ML110550663: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(4 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML110550663
| number = ML110550663
| issue date = 02/23/2011
| issue date = 02/23/2011
| title = Crystal River, Unit 3, E-mail, ME5208 Final RAIs Re Departure from a Method of Evaluation for the Auxiliary Building Overhead Crane and Revisions to Associated Commitments
| title = E-mail, ME5208 Final RAIs Re Departure from a Method of Evaluation for the Auxiliary Building Overhead Crane and Revisions to Associated Commitments
| author name = Saba F E
| author name = Saba F
| author affiliation = NRC/NRR/DORL/LPLII-2
| author affiliation = NRC/NRR/DORL/LPLII-2
| addressee name = Herrin D W, Rose P, Westcott D
| addressee name = Herrin D, Rose P, Westcott D
| addressee affiliation = Progress Energy Florida, Inc
| addressee affiliation = Progress Energy Florida, Inc
| docket = 05000302
| docket = 05000302
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:From: Saba, Farideh Sent: Wednesday, February 23, 2011 5:47 PM To: Daniel Westcott; Herrin, Dennis W.; Rose, Philip  
{{#Wiki_filter:From:                   Saba, Farideh Sent:                   Wednesday, February 23, 2011 5:47 PM To:                     Daniel Westcott; Herrin, Dennis W.; Rose, Philip


==Subject:==
==Subject:==
ME5208_ Final RAIs.docx Attachments: ME5208_ Final RAIs.docx  
ME5208_ Final RAIs.docx Attachments:           ME5208_ Final RAIs.docx Please see the attached RAIs regarding Departure from a Method of Evaluation for the Auxiliary Building Overhead Crane and Revisions to Associated Commitments (ME5208). Please let me know if you have any questions or comments.
 
: Thanks, Farideh}}
Please see the attached RAIs regarding Departure from a Method of Evaluation for the Auxiliary Building Overhead Crane and Revisions to Associated Commitments (ME5208). Please let me know if you have any questions or comments.
Thanks, Farideh}}

Latest revision as of 03:56, 13 November 2019

E-mail, ME5208 Final RAIs Re Departure from a Method of Evaluation for the Auxiliary Building Overhead Crane and Revisions to Associated Commitments
ML110550663
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 02/23/2011
From: Farideh Saba
Plant Licensing Branch II
To: Herrin D, Rose P, Westcott D
Progress Energy Florida
Saba F
References
TAC ME5208
Download: ML110550663 (1)


Text

From: Saba, Farideh Sent: Wednesday, February 23, 2011 5:47 PM To: Daniel Westcott; Herrin, Dennis W.; Rose, Philip

Subject:

ME5208_ Final RAIs.docx Attachments: ME5208_ Final RAIs.docx Please see the attached RAIs regarding Departure from a Method of Evaluation for the Auxiliary Building Overhead Crane and Revisions to Associated Commitments (ME5208). Please let me know if you have any questions or comments.

Thanks, Farideh