Inspection / Activity Plan Page 1 of 2 09/01/2010 13:27:59 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Farley OL RQ
- REQUAL INSPECTION 5
1, 2 IP Licensed Operator Requalification Program 7111111B 09/20/2010 09/24/2010 PSB1-TI
- TI-179 NSTS VERIFICATION 3
1, 2 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 10/18/2010 10/22/2010 1, 2 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 11/01/2010 11/05/2010 EB3ISI
- UNIT 1 INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 10/18/2010 10/22/2010 EB3TI172
- EB3 RX COOLANT SYS DM BUTT WELDS 1
1 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 10/18/2010 10/22/2010 PSB1-RP
- RP OCCUPATIONAL BASELINE WEEK1 3
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/18/2010 10/22/2010 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/18/2010 10/22/2010 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/18/2010 10/22/2010 1, 2 IP Occupational Dose Assessment 71124.04 10/18/2010 10/22/2010 1, 2 IP Radiation Monitoring Instrumentation 71124.05 10/18/2010 10/22/2010 1, 2 IP Performance Indicator Verification 71151 10/18/2010 10/22/2010 EB3SGISI
- UNIT 1 SG INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 10/25/2010 10/29/2010 PSB1-RP
- RP OCCUPATIONAL BASELINE WEEK 2 2
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/01/2010 11/05/2010 1, 2 IP Occupational ALARA Planning and Controls 71124.02 11/01/2010 11/05/2010 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/01/2010 11/05/2010 1, 2 IP Occupational Dose Assessment 71124.04 11/01/2010 11/05/2010 1, 2 IP Radiation Monitoring Instrumentation 71124.05 11/01/2010 11/05/2010 1, 2 IP Performance Indicator Verification 71151 11/01/2010 11/05/2010 PSB1EP
- EMERGENCY PREPAREDNESS EXERCISE 3
1, 2 IP Exercise Evaluation 7111401 12/06/2010 12/10/2010 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 12/06/2010 12/10/2010 1, 2 IP Performance Indicator Verification 71151 12/06/2010 12/10/2010 EB3HS
- HEAT SINK 1
1, 2 IP Heat Sink Performance 7111107T 01/31/2011 02/04/2011 TFPI
- TRIENNIAL FIRE PROTECTION INSPECTION 6
1, 2 IP Fire Protection [Triennial]
7111105T 03/07/2011 03/11/2011 1, 2 IP Fire Protection [Triennial]
7111105T 03/21/2011 03/25/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Inspection / Activity Plan Page 2 of 2 09/01/2010 13:27:59 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Farley OL EXAM
- INITIAL EXAM PREP 6
1 FARLEY/MAY 2011 EXAM AT POWER FACILITIES V23349 04/18/2011 04/22/2011 PSB1EP
- EMERGENCY PREPAREDNESS INSPECTION 1
1, 2 IP Alert and Notification System Testing 7111402 05/02/2011 05/06/2011 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 05/02/2011 05/06/2011 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 05/02/2011 05/06/2011 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 05/02/2011 05/06/2011 1, 2 IP Performance Indicator Verification 71151 05/02/2011 05/06/2011 OL EXAM
- INITIAL EXAM - WEEK 1 5
1 FARLEY/MAY 2011 EXAM AT POWER FACILITIES V23349 05/09/2011 05/14/2011 OL EXAM
- INITIAL EXAM - WEEK 2 5
1 FARLEY/MAY 2011 EXAM AT POWER FACILITIES V23349 05/16/2011 05/20/2011 PI&R
- PROBLEM IDENIFICATION AND RESOLUTION 4
1, 2 IP Identification and Resolution of Problems 71152B 06/06/2011 06/10/2011 1, 2 IP Identification and Resolution of Problems 71152B 06/20/2011 06/24/2011 CDBI
- COMPONENT DESIGN BASES INSPECTION 9
1, 2 IP Component Design Bases Inspection 7111121 08/15/2011 08/19/2011 1, 2 IP Component Design Bases Inspection 7111121 08/29/2011 09/02/2011 1, 2 IP Component Design Bases Inspection 7111121 09/12/2011 09/16/2011 1, 2 IP Component Design Bases Inspection 7111121 09/26/2011 09/30/2011 EB3 ISI
- UNIT 2 IN-SERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 10/17/2011 10/21/2011 PSB1-RP
- RP HAZARD ASSESSMENT 2
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/17/2011 10/21/2011 EB3SGISI
- UNIT 2 SG IN-SERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 10/24/2011 10/28/2011 PSB1-RP
- RP PUBLIC RADIATION PROTECTION INSP 3
1, 2 IP Occupational Dose Assessment 71124.04 12/12/2011 12/16/2011 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 12/12/2011 12/16/2011 1, 2 IP Radiological Environmental Monitoring Program 71124.07 12/12/2011 12/16/2011 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 12/12/2011 12/16/2011 1, 2 IP Performance Indicator Verification 71151 12/12/2011 12/16/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure