ML19257A206: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
Line 18: Line 18:
=Text=
=Text=
{{#Wiki_filter:*
{{#Wiki_filter:*
.
O STATUS OF Tile SEQUOYAll TRANSMISSION LINL RIGilTS OF WAY RECLAMATION AND REVEGETATION SINCE THE COMPLETION OF TRANSMISSION LINE CONSTRUCTION 1671  542 8001020 qQ2
O STATUS OF Tile SEQUOYAll TRANSMISSION LINL RIGilTS OF WAY RECLAMATION AND REVEGETATION SINCE THE COMPLETION OF TRANSMISSION LINE CONSTRUCTION 1671  542
      .
8001020 qQ2


.
    -
  .
TABLE OF CONTENTS Page Introduction......................................          1 Maintenance.......................................          1 Status of Transmission Lines......................          1 Conclusions.......................................          4 1671  34
TABLE OF CONTENTS Page Introduction......................................          1 Maintenance.......................................          1 Status of Transmission Lines......................          1 Conclusions.......................................          4 1671  34


    -
Introduction This report describes the transmission lines that were constructed to connect the Sequoyah Nuclear Plant switchyard into the TVA transmission system due to the Sequoyah Nuclear Plant having been built at its present location. TVA utilized common or existing rights of way whenever practical to reduce overall land requirements. In order to complete the switchyard tie-ins to the system, approximately 147 miles of new transmission lines were constructed on 74      miles of new and 73      miles of existing rights of way.
.
      '
                                                .
Introduction This report describes the transmission lines that were constructed to connect the Sequoyah Nuclear Plant switchyard into the TVA transmission system due to the Sequoyah Nuclear Plant having been built at its present location. TVA utilized common or existing rights of way whenever practical to reduce overall land requirements. In order to complete the switchyard
    -
tie-ins to the system, approximately 147 miles of new transmission lines were constructed on 74      miles of new and 73      miles of existing rights of way.
Faintenance The mechanical mowing that is required is programmed on a four-year cycle.
Faintenance The mechanical mowing that is required is programmed on a four-year cycle.
Whenever the terrain is rough and inaccessible TVA uses chemical maintenance.
Whenever the terrain is rough and inaccessible TVA uses chemical maintenance.
Line 43: Line 31:
1671    344
1671    344


                                          .
Sequoyah-Watts Bar 161-kV Line and Sequoyah-Chickamauga 161-kV Line No. 1-The right of way clearing and construction activities were completed and these loops were put in service in September 1973. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle. The vegetation is well established and most of the right of way has dense stands of brush species. The right of way has fully recovered from construction impacts and we have not identified any erosion problems.
Sequoyah-Watts Bar 161-kV Line and Sequoyah-Chickamauga 161-kV Line No. 1-The right of way clearing and construction activities were completed and these loops were put in service in September 1973. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle. The vegetation is well established and most of the right of way has dense stands of brush species. The right of way has fully recovered from construction impacts and we have not identified any erosion problems.
Sequoyah-Chickamauga No. 2 and Sequoyah-East Cleveland 161-kV Lines - The initial clearing and construction activities were completed and the loops were put in service in November 1973. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle.
Sequoyah-Chickamauga No. 2 and Sequoyah-East Cleveland 161-kV Lines - The initial clearing and construction activities were completed and the loops were put in service in November 1973. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle.
Line 51: Line 38:
1671    345
1671    345


.
Sequoyah-Franklin (AEDC) 500-kV Line - The initial clearing began in June 1973, construction was completed,and the line was put in service October 1975. Sections of the right of way were mechanically mowed in late 1978. This line required approximately 45 miles of new right of way and has approximately 602 acres of wooded right of way that requires maintenance and approximately 118 acres of the 602 acres consists of rough, inaccessible terrain that requires chemical application. In 1979, the 118 acres were sprayed by helicopter. The chemical formulation used was two gallons of Tordon 101 plus two gallons of DP, an amine formulation. This chemical combination is EPA approved and is environmentally acceptable.
Sequoyah-Franklin (AEDC) 500-kV Line - The initial clearing began in June 1973, construction was completed,and the line was put in service October 1975. Sections of the right of way were mechanically mowed in late 1978. This line required approximately 45 miles of new right of way and has approximately 602 acres of wooded right of way that requires maintenance and approximately 118 acres of the 602 acres consists of rough, inaccessible terrain that requires chemical application. In 1979, the 118 acres were sprayed by helicopter. The chemical formulation used was two gallons of Tordon 101 plus two gallons of DP, an amine formulation. This chemical combination is EPA approved and is environmentally acceptable.
The sections of the right of way that are mechanically mowed will be pro-grammed on four-year cycles. The areas that are sprayed by helicopP.er will be programmed on a six- to seven-year cycle. The right of way has fully recovered from the construction impacts and we have not identified any erosion problems.
The sections of the right of way that are mechanically mowed will be pro-grammed on four-year cycles. The areas that are sprayed by helicopP.er will be programmed on a six- to seven-year cycle. The right of way has fully recovered from the construction impacts and we have not identified any erosion problems.
Line 59: Line 45:
1671    346
1671    346


    -
.
                                              .
Conclusions All construction of new lines has been completed and full redress and recovery from construction impacts has been achieved. The vegetation on the rights of way consists of grass seeded areas, volunteer vegetation, and/or dense stands of brush species. The lines associated with the Sequoyah Nuclear Plant were last flown the week of October 9-12, 1979. TVA has not identified any erosion problems associated with the transmission lines.
Conclusions All construction of new lines has been completed and full redress and recovery from construction impacts has been achieved. The vegetation on the rights of way consists of grass seeded areas, volunteer vegetation, and/or dense stands of brush species. The lines associated with the Sequoyah Nuclear Plant were last flown the week of October 9-12, 1979. TVA has not identified any erosion problems associated with the transmission lines.
1671      347}}
1671      347}}

Latest revision as of 22:58, 1 February 2020

Status of Transmission Line Rights-of-Way Reclamation & Revegetation Since Completion of Transmission Line Const.
ML19257A206
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 12/27/1979
From:
TENNESSEE VALLEY AUTHORITY
To:
Shared Package
ML19257A205 List:
References
NUDOCS 8001020472
Download: ML19257A206 (6)


Text

O STATUS OF Tile SEQUOYAll TRANSMISSION LINL RIGilTS OF WAY RECLAMATION AND REVEGETATION SINCE THE COMPLETION OF TRANSMISSION LINE CONSTRUCTION 1671 542 8001020 qQ2

TABLE OF CONTENTS Page Introduction...................................... 1 Maintenance....................................... 1 Status of Transmission Lines...................... 1 Conclusions....................................... 4 1671 34

Introduction This report describes the transmission lines that were constructed to connect the Sequoyah Nuclear Plant switchyard into the TVA transmission system due to the Sequoyah Nuclear Plant having been built at its present location. TVA utilized common or existing rights of way whenever practical to reduce overall land requirements. In order to complete the switchyard tie-ins to the system, approximately 147 miles of new transmission lines were constructed on 74 miles of new and 73 miles of existing rights of way.

Faintenance The mechanical mowing that is required is programmed on a four-year cycle.

Whenever the terrain is rough and inaccessible TVA uses chemical maintenance.

The chemical formulation is EPA approved and is environmentally acceptable.

The areas that are chemically treated are programmed on a six- to seven-year cycle. The lines are normally flown four times a year to detect any potential mechanical or erosion problems associated with the transmission lines.

Status of Transmission Lines The status of the transmission lines are as follows:

Widows Creek-Charleston (Loop to Sequoyah) 161-kV - The initial clearing and construction activities were completed and the loop was put in service in August 1972. The right of way was mechanically mowed in April-May 1977 and is scheduled to be moved again in 1981. The right of way has a dense vegetative cover and we have not identified any erosion.

1671 344

Sequoyah-Watts Bar 161-kV Line and Sequoyah-Chickamauga 161-kV Line No. 1-The right of way clearing and construction activities were completed and these loops were put in service in September 1973. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle. The vegetation is well established and most of the right of way has dense stands of brush species. The right of way has fully recovered from construction impacts and we have not identified any erosion problems.

Sequoyah-Chickamauga No. 2 and Sequoyah-East Cleveland 161-kV Lines - The initial clearing and construction activities were completed and the loops were put in service in November 1973. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle.

The right of way has p dense vegetative cover and we have not identified any erosion.

Sequoyah-Concord 161-kV Line - The right of way clearing and construction activities were completed and these lines were put in service in September 1972. The right of way was mechanically mowed in 1977 and is scheduled for remowing in 1981. The right of way has fully recovered from construction impacts and we have not identified any erosion problems.

Sequoyah-Charleston No. 2 161-kV Line - This connection was provided by installing conductors on the vacant side of the existing Sequoyah-Charleston No. 1 161-kV transmission line. This line was placed in service in April 1974. The right of way was mechanically mowed in March-April 1976, and is re-scheduled to be mowed in the summer of 1980. The right of way has a dense vegetative cover and we have not identified any erosion problems.

1671 345

Sequoyah-Franklin (AEDC) 500-kV Line - The initial clearing began in June 1973, construction was completed,and the line was put in service October 1975. Sections of the right of way were mechanically mowed in late 1978. This line required approximately 45 miles of new right of way and has approximately 602 acres of wooded right of way that requires maintenance and approximately 118 acres of the 602 acres consists of rough, inaccessible terrain that requires chemical application. In 1979, the 118 acres were sprayed by helicopter. The chemical formulation used was two gallons of Tordon 101 plus two gallons of DP, an amine formulation. This chemical combination is EPA approved and is environmentally acceptable.

The sections of the right of way that are mechanically mowed will be pro-grammed on four-year cycles. The areas that are sprayed by helicopP.er will be programmed on a six- to seven-year cycle. The right of way has fully recovered from the construction impacts and we have not identified any erosion problems.

Sequoyah-Georgia State Line (Bowen) 500-kV Line - This transmission line required 21.4 miles of new right of way. The initial clearing began in 1971, construction was completed,and the line was put in service April 1972.

The right of way has fully recovered from construction impacts and we have not identified any erosion problems. The right of way was mechanically mowed in 1976 and mechanical mowing will be programmed on a four-year cycle.

Widows Creek-Bull Run Loop to Sequoyah 500 kV - The initial clearing and construction activities were completed and this loop was placed in service in April 1972. The right of way was mechanically mowed in June 1977, and is rescheduled to be mowed again in the summer of 1981. The right of way . has fully recovered from construction impacts and we have not identified any erosion problems.

1671 346

Conclusions All construction of new lines has been completed and full redress and recovery from construction impacts has been achieved. The vegetation on the rights of way consists of grass seeded areas, volunteer vegetation, and/or dense stands of brush species. The lines associated with the Sequoyah Nuclear Plant were last flown the week of October 9-12, 1979. TVA has not identified any erosion problems associated with the transmission lines.

1671 347