ML13246A110: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML13246A110
| number = ML13246A110
| issue date = 09/03/2013
| issue date = 09/03/2013
| title = 2013 Mid-Cycle Assessment Letter
| title = Mid-Cycle Assessment Letter
| author name = Ehrhardt F J
| author name = Ehrhardt F J
| author affiliation = NRC/RGN-II/DRP/RPB2
| author affiliation = NRC/RGN-II/DRP/RPB2

Revision as of 17:11, 28 April 2019

Mid-Cycle Assessment Letter
ML13246A110
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 09/03/2013
From: Ehrhardt F J
NRC/RGN-II/DRP/RPB2
To: Lynch T A
Southern Nuclear Operating Co
References
IR-13-006
Download: ML13246A110 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303

-1257 September 3, 2013 Mr. Tom A. Lynch Site Vice President

- Farley Southern Nuclear Operating Company, Inc.

7388 North State Highway 95 Columbia, AL 36319

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR JOSEPH M. FARLEY NUCLEAR PLANT (NRC INSPECTION REPORT 05000348, 364/201 3 00 6)

Dear Mr. Lynch:

On August 13, 2013, the NRC completed its mid

-cycle performance review of Joseph M. Farley Nuclear Plant, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 20 12 through June 30, 20 13. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility

. The NRC determined the performance at Joseph M. Farley Nuclear Plant Unit 1 and Unit 2 during the most recent quarter was within the Licensee Response Column of the NRC

's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e.,

Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31 , 201 4. Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end

-of-cycle performance review.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non

-publicly available correspondence.

We also plan on conducting Temporary Instruction 2515/182, "Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, Phase 2."

T Lynch 2 In accordance with 10 CFR 2.390 of the NRC

's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (404) 997-4 611 with any questions you have regarding this letter.

Sincerely, /RA/ Frank Ehrhardt, Chief Projects Branch 2 Division of Reactor Projects Docket Nos.

50-348, 50-364 License No.:

NPF-2, NPF-8

Enclosure:

Farley Inspection/Activity Plan (0 9/01/201 3 - 12/3 1/201 4) cc: Distribution via Listserv

_________________________

SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE JGW /RA/ FJE /RA/ NAME JWorosilo FEhrhardt DATE 08/22/2013 08/23/2013 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO T Lynch 3 Letter to T. A. Lynch from Frank Ehrhardt dated September 3, 2013

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR JOSEPH M. FARLEY NUCLEAR PLANT (NRC INSPECTION REPORT 05000348, 364/201 3 00 6) DISTRIBUTION

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMFarley Resource Institute of Nuclear Power Operations (INPO)

ROP Reports

FarleyInspection / Activity Plan 09/01/2013

-12/31/2014 Unit Number Page 1 of 2 09/03/2013 08:00:46 Report 22 No. of Staff on SitePlanned Dates Start EndInspection ActivityTitle 1 ISI-UNIT 1 INSERVICE INSPECTION 1 10/07/201310/11/2013 IP7111108P Inservice Inspection Activities - PWR 4 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 1, 2 11/04/201311/09/2013 IP71152B Problem Identification and Resolution 1, 2 11/18/201311/22/2013 IP71152B Problem Identification and Resolution 1 HS-TRIENNIAL HEAT SINK PERFORMANCE 1, 2 01/13/2014 01/17/2014 IP7111107T Heat Sink Performance 1TI-182-TI-182 BURIED PIPING/TANK - PHASE 2 1, 2 02/18/2014 02/20/2014 IP 2515/182Review of the Implementation of the Industry Init iative to Control Degradation of Underground Piping 1 EP-EP EXERCISE 1, 2 04/07/201404/11/2014 IP7111401 Exercise Evaluation 1, 2 04/07/201404/11/2014 IP71151Performance Indicator Verification 2OL RQ-REQUAL INSP 1, 2 03/10/2014 03/14/2014 IP7111111B Licensed Operator Requalification Program 6 CDBI-COMPONENT DESIGN BASES INSPECTION 1, 2 04/14/2014 04/18/2014 IP7111121 Component Design Bases Inspection 1, 2 05/05/2014 05/09/2014 IP7111121 Component Design Bases Inspection 1, 2 05/19/2014 05/23/2014 IP7111121 Component Design Bases Inspection 1, 2 06/02/2014 06/06/2014 IP7111121 Component Design Bases Inspection 4 TFPI-TRIENNIAL FIRE PROTECTION INSP 1, 2 07/14/2014 07/18/2014 IP7111105TFire Protection [Triennial]

1, 2 07/28/2014 08/01/2014 IP7111105TFire Protection [Triennial]

2OL EXAM-INITIAL LICENSE EXAM PREP 1 09/15/2014 09/19/2014 V23427FARLEY/OCTOBER 2014 INITIAL EXAM AT POWER FACILITIES 2OL EXAM-INITIAL LICENSE EXAM WEEK 1 1 10/06/2014 10/10/2014 V23427FARLEY/OCTOBER 2014 INITIAL EXAM AT POWER FACILITIES 2OL EXAM-INITIAL LICENSE EXAM WEEK 2 1 10/13/2014 10/17/2014 V23427FARLEY/OCTOBER 2014 INITIAL EXAM AT POWER FACILITIES 3 RP-RP OCCUPATIONAL BASELINE 1, 2 10/20/2014 10/24/2014 IP71124.01Radiological Hazard Assessment and Exposure Controls 1, 2 10/20/2014 10/24/2014 IP71124.02Occupational ALARA Planning and Controls 1, 2 10/20/2014 10/24/2014 IP71124.03In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/20/2014 10/24/2014 IP71124.04Occupational Dose Assessment This report does not include INPO and OUTAGE activities. This report shows only on-si te and announced inspection procedures.

FarleyInspection / Activity Plan 09/01/2013

-12/31/2014 Unit Number Page 2 of 2 09/03/2013 08:00:46 Report 22 No. of Staff on SitePlanned Dates Start EndInspection ActivityTitle 3 RP-RP OCCUPATIONAL BASELINE 1, 2 10/20/2014 10/24/2014 IP71124.05 Radiation Monitoring Instrumentation 1, 2 10/20/2014 10/24/2014 IP71151Performance Indicator Verification 1 ISI-UNIT 2 IN-SERVICE INSPECTION 2 10/27/2014 10/31/2014 IP7111108P Inservice Inspection Activities - PWR 2 RP-RP OCCUPATIONAL BASELINE WEEK2 1, 2 11/03/201411/07/2014 IP71124.01Radiological Hazard Assessment and Exposure Controls 1, 2 11/03/201411/07/2014 IP71124.02Occupational ALARA Planning and Controls 1, 2 11/03/201411/07/2014 IP71124.03In-Plant Airborne Radioactivity Control and Mitigation 1, 2 11/03/201411/07/2014 IP71124.04Occupational Dose Assessment 1, 2 11/03/201411/07/2014 IP71124.05 Radiation Monitoring Instrumentation 1, 2 11/03/201411/07/2014 IP71151Performance Indicator Verification 1 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 2 11/03/201411/07/2014 IP7111108P Inservice Inspection Activities - PWR Comments: This report does not include INPO and OUTAGE activities. This report shows only on-si te and announced inspection procedures.