Category:Letter
MONTHYEARML24351A1462024-12-16016 December 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000412/20243012024-12-0202 December 2024 Initial Operator Licensing Examination Report 05000412/2024301 L-24-254, Cycle 25 Core Operating Limits Report2024-11-15015 November 2024 Cycle 25 Core Operating Limits Report IR 05000334/20244032024-11-13013 November 2024 Cybersecurity Problem Identification and Resolution Inspection Report 05000334/2024403 and 05000412/2024403 (Cover Letter Only) IR 05000334/20240032024-11-13013 November 2024 Integrated Inspection Report 05000334/2024003 & 05000412/2024003 L-24-246, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-10-21021 October 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 L-24-223, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-09-26026 September 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations 2024-09-26
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24057A0782024-03-0101 March 2024 Amendments to Indemnity Agreements - Enclosure 2 ML24057A0772024-03-0101 March 2024 Conforming License Amendments - Enclosure 1 ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23019A0032023-03-16016 March 2023 – Issuance of Amendment Nos. 320 and 210 Adoption of Technical Specifications Task Force (Tstf) Traveler Tstf-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23062A5212023-03-0606 March 2023 – Issuance of Amendment No. 319 Revise Technical Specification (TS) 3.5.2, ECCS – Operating, Limiting Condition for Operation (LCO) 3.5.2, ML22277A8142022-10-0707 October 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22222A0862022-09-0101 September 2022 Issuance of Amendment Nos. 317 and 208 Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation ML22140A2092022-06-28028 June 2022 Issuance of Amendment No. 207 Correct TS 3.1.7 Change Made by TSTF-547 ML22095A2352022-05-10010 May 2022 Issuance of Amendment Nos. 316 and 206 Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML21286A7822022-05-0606 May 2022 Issuance of Amendment Nos. 315 and 205 Regarding Changes to the Emergency Plan ML22077A1342022-05-0202 May 2022 Issuance of Amendment Nos. 314 and 204 Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21320A3592021-11-23023 November 2021 Correction to License Page 4 ML21197A0092021-11-0101 November 2021 Issuance of Amendment Nos. 313 and 203 Reactor Coolant System, Pressure and Temperature Limits Report ML21214A2752021-10-15015 October 2021 Issuance of Amendment Nos. 312 and 202 Atmospheric Dump Valves ML21153A1762021-06-30030 June 2021 Issuance of Amendment No. 201 Revision of Technical Specifications Related to Steam Generator Tube Inspection, and Repair Methods ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML21070A0002021-03-22022 March 2021 Issuance of Amendment 310, Revise Technical Specification 5.5.5.1, Unit 1 SG Program, to Defer Spring 2021 Refueling Outage Steam Generator Inspections to Fall 2022 Refueling Outage ML20346A0222021-03-10010 March 2021 Issuance of Amendment Nos. 309 and 199 to Change Technical Specifications to Implement New Surveillance Methods for the Heat Flux Hot Channel Factor ML20335A0522021-02-18018 February 2021 Issuance of Amendment Nos. 308 and 198 to Modify Certified Fuel Handler Related Technical Specifications for Permanently Defueled Condition ML21034A3892021-02-18018 February 2021 Correction to Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address Generic Safety Issue 191 Issues ML21014A3042021-02-0505 February 2021 Correction to Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20345A2362021-01-28028 January 2021 Issuance of Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address GSI-191 Issues ML21014A1142021-01-12012 January 2021 Correction Letter Notification from Licensee ML20335A0232020-12-28028 December 2020 Issuance of Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20285A2662020-10-21021 October 2020 Correction to Safety Evaluation for Amendment Nos. 305 and 195 Issued September 23, 2020, Modify Primary and Secondary Coolant Activity Technical Specifications ML20213A7312020-09-23023 September 2020 Issuance of Amendment Nos. 305 and 195 to Modify Primary and Secondary Coolant Activity Technical Specifications ML20080H7112020-03-23023 March 2020 Correction Letter for Conforming License Amendments Nos. 304 and 194, Order Approving Transfer of Licenses and Conforming License Amendments ML20030A4402020-02-27027 February 2020 Issuance of Amendment Nos. 304, 194, 299, and 187; Order Approving Transfers of Facility Operating Licenses and Independent Spent Fuel Storage Installation General Licenses and Conforming Amendments ML19326A7592019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Non-Proprietary, Letter & Encl 2-5, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML18348B2062019-02-25025 February 2019 Issuance of Amendment No. 193 Revise Steam Generator Technical Specifications ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18099A2322018-04-18018 April 2018 Correction of an Error in the Renewed Facility Operating License No. DPR-66 Associated with License Amendment No. 301 CAC No. MF3301; EPID L-2013-LLF-0001) ML18022B1162018-03-0101 March 2018 Issuance of Amendment Nos. 302 and 191 Regarding the Use of Optimized ZIRLO Fuel Rod Cladding (CAC Nos. MF9580 and MF9581; EPID L-2017-LLA-0201) ML17291A0812018-01-22022 January 2018 Issuance of Amendments Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (CAC Nos. MF3301 and MF3302; EPID L-2013-LLF-0001) ML18016A1032018-01-19019 January 2018 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 300 and 189 (CAC Nos. MF8448 and MF8449; EPID L-2016-LLA-0011 and EPID L-2017-LRO-0069) ML17216A5702017-10-12012 October 2017 Issuance of Amendments Emergency Action Level Scheme Changed Based on NEI 99-01, Revision 6 (CAC Nos. MF8448 and MF8449; EPID L-2016-LLA-0011) ML17221A2802017-08-16016 August 2017 Issuance of Amendments to Adopt Technical Specifications Task Force (TSTF) Traveler 547, Revision 1 ML17157B2842017-06-0707 June 2017 Correction to Conforming Amendment No. 187 Order to Transfer License ML17115A1232017-05-30030 May 2017 Issuance of Amendment Application for Order to Transfer License and Conforming Amendment ML17081A5092017-05-11011 May 2017 ISFSI, Davis-Besse ISFSI, Perry Nuclear Power Plant, Perry Nuclear Power Plant ISFSI - Issuance of Amendments Re. Application to Revise Technical Specifications to Adopt TSTF-545 Revision 3 ML17081A4332017-04-14014 April 2017 Nonproprietary, Order Approving Transfer of License and Conforming Amendment ML16040A0842016-06-0707 June 2016 FENOC, Beaver Valley Power Station, Unit Nos. 1 and 2; and Davis-Besse Nuclear Power Station, Unit No. 1 - Issuance of Amendments Revision to Technical Specification 5.3.1, Unit Staff Qualifications ML15294A4392015-12-16016 December 2015 Issuance of Amendments License Amendment Request to Revise Steam Generator Technical Specifications (CAC Nos. MF6054 and 6055) ML15302A4332015-12-0101 December 2015 Issuance of Amendments Request to Change Cyber Security Implementation Plan Milestone 8 Completion Date ML15208A2852015-07-28028 July 2015 Correction to Amendment Nos. 294 and 182 Regarding Modification of Emergency Preparedness Plan Regarding the Emergency Planning Zone Boundary 2024-03-01
[Table view] Category:Safety Evaluation
MONTHYEARML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 ML23188A0982023-07-17017 July 2023 – Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23019A0032023-03-16016 March 2023 – Issuance of Amendment Nos. 320 and 210 Adoption of Technical Specifications Task Force (Tstf) Traveler Tstf-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23062A5212023-03-0606 March 2023 – Issuance of Amendment No. 319 Revise Technical Specification (TS) 3.5.2, ECCS – Operating, Limiting Condition for Operation (LCO) 3.5.2, ML22277A8142022-10-0707 October 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22235A7672022-09-0101 September 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22222A0862022-09-0101 September 2022 Issuance of Amendment Nos. 317 and 208 Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation ML22202A4642022-06-29029 June 2022 Emergency Plan Safety Evaluation ML22140A2092022-06-28028 June 2022 Issuance of Amendment No. 207 Correct TS 3.1.7 Change Made by TSTF-547 ML22095A2352022-05-10010 May 2022 Issuance of Amendment Nos. 316 and 206 Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML21286A7822022-05-0606 May 2022 Issuance of Amendment Nos. 315 and 205 Regarding Changes to the Emergency Plan ML22077A1342022-05-0202 May 2022 Issuance of Amendment Nos. 314 and 204 Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22082A2532022-03-29029 March 2022 Correction Letter - Issuance of Authorization of Proposed Alternative to Use ASME OM Code Case OMN-27 ML22012A2972022-01-21021 January 2022 Proposed Alternative to Use ASME OM Code Case OMN-27 ML21197A0092021-11-0101 November 2021 Issuance of Amendment Nos. 313 and 203 Reactor Coolant System, Pressure and Temperature Limits Report ML21214A2752021-10-15015 October 2021 Issuance of Amendment Nos. 312 and 202 Atmospheric Dump Valves ML21153A1762021-06-30030 June 2021 Issuance of Amendment No. 201 Revision of Technical Specifications Related to Steam Generator Tube Inspection, and Repair Methods ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML21070A0002021-03-22022 March 2021 Issuance of Amendment 310, Revise Technical Specification 5.5.5.1, Unit 1 SG Program, to Defer Spring 2021 Refueling Outage Steam Generator Inspections to Fall 2022 Refueling Outage ML20346A0222021-03-10010 March 2021 Issuance of Amendment Nos. 309 and 199 to Change Technical Specifications to Implement New Surveillance Methods for the Heat Flux Hot Channel Factor ML20335A0522021-02-18018 February 2021 Issuance of Amendment Nos. 308 and 198 to Modify Certified Fuel Handler Related Technical Specifications for Permanently Defueled Condition ML20345A2362021-01-28028 January 2021 Issuance of Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address GSI-191 Issues ML20335A0232020-12-28028 December 2020 Issuance of Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20285A2662020-10-21021 October 2020 Correction to Safety Evaluation for Amendment Nos. 305 and 195 Issued September 23, 2020, Modify Primary and Secondary Coolant Activity Technical Specifications ML20279A4402020-10-0808 October 2020 Energy Harbor Fleet-Beaver Valley Power Station; Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant - Request to Use a Provision of a Later Edition of the ASME Engineers Boiler and Pressure Vessel Code, Section XI ML20213A7312020-09-23023 September 2020 Issuance of Amendment Nos. 305 and 195 to Modify Primary and Secondary Coolant Activity Technical Specifications ML20223A0142020-08-20020 August 2020 Issuance of Relief Request SSR-1, Revision 0, from the Requirements of the ASME Code (EPID L-2020-LLR-0050 (COVID-19)) ML20206K8652020-08-0707 August 2020 Relief Requests 2-TYP-4-RV-06 and 2-TYP-4-RV-07 from the Requirements of the ASME Code (EPID L-2020-LLR-0053 and EPID L-2020-LLR-0054 (COVID-19)) ML20153A0142020-07-16016 July 2020 Relief from the Requirements of the American Society of Mechanical Engineers Code Regarding Request VRR4 (EPID L-2020-LLR-0052 (COVID-19)) ML20145A0002020-06-0303 June 2020 Relief from the Requirements of the ASME Code for Requests VRR6 and VRR5 (EPID L-2020-LLR-0049 and EPID L-2020-LLR-0051 (COVID-19)) ML20080J7892020-04-28028 April 2020 Relief Requests 2 TYP-3-B3.110-1, 2-TYP-3-C2.21-1, 2-TYP-3-C1.30-1, and 2-TYP-3-RA-1 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20079F8162020-03-26026 March 2020 Relief Requests 1-TYP-4-C2.21-1 and 1-TYP-4-RA-1 Regarding Weld Examination Coverage for the Fourth Inservice Inspection Interval ML19336A0282019-12-18018 December 2019 Safety Evaluation Irradiated Fuel Management Plans ML19305B1312019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Enclosure 6, Non-Proprietary Safety Evaluation, Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19275E2942019-10-16016 October 2019 Issuance of Relief Request Proposed Alternative to Reactor Vessel Nozzle Weld Examination Frequency Requirements in Lieu of Specific ASME Code Requirements ML19028A0302019-04-11011 April 2019 FENOC - Beaver Valley Power Station, Unit 1 & 2; Davis-Besse Nuclear Power Station Unit 1; and Perry Nuclear Power Plant Unit 1 - Approval of Certified Fuel Handler Training and Retraining Program ML18348B2062019-02-25025 February 2019 Issuance of Amendment No. 193 Revise Steam Generator Technical Specifications ML18249A1692018-09-0707 September 2018 Seismic Hazard Mitigation Strategies Assessment (CAC Nos. MF7800 and MF7801; EPID L-2016-JLD-0006) ML18227A7332018-08-27027 August 2018 Request for Relief from the Requirements of the ASME Code ML18205A2922018-08-10010 August 2018 Correction of Errors in Safety Evaluation Associated with Relief Request 2-TYP-4-RV-02 ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18178A1122018-07-0202 July 2018 Relief Request No. 2-TYP-4-RV-02 Regarding the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-729-4 Examination Requirements ML18065A4032018-04-0505 April 2018 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 301 and 190 ML18073A1062018-03-28028 March 2018 Safety Evaluation of Proposed Alternatives 1-TYP-4-BA-01 and TYP-4-BN-01 Regarding the Fourth 10- Year Interval of the Inservice Inspection Program 2024-07-16
[Table view] |
Text
August 28, 2006 Mr. James H. Lash Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO. 2 - ISSUANCE OF AMENDMENT RE: BATTERY CHARGER UPGRADE (TAC NO. MC8735)
Dear Mr. Lash:
The Commission has issued the enclosed Amendment No. 157 to Facility Operating License No. NPF-73 for the Beaver Valley Power Station, Unit No. 2 (BVPS-2). This amendment consists of changes to the Technical Specifications (TSs) in response to your application dated October 14, 2005, as supplemented March 31, 2006.
The amendment revises TSs 3/4 8.2.3 and 3/4 8.2.4 to permit implementation of design changes associated with a battery charger upgrade during the fall 2006 refueling outage.
A copy of the related safety evaluation is also enclosed. The Notice of Issuance will be included in the Commission's biweekly Federal Register notice.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412
Enclosures:
- 1. Amendment No. 157 to NPF-73
- 2. Safety Evaluation cc w/encls: See next page
August 28, 2006 Mr. James H. Lash Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO. 2 - ISSUANCE OF AMENDMENT RE: BATTERY CHARGER UPGRADE (TAC NO. MC8735)
Dear Mr. Lash:
The Commission has issued the enclosed Amendment No. 157 to Facility Operating License No. NPF-73 for the Beaver Valley Power Station, Unit No. 2 (BVPS-2). This amendment consists of changes to the Technical Specifications (TSs) in response to your application dated October 14, 2005, as supplemented March 31, 2006.
The amendment revises TSs 3/4 8.2.3 and 3/4 8.2.4 to permit implementation of design changes associated with a battery charger upgrade during the fall 2006 refueling outage.
A copy of our safety evaluation is also enclosed. The Notice of Issuance will be included in the Commission's biweekly Federal Register notice.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412
Enclosures:
- 1. Amendment No. 157 to NPF-73
- 2. Safety Evaluation cc w/encls: See next page DISTRIBUTION:
PUBLIC LPLI-1 R/F RidsNrrLpla RidsNrrPMTColburn RidsNrrLASLittle RidsOGC Rp RidsAcrsAcnwMailCenter GHill(2)
RidsNrrDirsItsb MMcConnell RBellamy, RI SBalwantDorl DPR ACCESSION NO. ML062290203 SE input provided. No substantive changes made.
OFFICE LPLI-1/PM LPLI-1/LA EEEB/BC LPLI-1/BC OGC NAME TColburn SLittle GWilson*
RLaufer DRoth DATE 8/21/06 8/21/06 08/11/06 8/28/06 8/24/06 OFFICIAL RECORD COPY
Beaver Valley Power Station, Unit Nos. 1 and 2 cc:
Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 Joseph J. Hagan Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-18 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-107 395 Ghent Road Akron, OH 44333 James H. Lash Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077 Lew W. Myers Executive Vice President, Special Projects FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SGRP P.O. Box 4, Route 168 Shippingport, PA 15077 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.
Harrisburg, PA 17110-9364 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149
Beaver Valley Power Station, Unit Nos. 1 and 2 (continued) cc:
Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077
FIRSTENERGY NUCLEAR OPERATING COMPANY FIRSTENERGY NUCLEAR GENERATION CORP.
OHIO EDISON COMPANY THE TOLEDO EDISON COMPANY DOCKET NO. 50-412 BEAVER VALLEY POWER STATION, UNIT 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 157 License No. NPF-73 1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by FirstEnergy Nuclear Operating Company, et al. (the licensee), dated October 14, 2005, as supplemented March 31, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (I) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-73 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 157, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated in the license. FENOC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
3.
This license amendment is effective as of the date of its issuance and shall be implemented within 90 days.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Richard J. Laufer, Chief Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the License and Technical Specifications Date of Issuance: August 28, 2006
ATTACHMENT TO LICENSE AMENDMENT NO. 157 FACILITY OPERATING LICENSE NO. NPF-73 DOCKET NO. 50-412 Replace the following page of Facility Operating License No. NPF-73 with the attached revised page. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.
Remove Insert 3a 3a Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert 3/4 8-9 3/4 8-9 3/4 8-12 3/4 8-12
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 157 TO FACILITY OPERATING LICENSE NO. NPF-73 FIRSTENERGY NUCLEAR OPERATING COMPANY FIRSTENERGY NUCLEAR GENERATION CORP.
OHIO EDISON COMPANY THE TOLEDO EDISON COMPANY BEAVER VALLEY POWER STATION, UNIT 2 DOCKET NO. 50-412
1.0 INTRODUCTION
By letter dated October 14, 2005 (ADAMS Accession No. ML05000412), as supplemented by letter dated March 31, 2006 (ADAMS Accession No. ML060970122), FirstEnergy Nuclear Operating Company (the licensee) requested an amendment to the Facility Operating License No. NPF-73 for Beaver Valley Power Station, Unit No. 2 (BVPS-2), and Appendix A, Technical Specifications (TSs) of the Facility Operating License. The proposed changes would revise TS Sections 3/4.8.2.3 and 3/4.8.2.4 to permit implementation of station battery charger upgrades, including installation of new battery chargers.
The supplement dated March 31, 2006, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the staffs original proposed no significant hazards consideration determination as published in the Federal Register on November 22, 2005 (70 FR 70642).
The licensee has proposed the following changes:
1.
Revise TS Limiting Condition for Operation (LCO) 3.8.2.3 to replace references to rectifiers 2-3 and 2-4 with references to chargers 2-3 and 2-4, respectively.
- 2.
Revise TS 3.8.2.3, Action "b" to delete reference to the rectifiers (chargers will continue to be referenced).
- 3.
Revise TS 3.8.2.3, Action "b" to refer to "a spare charger" instead of "spare charger 2-7."
- 4.
Revise Surveillance Requirement (SR) 4.8.2.3.2 to delete reference to "rectifier." The charger will continue to be referenced in SR 4.8.2.3.2.
- 5.
Editorial revision to TS LCO 3.8.2.3 Train "A" and Train "B" equipment list wording to correct grammar and for consistency.
- a.
The third occurrence of the ampersand ("&") symbol in the LCO 3.8.2.3 Train "A" equipment list will be changed to read "and" to be consistent with LCO 3.8.2.4 wording.
- b.
The word "charger" in both the LCO 3.8.2.3 Train "A" and Train "B" equipment list will be changed to read "chargers" to be grammatically correct.
- c.
The word "and" in the LCO 3.8.2.3 Train "A" equipment list will be changed to an ampersand symbol to be consistent with LCO 3.8.2.4 wording.
- d.
The second occurrence of the word "and" in the LCO 3.8.2.3 Train "B" equipment list will be changed to an ampersand symbol to be consistent with LCO 3.8.2.4 wording.
- 6.
Revise TS LCO 3.8.2.4.a and b to replace references to rectifiers 2-3 and 2-4 with references to chargers 2-3 and 2-4, respectively.
- 7.
Revise LCO 3.8.2.4 footnote associated with Spare Charger 2-7 to delete reference to "rectifier."
- 8.
Revise LCO 3.8.2.4 footnote associated with Spare Charger 2-7 to refer to "A spare charger" instead of "Spare Charger 2-7," and change the words "one charger or rectifier" to read "inoperable charger or charger removed from service for maintenance."
- 9.
Revise SR 4.8.2.4.2 to delete reference to "rectifier." The charger will continue to be referenced in SR 4.8.2.4.2.
- 10.
Editorial changes will be made to the LCO 3.8.2.4 Train "A" and Train "B" equipment list wording to correct grammar and for consistency.
- a.
The word "Busses" in both the LCO 3.8.2.3 Train "A" and Train "B" equipment list will be changed to read "busses" to be consistent with LCO 3.8.2.3 wording.
- b.
The words "Battery Banks" in both the LCO 3.8.2.3 Train "A" and Train "B" equipment list will be changed to read "battery banks" to be consistent with LCO 3.8.2.3 wording.
- c.
The word "Charger" in both the LCO 3.8.2.3 Train "A" and Train "B" equipment list will be changed to read "chargers" to correct grammar and to be consistent with LCO 3.8.2.3 wording.
2.0 REGULATORY EVALUATION
The following Nuclear Regulatory Commission (NRC) requirements are applicable to the NRC staffs review of the BVPS-2 license amendment request:
General Design Criterion (GDC) 17, Electric power systems, of Appendix A, General Design Criteria for Nuclear Power Plants, to Title 10 of the Code of Federal Regulations (10 CFR)
Part 50 requires, in part, that nuclear power plants have onsite and offsite electric power systems to permit the functioning of structures, systems, and components that are important to safety. The onsite system is required to have sufficient independence, redundancy, and testability to perform its safety function, assuming a single failure. The offsite power system is required to be supplied by two physically independent circuits that are designed and located so as to minimize, to the extent practical, the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions. In addition, this criterion requires provisions to minimize the probability of losing electric power from the remaining electric power supplies as a result of loss of power from the unit, the offsite transmission network, or the onsite power supplies.
GDC 18, Inspection and testing of electric power systems, requires that electric power systems that are important to safety must be designed to permit appropriate periodic inspection and testing.
10 CFR 50.36, Technical specifications, requires a licensees TSs to establish LCOs, which includes completion times for equipment that is required for safe operation of the facility.
10 CFR 50.65, Requirements for monitoring the effectiveness of maintenance at nuclear power plants, requires that preventive maintenance activities must not reduce the overall availability of the systems, structures, and components.
3.0 TECHNICAL EVALUATION
The BVPS-2, 120 Volt (V) alternating current (ac) vital bus uninterruptible power supply (UPS) consists of four independent Class 1E vital bus power supplies (2-1, 2-2, 2-3, and 2-4). Each bus provides 120 V ac power for engineered safety feature protection channel instrumentation and controls. Each vital bus UPS currently consists of an inverter, rectifier (systems 2-1 and 2-2), or rectifier/charger (systems 2-3 and 2-4), static switch/manual bypass switch, and alternate source line voltage regulator.
Each Class 1E 120 V ac vital bus normally receives power from its UPS unit which, in turn, receives power from an emergency 480 V motor control center (MCC). The UPS rectifier converts the 480 V ac to 125 V direct current (dc) and supplies it to the UPS inverter input. The interconnection with an emergency 480 V MCC provides the vital buses with the capability of an offsite (preferred) power source or an onsite (emergency) power source.
In the event that the rectifier source is lost, the inverter will receive 125 V dc directly from the 125 V dc battery. This input is normally the battery charger. Each system is designed such that the battery will not supply current to the UPS while ac power (rectifier input) is available and within specified limits.
Vital buses 2-3 and 2-4 are associated with Class 1E batteries 2-3 and 2-4, respectively. The dc loads on these systems are limited by design to only 2-3 and 2-4 channel 125 V dc circuits.
For this reason, the rectifier/chargers, in addition to being the primary source of dc power to the inverter assemblies, also serve as battery chargers for these batteries.
UPS units associated with vital buses 2-1 and 2-2 receive their dc inputs from Class 1E batteries 2-1 and 2-2, respectively, via dc switchboards. Several non-vital bus Class 1E loads not in this system are also powered from these two sources; consequently, batteries 2-1 and 2-2 are provided with separate battery chargers. Blocking diodes have been added to the input circuits of inverters 2-1 and 2-2, thus preventing back-feeding from rectifiers 2-1 and 2-2, and preventing the rectifier assemblies from providing dc input to the respective battery bus.
Currently, a spare mobile battery charger is available to provide charging current to the Class 1E batteries during charger maintenance, or in the event that a Class 1E battery charger fails. This spare charger and its associated connecting receptacles are qualified for Class 1E use.
Each dc subsystem has a charging component which is sized to supply all normal continuous loads and to simultaneously recharge the battery, after the design 2-hour duty cycle discharge, to the fully charged condition in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
The Class 1E batteries have the ability to supply normal loads for a minimum of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. The capacity of each Class 1E battery with the charger inoperable is large enough to cope with design-basis accident (DBA) conditions.
Each battery system is sized in conformance with the principles set out in the Institute of Electrical and Electronics Engineers (IEEE) Standard 308-1974, IEEE Standard Criteria for Class 1E Power Systems for Nuclear Power Generating Stations. The battery capacities for batteries 2-1 and 2-2 are 1,700 ampere hours (Ah) each. The capacities for batteries 2-3 and 2-4 are 1,140 Ah each. These capacities are sufficient to operate all connected dc loads under DBA conditions for a minimum of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.
The licensee proposed the aforementioned changes for two reasons. The replacement of battery chargers 2-1 and 2-2 are being proposed due to obsolescence. While the addition of new battery chargers 2-3 and 2-4 are being proposed to add diversity to the system, a single failure of the rectifier would no longer render the UPS and the dc bus inoperable.
3.1 Changes 1, 2, and 5 The licensee proposed revising TS LCOs 3.8.2.3 and 3.8.2.4 to reflect installation of new battery chargers (2-3 and 2-4). The licensee stated that these new battery chargers will satisfy the battery charging function previously satisfied by rectifiers 2-3 and 2-4 and will be capable of recharging the connected battery while simultaneously carrying the associated dc bus load on any of the Class 1E 125 V dc buses. The licensee further stated that rectifiers 2-3 and 2-4 will no longer be used for charging the battery. However, the rectifiers will continue to provide the primary source of dc power to the vital bus inverter assemblies. Since the new battery chargers will be seismically and electrically equivalent to battery chargers 2-1 and 2-2, and satisfy the applicable Updated Final Safety Analysis Report design basis, the NRC staff finds the proposed changes acceptable.
3.2 Changes 3 and 8 The licensee proposed revising the references to spare charger 2-7 in LCO 3.8.2.3, Action b and the footnote associated with LCO 3.8.2.4.
The NRC staff finds that the relocation of the descriptive text identifying the spare battery charger from the TSs to the TS Bases is acceptable because this type of information can be adequately controlled in the TS Bases. With the proposed change, the TSs will continue to require (in the case of LCO 3.8.2.3, Action b) and allow (in the case of the footnote associated with LCO 3.8.2.4) that a spare equivalent battery charger be placed in service when a charger is inoperable or removed from service for maintenance.
The staff also finds that revising the footnote for LCO 3.8.2.4 to indicate that a spare battery charger may be substituted for an inoperable charger or charger removed from service for maintenance is acceptable since the revised TS wording is clarified to ensure proper understanding of the requirement.
3.3 Changes 4, 7, and 9 The licensee proposed deleting references to "rectifier" in SR 4.8.2.3.2, in the footnote associated with LCO 3.8.2.4, and in SR 4.8.2.4.2, since the rectifiers will no longer be used to satisfy the battery charger function. The licensee stated that the rectifiers will continue to provide dc power to the inverter assemblies and this design function will continue to be verified by SR 4.8.2.1 and 4.8.2.2.
Based on this information and the addition of new battery chargers 2-3 and 2-4 to satisfy the battery charging function, the NRC staff finds these changes acceptable.
3.4 Changes 5 and 10 The licensee proposed revising the equipment list wording for Train A and Train B in LCOs 3.8.2.3 and 3.8.2.4 to correct grammar and for consistency. The NRC staff finds that these changes are administrative in nature, and therefore, are acceptable.
On the basis of the above discussions, the staff concludes that the proposed amendment to revise BVPS-2 TSs 3/4.8.2.3 and 3/4.8.2.4 is acceptable.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Pennsylvania State official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes surveillance requirements. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (70 FR 70642). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: M. McConnell Date: August 28, 2006