Calculation No. S10-0063, Auxiliary Building Overhead Crane (FHCR-5) Supporting Steel Structure - Connection Evaluation
ML11314A121
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/05/2011
From: Carter G
Enercon Services
To:
Office of Nuclear Reactor Regulation
References
3F0911-01, TAC ME5208 S10-0063
Download: ML11314A121 (29)


Text

Systems 7127 Calc. Sub-Type Priority Code 3 Quality Class S NUCLEAR GENERATION GROUP ANALYSIS I CALCULATION 510-0063 (Calculation #)

Auxiliary Building Overhead Crane (FHCR-5) Supporting Steel Structure - Connection Evaluation (Title including structures, systems, components) o BNP UNIT

[gJ CR3 0 HNP 0 RNP 0 NES 0 ALL APPROVAL Electronically Approved Rev Su ervisor Signature Name Kyong S. Pak 0 ENERCON Date Date (For Vendor Calculations)

Vendor Enercon Services Inc. Vendor Document No. N/A


~----------------

Owner's Review By Date


Calculation No. S10-0063 Page i Revision 0 List Of Effective Pages Page Rev Page Rev Page Rev Page Rev i 0 ii 0 iii 0 iv 0 v 0 vi 0 vii 0 viii 0 ix 0 x 0 xi 0 xii 0 xiii 0 xiv 0 xv 0 xvi 0 xvii 0 xviii 0 xix 0 xx 0 xxi 0 xxii 0 1 0203040 5 060 Attachments Attach. Number of Attach. Number of Attach. Number of Rev Rev Rev Number Pages Number Pages Number Pages 1 0 406 2 0 611 3 0 77 4 0 4893 5 0 5 6 0 681 7 0 6 Amendments Rev & No of Rev & No of Rev & No of Rev & No of Letter Pages Letter Pages Letter Pages Letter Pages

Calculation No. S10-0063 Page ii Revision 0 Table Of Contents Page No.

List of Effective Pages ........................................................................................................................................ i Table of Contents ............................................................................................................................................... ii Revision Summary .............................................................................................................................................iii Document Indexing Tables ................................................................................................................................iii Record of Lead Review .................................................................................................................................... vi Record of Interdisciplinary Review ................................................................................................................. xxii 1.0 PURPOSE AND SCOPE ....................................................................................................................... 1

2.0 CONCLUSION

........................................................................................................................................ 1

3.0 INTRODUCTION

.................................................................................................................................... 3

4.0 REFERENCES

....................................................................................................................................... 4 4.1 Site Specifications and Procedures ................................................................................................... 4 4.2 Industrial Codes, Standards, and Manuals ........................................................................................ 4 4.3 Drawings and Sketches ...................................................................................................................... 4 4.4 Calculations......................................................................................................................................... 5 4.5 Other References ............................................................................................................................... 5 5.0 ASSUMPTIONS ..................................................................................................................................... 5 6.0 DESIGN INPUT ...................................................................................................................................... 5 6.1 Design Load ........................................................................................................................................ 5 7.0 METHODOLOGY ................................................................................................................................... 6 8.0 CALCULATIONS .................................................................................................................................... 6 Attachments Total Page(s) 1 Member Connection Evaluation (Beam Moment Connections, Vertical and Horizontal Bracing Connections)............................................................................................................. 406 2 Member Connection Evaluation (Beam, Girder and Purlin End Connections) ..................................... 611 3 Crane Girder Connection Evaluation ........................................................................................................ 77 4 Steel Column Base Connection Evaluation .......................................................................................... 4893 5 Location of Modifications ............................................................................................................................. 5 6 Column 301-K Baseplate Connection Evaluation .................................................................................. 681 7 Old and New Load Comparison at Column Base Plates ........................................................................... 6

Calculation No. S10-0063 Page iii Revision 0 Revision Summary Revision # Revision Summary (Include brief description of revision and a list of ECs and other modifications incorporated into revision) 0 Original Issue per EC 70139 Document Indexing Tables Document Management System Data (For update of PassPort Controlled Document information Document Service is to delete roll over data only if shown for DELETE in the following tables)

Notes - General Doc Services Text of General Notes Action (Enter ADD, DELETE, or )

ADD This calculation is issued to support the ISFSI project (EC 70139).

Reference Numbers - Reference Systems Doc Services System Action (Two letter code for systems affected by results)

(Enter ADD, DELETE, or )

ADD 7127 Reference Numbers - Other References (references to PassPort products)

Doc Services Type Reference Sub Title Action (e.g. AR, (e.g. AR No, EC No, (AR Assign No, (Enter ADD, EC, WO, WO No, etc) WO Task No, DELETE, or ) etc) etc.)

ADD EC 70139 ISFSI Auxiliary Building Crane Upgrade (FHCR-5)

Calculation No. S10-0063 Page iv Revision 0 Input Document References - Controlled Documents with Cross References Doc Services Doc. Type Document Document ID Sheet Doc Minor Ref Action (e.g. CALC, Sub-Type (e.g., Calc No., Dwg. (Dwg. sheet Rev Rev Type DWG, NPAS, No., Procedure No) number if (Enter ADD, REV, (for Calc (for NPAS POM, etc) Applicable)

DELETE, or ) Amendments) Docs)

ADD CALC S09-0036 0 ADD DWG 422-057 1 0 ADD DWG 521-142 1 0 ADD DWG 521-142 2 0 ADD DWG 521-142 3 0 ADD DWG 521-142 4 0 ADD DWG 521-142 5 0 ADD DWG 521-142 6 0 ADD DWG 522-041 1 0 ADD DWG 522-041 2 0 ADD DWG 522-041 3 0 ADD DWG 522-041 4 0 ADD DWG 522-041 5 0 ADD DWG 522-041 6 0 ADD DWG 522-041 7 0 ADD DWG 522-041 8 0 ADD DWG 522-041 9 0 ADD DWG 522-041 10 0 ADD DWG 522-041 11 0 ADD DWG 522-041 12 0 ADD DWG 522-041 13 0 ADD DWG 522-041 14 0 ADD DWG 522-041 15 0 ADD DWG 522-041 16 0 ADD DWG 522-041 17 0 ADD DWG 522-041 18 0 ADD DWG 522-041 19 0 ADD DWG 522-041 20 0 ADD DWG 522-041 21 0 ADD DWG 522-041 22 0 ADD DWG 522-041 23 0 ADD DWG 522-041 24 0 ADD CALC 2:01.10 -

Calculation No. S10-0063 Page v Revision 0 Doc Services Doc. Type Document Document ID Sheet Doc Minor Ref Action (e.g. CALC, Sub-Type (e.g., Calc No., Dwg. (Dwg. sheet Rev Rev Type DWG, NPAS, No., Procedure No) number if (Enter ADD, REV, (for Calc (for NPAS POM, etc) Applicable)

DELETE, or ) Amendments) Docs)

ADD CALC 2:01.12 -

ADD CALC 2:01.13 -

ADD CALC 2:01.14 -

ADD CALC 2:01.15 -

Description Codes (Key Words)

Doc Services Code Action (Codes for Key Words)

(Enter ADD, (To be recorded as document DELETE, or ) description codes in PassPort)

ADD ISFSI ADD AUXILIARY BUILDING ADD FHCR-5 ADD OVERHEAD CRANE Output Document References (Doc Service is to open listed documents and add or delete this Calc as a reference)

Doc Services Document Document Document ID Revision Action Tracking Action Type Sub-Type (e.g., Calc No., Dwg. No., (AR number or EC number (Enter ADD, (e.g. CALC, DWG, Procedure No., Software that will track revision of DELETE, or ) TAG, PROCEDURE, name and version) affected document for the SOFTWARE) results of this calculation)

Equipment Database Data (For update of PassPort Equipment Database information)

Equipment Document References Config Mgt Equipment Equipment Type Relationship to Calc.

Action Tag (includes SFTAPL for (e.g. equipment operation affected by results, (Enter ADD, analysis software) equipment design affected by results, analysis DELETE, or ) software)

Evaluation of supporting structure for ADD FHCR-5, CRN CRN new/replacement crane

Calculation No. S10-0063 Page vi Revision 0 Record of Lead Review Document S1 0-0063 Revision A, B, 0 The signature below of the Lead Reviewer records that:

- the review indicated below has been performed by the Lead Reviewer;

- appropriate reviews were performed and errors/deficiencies (for all reviews performed) have been resolved and these records are included in the design package;

- the review was performed in accordance with EGR-NGGC-0003.

Design Verification Review Engineering Review Owners Review Design Review Alternate Calculation Qualification Testing Special Engineering Review YES N/A Other Records are attached.

12/12/2010 Michael Black Civil/Structure 2/9/2011 Lead Reviewer (print/sign) Discipline Date Item Deficiency Resolution No.

1 NONE FORM EGR-NGGC-0003-2-10 This form is a QA Record when completed and included with a completed design package. Owners Reviews may be processed as stand alone QA records when Owners Review is completed.

Calculation No. S10-0063 Page vii Revision 0 Document S1 0-0063 Revision A The signature below of the Lead Reviewer records that:

- the review indicated below has been performed by the Lead Reviewer;

- appropriate reviews were performed and errors/deficiencies (for all reviews performed) have been resolved and these records are included in the design package;

- the review was performed in accordance with EGR-NGGC-0003.

Design Verification Review Engineering Review Owners Review Design Review Alternate Calculation Qualification Testing Special Engineering Review YES N/A Other Records are attached.

Casaba Ranganath Civil/Structure Lead Reviewer (print/sign) Discipline Date Item Deficiency Resolution No.

1 Attachment 1: Page 121, allowable for The required number and size of bolts remains capacity of the bracing connection can be the same, even if 1.0 Sy is used.

increased to elastic limit (1.0 Sy).

2 Attachment 1: Page 132: Why is the bolt The bolt shear capacity is set to a certain shear capacity reduced by 75% and what is percentage of the full shear capacity in order to the basis. maximize the bolt shear and bolt tension capacities needed for the given shear and tension forces applied to the bolt group. See AISC 6th edition, Section 1.6.3 Shear and Tension.

3 Attachment 1: Page 134. Why is factor 1.16 The coefficients in Table XV (pg 4-60) of AISC used for E70XX electrode. 6th edition are based on E60XX electrodes.

When E70XX electrodes are used, multiply coefficients by 1.16 per Table XV.

4 Attachment 1, Page 135, the new brace load Revised page 135 (now 143) to show design should be 72.48 kips per Page 12 of force of 72.48 kips instead of 71.05 kips.

calculation.

Page 135 (now 143) is the Existing Capacity calculation. Page 160 (now 168) is the Modification calculation where the correct design force of 72.48 kips was used.

This will not impact modification requirements.

Calculation No. S10-0063 Page viii Revision 0 5 Attachment 1, Page 138, the new brace load Revised page 138 (now 146) to show design should be 134.44 kips per Page 12 of force of 134.44 kips instead of 135.16 kips.

calculation.

Page 138 (now 146) is the Existing Capacity calculation. Page 166 (now 174) is the Modification calculation where the correct design force of 134.44 kips was used.

This will not impact modification requirements.

6 Attachment 1, Page 141, New brace load Revised page 141 (now 149) to show 163.09 from GTSTRUDL is 163.09 Kips per Page kips instead of 152.63 kips.

12 of calculation not 152.63 Kips.

Page 141 (now 149) is the Existing Capacity calculation. Page 170 (now 178) is the Modification calculation where the correct design force of 163.09 kips was used.

This will not impact modification requirements.

7 Attachment 1, Page 144, the new brace load Revised page 144 (now 152) to show design is 159.12 not 148.98 kips per Page 12 of force of 159.12 kips instead of 148.98 kips.

calculation.

Page 144 (now 152) is the Existing Capacity calculation. Page 174 (now 182) is the Modification calculation where the correct design force of 159.12 kips was used.

This will not impact modification requirements.

8 Attachment 1, Page 147, the new brace load Revised page 147 (now 155) to show design is 101.74 and not 94.83 kips shown. force of 101.74 kips instead of 94.83 kips.

Page 147 (now 155) is the Existing Capacity calculation. Page 177 (now 182) is the Modification calculation where the correct design force of 101.74 kips was used.

This will not impact modification requirements.

9 Attachment 1, Page 150, the new brace load Revised page 150 (now 158) to show 50.49 is 50.49 kips and not 34.65 Kips shown. kips instead of 34.65 kips.

This may require mod, verify. In Page 149 add x2 for bolt shear capacity (D.S). A new modification is required. Calculation and drawings have been updated.

Included double shear for bolts.

Calculation No. S10-0063 Page ix Revision 0 10 Attachment 1, page 153, the new brace load Revisde page 153 (now 161) to show 80.74 is 80.74 kips and not 68.87 kips shown. kips instead of 68.87 kips.

A new modification is required. Calculation and drawings have been updated.

11 Attachment 1, Page 156, the new brace load Revised page 156 (now 164) to show 87.13 is 87.13 kips and not 96.65 kips as shown. kips instead of 96.65 kips.

Page 156 (now 164) is the Existing Capacity calculation. Page 181 (now 196) is the Modification calculation where the correct design force of 87.13 kips was used.

This will not impact modification requirements.

12 Attachment 1, Page 158, Why change bolts Yes, the existing bolts will work for the new between brace and gusset plate, since the force. However, the existing bolts must be existing bolts have 72.12 x 1.33 = 96.16 kips removed to install new gusset plate. Therefore, capacity greater than the new load 72.48 bolts must be replaced (See Detail 2 on 522-kips. Also in Page 160 why is the bolt shear 041-008).

capacity set equal to 50% of full shear capacity. The bolts are not being replaced at other end of brace (See Detail 3 on 522-041-008).

For 50% shear capacity, see combined shear and tension explanation given in Item #2 above.

13 Attachment 1, Page 166: the bolt shear Yes, the existing bolts will work for the new capacity for gusset to angle brace is 105.78 force. However, the existing bolts must be (Page 137) x 1.33 = 141.04 Kips greater removed to reinforce the existing gusset plate.

than the load on brace 134.44 kips, why Therefore, bolts must be replaced (See Detail 3 change the bolts for this connection. on 522-041-008) 14 Attachment 1, Page 172: Gusset to column 28 ksi is incorrect. This should be 22 ksi. The connection, what is the reference for bolt calculation has been revised. (now 180) allowable for Type I 325 bolts of 28 ksi.

This will not impact modification requirements.

Calculation No. S10-0063 Page x Revision 0 15 Attachment 1, Page 188, the design force Revise page 188 (now 203) to show design should be 41.92 kips not 30 kips, in addition force of 41.92 kips instead of 30 kips. Yes, bolt the bolt allowable shown 11.99 kips should allowable can be increased. The calculation has be 18.06 per AISC 4-44, with this increase been revised to show this increase.

in allowable no change to bolt is required between gusset plate and brace, verify. Page 188 (now 203) is the Existing Capacity calculation. Page 200 (now 215) is the Modification calculation where the correct design force of 41.92 kips was used. The Modification calculation does not need to be revised.

The bolts must be removed and replaced for new gusset plate installation. However, 7/8 diameter bolts should be used instead of the 1 diameter bolts called out on Detail 1 of drawing 522-041-006. Drawing has been revised.

16 Attachment 1, Page 197: Delete inches in inches has been deleted from pages 197 (now no. of bolts 2, same comment in Page 200. 212) and 200 (now 215).

Also in Page 188, the design force should be 41.92 kips not 30 kips, in addition the bolt allowable shown 11.00 kips should be 18.06 per AISC 4-44, with this increase in allowable no change to bolt is required between gusset plate and brace, verify.

17 Attachment 1, page 202: Design force Revised page 202 (now 217) to show design should be 163.09 kips per Page 12 of force of 163.09 kips instead of 152.63 kips.

calculation.

Page 202 (now 217) is the Existing Capacity calculation. Page 209 (now 224) is the Modification calculation where the correct design force of 163.09 kips was used.

This will not impact modification requirements.

18 Attachment 1, page 204: Design force Revised page 204 (now 219) to show design should be 159.12 kips per Page 12 of force of 159.12 kips instead of 150 kips.

calculation instead of 150 kips.

Page 204 (now 219) is the Existing Capacity calculation. Page 211 (now 226) is the Modification calculation where the correct design force of 159.12 kips was used.

This will not impact modification requirements.

Calculation No. S10-0063 Page xi Revision 0 19 Attachment 1, page 206: Design force Revised page 206 (now 221) to show design should be 87.13 kips per Page 12 of force of 87.13 kips instead of 96.65 kips.

calculation instead of 96.65 kips.

Page 206 (now 221) is the Existing Capacity calculation. Page 214 (now 229) is the Modification calculation where the correct design force of 87.13 kips was used.

This will not impact modification requirements.

20 Attachment 1, Page 217: Shows this as a Page 217 (now 232) checks the Existing Type 5 with L5X5X1/2 brace, however, capacity of connection at Grid 301-L, TOS EL Page 168 shows this as Type 2 with 161-4. The existing brace is L5x5x1/2 (See L6x6X3/4 brace, L6x6x3/4 is correct, verify. VB-15 sketch on page 239 (now 254)).

Also in Page 218 why the bolt shear capacity is reduced to 75% and the new Page 168 (now 176) is a Modification brace force per Page 12 of calculation is calculation at Grid 301-M1, TOS EL 161-4.

163.09 kips, this should be revised in Page The modified angle size is L6x6x3/4 (See VB-219. 5 sketch on page 167 (now 175)).

Page 219 (now 234) has been revised to show 163.09 kips instead of 152.63 kips.

Page 219 (now 234) is the Existing Capacity calculation. Page 242 (now 257) is the Modification calculation where the correct design force of 163.09 kips was used.

This will not impact modification requirements.

See Item 2 above for explanation of 75% shear capacity at combined tension and shear condition.

21 Attachment 1, page 225: Design force Revised page 225 (now 240) to show design should be 159.12 kips per Page 12 of force of 159.12 kips instead of 148.98 kips.

calculation instead of 148.98 kips.

Page 225 (now 240) is the Existing Capacity calculation. Page 250 (now 265) is the Modification calculation where the correct design force of 159.12 kips was used.

This will not impact modification requirements.

Calculation No. S10-0063 Page xii Revision 0 22 Attachment 1, page 228: Design force Revised page 228 (now 243) to show design should be 101.74 kips per Page 12 of force of 101.74 kips instead of 94.83 kips.

calculation instead of 94.83 kips.

Page 228 (now 243) is the Existing Capacity calculation. Page 253 (now 268) is the Modification calculation where the correct design force of 101.74 kips was used.

This will not impact modification requirements.

23 Attachment 1, page 231: Design force Revised page 231 (now 246) to show design should be 51 kips per Page 12 of calculation force of 51 kips instead of 35.86 kips.

instead of 35.86 kips. The capacity of the bracing connection as per Page 231 is A new modification is required. Calculation and 47.96 kips. This may require a mod verify. drawings have been updated.

24 Attachment 1, page 234: Design force Revised page 234 (now 249) to show design should be 80.74 kips per Page 12 of force of 80.74 kips instead of 68.87 kips.

calculation and the capacity of the bracing connection is 71.94 kips as per Page 234. A new modification is required. Calculation and This may required a mod, verify. drawings have been updated.

25 Attachment 1, page 240: Member 7315 See explanation in Item 20 above.

shows Type 5, Page 168 shows Type 2, verify, also this appears to be a duplicate Note that page 240 (now 255) is the calc for this member. modification at Grid 301-L, and page 217 (now 232) is the existing capacity at Grid 301-L.

26 Attachment 1, Page 249: Why reduced See explanation concerning combined shear capacity for shear to 75% for gusset to and tension in Item 2 above.

beam connection.

27 Attachment 1, Page 252: Why reduced See explanation concerning combined shear capacity for shear to 65% for gusset to and tension in Item 2 above.

beam connection.

28 Attachment 1, Page 256: Why reduced See explanation concerning combined shear capacity for shear to 70% for gusset to and tension in Item 2 above.

beam connection.

29 Attachment 1, page 258: Design force Revised page 258 (now 280) to show force of should be 51 kips per Page 12 of calculation 51 kips instead of 35.86 kips.

instead of 35.86 kips.

Modification is not required.

Calculation No. S10-0063 Page xiii Revision 0 30 Attachment 1, page 261: Design force Revised page 261 (now 283) to show force of should be 41.92 kips per Page 12 of 41.92 kips instead of 32.92 kips.

calculation instead of 32.92 kips. Why compressive force in this brace. Page 261 (now 283) is the Existing Capacity calculation. Page 265 (now 287) is the Modification calculation where the correct design force of 41.92 kips was used.

This will not impact modification requirements.

This is a Tension/Compression brace. See Gilbert drawing S-522-006 (+/- 30 kips) 31 Attachment 1, page 268: Design force Revised page 268 (now 290) to show force of should be 93.97 kips per Page 12 of 93.97 kips instead of 90.06 kips.

calculation instead of 90.06 kips.

Page 268 (now 290) is the Existing Capacity calculation. Page 279 (now 301) is the Modification calculation where the correct design force of 93.97 kips was used.

This will not impact modification requirements.

32 Attachment 1, page 271: Design force Revised page 271 (now 293) to show force of should be 101.74 kips per Page 12 of 101.74 kips instead of 94.83 kips.

calculation instead of 94.83 kips.

Page 271 (now 293) is the Existing Capacity calculation. Page 284 (now 306) is the Modification calculation where the correct design force of 101.74 kips was used.

This will not impact modification requirements.

33 Attachment 1, page 274: Design force Revised page 274 (now 296) to show force of should be 80.74 kips per Page 12 of 80.74 kips instead of 68.87 kips.

calculation instead of 68.87 kips. Bolts between gusset and brace not OK with the Page 274 (now 296) is the Existing Capacity increased load, see Page 275. calculation. Page 289 (now 311) is the Modification calculation where the correct design force of 80.74 kips was used.

This will not impact modification requirements.

34 Attachment 1, Pages 297, 298, and 299 are The portions of the calculation that are not not legible. legible are not applicable, and have been removed.

(now 319, 320, and 321)

Calculation No. S10-0063 Page xiv Revision 0 35 Attachment 1, Page 301361: There is a mod The modification in question is a Horizontal sketch for Members 7246 to 7253. The Bracing connection.

sketch shows modification at the end of the member, however, could not locate any See modification sketches HB-1 & HB-1a calculation for this mod. and also this mod is (pages 360 (now 382) & 361 (now 383)).

not identified in Page 2 of calculation that provides a table of all the modifications and See calculation pages 365 (now 387) and 367 it is not in the modification drawings, verify. (now 389) (Information at Gusset to 30WF116 and Gusset to 30WF116 Beam Connection).

See page 325 (now 347) for modification location on Gilbert drawing S-521-102.

See modification Detail 2 on drawing 521-142-001.

36 Attachment 2, Page 217: Change Mark# This is a CONNECTION CAPACITY for all W36 W36 to B59E, also total applied axial force members with 1/4 welds in this sub-section and total shear capacity should this be (2.3.1) of the calculations (not only Mark Connection capacity instead of applied #B59E.) References have been revised at the force, clarify. This is general comment that INPUT section of the spread sheet to better applies at other locations. explain.

37 Attachment 2, Page 222: Change Mark# This is a CONNECTION CAPACITY for all W36 W36 to B51C. members with 5/16 welds in this sub-section (2.3.1) of the calculations (not only Mark

  1. B51C.) References have been revised at the INPUT section of the spread sheet to better explain.

38 Attachment 2, Page 227: Change Mark# This is a CONNECTION CAPACITY for W14 at W14W to B56D. the West end of B56D. References have been revised at the INPUT section of the spread sheet to better explain.

39 Attachment 2, Page 232: Change Mark# This is a CONNECTION CAPACITY for W14 at W14E to B50D. the East end of B56D (not B50D.) References have been revised at the INPUT section of the spread sheet to better explain.

40 Attachment 2, Page 237: Change Mark# C8 References have been revised at the INPUT to B56F. section of the spread sheet to better explain.

41 Attachment 2, Page 243: Total Applied Revised shear to match EnvC - NO CHANGE Shear 33.82 is due to EnvA not EnvC, TO RESULTS OR MODIFICATIONS.

verify. [tREQ'D = 0.673 > t = 0.375]

42 Attachment 2, Page 248: Total Applied Revised shear to match EnvC - NO CHANGE Shear 33.82 is due to EnvA not EnvC, TO RESULTS OR MODIFICATIONS.

verify. [tREQ'D = 0.704 > t = 0.375]

43 Attachment 2, Page 258: Total Applied Revised shear to match EnvB (Case EnvB Shear 30.24 is due to EnvA not EnvC, noted on Revision A calculation - not EnvA) -

verify. NO CHANGE TO RESULTS OR MODIFICATIONS.

[tREQ'D = 0.781 > t = 0.375]

Calculation No. S10-0063 Page xv Revision 0 44 Attachment 2, Page 263: Total Applied Revised shear to match EnvB (Case EnvB Shear 30.24 is due to EnvA not EnvC, noted on Revision A calculation - not EnvA) -

verify. NO CHANGE TO RESULTS OR MODIFICATIONS.

[tREQ'D = 0.781 > t = 0.375]

45 Attachment 2, Page 281: Revise W36 This is a CONNECTION CAPACITY for all W36 shown under CASE. The total applied force members BUT WAS NOT REQUIRED and shear are not as per load table in page BECAUSE THE EXISTING FORCE WAS >

274, clarify. THE REVISED (CURRENT) FORCE.

MARKED VOID (NOT REQUIRED) UNDER COMMENT.

(Pages 274 thru 276 were shifted to 275 thru 277.)

46 Attachment 2, Page 286: Revise W30 This is a CONNECTION CAPACITY for all W30 shown under CASE. members this sub-section (2.3.2) of the calculations (Table pgs 278-280.) References have been revised at the INPUT section of the spread sheet.

47 Attachment 2, Page 291: Revise W24 This is a CONNECTION CAPACITY for like or shown under CASE. similar W24 members this sub-section (2.3.2) of the calculations (Table pgs 278-280.)

References have been revised at the INPUT section of the spread sheet.

48 Attachment 2, Page 296: Revise W24 Same as ITEM 47.

shown under CASE. Add D after EN under Added D (at NORTH END) under COMMENT.

COMMENT.

49 Attachment 2, Page 306: Revise W24 Same as ITEM 47.

shown under CASE.

50 Attachment 2, Page 311: Revise W24 This is a CONNECTION CAPACITY for W24 shown under CASE. The total applied force @Mark #B57B (North End) BUT WAS NOT and shear are not as per load table in page REQUIRED BECAUSE THE EXISTING 275, clarify. FORCE WAS > THE REVISED (CURRENT)

FORCE. MARKED VOID (NOT REQUIRED)

UNDER COMMENT.

51 Attachment 2, Page 316: Revise W24 Same as ITEM 47.

shown under CASE.

52 Attachment 2, Page 321: Revise W24 Same as ITEM 47.

shown under CASE.

53 Attachment 2, Page 326: Revise W18 This is a CONNECTION CAPACITY for like or shown under CASE. This is a general similar W18 members this sub-section (2.3.2) of comment at various other locations in this the calculations (Table pgs 278-280.)

attachment. References have been revised at the INPUT section of the spread sheet. The same revision was made to all subsequent applications of the spread sheets where it (the spread sheet) was used to determine a CONNECTION CAPACITY (based upon nominal beam depth) rather than to analyze a connection for a specific load condition. This was addressed at all subsections where connection capacities where determined.

Calculation No. S10-0063 Page xvi Revision 0 54 Attachment 3, Page 7, Section 4.2.0: In the 71090 has been added. Mz has been changed second paragraph should also add Member to 237 kip-ft.

71090 and Mz as per Attachment 3.2 is 237 kip-ft.

55 Attachment 3, Page 7, Section 4.2.8: Why fv fv is a crane longitudinal force and does not and ft are not taken to act at the same time. act at the same time as ft which is a crane transverse force based on the GTStrudl load combinations.

56 Attachment 3: Why the strong axis allowable Strong axis forces are gravity forces and are are not increased by 1/3. viewed as constant loads. Transverse and longitudinal forces are viewed as impact loads and are present for a very short time. The design check and modification for the bracket have be based on the continuous presents of the gravity forces, therefore, the increase allowable was not taken for the gravity forces.

57 Attachment 3, Section 4.2.20: Why the axial Transverse and longitudinal forces are impact stress not included with the bending and loads and are not present at the same time. The shear stress in this section. axial stress is less the weak axis forces, therefore, the axial stress combined with the strong axis bending will not control the design.

58 Attachment 3, Section 4.3.0: Fy is 249.9 Have revised Fy to 249.9 kips and updated the kips as per Page 1 of Attachment 3.1. This calculation the reflect change requires to be corrected at all other locations in the calculation.

59 Attachment 3, section 4.3.12: Why is axial Same as 56 stress not combined with bending and shear stress in this section.

60 Attachment 3, Section 4.4.0: Verify if 7120 7120 should be 71200 is correct.

should be 71200. My should be 74 kip-ft per Colum Q1-301 does not control design, Attachment 3.2. Also under the lower Column Q1-302A controls the design. The column shaft connection, the Fy load at section has been corrected to show this.

Column Q1-301 is shown as 272.2 kips + Vertical force in column are 165.8 kips, as per Attachment 3.1, it is 33.8 236.9 kips + 143.8 kips.

kips + 165.8 kips, verify.

61 Attachment 4: Calculation number should be The calculation number has been changed to S10-0063 and not S09-0063. S10-0063 62 Attachment 4, Section 4.7: Why the existing In this case, the base plate is bending about the wing plates not considered in this strong axis of the column. The existing wing calculation. Why 22 ksi chosen in calculating plates do not affect the plate bending in this MALL. direction.

63 Attachment 4, Section 4.7, Page 23: Under The dimensions shown in the figure are Connection welds, the bending stress incorrect and have been corrected.

diagram it is not clear what the 1.21 and 7.79 correspond to. The numbers shown do not correspond to the values calculated in Pages 22 and 23.

Calculation No. S10-0063 Page xvii Revision 0 64 Attachment 4, Page 22: In the table that The amount of required shear reinforcement shows the length of shear reinforcement has been significantly reduced from the original required, it appears that the loads at Q-301 calculation. The reinforcement at Q-301 has and Q-302A are very much similar, however been reduced to 12 and 35 in the two Q-301 has 18 and 53 length shear lugs and orthogonal directions.

Q-302A do not require any shear reinforcement. Why such a big difference. The shear reinforcement design is based on supplied reactions from the GTSTRUDL Also is it acceptable to distribute the shear analysis model. Examination of the reactions reinforcement on opposite sides as long as indicates that the shear reactions at Q1-301 are the total length of the shear reinforcement much larger than the shear reactions at Q1-L1and L2 are maintained and they are 302A. Dwg. 522-006 indicates that a vertical placed symmetrically from the center line of brace frames into the base of Q1-301 while Q1-column. 302A has no such bracing. The basis of the owners comment is uncertain.

The latest drawings have distributed the reinforcement around the edges of the base plates to clear interferences. Symmetric redistribution of the reinforcement would be permissible, but is probably no longer necessary.

FORM EGR-NGGC-0003-2-10 This form is a QA Record when completed and included with a completed design package. Owners Reviews may be processed as stand alone QA records when Owners Review is completed.

Calculation No. S10-0063 Page xviii Revision 0 Document S1 0-0063 Revision B, 0 The signature below of the Lead Reviewer records that:

- the review indicated below has been performed by the Lead Reviewer;

- appropriate reviews were performed and errors/deficiencies (for all reviews performed) have been resolved and these records are included in the design package;

- the review was performed in accordance with EGR-NGGC-0003.

Design Verification Review Engineering Review Owners Review Design Review Alternate Calculation Qualification Testing Special Engineering Review YES N/A Other Records are attached.

Casaba Ranganath Civil/Structure 3-12-11 Lead Reviewer (print/sign) Discipline Date Item Deficiency Resolution No.

1 Attachment 1, Pages 41& 48: 301-N1 and Attachment 1, Page 48 revised to account for 302-N1 moment connection: Since the Unbalanced Force Distribution. This flange connection bolts at the top and modification occurs at 302A-N1 only (at elevator bottom flanges are not symmetrical, in that wall).

one half of the flange has more bolts and the bolts are in double shear, this would Page 41 (301-N1) does not require a Revision.

induce eccentric load on the connection.

This eccentric loading should be considered.

2 Attachment 3, Page 1: Change title from Title revised per request.

Crane connection to Crane Girder Connection.

3 Attachment 3, Page 27: Strong axis Mz load If we use the 1/3 increase on the gravity forces, (291.3 K-ft) is the envelope load due to the Unity Check (Section 4.4.12) would change gravity as well as seismic as per STRUDL from 2.46 to 2.14. This would still require the output Attachment 3.2, Page 67. Hence the modifications to be made to the connections in allowable for the strong axis can be question.

increased by 1/3, since it is not just gravity Therefore, calculation will remain as is load (as indicated in the response to Item 53 knowing that by not allowing the 1/3 increase for in Revision A of owners review comment) the gravity forces would be a conservative.

but also includes seismic load. The same Following statement added to page 27:

comment applies to crane girder bracket Conservatively, normal allowable are used for design in Revision A of this calculation. the strong axis even though the load includes seismic load.

Calculation No. S10-0063 Page xix Revision 0 4 Attachment 4, Page 112, Section 4.9, Last The word be added to last sentence on page sentence: after will add be 112.

Attachment 4, Page 618: Foundation capacity at S1-301 and S1-302A: By No, the concrete beam about 3-6 below the connecting S1-301 and S1-302A with a grade will not cause any change in response of concrete beam about 3-6 below grade, will the steel super structure presently evaluated in this change response of the steel super calculation S09-0036. Forces in super structure structure that are presently modeled in model (S09-0036) are governed by the STRUDL under Calculation S09-0036. In boundary conditions defined at the column line other words does the STRUDL model in S1, which are still true (column to foundation S09-0036 require to be modified to include connection is represented in terms of boundary this concrete beam. conditions at column end and no foundations Also in the STRUDL input in Page 1492, are represented in the model, which is Joint 1001 and 1012 Y coordinate should be consistent with the original calculation). When a 1.1425 E +02, verify. column is considered fixed in a particular direction, it is an inherent assumption that grade below/foundation is able to transfer the forces and moments effectively. In the case of column at S1, the foundations were not stiff enough to transfer the moments effectively and hence the beam was added between foundations S1-301

& S1-302A to reflect the assumptions made in the GTSTRUDL model in S09-0036. No further modifications are required.

Yes, the dimension should been 1.1425E+02 instead of 1.145E+02 which should have insignificant impact on results. Following note added to the page 618 of this attachment:

Minor differences in the actual dimensions and GTSTRUDL dimensions will have insignificant impact on the analysis result.

5 Attachment 4: It is mentioned in Page 113 In several cases, the Case 2 analysis as that all Case 2 excessive bearing stress and indicated in the spreadsheet is exactly correct inadequate shear capacity conditions will be and is not affected by a strain compatibility reexamined. However, several of the load analysis. This occurs when the length of cases shown in Attachment 4.1 where the bearing at the bottom of the base plate is bearing stress has been exceeded for Case greater than the distance from the edge of the 2 the evaluation could not be located. For base plate to the far anchor bolts. In these example Page 648, Load Case 3000, Run cases the anchor bolts are not in tension and 79, which has Fy=406.2 kips and Mx = - excessive bearing stress is not reduced by the 230K, so also in Page 649, Run 82, Load strain compatibility analysis. For S1-301, this case 3000, which has Fy=389.5 kips and occurs in four cases, P=406.2 kips and Mx =

Mx=-233.2 kft. There are a few other cases 230 kip feet, P=389.5 kips and Mx=233.2 kip where the evaluation could not be located feet, P=398 kips and Mx=229 kip feet, and even though bearing stress is exceeded as P=411.2 kips and Mx=236.4 kip feet. The shown in Attachment 4.1. excessive bearing stress for these load cases is Also in the fourth line in Page 113 add e addressed in the write up on page 610 of the before < l/6. calculation.

e added in the fourth line on page 113.

Calculation No. S10-0063 Page xx Revision 0 6 Attachment 6: In this Attachment 6, the Connection is considered as semi-rigid in this column K-301 at base is fixed along the attachment. Also an evaluation is carried out to Global X-axis. This boundary condition is ensure that anchor bolts are the weak link in the different from the boundary condition used connection configuration, as a result, under the in all the earlier STRUDL runs in Calculation extreme loading anchor bolt will yield and S09-0036. Even though it is mentioned in connection will act as a pin connection Page 3 that fixed condition is required to (consistent with GTStrudl runs in calculation eliminate the excessive loading clarify this S09-0036). Whereas under initial normal change in the boundary condition and the condition the connection will act as fixed effect of this change for the coupled model connection and continue to serve its purpose provided to MMH for their crane analysis. without any adverse impact on structure as discussed in second paragraph on section 1 (pg. 3).

The column K-301 at base is fixed along the Global X-axis, to determine the maximum moment acting on the connection (if connection is considered fixed) and to determine the forces at which the anchor bolt will yield to behave as pin connection as discussed in the attachment 6.

A modification to the boundary condition of connection (fixed to pinned) is required to eliminate the excessive loading (as discussed in Calculation S09-0036). The computer model in calculation S09-0036 at joint 6101 (Ref. 7) has a pin boundary condition to reflect this issue.

The pin boundary condition representation of the support is the worst case depiction of the connection behavior (more conservative for whole structure) considering that the existing anchor bolts are not present and joint is free to rotate. Hence, the results obtained for design purposes tend to be more conservative compared to when a fixed connection or semi-rigid connection is considered in the analysis.

7 Attachment 4: Sub Section 4.4 and Section See page 618 of Attachment 4. Also, see (03/25 show the original load on the vertical load on Gilbert calculation page 2:01.3D-7.

/2011) the column as P max =744 K and P min = -

155K, where is it taken from the original calculation, was not able to locate them in the original calculation. Also Section 4.4 shows the moment at joint 1 from original calculation as 1640 K. The moment at Joint 1 should be zero as per original calculation, explain.

Calculation No. S10-0063 Page xxi Revision 0 8 In response to my Comment 46 under 70% The justification of concrete slab cut-out/repair (03/25 EC, it is mentioned that the concrete cut out has been added to the section 4.1.1 of

/2011) for moment connection at Elevation 162-0 Attachment 1 of this calculation.

evaluation have been added. However, could not locate this evaluation in Revision B of the calculation. Please identify where this evaluation is included.

9 General: As per Attachment 4 of this calculation, the new (03/25 Evaluation of concrete structure due to tension force in anchor bolts is less than the

/2011) revised load on concrete from steel columns original design tension force shown in Gilbert as a result of crane upgrade. Calculation 2.01.10. Also, the concrete is checked for the bearing and shear requirements in the same attachment and necessary modifications are provided. Attachment 7 is added to compare old and new load for concrete bearing and shear load. As there is no increase in the force, further evaluation of concrete structure below steel structure is not required.

10 With regard to the response to comment 6 in The statement is made based on the (03/22 the Owner Review, is there a comparison or engineering judgment. Lateral forces

/2011) a STRUDL run to show that using column K- redistribution takes place along the column k-301 base as pinned is more conservative 301 based on its boundary condition. When and provides the conservative response at boundary condition is considered to be pinned:

all locations in the building structure all the lateral wind force is transferred to the compared to the base being fixed in the adjutant beams and roof beams, whereas under global X direction. fixed condition column will provided direct load path to the lateral wind force and adjutant Calculation S10-0063 Rev. B Attachment 6, beams and roof beams will see less forces.

Section 1, Page 3 just makes a statement, Moments generated due to seismic excitation can this be confirmed through a comparison at this column base are approximately 50% of showing numbers at critical locations. that of the designed wind moments. Fix connection will make the structure more rigid and the natural frequency should rise slightly in the X direction. Natural frequency of the coupled crane and structure is mainly governed by the crane natural frequency which are in the approx. range of 1.2 Hz to 8 Hz and as per the review of response spectra curve (DCD), slight shift to right in this frequency range on response spectra curve will reduce the acceleration values and will results in lower forces due to EQ.

FORM EGR-NGGC-0003-2-10 This form is a QA Record when completed and included with a completed design package. Owners Reviews may be processed as stand alone QA records when Owners Review is completed.

Calculation No. S10-0063 Page xxii Revision 0 Record of Interdisciplinary Reviews PART I DESIGN ASSUMPTION / INPUT REVIEW: APPLICABLE Yes No The following organizations have reviewed and concur with the design assumptions and inputs used in this calculation:

Systems Engineering Name Signature Date Operations Name Signature Date Other Name Signature Date PART II RESULTS REVIEW:

The following organizations are aware of the impact of the results of this calculation (on designs, programs and procedures):

Systems Engineering Yes NO Name Signature Date Comments:

Operations Yes NO Name Signature Date Comments:

Other Name Signature Date Comments:

Other Name Signature Date Comments:

Other Name Signature Date Comments:

Calculation No. S10-0063 Page 1 Revision 0 1.0 PURPOSE AND SCOPE The Progress Energy Crystal River Unit 3 (CR3) Auxiliary Building (AB) Overhead Crane support steel structure is being evaluated for overhead crane (FHCR-5) replacement (EC 70139, Ref.

4.1.3). The purpose of this calculation is to verify/evaluate the existing connections for Auxiliary Building (AB) Overhead Crane support steel structure, crane brackets, crane stops, crane rails and column base connections. This calculation also addresses the qualification of modified structural connections.

2.0 CONCLUSION

All of the Auxiliary Building steel structure connections are structurally acceptable and meet the necessary code requirements listed in Design Criteria Document (Ref. 4.5.3).

Table below shows the summary of modifications required to the Auxiliary Building steel structure as a result of Overhead Crane (FHCR-5) replacement.

See drawings 422-057 Sht. 1 (Ref. 4.3.15), 521-142 Sht. 1 through 6 (Ref. 4.3.13) and 522-041 Sht.

1 through 24 (Ref. 4.3.14) for modification details. See Attachment 5 for location of modifications.

Calculation No. S10-0063 Page 2 Revision 0 Type of Modification Total No. Att. Drawings 522-041 SH. 1 thru 9, 24 Vertical Bracing Connections 51 1.3 522-006 Horizontal Bracing Connections at Roof EL. 521-142 SH. 1 2 1.4 209-1 (between column line I1 & J1) 521-102 E-W Member Connections at Roof EL. 522-041 SH. 14 2 2.1 209-1 (at column line S1) 522-004 N-S Member Connections at Roof EL. 209- 522-041 SH. 1 & 4 2 2.1 1 (between column line P1 & Q1) 522-004 521-142 SH. 1 N-S Member Connections (Purlin) at Roof 522-041 SH. 15 98 2.1 EL. 209-1 521-102 522-004 E-W Member Connections at EL. 189-9 (at 522-041 SH. 1 & 17 3 2.2 column line S1) 522-004 Horizontal Bracing Connections at Floor EL. 522-041 SH. 10 & 15 1 1.4 162-0 (between column line N1 & O1) 522-003 E-W Member Moment Connections at Floor 522-041 SH. 10,12,13,20 8 1.1 EL. 162-0 522-003 E-W Member Connections at EL. 162-0 (at 522-041 SH. 10 & 16 column line L, at column line S1, and 5 2.3 522-003 between column line M1 & N1) 522-041 SH. 10,14,15,16 N-S Member Connections at EL. 162-0 32 2.3 522-003 522-041 SH. 1,10,17 Miscellaneous N-S Member Connections 8 2.4 522-003 521-142 SH. 2 522-041 SH. 11 Crane Girder Bracket Connections 15 3 521-102 522-004 521-142 SH. 3 & 4 Column Connections to Concrete Floor 13 4 522-041 SH. 18 & 19 Concrete Tie-Beam between S1-301 & S1-1 4 422-057 SH. 1 302A Concrete Column Pier at EL. 119-0

Calculation No. S10-0063 Page 3 Revision 0

3.0 INTRODUCTION

Progress Energy Crystal River Unit 3 (CR3) is implementing the Independent Spent Fuel Storage Installation (ISFSI) for Dry Fuel Storage campaign. The Transfer Casks (TC) containing the Dry Shield Canisters (DSCs) are placed into and removed from the Spent Fuel Pool (SFP) using the AB Overhead Crane (FHCR-5). The existing overhead crane capacity (120 tons but has subsequently been derated by 40% to 72 tons, and recently derated further to 25 tons per reference 4.1.4) is inadequate to handle the proposed TC to be used at CR3. In addition, the existing overhead crane does not meet the single-failure-proof criteria of NUREG 0554 (Ref. 4.2.5) and NUREG 0612 (Ref.

4.2.6). Therefore, the overhead crane must be upgraded to increase load capacity to 130 tons/15 tons, main and aux hook capacities. The existing crane is not modified. Instead, complete new crane, including the crane bridge structure as well as the trolley, is provided by the crane vendor.

Therefore, the Auxiliary Building is evaluated with the new crane loads along with other loads (e.g.,

dead loads, live loads, earthquake loads and wind loads).

The existing Auxiliary Building is designed to resist Operating Basis Earthquake (OBE) seismic loads and a design wind speed of 110 mph (Refs. 4.1.2, 4.4.1 and 4.4.6). This calculation and structural member evaluation calculation S09-0036 (Ref. 4.4.5) together demonstrate that the modified crane support structure can accommodate an upgraded single-failure-proof crane under heavy load cask handling to 130 tons capacity in conjunction with the loads defined by the original plant licensing basis and ASME NOG-1 (Ref. 4.2.1). This calculation and the Design Criteria Document (Ref. 4.5.3) describe the load combinations, analysis methodology, and acceptance criteria. The intent of this calculation is to use the identified critical loads from calculation S09-0036 (Ref. 4.4.5) for the design/evaluation of the member connections, column base connections, crane brackets, crane stops, crane rails and rail splice joints. The interface point between ENERCON and crane vendor is at the top of the runway rail where crane and supporting structure meet.

ENERCON is responsible for the structure below the interface, i.e., the supporting structure and crane vendor is responsible for above the interface, i.e., the crane bridge.

Calculation No. S10-0063 Page 4 Revision 0

4.0 REFERENCES

4.1 Site Specifications and Procedures 4.1.1 Design Basis Document 1/3, Major Class I Structures, Rev. 6 4.1.2 Crystal River Nuclear Unit 3 Final Safety Analysis Report, Rev. 32 4.1.3 EC 70139, ISFSI Auxiliary Building Crane Upgrades (FHCR5), Rev. 0 (Draft) 4.1.4 OP0421C, Operation of the Auxiliary Building Overhead Crane FHCR-5, Rev. 33 4.2 Industrial Codes, Standards, and Manuals 4.2.1 Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder), ASME NOG-1, 2004 4.2.2 AISC Manual of Steel Construction, Allowable Stress Design 6th Edition, 1963 4.2.3 AISC Manual of Steel Construction, Volume II Connections 1st Edition, 1992 4.2.4 AISC Manual of Steel Construction, Allowable Stress Design 9th Edition, 1989 4.2.5 NUREG-0554, Single-Failure-Proof Cranes for Nuclear Power Plants, May 1979 4.2.6 NUREG-0612, Control of Heavy Loads at Nuclear Power Plants, July, 1980 4.3 Drawings and Sketches 4.3.1 522-001, Auxiliary Building - Steel Framing Column Schedule, Rev. 1 4.3.2 522-003, Auxiliary Building South Steel Framing Roof at Elev. 167-6 and 162-0, Rev. 6 4.3.3 522-004, Auxiliary Building South Steel Framing Roof at Elev. 209-1 Crane Runway at Elev. 193-7, Rev. 4 4.3.4 522-006, Auxiliary Building South Steel Framing Column Bracing, Rev. 3 4.3.5 521-102, Auxiliary Building North Steel Framing Roof Steel Plan-Crane Runway. Roof Elev.

200-4 and 209-1, Rev. 6 4.3.6 0129-E1, Auxiliary Building - Steel Framing Column Schedule, Dated 3-5-71 4.3.7 0129-E3, Auxiliary Building South Steel Framing Roof Elev. 167-6 and 162-0, Dated 2-24-71 4.3.8 0129-E4, Auxiliary Building South Steel Framing Roof at Elev. 209-1 Crane Runway at Elev. 193-7, Dated 3-5-71 4.3.9 0129-E5, Auxiliary Building South Steel Framing Column Bracing, Date not legible 4.3.10 0129-E9, Auxiliary Building North Steel Framing Roof Steel Plan-Crane Runway. Roof Elev. 200-4 and 209-1, Date not legible 4.3.11 0129-D1 to 0129-D105 Shop Details 4.3.12 0129-BD2 to 0129-BD17 Vertical Bracing Layout Details 4.3.13 521-142 Sht. 1 through 6, Auxiliary Building - North Steel Framing Modifications Details, Rev. 0 4.3.14 522-041 Sht. 1 through 24, Auxiliary Building - South Steel Framing Modifications Details, Rev. 0 4.3.15 422-057 Sht. 1, Auxiliary Building Modification - South Column Modifications Details, Rev. 0

Calculation No. S10-0063 Page 5 Revision 0 4.4 Calculations 4.4.1 Calculation 2:01.10, Steel Frames 4.4.2 Calculation 2:01.12, Vertical Bracing 4.4.3 Calculation 2:01.14, Steel Floor Framing @ 162-0 4.4.4 Calculation 2:01.15, Roof Framing, Girts, and Miscellaneous Steel 4.4.5 S09-0036, Auxiliary Building Overhead Crane (FHCR-5) Supporting Steel Structure -

Analysis, Rev. 0 4.4.6 Calculation 2:01.50, Structural Steel - Aux. Building 4.5 Other References 4.5.1 Formulas for Stress and Strain, by Roark and Young, 5th edition 4.5.2 Experimental Investigation of Stresses in Gusset Plates, by R.E. Whitmore, Bulletin No. 16, Engineering Experiment Station, University of Tennessee, 1952 4.5.3 FPC118-PR-001, Design Criteria Document for Crystal River Unit 3 Auxiliary Building Evaluation for Crane Upgrades, Revision 1 (Attachment 1 of Ref. 4.4.5 and Attachment Z23 of Ref. 4.1.3)

NOTE: See Attachments 1, 2, 3, 4, 6 and 7 for additional reference documents used for evaluation.

5.0 ASSUMPTIONS It is assumed that the Auxiliary Building steel structure has not experienced degradation and that the as-built condition of the structural members and their connections are consistent with the original structural design drawings and the original fabrication drawings.

See Assumption section in Attachment 1, 2, 3, 4, 6 and 7 for any additional assumptions.

There is no open assumption in this calculation which requires later verification 6.0 DESIGN INPUT 6.1 Design Load GTSTRUDL force output results are documented in Attachment 7, 8 and 10 of calculation S09-0036 (Ref. 4.4.5) and shall be used as new design forces for the evaluation. Existing connection forces are taken from the steel structural drawings (Ref. 4.3.1 to 4.3.5). Existing connection type is determined using the shop drawings (Ref. 4.3.6 to 4.3.12).

Any additional design inputs required for the evaluation are addressed along the body of each Attachment.

Calculation No. S10-0063 Page 6 Revision 0 7.0 METHODOLOGY An analysis model for the Auxiliary Building has been developed using GTSTRUDL. The forces generated from the GTSTRUDL model have been compared to the original design forces developed by Gilbert Associates (Ref. 4.4.1 to 4.4.4). Any member connections that have new forces exceeding the original forces, have been evaluated, and modified where necessary.

The evaluation and modification of the existing member connections have been analyzed and designed according to the requirements set forth in the 6th edition of the AISC Manual of Steel Construction (Ref. 4.2.2).

Per Section 1.5.6 of AISC 6th edition, the allowable stresses were increased by one third when the design forces were produced from load combinations involving wind or seismic.

There are two exceptions to using the AISC 6th edition. The first occurs when analyzing or designing a connection for prying action. Because the AISC 6th edition does not address prying action, the 9th edition of AISC (Ref. 4.2.4) was used for prying action.

The other exception involves different types of bolts being offered today, versus what was offered when the AISC 6th edition was written. The AISC 6th edition offers high strength bolt types of A325 and A354 Gr. BC. Because AISC has replaced type A354 Gr. BC bolts with type A490 bolts, type A490 bolts were used for connection modifications when necessary. The A490 bolt allowable stress values were taken from the AISC 9th edition (Ref. 4.2.4).

See Attachment 1, 2, 3, 4, 6 and 7, Methodology section for any additional methodology to perform an evaluation of Moment Connection, Vertical and Horizontal Bracing Connection, Beam Shear/Axial Connection, Crane Connection, and Column Base Connection.

8.0 CALCULATIONS See the following Attachments for evaluation of various connection types.

3/4 Attachment 1: Member Connection Evaluation (Beam Moment Connections, Vertical and Horizontal Bracing Connections) 3/4 Attachment 2: Member Connection Evaluation (Beam, Girder and Purlin End Connections) 3/4 Attachment 3: Crane Girder Connection Evaluation 3/4 Attachment 4: Steel Column Base Connection Evaluation 3/4 Attachment 6: Column 301-K Baseplate Connection Evaluation 3/4 Attachment 7: Old and New Load Comparison at Column Base Plates