|
|
(2 intermediate revisions by the same user not shown) |
Line 3: |
Line 3: |
| | issue date = 08/04/2010 | | | issue date = 08/04/2010 |
| | title = Record of Conference Call - Discuss Dominion Kewaunee'S Response to Recent Steam Generator Divider Plate RAI | | | title = Record of Conference Call - Discuss Dominion Kewaunee'S Response to Recent Steam Generator Divider Plate RAI |
| | author name = Daily J W | | | author name = Daily J |
| | author affiliation = NRC/NRR/DLR/RPOB | | | author affiliation = NRC/NRR/DLR/RPOB |
| | addressee name = Aitken P C, Hiser A L, Karwoski K J, Vaucher R | | | addressee name = Aitken P, Hiser A, Karwoski K, Vaucher R |
| | addressee affiliation = NRC/NRR, NRC/NRR/DCI, NRC/NRR/DLR | | | addressee affiliation = NRC/NRR, NRC/NRR/DCI, NRC/NRR/DLR |
| | docket = 05000305 | | | docket = 05000305 |
Line 14: |
Line 14: |
| | page count = 2 | | | page count = 2 |
| | project = TAC:MD9408 | | | project = TAC:MD9408 |
| | stage = RAI | | | stage = Other |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:From: Daily, John Sent: Wednesday, August 04, 2010 9:17 AM To: Hiser, Allen; Karwoski, Kenneth; 'Rachel Vaucher'; 'Paul Aitken' Cc: Robinson, Jay; Brady, Bennett | | {{#Wiki_filter:From: Daily, John Sent: Wednesday, August 04, 2010 9:17 AM To: Hiser, Allen; Karwoski, Kenneth; 'Rachel Vaucher'; 'Paul Aitken' Cc: Robinson, Jay; Brady, Bennett |
|
| |
|
| ==Subject:== | | ==Subject:== |
| Record of conference call - Discuss Dominion Kewaunee's response to recent Steam Generator Divider Plate RAI LICENSEE: Dominion Energy Kewaunee, Inc. | | Record of conference call - Discuss Dominion Kewaunee's response to recent Steam Generator Divider Plate RAI LICENSEE: Dominion Energy Kewaunee, Inc. |
| FACILITY: Kewaunee Power Station | | FACILITY: Kewaunee Power Station |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF DISCUSSION ON JULY 29, 2010, BETWEEN DOMINION ENERGY KEWAUNEE, INC. AND THE U.S. NUCLEAR REGULATORY COMMISSION TO DISCUSS DOMINION RESPONSE TO RAI ON STEAM GENERATOR DIVIDER PLATE (TAC NO. MD9408) | | OF DISCUSSION ON JULY 29, 2010, BETWEEN DOMINION ENERGY KEWAUNEE, INC. AND THE U.S. NUCLEAR REGULATORY COMMISSION TO DISCUSS DOMINION RESPONSE TO RAI ON STEAM GENERATOR DIVIDER PLATE (TAC NO. MD9408) |
| | On July 29, 2010, the U.S. Nuclear Regulatory Commission (NRC or the staff) conducted a telephone conference call (teleconference) with representatives from Dominion Energy Kewaunee, Inc. (DEK or the applicant). Applicant invited representatives from Westinghouse, EPRI, and PSE&G Salem Nuclear Plant to also listen in/participate on the call. The staff requested the call in order to obtain a better understanding of applicants Request for Additional Information (RAI) Response dated July 22, 2010, to RAI 3.1.2.2.13-01, Cracking Due to PWSCC in SG Divider Plates, as staff continues to review applicants response. |
| | Staff, the applicant, and certain of applicants invitees discussed applicants RAI response. Staff stated that it is continuing to evaluate applicants RAI response, and that follow-up RAIs on the issue could be forthcoming in order to fully resolve the issue as it relates to applicants license renewal application for the Kewaunee Power Station. |
| | A list of discussion participants is enclosed. |
| | LIST OF PARTICIPANTS DISCUSSION DOMINION ENERGY KEWAUNEE, INC. |
| | KEWAUNEE POWER STATION July 29, 2010 PARTICIPANTS AFFILIATION John Daily U.S. Nuclear Regulatory Commission (NRC) |
| | Allen Hiser U.S. Nuclear Regulatory Commission (NRC) |
| | Ken Karwoski U.S. Nuclear Regulatory Commission (NRC) |
| | Rachel Vaucher U.S. Nuclear Regulatory Commission (NRC) |
| | Paul Aitken Dominion Energy Kewaunee, Inc. (Dominion) |
|
| |
|
| On July 29, 2010, the U.S. Nuclear Regulatory Commission (NRC or the staff) conducted a telephone conference call (teleconference) with representatives from Dominion Energy Kewaunee, Inc. (DEK or the applicant). Applicant invited representatives from Westinghouse, EPRI, and PSE&G Salem Nuclear Plant to also listen in/participate on the call. The staff requested the call in order to obtain a better understanding of applicant's Request for Additional Information (RAI) Response dated July 22, 2010, to RAI 3.1.2.2.13-01, Cracking Due to PWSCC in SG Divider Plates, as staff continues to review applicant's response.
| | Marc Hotchkiss Dominion Energy Kewaunee, Inc. (Dominion) |
| Staff, the applicant, and certain of applicant's invitees discussed applicant's RAI response. Staff stated that it is continuing to evaluate applicant's RAI response, and that follow-up RAIs on the issue could be forthcoming in order to fully resolve the issue as it relates to applicant's license renewal application for the Kewaunee Power Station.
| | John Voss Dominion Energy Kewaunee, Inc. (Dominion) |
| A list of discussion participants is enclosed.
| | Viki Armentrout Dominion Energy Kewaunee, Inc. (Dominion) |
| | | Charles Tomes Dominion Energy Kewaunee, Inc. (Dominion) |
| LIST OF PARTICIPANTS DISCUSSION DOMINION ENERGY KEWAUNEE, INC. KEWAUNEE POWER STATION July 29, 2010 PARTICIPANTS AFFILIATIONJohn Daily U.S. Nuclear Regulatory Commission (NRC) Allen Hiser U.S. Nuclear Regulatory Commission (NRC)
| | Chris Cassino Westinghouse Herm Lagally Westinghouse Helen Cothron EPRI Pat Fabian PSE&G Salem Nuclear Station Sam Speer PSE&G Salem Nuclear Station John Daily, MBA, PMP Senior Project Manager, Division of License Renewal Office of Nuclear Reactor Regulation USNRC John.Daily@NRC.Gov (301) 415-3873}} |
| Ken Karwoski U.S. Nuclear Regulatory Commission (NRC) Rachel Vaucher U.S. Nuclear Regulatory Commission (NRC) Paul Aitken Dominion Energy Kewaunee, Inc. (Dominion)
| |
| Marc Hotchkiss Dominion Energy Kewaunee, Inc. (Dominion) John Voss Dominion Energy Kewaunee, Inc. (Dominion) | |
| Viki Armentrout Dominion Energy Kewaunee, Inc. (Dominion) | |
| Charles Tomes Dominion Energy Kewaunee, Inc. (Dominion) | |
| Chris Cassino Westinghouse Herm Lagally Westinghouse Helen Cothron EPRI Pat Fabian PSE&G Salem Nuclear Station Sam Speer PSE&G Salem Nuclear Station John Daily, MBA, PMP Senior Project Manager, Division of License Renewal Office of Nuclear Reactor Regulation USNRC John.Daily@NRC.Gov (301) 415-3873}} | |
Letter Sequence Other |
---|
|
Results
Other: ML083370231, ML090530003, ML091470382, ML091900081, ML091900449, ML092790582, ML092800441, ML093230257, ML093240038, ML093260003, ML093310360, ML093431339, ML102160127
|
MONTHYEARML0833702312008-12-0303 December 2008 Project Manager Change for the License Renewal Review for Kewaunee Power Station Project stage: Other ML0833702452008-12-0909 December 2008 Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application Project stage: Approval ML0905300032009-03-23023 March 2009 Request to Supplement the Kewaunee Power Station License Renewal Application in Regards to the Use of the Work Control Process as an Aging Management Program Project stage: Other ML0907607862009-04-0303 April 2009 License Renewal Application Review, Request for Additional Information - Balance of Plant Scoping and Screening Project stage: RAI ML0908609462009-04-15015 April 2009 Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application Project stage: Approval ML0911201992009-04-30030 April 2009 RAI, Review of the License Renewal Application - Scoping & Screening Methodology Project stage: RAI ML0914703822009-05-28028 May 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Kewaunee Power Station License Renewal Application Review Project stage: Other ML0911903892009-07-0707 July 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - Leak-Before-Break Project stage: RAI ML0918109582009-07-13013 July 2009 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application - Aging Management Programs Project stage: RAI ML0919000812009-07-13013 July 2009 Scoping and Screening Audit Report Regarding the Kewaunee Power Station, License Renewal Application Project stage: Other ML0918805552009-07-16016 July 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - Structures Scoping/Fire Protection Project stage: RAI ML0921006032009-07-28028 July 2009 LRA Review - Slides Public Meeting July 28, 2009 Project stage: Request ML0922306182009-08-0606 August 2009 Response to Request for Additional Information for the Review of the License Renewal Application - Leak Before Break/Boral Project stage: Response to RAI ML0921006122009-08-10010 August 2009 07/28/2009 Summary of Public Meeting Related to the Review of the Kewaunee Power Station License Renewal Application Project stage: Meeting ML0919004492009-08-12012 August 2009 AMP Audit Report Regarding the Kewaunee Power Station, License Renewal Application Project stage: Other ML0923200932009-08-17017 August 2009 Response to Request for Additional Information for Review of License Renewal Application - Aging Management Programs Project stage: Response to RAI ML0921205462009-08-28028 August 2009 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application - Aging Management Review Results Project stage: RAI ML0927100452009-09-25025 September 2009 Supplemental Information for the Review of the License Renewal Application - Changes to the Work Control Process Aging Management Program Project stage: Supplement ML0927905852009-10-13013 October 2009 Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application Project stage: Approval ML0923900632009-10-13013 October 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - Aging Management Review Results Project stage: RAI ML0927905822009-10-14014 October 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Kewaunee Power Station License Renewal Application Review Project stage: Other ML0928004412009-10-16016 October 2009 Summary of Conference Call with Dominion Energy Kewaunee Inc., to Discuss the ASME Section XI Inservice Inspection Aging Management Program Project stage: Other ML0918908362009-11-20020 November 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML0932302572009-11-27027 November 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Program for Neutron Absorbing Material Project stage: Other ML0932400382009-11-27027 November 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Inaccessible Cables Program Project stage: Other ML0932600032009-12-14014 December 2009 Wcp AMP Audit Report Regarding the Kewaunee Power Station License Renewal Application Project stage: Other ML0933104432009-12-16016 December 2009 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - AMRs Project stage: RAI ML0934313392009-12-16016 December 2009 Summary of Telephone Conference Call on December 9, 2009, Between Dominion Energy Kewaunee Inc., and U.S. NRC to Discuss Tables Referenced in the Work Control Process Amendment Letter Project stage: Other ML0933103602009-12-17017 December 2009 Safety Project Manager Change for the License Renewal Review for the Kewaunee Power Station Project stage: Other ML0935003062010-01-0404 January 2010 Request for Additional Information Regarding the Review of the Kewaunee Power Station License Renewal Application - AMRs Project stage: RAI ML1001104472010-01-13013 January 2010 Summary of Telephone Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Duplicate RAI Number Project stage: RAI ML1002200662010-01-21021 January 2010 Response to Request for Additional Information for the Review of the License Renewal Application - Aging Management Review/Aging Management Program Project stage: Response to RAI ML1003210772010-02-16016 February 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and USNRC to Discuss Certain Request for Additional Information on Structural Items Project stage: RAI ML1006903992010-03-11011 March 2010 Request for Additional Information for the Review of the Kewaunee Power Station, License Renewal Application Project stage: RAI ML1007107412010-03-31031 March 2010 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and the NRC to Discuss Certain RAI Responses on Two Mechanical Systems Project stage: RAI ML1009503792010-04-14014 April 2010 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML1012504442010-05-10010 May 2010 Revision of Schedule for the Conduct of the Review of the Kewaunee Power Station License Renewal Application TAC MD9408) Project stage: Approval ML1014103222010-05-27027 May 2010 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML1016003242010-06-16016 June 2010 Letter Change in Schedule for Review of the Kewaunee Power Station License Renewal Application Safety Evaluation Project stage: Approval ML1011903452010-07-15015 July 2010 Transmittal of Kewaunee Safety Evaluation Report with Open Items Related to License Renewal of Kewaunee Power Station Project stage: Approval ML1021601272010-08-0404 August 2010 Record of Conference Call - Discuss Dominion Kewaunee'S Response to Recent Steam Generator Divider Plate RAI Project stage: Other ML1025003572010-09-10010 September 2010 Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI ML1023901982010-09-16016 September 2010 08/26/10 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and NRC Concerning a D-RAI Pertaining to the Kewaunee Power Station License Renewal Application Project stage: RAI ML1024402012010-09-16016 September 2010 08/31/10 Summary of Telephone Conference Call Between Dominion Energy Kewaunee, Inc. and the U.S. Nuclear Regulatory Commission Concerning a Draft Request for Additional Information Pertaining to the Kewaunee Power Station License Renewal A Project stage: Draft RAI ML1030001312010-11-0404 November 2010 Letter- Transmittal of Safety Evaluation Report Related to the License Renewal of Kewaunee Power Station Project stage: Approval ML12233A7332012-08-20020 August 2012 Entergy Pre-Filed Evidentiary Hearing Exhibit ENT000562, Letter from J. Daily, NRC, to D. Heacock, President, Dominion Energy Kewaunee, Inc., Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Ap Project stage: RAI ML12340A7312012-08-20020 August 2012 Official Exhibit - ENT000562-00-BD01 - Letter from J. Daily, NRC, to D. Heacock, President, Dominion Energy Kewaunee, Inc., Request for Additional Information for the Review of the Kewaunee Power Station License Renewal Application Project stage: RAI 2009-08-12
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24030A0672024-01-26026 January 2024 Email EA Fonsi Notice to Kewaunee Solutions for Exemptions on Site Restoration Activities ML23268A4362023-09-21021 September 2023 Extension Date Approval for Request for Additional Information for Exemptions on Site Restoration Activities ML23134A0012023-05-0909 May 2023 NRC Email Acceptance - Kewaunee Solutions Exemption Request Regarding Decommissioning Trust Funds for Site Restoration Activities (Docket No. 50-305) ML23129A0672023-05-0505 May 2023 NRC Email Acceptance - Kewaunee Solutions Exemption Request for Low-Level Radioactive Waste Transport Change from 20 to 45 Days Acknowledgement ML23100A0032023-04-0404 April 2023 Solutions - Acknowledgement Email Regarding Exemption Regarding Decommissioning Trust Funds for Site Restoration Activities (Docket No 50-305) ML23094A1442023-03-31031 March 2023 Solutions - Acknowledgement Email Regarding Exemption for Low-Level Radioactive Waste Transport within 20 Days (Docket No. 50-305) ML22108A1762022-04-14014 April 2022 E-mail: Proposed Order Conditions for In-Direct Transfer of Licenses Held by Energysolutions, LLC (Zion, TMI Unit-2, La Crosse Boiling Water Reactor, Kewaunee, Energysolutions Radioactive Materials License, and Energysolutions Export Licens ML22053A2992022-02-18018 February 2022 Email - Additional Time for Request for Additional Information Response Regarding Kewaunee Solutions Decommissioning Quality Assurance Program; NRC Response Included; (EPID L-2021-LLO-0002 and L-2021-DP3-0000) ML22027A3642022-01-26026 January 2022 KPS: CY2022 Inspection Plan, Docket No. 05000305, License No. DPR-43 ML22007A3182022-01-0707 January 2022 E-mail from C. Adams, State of Wisconsin, to K. Sturzebecher, NRC, Notification and Request Kewaunee Power Station License Transfer (L-2021-LLO-002) ML21348A0522021-12-0303 December 2021 E-mail to P. Schmidt, State of Wisconsin, from K. Sturzebecher, NRC - Notification and Request Kewaunee Power Station License Transfer ML21096A1332021-04-0606 April 2021 E-mail for Approval of Proprietary Withholding for Dominion Energy Exemptions for the Magnastor Storage Cask ML20015A3002020-01-14014 January 2020 KPS: CY2020 Master Inspection Plan ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19072A0652019-03-0606 March 2019 Conversation Record with T. Szymanski/Dominion Energy Response to 10 CFR 72.30(c)(3) in Triennial Update for Kewaunee ML19070A2642019-03-0505 March 2019 Email Conversation with T. Szymanski/Dominion Energy Decommissioning Funding Plan (Dfp): Kewaunee ML18351A2742018-12-17017 December 2018 KPS: CY2019 Master Inspection Plan ML17354A9382017-12-20020 December 2017 CY2018 Master Inspection Plan ML17156A0032017-06-0202 June 2017 NRR E-mail Capture - Acceptance for Review of Revision 24 to the Dominion Nuclear Facility Quality Assurance Program Description (QAPD) Topical Report (CAC Nos. MF9732-MF9739) ML17040A0222016-10-18018 October 2016 Wisconsin State Notification (LAR259-L53082) ML16287A7142016-10-13013 October 2016 E-mail - Request for Additional Information: Dominion Energy Kewaunee, Dominion Nuclear Connecticut and Virginia Electric Power Company Nuclear Facility Quality Assurance Program Description Topical Report ML16041A2732016-02-10010 February 2016 Final RAIs Regarding LAR 259 ML16054A2382015-10-14014 October 2015 E-44108 Attachment 8 E-mail from Stewart J. Yuen (Kewaunee Power Station) to Don Shaw (Areva) for Kewaunee Power Station ML15090A4872015-03-26026 March 2015 OEDO-15-00251 - Michael Mulligan, Citizen Ltr 2.206 - Emergency Ultrasonic Inspection Test or Best Available Flaw Detection Technology for USA Reactor Plants Similar to the Thousands of Cracks Discovered in Belgium Nuclear Power Plants ML15071A2752015-03-12012 March 2015 NRR E-mail Capture - Request for Additional Information on Kewaunee 50.54(p) Changes to Physical Security Plan - TAC MF5779 ML15057A2192015-02-25025 February 2015 NRR E-mail Capture - Acceptance Review: Dominion Fleet-Request for Approval of Cyber Security Plan (CSP) Revised Implementation Schedule ML14258A7432014-09-0505 September 2014 NRR E-mail Capture - FW: Comparison of Crystal River'S Exemption Secy Paper with Kewaunee'S ML14251A0972014-08-22022 August 2014 NRR E-mail Capture - Draft RAI to Kewaunee Power Station on Control Room Staffing Issue ML14164A0742014-06-0202 June 2014 NRR E-mail Capture - Draft Request for Additional Information Concerning Dek'S Request for Exemption from Conducting Annual Force-on-Force Exercises at Kewaunee Power Station ML14132A2062014-04-27027 April 2014 NRR E-mail Capture - Kewaunee Amendment Request for Emergency Plan Changes MF3411 - Draft RAIs ML14155A0402014-04-0707 April 2014 NRR E-mail Capture - Summarry of Kewaunee Mitigation Strategy Phone Call Last Week ML14134A5872014-04-0707 April 2014 NRR E-mail Capture - Minor Editorial/Typographical Changes to License Condition TAC MF1771) ML14097A5112014-04-0101 April 2014 NRR E-mail Capture - Draft RAI Related to Kewaunee Proposed Deletion of License Condition on Mitigation Strategy ML14069A3832014-03-0606 March 2014 NRR E-mail Capture - Draft RAI on Kewaunee Permanently Defueled Technical Specifications ML13312A2422013-11-0707 November 2013 NRR E-mail Capture - MF1952-RAII-SRXB-Cunana-002-2011-11-08, Request for Additional Information ML13297A0482013-10-23023 October 2013 NRR E-mail Capture - MF2567 - Kewaunee Eplan RAI #1 and Comparable Wording from Other Eplans ML13295A5672013-10-22022 October 2013 NRR E-mail Capture - MF2567 Kewaunee Exemption Nlar 102 (50.47 and 10 CFR Appendix E) Includes Kewaunee EP Briefing - 19 June 2013 Handout ML13275A0772013-10-0101 October 2013 NRR E-mail Capture - MF2743-RAII-AHPB-Keefe-001-2013-10-01 Request for Additional Information ML13275A0722013-10-0101 October 2013 NRR E-mail Capture - FW: MF1771-MF1952 RAI 9-27-2013.docx ML13275A0622013-09-27027 September 2013 NRR E-mail Capture - FW: MF2370 - Review of Training Plan for Certified Fuel Handler (CFH) Training - (Corrected) Request for Additional Information (RAI) ML13246A0032013-08-30030 August 2013 NRR E-mail Capture - Record of Docketing of Certifications Pertaining to Decommissioning of Kewaunee Power Station (KPS) ML13218B3722013-08-0606 August 2013 NRR E-mail Capture - MF1952 KPS Permanently Defueled License and TS - Request for Additional Information - MF1952-RAII-SCVB-Heida-001-2013-08-06 ML13186A0212013-07-0303 July 2013 NRR E-mail Capture - MF1771 - Correction to Stated Date Due for Request for Information Dated 6/26/2013 (ML13178A011) ML13178A0112013-06-26026 June 2013 NRR E-mail Capture - MF1771 (and Part of MF1952) - KPS - Record of Clarification Call and Associated Request for Additional Information (RAI) Deletion of License Condition 2.C.(15) ML13151A2452013-05-29029 May 2013 NRR E-mail Capture - Kewaunee Correspondence - Dispositioning Flawed Document, Summary of Facility Changes, Tests and Experiments and Summary of Commitment Changes ML13149A0412013-05-28028 May 2013 NRR E-mail Capture - MF1771 - Kewaunee LAR 255 Deletion of Licensing Condition 2.C.(15) - LIC-109 Acceptance Review Results ML13144A1002013-05-23023 May 2013 NRR E-mail Capture - Record of Docketing of Outgoing NRC Correspondence Serial No. 13-293: Certification of Permanent Removal of Fuel -- Confirming Successful EIE Docketing ML13134A5272013-05-14014 May 2013 NRR E-mail Capture - ML13133A086 = MF1438 - KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results ML13133A0862013-05-10010 May 2013 NRR E-mail Capture - FW: MF1438 KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results ML13128A3612013-05-0707 May 2013 NRR E-mail Capture - MD7112 - Record of Permanent Cessation of Operations 10CFR50.4(b)(8), 10CFR50.82, and the Scheduling of Certain Future Decommissioning Events 2024-01-26
[Table view] |
Text
From: Daily, John Sent: Wednesday, August 04, 2010 9:17 AM To: Hiser, Allen; Karwoski, Kenneth; 'Rachel Vaucher'; 'Paul Aitken' Cc: Robinson, Jay; Brady, Bennett
Subject:
Record of conference call - Discuss Dominion Kewaunee's response to recent Steam Generator Divider Plate RAI LICENSEE: Dominion Energy Kewaunee, Inc.
FACILITY: Kewaunee Power Station
SUBJECT:
SUMMARY
OF DISCUSSION ON JULY 29, 2010, BETWEEN DOMINION ENERGY KEWAUNEE, INC. AND THE U.S. NUCLEAR REGULATORY COMMISSION TO DISCUSS DOMINION RESPONSE TO RAI ON STEAM GENERATOR DIVIDER PLATE (TAC NO. MD9408)
On July 29, 2010, the U.S. Nuclear Regulatory Commission (NRC or the staff) conducted a telephone conference call (teleconference) with representatives from Dominion Energy Kewaunee, Inc. (DEK or the applicant). Applicant invited representatives from Westinghouse, EPRI, and PSE&G Salem Nuclear Plant to also listen in/participate on the call. The staff requested the call in order to obtain a better understanding of applicants Request for Additional Information (RAI) Response dated July 22, 2010, to RAI 3.1.2.2.13-01, Cracking Due to PWSCC in SG Divider Plates, as staff continues to review applicants response.
Staff, the applicant, and certain of applicants invitees discussed applicants RAI response. Staff stated that it is continuing to evaluate applicants RAI response, and that follow-up RAIs on the issue could be forthcoming in order to fully resolve the issue as it relates to applicants license renewal application for the Kewaunee Power Station.
A list of discussion participants is enclosed.
LIST OF PARTICIPANTS DISCUSSION DOMINION ENERGY KEWAUNEE, INC.
KEWAUNEE POWER STATION July 29, 2010 PARTICIPANTS AFFILIATION John Daily U.S. Nuclear Regulatory Commission (NRC)
Allen Hiser U.S. Nuclear Regulatory Commission (NRC)
Ken Karwoski U.S. Nuclear Regulatory Commission (NRC)
Rachel Vaucher U.S. Nuclear Regulatory Commission (NRC)
Paul Aitken Dominion Energy Kewaunee, Inc. (Dominion)
Marc Hotchkiss Dominion Energy Kewaunee, Inc. (Dominion)
John Voss Dominion Energy Kewaunee, Inc. (Dominion)
Viki Armentrout Dominion Energy Kewaunee, Inc. (Dominion)
Charles Tomes Dominion Energy Kewaunee, Inc. (Dominion)
Chris Cassino Westinghouse Herm Lagally Westinghouse Helen Cothron EPRI Pat Fabian PSE&G Salem Nuclear Station Sam Speer PSE&G Salem Nuclear Station John Daily, MBA, PMP Senior Project Manager, Division of License Renewal Office of Nuclear Reactor Regulation USNRC John.Daily@NRC.Gov (301) 415-3873