IR 05000269/2023011

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection Report 05000269/2023011 and 05000270/2023011 and 05000287/2023011
ML23236A615
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 08/25/2023
From: James Baptist
Division of Reactor Safety II
To: Snider S
Duke Energy Carolinas
References
IR 2023011
Download: ML23236A615 (1)


Text

SUBJECT:

OCONEE NUCLEAR STATION - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000269/2023011 AND 05000270/2023011 AND 05000287/2023011

Dear Steven M. Snider:

On July 20, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Oconee Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Oconee Nuclear Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Oconee Nuclear Station.

August 25, 2023 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 05000269 and 05000270 and 05000287 License Nos. DPR-38 and DPR-47 and DPR-55

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000269, 05000270 and 05000287

License Numbers:

DPR-38, DPR-47 and DPR-55

Report Numbers:

05000269/2023011, 05000270/2023011 and 05000287/2023011

Enterprise Identifier:

I-2023-011-0027

Licensee:

Duke Energy Carolinas, LLC

Facility:

Oconee Nuclear Station

Location:

Seneca, SC

Inspection Dates:

June 26, 2023, to July 21, 2023

Inspectors:

P. Braaten, Senior Reactor Inspector

S. Downey, Senior Reactor Operations Engineer

D. Jackson, Senior Project Engineer

J. Montgomery, Senior Reactor Inspector

G. Ottenberg, Senior Reactor Inspector

A. Ruh, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Comprehensive Engineering Team Inspection at Oconee Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Inappropriate Procedure, Instructions and Evaluation for Online RBCU Cleaning Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000270/2023011-01 Open/Closed

[H.5] - Work Management 71111.21M Inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, when the licensee used an operating procedure and clearance that failed to address containment operability when breaching closed loop piping in containment during online reactor building cooling unit (RBCU) cleaning.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

For each component sample, the inspectors reviewed the licensing and design bases. The inspectors reviewed a sample of operator actions, corrective action program documents, internal and external operating experience, test records, preventive maintenance records, work orders, aging management programs, and performed a walkdown of the component or procedure. Additional component specific design attributes reviewed by the inspectors are:

(1)2B Reactor Building Cooling Unit (RBCU)

Compliance with Updated Final Safety Analysis Report (UFSAR), Technical Specifications (TS), and TS Bases

Surveillance testing & maintenance records

Design bases documents and calculations, including heat transfer capacity and design basis accident response capability

Aging Management

(2) MOV-3-V-186, Unit 3 Condenser Vacuum Breaker Motor-Operated Valve (MOV)

Visual inspection during walkdown of component

Design bases documents and setup calculation assumption agreement with installed configuration

Surveillance testing & maintenance records

Time critical operator actions (3)1B2 Reactor Coolant Pump (RCP) Seal

Compliance with UFSAR, TS, and TS Bases

Surveillance testing & maintenance records

Design bases documents and calculations

Flow diversion and inventory control (4)2RC-67, Pressurizer Code Safety Valve

Compliance with UFSAR, TS, and TS Bases

Surveillance testing & maintenance records

Upper, middle, and lower ring settings

Post event analysis and conclusions

(5) DCSF, Standby Shutdown Facility (SSF) Normal Battery

Compliance with UFSAR, TS, and TS Bases

Visual inspection during walkdown

Surveillance testing & maintenance records

Protection and coordination

Battery sizing calculation revision

(6) CT2, Unit 2 Startup Transformer

Compliance with UFSAR, TS, and Bases

Visual inspection during walkdown of various components in system

Environmental conditions

Design requirements

Surveillance testing & maintenance records

Periodic testing, inspection, and post-test analyses

Protection and coordination

Conformance with manufacturer instructions for installation, maintenance, testing and operation (7)3B Low Pressure Service Water (LPSW) Pump

Visual inspection during walkdown of component

Surveillance testing & maintenance records

Design bases documents and calculations, including net positive suction head

Abnormal operation procedure controls during first-siphon operation and turbine building flood scenarios

Integration with water hammer prevention system

Modifications (IP section 03.02) (4 Samples)

(1) EC 102450, Replace Unit 1 Low Pressure Service Water (LPSW) Outlet Piping for "A" RCPM Air Coolers with Stainless Steel, Revision 3; EC 102458, Replace Carbon Steel LPSW Piping from 1B RCP with Stainless Steel Inside Cavities, Revision 7; EC

===102459, Replace Carbon Steel LPSW Inlet Piping to 1A RCP with Stainless Steel Inside Cavities, Revision 9

(2) EC 417411, MCC 3XS4 Primary Control Power Fuse KTK-2 to KTK-3, Revision 0
(3) EC 408968, Unit 2 Start-Up Transformer (CT2) Open Phase Protection Equipment Installation & Tie-Ins, Revision 14
(4) EC 411560, Lake Level Reduction Commissioning Project, Revision 1 10 CFR 50.59 Evaluations/Screening (IP section 03.03)===

(1)10 CFR 50.59 Evaluation; AR 2004416, 10 CFR 50.59 Evaluation for EC 112474, Modify U1 SSF RCS (2)10 CFR 50.59 Evaluation; AR 2352826, Revision to ONS UFSAR 6.2.1 - LOCA Long-Term Containment Response (3)10 CFR 50.59 Evaluation; AR 2420522, R017 Unit Runback (4)10 CFR 50.59 Evaluation; AR 2373422, 10 CFR 50.59 Evaluation for EC 400480, Gardell CMSS upgrade (5)10 CFR 50.59 Evaluation; AR 2322877, 525 kV Switchyard 62B Breaker Failure Relay Replacement (6)10 CFR 50.59 Evaluation; AR 1974647, EC 96547, Rev. 0, U1 Main Power System Protective Relaying Upgrade, Revision 1 (7)10 CFR 50.59 Screening; AR 2356028, EC 408968, Rev. 15, Unit 2 Start-Up Transformer (CT2) Open Phase Protection Equipment Installation & Tie-Ins, 09/14/21 (8)10 CFR 50.59 Screening; AR 2278976, Replace 30", Class F, Expansion Joint

Operating Experience Samples (IP section 03.04) (1 Sample)

(1) NRC Information Notice 2018-09: Electrical Arc Flash Caused By Foreign Material Damages Fire Door

INSPECTION RESULTS

Inappropriate Procedure, Instructions and Evaluation for Online RBCU Cleaning Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000270/2023011-01 Open/Closed

[H.5] - Work Management 71111.21M Inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, when the licensee used an operating procedure and clearance that failed to address containment operability when breaching closed loop piping in containment during online reactor building cooling unit (RBCU) cleaning.

Description:

On April 17, 2023, the licensee began a planned maintenance activity on unit 2 to clean the heat exchanger tubes of the A RBCU in containment. This activity was being completed to proactively restore heat transfer capacity margin to the unit based on an observed declining performance trend during routine thermal performance testing. The licensee used operating procedure OP/2/A/1104/010 Low Pressure Service Water (LPSW),enclosure 4.7 Isolation of LPSW to 2A RBCU (MODE 1, 2, 3 or 4) to perform the isolation.

The enclosure was intended for isolating a leaking RBCU and was focused on precluding the possibility of thermal over-pressurization caused by heating of water trapped between the supply and return isolation valves during an accident condition. As a result, the steps required operators to vent the RBCU piping to containment to avoid this adverse effect. The procedure steps were sequenced such that a 1 vent valve (2LPSW-532), was opened prior to closing and deactivating the 2A RBCU outlet valve (2LPSW-18). While in this configuration, a direct pathway existed from containment to the environment (Lake Keowee) through the LPSW outlet piping of a size capable of exceeding the limit associated with operability of containment. The duration of this condition was approximately no more than three hours based on available information. The procedure required operators to enter Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.3 "Containment Isolation Valves," Condition C while the 1" vent valve was open, but this step was in error since the vent valve was neither a containment isolation valve nor associated with a particular containment penetration described in the Updated Final Safety Analysis Report (UFSAR).

The specified safety function impacted by breaching the LPSW system pressure boundary was actually containment itself per TS LCO 3.6.1 "Containment," Condition A, which has a 1-hour completion time for restoring containment operability before requiring the unit to be shutdown to Mode 3 within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. Contrary to the licensees topical report DUKE-QAPD-001-A, Quality Assurance Program Description, section D17.3.2.14, Document Control, the use of the enclosure and the errors it contained made it not appropriate for the circumstance that it was being used for.

Later, during the RBCU cleaning activity, the LPSW system was breached to a much larger extent to gain access to the tubesheet of the RBCU. While in this configuration, the 6-inch outlet LPSW piping penetration was isolated by the deactivated motor operated valve 2LPSW-18 and a second manual valve 2LPSW-81 by a clearance. These isolations were credited to permit continued operation by satisfying the required actions of TS LCO 3.6.3, Condition C, but, as previously discussed, TS LCO 3.6.1, Condition A was the proper condition to evaluate. Licensee procedure AD-OP-ALL-0200 Clearance and Tagging, section 5.5.29 required that "safety related clearances shall include consideration of TS adherence and LCOs," but the clearance did not identify applicability of TS LCO 3.6.1. Since the TS adherence error was not recognized, the clearance for the maintenance was ultimately an unrecognized compensatory measure used for maintaining the operability of containment during the maintenance period of approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Licensee procedure AD-OP-ALL-0105 Operability Determinations required a documented operability determination supporting basis and 10 CFR 50.59 evaluation for temporary facility changes that use compensatory measures to maintain operability of structures, systems or components (SSCs) affected by a deficient condition that may compromise the SSC's required capability. In this case, LPSW system breaches compromised the required leak tight barrier of containment, and the licensee implemented a change to the facility by modifying the design function of an RBCU outlet valve to be a closed leak tight valve in order to maintain containment operability. However, the suitability of these valves for maintaining containment operable was not formally evaluated by the licensee. Inspectors questioned whether leakage would be limited to less than or equal to the maximum allowable leakage rate (La) and if TS LCO 3.6.1 surveillance requirements would be satisfied by use of these valves. Inspectors noted that these valves were not described as containment isolation valves in the current version of the UFSAR and that 2LPSW-18 had been previously excluded from the 10 CFR Part 50, Appendix J, leakage testing program on the basis that the closed loop LPSW system piping, containing the RBCU, in containment was designed to remain intact and operating throughout a post-accident period. When the licensee breached this closed loop and credited the valve isolation, the licensee rendered the exclusion basis for the LPSW outlet penetration valve invalid. Licensee procedure AD-LS-ALL-0008, 10 CFR 50.59 Review Process, section 5.1.10 indicated that Intentionally creating a deficient condition and corresponding compensatory action as a means of bypassing a technical specification LCO action statement, action time, or other license condition is prohibited. In this case, the licensee created a deficient condition affecting containment and bypassed TS LCO 3.6.1 by mis-applying TS LCO 3.6.3. Additionally, the licensee did not review the compensatory action under 10 CFR 50.59 to confirm it would not affect other ancillary aspects of the facility.

At the completion of the cleaning activity, the licensee attempted to refill the 2A RBCU piping from the outlet direction while sequentially observing four different 1 vent valves for a solid stream of flow to indicate the piping was filled. Similar to the initial isolation sequence, while in this configuration, a direct pathway existed from containment to the environment through the LPSW outlet piping of a size capable of exceeding maximum allowable leakage rate for containment. The duration of this condition was approximately ten hours based on available information. A similar sequence of events was completed between April 18 and 19, 2023, for cleaning of the 2C RBCU.

Corrective Actions: The licensee developed actions to update operating procedures, design basis documents, evaluate licensee event reporting and to ensure any resulting compensatory measures are evaluated per 10 CFR 50.59.

Corrective Action References: ARs 2477886, 2477925, 2480047, 2480068

Performance Assessment:

Performance Deficiency: For the evolution of conducting online RBCU cleaning, the failure to utilize a procedure maintained appropriate for the circumstance per DUKE-QAPD-001-A, section D17.3.2.14, and failure to include consideration of TS adherence and LCOs during clearance development per AD-OP-ALL-0200, section 5.5.29, was a performance deficiency.

Specifically, operators used an enclosure of OP/2/A/1104/010 which was written for a different circumstance and neither the enclosure nor the developed clearance accurately considered TS LCO 3.6.1 adherence during the activity.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Configuration Control attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the performance deficiency created circumstances where breaches in containment exceeded the allowable leakage rate for containment operability.

Significance: The inspectors assessed the significance of the finding using the barrier integrity screening questions associated with reactor containment in Inspection Manual Chapter (IMC) 0609, Appendix A, Exhibit 3, subsection C, and because the finding represented an actual open pathway in the physical integrity of reactor containment through valves, IMC 0609 Appendix H, Containment Integrity SDP was used. The finding was considered to be a Type B finding because it was not expected to have any impact on the core damage frequency of the facility. Based on IMC 0609 Appendix H, Table 4.1, and section 03.03 of IMC 0308, Attachment 3, Appendix H, small lines (less than 2.5 inches in diameter for pressurized water reactors with large dry containments) would not generally contribute to LERF. Since the open pathway during the vent/drain/refill evolutions was limited to approximately 0.75 inches in diameter and any leakage through isolation valves used during the cleaning process (while the cooling coil heads were removed) was not expected to resemble a leak path through a 2.5-inch diameter hole, the finding screened as Green.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. In this case, the licensee performed a first-time evolution for an activity normally performed during outages, and did not demonstrate the characteristic of planning, controlling, and executing work activities such that nuclear safety functions would be maintained.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," required, in part, that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings." Contrary to the above, between April 17 and 19, 2023, the isolation and restoration procedures and instructions used for performing online RBCU cleaning were not appropriate to the circumstances. Specifically, neither the operating procedure nor the clearance properly identified how containment TS operability would be impacted when breaching the pressure boundary of the closed loop RBCU LPSW piping in containment.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 20, 2023, the inspectors presented the Comprehensive Engineering Team Inspection results to Steven M. Snider and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ONEI-0400-400

Revised Reactor Building Cooling Unit Requirements in

Support of 1-year Mission Times

2

OSC-11485

Failure Mode and Effects Analysis for EC 96547, Unit 1

Main Power Relay Upgrade

OSC-11802

Deentrainment Study of CCW Discharge Piping

OSC-11804

Evaluation of Oconee Motor Protective Device Trip Times

During Open Phase Conditions

OSC-11939

Oconee PRA Analysis of Implementation Options for Open

Phase Condition Protection

OSC-11956

Reactor Building Cooling Units Performance Test

007

OSC-2280

LPSW NPSHa and Minimum Required Lake Level

OSC-2322

SSF Suction Supply Availability

OSC-4300

(Elec) Protective Relay Settings

OSC-5349

Minimum Lake Level Required to Maintain Sufficient NPSH

to the LPSW Pumps via Gravity Flow

OSC-6195

U1/2/3, SSF 125VDC Power System Battery and Charger

Sizing, Voltage Drop and Short Circuit Analysis

OSC-6522

Turbine Building Flood CCW Reverse Flow Analysis

OSC-6550

Hydraulic Model of Condenser Service Water for Chillers A

and B

OSC-6577

CCW Turbine Building Flood Analysis

OSC-8064

ROTSG Long Term Containment Response Following a

Large Break LOCA

24

OSC-8064,

Appendix O

ROTSG Long-Term Containment Response Following a

Large-Break LOCA, ONS GOTHIC LBLOCA Cold Leg Break

Analyses with RBCU capacities adjusted for latest

AEROFIN Fouling Data

24

OSC-8508

Time Critical Valve Force Requirement Evaluation

Calculation [for 3V-0186]

Calculations

OSC-8769

Oconee PRA Low Pressure Service Water (LPSW) System

Notebook

71111.21M

Corrective Action

1774378,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

1884665,

286307,

25530,

2330063,

2392335,

2393844,

2401187,

2473099,

2317121,

278976,

278976,

2407202,

2474094,

294192,

2356028,

2333096,

2476828

CETI23: CLEAN/INSPECT SMALL OIL LEAK / 3HP-26

2476829

CETI23: INSPECT/REPLACE BROKEN, MISSING

ELECTRICAL COVER / 3HP-26

2477315

CETI23 - Restore Reference to OSS-254.00-00-2020

2477425

CETI23 Remove reference 2.5.2.1.2 (Duke Calc OSC-3610)

from OSS-0254.00-00-1035

2477474

CETI23 Reference Errors in DBDs OSS-254.00-00-1035 &

20

2477539

Non-Conservative Method Used in OSC-6550 for Change in

Solubility Calc

2477541

CETI23-Fusion records for NCR 02296030 and NCR

2356836 are incomplete records

2477607

CETI23 - error identified in OSC-11956

2477789

CETI2023 OSC-6195 has a conflict in regard to SSF battery

design margin

2477793

CETI23 - Issues with eRead communications provided to

OPS on CT2 OPP system

Corrective Action

Documents

Resulting from

Inspection

2477797

CETI2023 SSF 125 VDC Essential Power System DBD has

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

misleading statement

2477882

CETI23: OSC-8508 contains unsubstantiated assumptions

2477886

Possible Seat Leakage Not Mentioned in RBCU Online

Isolation Procedure

2477908

CETI23 - RBCU LPSW Temperature Design Control

Concern

2477925

Questions Regarding T.S. Entry During Online RBCU

Isolation

2477974

CETI23 - Training package OP-OC-SF-062 contains

incorrect info

2478002

CETI23 NRC identified questions about GARDEL CDA

classification

2478374

CETI23 - NRC Observation on Alarm Response Guides for

Open Phase Conditions

2479288

CETI23 - TS SR 3.7.8.3 is Non-Conservative

2479310

Areas for Improvement in AP/11

2479324

OSC-11802 Contains Incorrect Methodology for Determining

Deentrainment

2479697

CETI23 - Typographical Error in 50.59 Eval Changes

Intended Meaning

2479861

CETI23 - ONS Calculation OSC-6522 should have been

made historical or superceded

2479874

OSC-11802 Does Not Account for Air Leakage Thru

Concrete Joints/Cracks

2479888

CETI23 - Unit 1 MPR 11U1 and 11U3 LED Illuminated

2479940

OSC-5349 Needs to Be Updated

2480022

CETI23 - UFSAR DESCRIPTION OF PZR CODE SAFETY

RING SETTINGS REQUIRES

2480047

Containment Inoperable for >1 hr during 2A RBCU Cleaning

Restoration

2480068

Unrecognized Comp Measure for Containment Operability

2480075

CETI23 - Questions on EC 406309 50.59 Evaluation

Conclusions

2480078

Area for Improvement in Controlling LPSW Pumps in TB

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Flood Scenarios

2480084

IST Functions for RBCU Isolation Valves Need to be

Evaluated

2480089

CETI23 - Updates to 1,2,3V-186 EV attributes

0-1709

Three Line Diagram Transformers No. 2, 2T, & CT2

O-0325

Condenser Discharge Structure Units 1-3 Concrete &

Miscellaneous Steel Plan & Elevations

O-0336-A

Units 1-3 Condenser Cooling Water Pipe Emergency CCW

Discharge Pipe

O-0424-A

Piping Layout Miscellaneous Outside Yard Piping General

Layout

O-0510C

Piping Layout Miscellaneous Piping Sections and Details

Turbine Building

O-1400-I

Piping Layout Basement Floor Sections Turbine Building

OEE-71-01

Elementary Diagram Start-Up Trans. No. CT2 Diff. Lock-Out

Relay

OFD-100A-1.1

Flow Diagram of Reactor Coolant System

OFD-133A-02-01

Flow Diagram of Condenser Circulating Water System

(CCW Intake Pumps Discharge)

OFD-133A-02-02

Flow Diagram of Condenser Circulating Water System

(Normal Intake & Discharge)

OFD-133A-02-03

Flow Diagram of Condenser Circulating Water System

(Condensate Coolers)

OM 1300. --

0009.001

Elementary Diagram GEI-70357 364D900DA SH. 1

Transformer CT2

D4

OM 1300. --

0004.001

Vendor Drawing No. NP254501

OM 1300. --

0009.002

Station Service Transformer No CT2 Elementary Diagram

OM 1300. --

0012.001

CT2 Transformer G.E. Instruction Power Transformers

Drawings

OM-200-0150-

001

Vacuum Breaker Valve

Engineering

104170

Replace 30, Class F, Expansion Joint 3-C-MJ-0009 in EFW

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Changes

Supply

Clearance OPS-

2-23-LPS-2A

RBCU CLN-0661

DUKEONS008-

RPT-001

Study Report for Lake Keowee Water Level Reduction

IQ Review

Large Oil Filled Transformers

NEI 01-01

Guideline on Licensing Digital Upgrades

03/15/2002

NEI 19-02

Guidance for Assessing Open Phase Condition

Implementation

NRC Regulatory

Issue Summary

2002-22

Use of EPRI/NEI Joint Task Force Report, "Guideline on

Licensing Digital Upgrades: EPRI TR-102348, Revision 1,

NEI 01-01: A Revision of EPRI TR-102348 to Reflect

Changes to the 10 CFR 50.59 Rule"

11/25/2002

ON-1607.32-05-

03.EL_BECK RL

ON-1607.32-05-

03.EL_SEL RL

OP-OC-SF-062

Simulator Exercise Guide (SF-062)

11b

OSS-0254.00-00-

1035

(MECH) Design Basis Specification for Vacuum System

20

OSS-0254.00-00-

2000

(Elect) 4KV Essential Auxiliary Power System

OSS-0254.00-00-

2004

(Elect) 230 KV Switchyard System

OSS-0254.00-00-

20

(Elect) SSF 125 VDC Essential Power System

Miscellaneous

TI 2515/194, NRC

Temporary

Instruction

Inspection of Licensees Implementation of Industry Initiative

Association with the Open Phase Condition Design

Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

11/01/2017

AD-MN-ALL-0002

Foreign Material Exclusion

AP/0/4/1700/048

Loss of a Startup Transformer

Procedures

AP/0/A/1700/025

Standby Shutdown Facility Emergency Operating Procedure

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AP/1/A/1700/011

Recovery from Loss of Power

AP/1/A/1700/024

Loss of LPSW

AP/2/A/1700/010

Turbine Building Flood

AP/3/A/1700/027

Loss of Condenser Vacuum

006

CNM-1392.00-

0013.001

DOBLE Evaluation Criteria

EP/3/A/1800/001

0M, Encl 5.9

Unit 3 EOP, Enclosure 5.9, Extended EFDW Operation

2

IP/0/A/2007/001

Transformer Inspection and Maintenance

IP/0/A/2400/002

Substation Insulators, Lightning Arrestors, CCVT, and

Transmission Bus-Line Inspection and Maintenance

IP/0/A/3000/003

N

SSF Battery DCSF Service Test and Annual Surveillance

OP/0/A/1106/029

Control Room, Equipment Room, And Cable Room Chillers

OP/2/A/1102/020

D

SSF and Outside Rounds

103

OP/2/A/1107-02

Removal and Restoration of CP2 Transformer

OP/2/A/6102/014

Alarm Response Guide 2SA-14

PT-0-A-0160-006

Reactor Building Cooling Units Performance Test

PT/0/A/0120/033,

13.3

Time Critical Action Verification, Transfer of MDEFW

Suction to Hotwell

009

PT/3/A/0152/019

Vacuum System Valve Stroke Test

TE-MN-ALL-0002

Foreign Material Exclusion Level and Controls Screening

TE-MN-ALL-0202

Transformer and Apparatus Testing, Rev. 2

11/19/2021

Work Orders

20389789,

20458839,

20527603,

20416132,

20417510,

20551006,

20567981,

20583375,

236384,

20595716,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20383112-09,

20450277-01,

20450285-01,

20383112-01,

20450284-01,

209404-09,

209404-08,

209404-74,

209404-78