Report 22, Inspection/Activity Plan 01/01/2011 - 06/30/2012
ML110630148
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 03/04/2011
From:
NRC/RGN-II
To:
Southern Nuclear Operating Co
Shared Package
ML110630133 List:
References
IR-11-001
Download: ML110630148 (2)


Text

Page 1 of 2 Farley 03/04/2011 08:54:42 Inspection / Activity Plan Report 22 01/01/2011 - 06/30/2012 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EB3 HS - HEAT SINK 1 1, 2 02/14/2011 02/18/2011 IP 7111107T Heat Sink Performance TFPI - 805 TFPI 6 1, 2 03/07/2011 03/11/2011 IP 7111105P Fire Protection-NFPA 805 Transition Period [Triennial]

1, 2 03/21/2011 03/25/2011 IP 7111105P Fire Protection-NFPA 805 Transition Period [Triennial]

OL EXAM - INITIAL EXAM PREP 6 1 04/18/2011 04/22/2011 V23349 FARLEY/MAY 2011 EXAM AT POWER FACILITIES PSB1EP - EMERGENCY PREPAREDNESS INSPECTION 1 1, 2 05/02/2011 05/06/2011 IP 7111402 Alert and Notification System Testing 1, 2 05/02/2011 05/06/2011 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 05/02/2011 05/06/2011 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/02/2011 05/06/2011 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 05/02/2011 05/06/2011 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM - WEEK 1 5 1 05/09/2011 05/14/2011 V23349 FARLEY/MAY 2011 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 2 5 1 05/16/2011 05/20/2011 V23349 FARLEY/MAY 2011 EXAM AT POWER FACILITIES PI&R - PROBLEM IDENIFICATION AND RESOLUTION 4 1, 2 06/06/2011 06/10/2011 IP 71152B Identification and Resolution of Problems 1, 2 06/20/2011 06/24/2011 IP 71152B Identification and Resolution of Problems CDBI - COMPONENT DESIGN BASES INSPECTION 9 1, 2 08/15/2011 08/19/2011 IP 7111121 Component Design Bases Inspection 1, 2 08/29/2011 09/02/2011 IP 7111121 Component Design Bases Inspection 1, 2 09/12/2011 09/16/2011 IP 7111121 Component Design Bases Inspection 1, 2 09/26/2011 09/30/2011 IP 7111121 Component Design Bases Inspection EB3 ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 10/17/2011 10/21/2011 IP 7111108P Inservice Inspection Activities - PWR EB3SGISI - UNIT 2 SG IN-SERVICE INSPECTION 2 2 10/17/2011 10/21/2011 IP 7111108P Inservice Inspection Activities - PWR PSB1-RP - RP HAZARD ASSESSMENT 2 1, 2 10/24/2011 10/28/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls PSB1-RP - RP PUBLIC RADIATION PROTECTION INSP 4 1, 2 12/12/2011 12/16/2011 IP 71124.04 Occupational Dose Assessment 1, 2 12/12/2011 12/16/2011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 12/12/2011 12/16/2011 IP 71124.07 Radiological Environmental Monitoring Program This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Farley 03/04/2011 08:54:42 Inspection / Activity Plan Report 22 01/01/2011 - 06/30/2012 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1-RP - RP PUBLIC RADIATION PROTECTION INSP 4 1, 2 12/12/2011 12/16/2011 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 12/12/2011 12/16/2011 IP 71151 Performance Indicator Verification MC&A - MC&A INSPECTION 2 1, 2 01/02/2012 12/31/2012 IP 7113011 Material Control and Accounting (MC&A)

EB3 ISI - UNIT 1 INSERVICE INSPECTION 1 1 04/02/2012 04/06/2012 IP 7111108P Inservice Inspection Activities - PWR PSB1-RP - OCCUPATIONAL RP BASELINE WK1 3 1, 2 04/02/2012 04/06/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/02/2012 04/06/2012 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 04/02/2012 04/06/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/02/2012 04/06/2012 IP 71124.04 Occupational Dose Assessment 1, 2 04/02/2012 04/06/2012 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 04/02/2012 04/06/2012 IP 71151 Performance Indicator Verification EB3SGISI - UNIT 1 SG INSERVICE INSPECTION 1 1 04/09/2012 04/13/2012 IP 7111108P Inservice Inspection Activities - PWR PSB1-RP - OCCUPATIONAL RP BASELINE WK2 3 1, 2 04/16/2012 04/20/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/16/2012 04/20/2012 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 04/16/2012 04/20/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/16/2012 04/20/2012 IP 71124.04 Occupational Dose Assessment 1, 2 04/16/2012 04/20/2012 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 04/16/2012 04/20/2012 IP 71151 Performance Indicator Verification PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 3 1, 2 05/07/2012 05/11/2012 IP 7111401 Exercise Evaluation 1, 2 05/07/2012 05/11/2012 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/07/2012 05/11/2012 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM PREP 4 1 05/28/2012 06/01/2012 V23373 FARLEY / JUNE 2012 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 1 4 1 06/18/2012 06/22/2012 V23373 FARLEY / JUNE 2012 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 2 4 1 06/25/2012 06/29/2012 V23373 FARLEY / JUNE 2012 EXAM AT POWER FACILITIES This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure