| number = ML060580625
| number = ML060580625
| issue date = 03/02/2006
| issue date = 03/02/2006
| title = Beaver Valley Power Station, Unit No. 2 (BVPS-2) - Request for Additional Information (RAI) - Station Battery Charger Upgrade
| title = (BVPS-2) - Request for Additional Information (RAI) - Station Battery Charger Upgrade
| author name = Colburn T G
| author name = Colburn T
| author affiliation = NRC/NRR/ADRO/DORL/LPLA
| author affiliation = NRC/NRR/ADRO/DORL/LPLA
| addressee name = Lash J H
| addressee name = Lash J
| addressee affiliation = FirstEnergy Nuclear Operating Co
| addressee affiliation = FirstEnergy Nuclear Operating Co
| docket = 05000412
| docket = 05000412
| license number = NPF-073
| license number = NPF-073
| contact person = Colburn T G, NRR/DLPM, 415-1402
| contact person = Colburn T, NRR/DLPM, 415-1402
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
| page count = 5
| page count = 5
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:March 2, 2006Mr. James H. LashVice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station
{{#Wiki_filter:March 2, 2006 Mr. James H. Lash Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station P. O. Box 4 Shippingport, PA 15077
 
P. O. Box 4 Shippingport, PA 15077


==SUBJECT:==
==SUBJECT:==
BEAVER VALLEY POWER STATION, UNIT NO. 2 (BVPS-2) - REQUEST FORADDITIONAL INFORMATION (RAI) - STATION BATTERY CHARGER UPGRADE (TAC NO. MC8735)
BEAVER VALLEY POWER STATION, UNIT NO. 2 (BVPS-2) - REQUEST FOR ADDITIONAL INFORMATION (RAI) - STATION BATTERY CHARGER UPGRADE (TAC NO. MC8735)


==Dear Mr. Lash:==
==Dear Mr. Lash:==


By letter dated October 14, 2005, FirstEnergy Nuclear Operating Company requested anAmendment to the BVPS-2, Technical Specifications (TSs). The proposed changes would revise TSs 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades,including installation of new battery chargers. The Nuclear Regulatory Commission (NRC) staffhas determined that the information contained in the enclosed RAI will be needed for the NRCstaff to complete its review. As discussed with your staff, we request your response within 30 days of receipt of this letter inorder to maintain our review schedule. If you have any questions, please contact me at 301-415-1402.Sincerely,/RA/Timothy G. Colburn, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-412
By letter dated October 14, 2005, FirstEnergy Nuclear Operating Company requested an Amendment to the BVPS-2, Technical Specifications (TSs). The proposed changes would revise TSs 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades, including installation of new battery chargers. The Nuclear Regulatory Commission (NRC) staff has determined that the information contained in the enclosed RAI will be needed for the NRC staff to complete its review.
As discussed with your staff, we request your response within 30 days of receipt of this letter in order to maintain our review schedule. If you have any questions, please contact me at 301-415-1402.
Sincerely,
                                            /RA/
Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412


==Enclosure:==
==Enclosure:==
RAIcc w/encl:  See next page


ML060580625*Input received. No substantive changes made.OFFICELPLI-1/LALPLI-1/PMEEEB/BC(A)LPLI-1/BCNAMESLittleTColburnEBrown*RLauferDATE 3/01/063/01/06   02/17/063/02/06 EnclosureREQUEST FOR ADDITIONAL INFORMATION (RAI)BEAVER VALLEY POWER STATION, UNIT NO. 2 (BVPS-2) STATION BATTERY CHARGER UPGRADEDOCKET NO. 50-412 By letter dated October 14, 2005 (Agencywide Documents Access and Management SystemAccession No. ML052920419), FirstEnergy Nuclear Operating Company requested an amendment to the BVPS-2 Technical Specifications (TSs). The proposed changes would revise TSs 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades,including installation of new battery chargers. The Nuclear Regulatory Commission (NRC) staffhas determined that the information contained below is needed for the NRC staff to complete itsreview. 1.Provide assurance that any spare charger that could be credited by removing '2-7' from TS 3.8.2.3 ACTION b and the note in TS 3.8.2.4 would be equivalent towhat is detailed in the BVPS-2 Updated Final Safety Analysis Report (UFSAR). 2.The Institute of Electrical and Electronics Engineers (IEEE) Standard - 450(1987-2002), "IEEE Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications," states that degradation is indicated when the battery capacity drops more than 10%
RAI cc w/encl: See next page
from its capacity on the previous performance test, or is below 90% of manufacturer's rating. Provide assurance that the current definition for battery degradation being usedat BVPS-2 provides an accurate indication of each battery's condition.3.Provide assurance that the BVPS-2 UFSAR will reflect the proposed designchange. 4.Provide an updated electrical one-line diagram that shows the proposed designconfiguration.5.How will you prevent the rectifier assemblies from providing direct current i nputto the respective 125-volt direct current bus? Beaver Valley Power Station, Unit Nos. 1 and 2 cc:Gary R. LeidichPresident and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH  44308Joseph J. HaganSenior Vice Presdient of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308Danny L. PaceSenior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308Jeannie M. RinckelVice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH  44308David W. Jenkins, AttorneyFirstEnergy Corporation Mail Stop A-GO-18 76 South Main Street Akron, OH  44308Manager, Fleet LicensingFirstEnergy Nuclear Operating Company Mail Stop A-GHE-107 395 Ghent Road Akron, OH  44333Lew W. MyersExecutive Vice President, Special ProjectsFirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SGRP P.O. Box 4, Route 168 Shippingport, PA 15077Manager, Site Regulatory ComplianceFirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077Commissioner James R. LewisWest Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305Director, Utilities DepartmentPublic Utilities Commission 180 East Broad Street Columbus, OH 43266-0573Director, Pennsylvania Emergency   Management Agency 2605 Interstate Dr.
 
Harrisburg, PA 17110-9364Ohio EPA-DERRATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149Dr. Judith JohnsrudEnvironmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Beaver Valley Power Station, Unit Nos. 1 and 2 (continued) cc:
ML060580625                     *Input received. No substantive changes made.
DirectorBureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA  15077Regional Administrator, Region IU.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA  19406Resident InspectorU.S. Nuclear Regulatory Commission
OFFICE LPLI-1/LA                LPLI-1/PM            EEEB/BC(A)         LPLI-1/BC NAME SLittle                    TColburn              EBrown*             RLaufer DATE      3/01/06              3/01/06                 02/17/06          3/02/06 REQUEST FOR ADDITIONAL INFORMATION (RAI)
BEAVER VALLEY POWER STATION, UNIT NO. 2 (BVPS-2)
STATION BATTERY CHARGER UPGRADE DOCKET NO. 50-412 By letter dated October 14, 2005 (Agencywide Documents Access and Management System Accession No. ML052920419), FirstEnergy Nuclear Operating Company requested an amendment to the BVPS-2 Technical Specifications (TSs). The proposed changes would revise TSs 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades, including installation of new battery chargers. The Nuclear Regulatory Commission (NRC) staff has determined that the information contained below is needed for the NRC staff to complete its review.
: 1.     Provide assurance that any spare charger that could be credited by removing 2-7' from TS 3.8.2.3 ACTION b and the note in TS 3.8.2.4 would be equivalent to what is detailed in the BVPS-2 Updated Final Safety Analysis Report (UFSAR).
: 2.     The Institute of Electrical and Electronics Engineers (IEEE) Standard - 450 (1987-2002), IEEE Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications, states that degradation is indicated when the battery capacity drops more than 10%
from its capacity on the previous performance test, or is below 90% of manufacturers rating.
Provide assurance that the current definition for battery degradation being used at BVPS-2 provides an accurate indication of each batterys condition.
: 3.     Provide assurance that the BVPS-2 UFSAR will reflect the proposed design change.
: 4.     Provide an updated electrical one-line diagram that shows the proposed design configuration.
: 5.     How will you prevent the rectifier assemblies from providing direct current input to the respective 125-volt direct current bus?
Beaver Valley Power Station, Unit Nos. 1 and 2 Enclosure
 
cc:
Gary R. Leidich                          Executive Vice President, Special Projects President and Chief Nuclear Officer     FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company   Beaver Valley Power Station Mail Stop A-GO-19                        Mail Stop A-BV-SGRP 76 South Main Street                     P.O. Box 4, Route 168 Akron, OH 44308                          Shippingport, PA 15077 Joseph J. Hagan                          Manager, Site Regulatory Compliance Senior Vice Presdient of Operations      FirstEnergy Nuclear Operating Company and Chief Operating Officer            Beaver Valley Power Station FirstEnergy Nuclear Operating Company    Mail Stop A-BV-A Mail Stop A-GO-14                        P.O. Box 4, Route 168 76 South Main Street                    Shippingport, PA 15077 Akron, OH 44308 Commissioner James R. Lewis Danny L. Pace                            West Virginia Division of Labor Senior Vice President, Fleet Engineering 749-B, Building No. 6 FirstEnergy Nuclear Operating Company    Capitol Complex Mail Stop A-GO-14                        Charleston, WV 25305 76 South Main Street Akron, OH 44308                          Director, Utilities Department Public Utilities Commission Jeannie M. Rinckel                      180 East Broad Street Vice President, Fleet Oversight          Columbus, OH 43266-0573 FirstEnergy Nuclear Operating Company Mail Stop A-GO-14                        Director, Pennsylvania Emergency 76 South Main Street                      Management Agency Akron, OH 44308                          2605 Interstate Dr.
Harrisburg, PA 17110-9364 David W. Jenkins, Attorney FirstEnergy Corporation                  Ohio EPA-DERR Mail Stop A-GO-18                        ATTN: Zack A. Clayton 76 South Main Street                    P.O. Box 1049 Akron, OH 44308                          Columbus, OH 43266-0149 Manager, Fleet Licensing                Dr. Judith Johnsrud FirstEnergy Nuclear Operating Company    Environmental Coalition on Nuclear Power Mail Stop A-GHE-107                      Sierra Club 395 Ghent Road                          433 Orlando Avenue Akron, OH 44333                          State College, PA 16803 Lew W. Myers


P.O. Box 298 Shippingport, PA 15077}}
Beaver Valley Power Station, Unit Nos. 1 and 2 (continued) cc:
Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077}}

Latest revision as of 08:35, 14 March 2020

(BVPS-2) - Request for Additional Information (RAI) - Station Battery Charger Upgrade
ML060580625
Person / Time
Site: Beaver Valley
Issue date: 03/02/2006
From: Colburn T
NRC/NRR/ADRO/DORL/LPLA
To: Lash J
FirstEnergy Nuclear Operating Co
Colburn T, NRR/DLPM, 415-1402
References
Download: ML060580625 (5)


Text

March 2, 2006 Mr. James H. Lash Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station P. O. Box 4 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NO. 2 (BVPS-2) - REQUEST FOR ADDITIONAL INFORMATION (RAI) - STATION BATTERY CHARGER UPGRADE (TAC NO. MC8735)

Dear Mr. Lash:

By letter dated October 14, 2005, FirstEnergy Nuclear Operating Company requested an Amendment to the BVPS-2, Technical Specifications (TSs). The proposed changes would revise TSs 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades, including installation of new battery chargers. The Nuclear Regulatory Commission (NRC) staff has determined that the information contained in the enclosed RAI will be needed for the NRC staff to complete its review.

As discussed with your staff, we request your response within 30 days of receipt of this letter in order to maintain our review schedule. If you have any questions, please contact me at 301-415-1402.

Sincerely,

/RA/

Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412

Enclosure:

RAI cc w/encl: See next page

ML060580625 *Input received. No substantive changes made.

OFFICE LPLI-1/LA LPLI-1/PM EEEB/BC(A) LPLI-1/BC NAME SLittle TColburn EBrown* RLaufer DATE 3/01/06 3/01/06 02/17/06 3/02/06 REQUEST FOR ADDITIONAL INFORMATION (RAI)

BEAVER VALLEY POWER STATION, UNIT NO. 2 (BVPS-2)

STATION BATTERY CHARGER UPGRADE DOCKET NO. 50-412 By letter dated October 14, 2005 (Agencywide Documents Access and Management System Accession No. ML052920419), FirstEnergy Nuclear Operating Company requested an amendment to the BVPS-2 Technical Specifications (TSs). The proposed changes would revise TSs 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades, including installation of new battery chargers. The Nuclear Regulatory Commission (NRC) staff has determined that the information contained below is needed for the NRC staff to complete its review.

1. Provide assurance that any spare charger that could be credited by removing 2-7' from TS 3.8.2.3 ACTION b and the note in TS 3.8.2.4 would be equivalent to what is detailed in the BVPS-2 Updated Final Safety Analysis Report (UFSAR).
2. The Institute of Electrical and Electronics Engineers (IEEE) Standard - 450 (1987-2002), IEEE Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications, states that degradation is indicated when the battery capacity drops more than 10%

from its capacity on the previous performance test, or is below 90% of manufacturers rating.

Provide assurance that the current definition for battery degradation being used at BVPS-2 provides an accurate indication of each batterys condition.

3. Provide assurance that the BVPS-2 UFSAR will reflect the proposed design change.
4. Provide an updated electrical one-line diagram that shows the proposed design configuration.
5. How will you prevent the rectifier assemblies from providing direct current input to the respective 125-volt direct current bus?

Beaver Valley Power Station, Unit Nos. 1 and 2 Enclosure

cc:

Gary R. Leidich Executive Vice President, Special Projects President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-GO-19 Mail Stop A-BV-SGRP 76 South Main Street P.O. Box 4, Route 168 Akron, OH 44308 Shippingport, PA 15077 Joseph J. Hagan Manager, Site Regulatory Compliance Senior Vice Presdient of Operations FirstEnergy Nuclear Operating Company and Chief Operating Officer Beaver Valley Power Station FirstEnergy Nuclear Operating Company Mail Stop A-BV-A Mail Stop A-GO-14 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Commissioner James R. Lewis Danny L. Pace West Virginia Division of Labor Senior Vice President, Fleet Engineering 749-B, Building No. 6 FirstEnergy Nuclear Operating Company Capitol Complex Mail Stop A-GO-14 Charleston, WV 25305 76 South Main Street Akron, OH 44308 Director, Utilities Department Public Utilities Commission Jeannie M. Rinckel 180 East Broad Street Vice President, Fleet Oversight Columbus, OH 43266-0573 FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 Director, Pennsylvania Emergency 76 South Main Street Management Agency Akron, OH 44308 2605 Interstate Dr.

Harrisburg, PA 17110-9364 David W. Jenkins, Attorney FirstEnergy Corporation Ohio EPA-DERR Mail Stop A-GO-18 ATTN: Zack A. Clayton 76 South Main Street P.O. Box 1049 Akron, OH 44308 Columbus, OH 43266-0149 Manager, Fleet Licensing Dr. Judith Johnsrud FirstEnergy Nuclear Operating Company Environmental Coalition on Nuclear Power Mail Stop A-GHE-107 Sierra Club 395 Ghent Road 433 Orlando Avenue Akron, OH 44333 State College, PA 16803 Lew W. Myers

Beaver Valley Power Station, Unit Nos. 1 and 2 (continued) cc:

Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077