NL-23-0628, Readiness for Supplemental Inspection EA-22-101
| ML23207A131 | |
| Person / Time | |
|---|---|
| Site: | Farley |
| Issue date: | 07/26/2023 |
| From: | Brown K Southern Nuclear Operating Co |
| To: | NRC/RGN-II, Document Control Desk |
| References | |
| NL-23-0628, EA-22-101 | |
| Download: ML23207A131 (1) | |
Text
.. Southern Nuclear Regulatory Affairs July 26, 2023 3535 Colonnade Parkway Birmingham, AL 35243 205 992 5000 Docket Nos.: 50-348 50-364 NL-23-0628 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant, Units 1 and 2 Readiness for Supplemental Inspection EA-22-101 Ladies and Gentlemen:
In the Nuclear Regulatory Commission's (NRC) final significance determination letter dated March 30, 2023 (Reference 1 ), Southern Nuclear Operating Company (SNC) was requested to notify the NRC staff when ready for the supplemental inspection at the Farley Nuclear Plant (FNP). SNC has completed the investigations associated with this issue and is ready to accommodate this inspection.
This letter contains no NRC commitments. Should you have any questions regarding this information, please contact Ryan Joyce, Regulatory Affairs Licensing Manager, at 205-992-6468.
Respectfully submitted, Keith Brown Director, Regulatory Affairs cc:
Regional Administrator, Region II NRR Project Manager - Farley Nuclear Plant 1 & 2 Senior Resident Inspector - Farley Nuclear Plant 1 & 2 RTYPE: CFA04.054
References:
- 1. Farley Nuclear Plant, Units 1 & 2 - Final Significance Determination for a Security-Related Greater Than Green Finding, Notice of Violation and Assessment Followup Letter, Inspection Report Nos. 05000348/2023440 and 05000364/2023440, dated March 30, 2023.