawings

0-0702

One Line Diagram, 6900 & 4160 STA Auxiliary Sys

Rev. 39

O-0703-K

One Line Diagram - 600V & 208V Essential Motor Control

Aux Pwr Sys SSF

Rev. 81

O-1422M-034-01

Instrument Detail Emergency Feedwater Control Valve

2FDW-316

Rev. 1

O-702-A

6900 & 4160V Auxiliary System

Rev. 38

O-703-K

One Line Diagram - 600V & 208V Essential Motor Control

Aux Pwr Sys SSF

Rev. 81

OFD-100A-1.5

Flow Diagram of Reactor Coolant System, 1. Control Rod

Drive Venting Sys., 2. Center Control Rod Drive Gas

Sampling

Rev. 4

OFD-100A-3.5

Flow Diagram of Reactor Coolant Sys. 1. Control Rod Drive

Venting Sys.

Rev. 3

OFD-102A-01-02

Flow System Diagram of Low Pressure Injection System

(LPI Pump Discharge)

Rev. 61

OFD-102A-01-03

Flow Diagram of Low Pressure Injection System (Core

Flood)

Rev. 31

OFD-102A-1.1

Flow Diagram of Low Pressure Injection System Borated

Water Supply & LPI Pump Suction

Rev. 71

OFD-137B-1.1

Flow Diagram of Instrument Air System (Air Compressors,

After Coolers, Receivers, Air Dryers)

Rev. 27

OFD-137B-1.2

Flow Diagram of Instrument Air System (Layout of Major

Headers)

Rev. 29

OFD-137B-1.3

Flow Diagram of Instrument Air System Auxiliary Building

Receiver Tanks and Instrument Air Headers

Rev. 11

OFD-137B-1.4

Flow Diagram of Instrument Air Accumulator Supply to Main

and Start-up Feedwater Control Valves

Rev. 1

OFD-137B-2.4

Flow Diagram of Instrument Air Accumulator Supply to Main

and Start-up Feedwater Control Valves

Rev. 0

OFD-137B-3.4

Flow Diagram of Instrument Air Accumulator Supply to Main

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

and Start-up Feedwater Control Valves

OFD-144A-1.3

Flow Diagram of Component Cooling System (Control Rod

Drive Service Structure & Filters)

Rev. 10

OFD-144A-2.3

Flow Diagram of Component Cooling System (Control Rod

Drive Service Structure & Filters)

Rev. 10

OFD-144A-3.3

Flow Diagram of Component Cooling System (Control Rod

Drive Service Structure & Filters)

Rev. 10

OM 245.--

2055.001

DMV-2158 1/53/040 and 2/53/040 O/L Dwg for 12"

Walworth Gate Valve

Rev. 2

ONTC-1-124A-

0005-001

Oconee Nuclear Station Unit 1 LPSW Pump Minimum Flow

Line Test Acceptance Criteria

Rev. 0

Engineering

Changes

0000112329

Install New Unit 2 LPSW Supply to the MDEFWP Motor

Coolers and Separate It

007

96548

U2 Main Power System Protective Relay Upgrade

Rev. 000

EC 1057578

Actuator Change for 1LP-2 to Increase Stroke Time

Rev. 1

EC 109172

Unit 3 CC Pipe Support Modification Per O-12-6670 and O-

2-6673 (OBDN)

Rev. 002

EC 109885

Reduce Design Temp for CC on Units 1, 2, and 3

Rev. 0

EC 113381

Re-Route Unit 1 LPSW Supply to the MDEFWPS

Rev. 005

EC 417486

Provide Cooling to the PIAC Control Cabinet IACCP1

Rev. 000

EC 95361

Keowee Main Step-up (KMSU) Transformer Replacement

Rev. 24

EC113581

Replace the SSF RC Make-up Pump Motor With a New

Motor

Rev. 5

Miscellaneous

B01019

Qualification Type Test Report of Multi-Point Terminal Strips

for Use in Limitorque Valve Actuators for PWR Service

07/01/1982

B0212

Nuclear Power Station Qualification Type Test Report

Limitorque Valve Actuators with Type LR Motor for

Westinghouse PWR

04/10/1985

DBD-OSS-

254.00-00-1028

Design Requirement for Inter-system Leakage

Rev. 60

DCP-

1381.05000049,

Environmental Qualification (EQ) Evaluation of Limitorque

MOV Actuator SB Inside and Outside Containment

Rev. 1

EC 405874

Modify Three Pipe Supports on Unit 3 HPI Injection Due to

Thermal Stratification; 51A-0-2479A-H2D, 51A-0-2479A-

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

H13A, and 51A-0-2479A-H16A

EQMM-1393.01-

A02-00

Environmental Qualification Maintenance Manual Equipment

Type: Actuator - Manufacturer Limitorque - Model/Series

SMB/SBD/SB Inside & Outside Containment

Rev. 18

KM 301.--

0010.001

I/B - (Viewable) G.E. Power Transformer

Rev. 15

KM 301.--

0059.001

Single Failure Analysis FMEA for Keowee Transformer

(RAI311531)

Rev. 0

KM 301.--

0060.001

Keowee Main Step-Up Transformer ABB Factory

Acceptance Test Report

Rev. 1

KM 401.--

0058.001

FMEA for Keowee Transformer (RAI311531)

Rev. 0

Metallurgic

Services File #

6033

ONS-2LP-196 Bellows

2/11/2020

NSM ON-33093

U-3, LPI Positive Cross Connect Modification

07/22/2003

OM 302.-

0105.001

ABB HK Switchgear Instruction Manual

Rev. D10

OM 322.-

21.001

SEL-487-E-3, E-4 Relay Current Differential and Voltage

Protection

09/15/2015

OM-245-0979.001 Limitorque Valve Actuator Qualification for Nuclear Power

Station Service Report B0058

09/25/2012

On-19-0032

Replace GR-15 Relays

09/11/2019

ONS-2015-058

TIA 2014-05, Potential Un-analyzed Condition Associated

with Emergency power System

05/11/2015

OS.813.20

Memorandum-Order for Modification of Licenses Concerning

Primary Coolant System Pressure Isolation Valves

04/20/1981

OSS-0243.00-00-

0001

(MECH) Piping Installation Specification

Rev. 033

OSS-0254.00-00-

28

(Mech) Design Basis Spec for the Low-Pressure Injection

and Core Flood System (LPI)

Rev. 60

OSS-0254.00-00-

2000

Design Basis Specification doe the 4 KV Essential Auxiliary

Power System

Rev. 24

OSS-0254.00-00-

Design Basis Spec for the Oconee Definition of QA

Rev. 11

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

21

Condition 1

PT-1, 2, 3-A-

0150-015D

Design Bases Objectives RCS to LPI PIVs

2/11/2008

PT-2A-0152-013

Low Pressure SW System Valve Stroke Test

2/06/2020

PT-2A-0251-077

LPSW Water Hammer Protection System Valve and Air

Accumulator Test

2/01/2019

PT-2A-0251-078

LPSW Water Hammer Protection System and Valve and Air

Accumulator Test

Completed

11/30/2019

to 12/1/2019

ST3250

Transformer Station Health Report

08/05/2020

TR-1002847

EPRI Report: Updated Guidance for Evaluating Thrust

Requirements for Gate Valves with Stainless Steel Guides

06/01/2001

TR-144

Oconee Emergency Power 5HK Switchgear Test

08/10/95

Procedures

AD-EG-ALL-1107

Quality Classifications

Rev. 5

AD-EG-ALL-1117

Design Analyses and Calculations

Rev. 1

AD-EG-ALL-1612

Environmental Qualification (EQ) Program

Rev. 6

AD-EG-ALL-1903

Cyber Security Critical Systems and Critical Digital Assets

Identification and Assessment

Rev. 5

AD-OP-ALL-1000

Conduct of Operations

Rev. 17

AD-OP-ALL-1001

Conduct of Abnormal Operations

Rev. 3

AD-OP-ONS-

0001

ONS Operations Administrative Commitments

Rev. 001

AD-PI-ALL-0100

Corrective Action Program

Rev. 23

AP/1/A/1700/022

Loss of Instrument Air

Rev. 30

AP/3/A/1700/003

Boron Dilution

Rev. 15

AP/3/A/1700/011

Recovery from Loss of Power

Rev. 52

AP/3/A/1700/020

Loss of Component Cooling

Rev. 13

AP/3/A/1700/039

Unintentional Boration

Rev. 2

DPS-1205.19-00-

0002

Guideline for Performing Motor Operated Valve Reviews

and Calculations

Rev. 4

EDM 101

Engineering Calculations/Analyses

Rev. 16

EM 5.1

Engineering Emergency Response Plan

Rev. 37

EP/1/A/1800/001

Unit 1 EOP LOCA Cooldown

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0I

IP/0/A/3001/001

Limitorque Preventative Maintenance

Rev. 96

IP/0/A/3001/011 L

Diagnostic Testing Motor Operated Valves Using

Teledyne/Quiklook System

Rev. 7

MP/0/A/1200/146

B

Valve - Ball - Three Piece - Air Operated - Disassembly,

Repair, and Reassembly

Rev. 13

MP/0/A/1210/010

A

Valve Stem Lubrication for Motor Operated Valves

Rev. 8

NSD-121

Electromagnetic Interference On Plant Equipment

Rev. 2

NSD-806

Digital System Quality Program

Rev. 5

OP/0/A/1106/019

Keowee Hydro At Oconee

Rev. 108

OP/0/A/1106/027

Instrument Air System

Rev. 124

OP/1/A/1104/004

Low Pressure Injection System

Rev. 156

OP/1/A/1104/010

Low Pressure Service Water

Rev. 151

OP/3/A/1107/002

Duke Energy Oconee Nuclear Station Normal Power

Rev. 071

PT-1A-0150-015D Inter-system LOCA Leak Test

Rev. 47

PT/3/A/0610/28 A

Main Feeder Bus 2 Lockout Relay Test

Rev. 3

Work Orders

2139658,

2161814,

2161815,

20043385-01,

20052397-01,

20171404-14,

20185846-01,

20198416-01,

287412-01,

293942-14,

20304469-01,

20304469-01,

20328085-14,

20330007-01,

20355231-14,

20371279-14,

20390877-14

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2160810

2160810

TB Basement near valves LPSW-27 and LPSW-30 (TB, N of

Col. H-25, Elev. 775+15), also on the 3" piping

downstream of LPSW-27 and -30 (TB, N of Col. H-28, Elev.

775+15)

08/24/2015

20050014

20050015

20050015

20174777

20181184

20303828

20303829

20387447

20401703