ML16060A012

From kanterella
Jump to navigation Jump to search

FENOC - Email RAI to Licensee Regarding LAR for Changes to TS 5.3.1 CAC Nos. MF7118, MF7119, and MF7120
ML16060A012
Person / Time
Site: Beaver Valley, Davis Besse
Issue date: 02/29/2016
From: Bhalchandra Vaidya
Plant Licensing Branch III
To: Lashley P, Lentz T
FirstEnergy Nuclear Operating Co
Vaidya B, NRR/DORL/LPL3-2, 415-3308
References
CAC MF7118, CAC MF7119, CAC MF7120
Download: ML16060A012 (1)


Text

From:

Vaidya, Bhalchandra Sent:

Monday, February 29, 2016 7:43 AM To:

Lashley, Phil H. (phlashley@firstenergycorp.com);

'tlentz@firstenergycorp.com' Cc:

Kolb, Timothy; Green, Brian; West, Khadijah; Sloan, Scott; Weerakkody, Sunil; Elliott, Robert; Poole, Justin

Subject:

FENOC - RAI Regarding LAR for Changes to TS 5.3.1 CAC Nos. MF7118, MF7119, and MF7120 Phil and Tim, By letter dated November 19, 2015, (ADAMS Accession No. ML15), the licensee submitted a License Amendment Request (LAR) regarding changes to TS 5.3.1, Staff Qualifications, for Beaver Valley Units 1 and 2, and Davis-Besse.

The NRC staff is reviewing the application and needs the following additional information to complete its review. The Request for Additional Information (RAI) is provided below:

============================================================
=================================

APHB/IOLB RAI-1 The proposed line item added to TS 5.3.1 uses language that varies from precedent set by other plants (For example, Braidwood, Clinton, Dresden, LaSalle, Limerick, and Quad Cities all specify that the operators need to comply only with the requirements of 10 CFR 55). The proposed addition to the TS omits the word only which may lead to inconsistent interpretations by some operators. Please provide a justification for why the word only has been left out of the proposed change or revise the TS accordingly to ensure that operators will interpret it appropriately.

============================================================
===============================

The NRC staff would like to receive the response to this RAIs with 30 days from the date of this communication. Please contact me to schedule a telephone conference, if you need any clarification for this RAI, or need additional time to respond.

Please contact me, if you have any questions.