{{#Wiki_filter:Appendix D Scenario Outline Form ES-D-1 NRC F INAL  Facility: E. I Hatch Scenario No.:
{{#Wiki_filter:Appendix D                               Scenario Outline                         Form ES-D-1 NRC FINAL Facility:   E. I Hatch             Scenario No.: 9-02       Op-Test No.:   2015-301 Examiners:                                     Operators:                                         SRO RO BOP Initial Conditions. Unit 2 is operating at 75%RTP.
9-02 Op-Test No.: 2015-301 Examiners:
Turnover: Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82%
Operators:
RTP using the Recirculation System.
SRO   RO   BOP Initial Conditions
Event       Malf. No.     Event                                    Event No.                      Type*                                 Description Restoration To Normal Hydrogen Seal Oil System Lineup starting at 1    N/A                N (BOP) step 7.3.3.2.5 of 34SO-N42-001-2.
. Unit 2 is operating at 75%RTP.
2   N/A               R (ATC)     Raise Reactor power to 82% using Recirc.
Turnover: Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 8 2% RTP using the Recirculation System.
mfR22_183 4160V Emergency Bus 2F de-energizes due to a hard ground. With mfR22_256          C (BOP) 3                                  time compression repair and re-energizes. 1B EDG Generator Over mf65223700        TS (SRO) current Alarm (off).
Event No. Malf. No. Event Type* Event Description 1 N/A N (BOP) Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. 2 N/A R (ATC) Raise Reactor power to 82% using Recirc. 3 mfR22_183 mfR22_256 mf65223700 ET-R43-1 C (BOP) TS (SRO) 4160V Emergency Bus '2F' de
ET-R43-1 4   N/A               C (ATC)     Loss of CRD due to power failure.
-energizes due to a hard ground. With time compression repair and re
Feedwater pump 2B cooling water controller failure. TC repair and 5    mfN21_88B          I (BOP) return to auto.
-energizes. 1B EDG Generator Over current Alarm (off)
mfB31_39A mfB31_45A         C (ATC) Recirc Pump A Seal Leakage causes DW leakage & pressure 6    mfB31_29          TS (SRO) increase. Pump is secured & isolated. (Critical Task) mf60213160 7   mfG31_242         M (ALL)     Leak in Drywell causes High Drywell pressure scram.
. 4 N/A C (ATC) Loss of CRD due to power failure.
ET-E11-11                     1st RHR 2E11-F016A/B Containment Spray Valve causes associated 8                      C (ATC)
5 mfN21_88B I (BOP) Feedwater pump 2B cooling water controller failure. TC repair and return to auto.
ET-E11-12                      RHR pumps to trip. (Critical Task)
6 mfB31_39A mfB31_45A mfB31_29 mf60213160 C (ATC) TS (SRO) Recirc Pump "A" Seal Leakage causes DW leakage & pressure increase. Pump is secured & isolated.
*       (N)ormal,       (R)eactivity,   (I)nstrument,       (C)omponent,       (M)ajor
(Critical Task
 
) 7 mfG31_242 M (ALL) Leak in Drywell causes High Drywell pressure scram.
Appendix D                     Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:         1                     Page 2 of 28 Event
8 ET-E11-11 ET-E11-12 C (ATC) 1st RHR 2E11
-F016A/B Containment Spray Valve causes associated RHR pumps to trip
. (Critical Task
) * (N)ormal,   (R)eactivity,     (I)nstrument,   (C)omponent, (M)ajor Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
1 Page 2 of 28 Event


== Description:==
== Description:==
Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2.
Time    Position  Applicant's Actions or Behavior Simulator Operator, IF contacted as SO, report the following:
* Seal Oil Vacuum Pump Separator Tank oil level is between the High AND Low Oil Level on 2N42-LG-R306, Separator Tank Sight Glass 10
* 2N42-F042, Vacuum Tank Inlet Valve, open Mins
* Oil level in the Vacuum Tank is above the bottom of the lower observation window
* Seal Oil Vacuum Pump shaft has been manually rotated.
* Enters Restoration To Normal Hydrogen Seal Oil System Lineup at step 7.3.3.2.5
* Starts 2N42-C001, H 2 Seal Oil Vacuum Pump, (2H11-P651).
Simulator Operator, WHEN contacted as SO, 2N42-R302, Vacuum Tank Pressure, is 26.5 in. Hg and steady.
* Confirms 2N42-R302, Vacuum Tank Pressure, stabilizes above 26 in. Hg. by contacting SO locally.
BOP
* Starts 2N42-C003, Recirc H 2 Seal Oil Pump.
* Starts 2N42-C004, Main H 2 Seal Oil Pump.
* Secure 2N42-C002, Emergency Seal Oil Pump, as follows:
* Holds control switch for ESOP in OFF Pull To Lock position until pump stops as indicated by its extinguished red AND green lights
* Alarm EMERG SEAL OIL PUMP RUNNING, (651-216) will clear after the SO resets the local panel.
* AFTER pump stops, releases control switch.
* Confirm its green light is illuminated.
Simulator Operator, when contacted as SO, report the following:
* 2N42-R300, Seal Oil Pump Disch Press, is 105 psig
* 2N42-R301, Seal Oil / Machine Gas dP, pressure, is 8 psig above generator gas pressure.
* If asked, inform BOP the Emergency Seal Oil Pump shaft has stopped rotating.


Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Time Position Applicant's Actions or Behavior 10 Mins  Simulator Operator, IF contacted as SO, report the following:
Appendix D                     Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       1                       Page 3 of 28 Event
Seal Oil Vacuum Pump Separator Tank oil level is between the High AND Low Oil Level on 2N42
-LG-R306, Separator Tank Sight Glass 2N42-F042, Vacuum Tank Inlet Valve, open  Oil level in the Vacuum Tank is above the bottom of the lower observation window Seal Oil Vacuum Pump shaft has been manually rotate
: d. BOP  Enters Restoration To Normal Hydrogen Seal Oil System Lineup at step 7.3.3.2.5  Starts 2N42
-C001, H 2 Seal Oil Vacuum Pump, (2H11
-P651). Simulator Operator, WHEN contacted as SO, 2N42-R302, Vacuum Tank Pressure, is 26
.5 in. Hg and steady.
Confirms 2N42-R302, Vacuum Tank Pressure, stabilizes above 26 in. Hg.
by contacting SO locally.
Starts 2N42
-C003, Recirc H 2 Seal Oil Pump.
Starts 2N42
-C004, Main H 2 Seal Oil Pump.
Secure 2N42
-C002, Emergency Seal Oil Pump, as follows:
Holds control switch for ESOP in OFF Pull To Lock position until pump stops as indicated by its extinguished red AND green lights Alarm EMERG SEAL OIL PUMP RUNNING, (651-216) will clear after the SO resets the local panel.
AFTER pump stops, releases control switch.
Confirm its green light is illuminated
.            Simulator Operator, when contacted as SO, report the following:
2N42-R300, Seal Oil Pump Disch Press, is 105 psig 2N42-R301, Seal Oil / Machine Gas dP, pressure, is 8 psig above generator gas pressure.
If asked, inform BOP the Emergency Seal Oil Pump shaft has stopped rotating.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
1 Page 3 of 28 Event


== Description:==
== Description:==
Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2.
Time    Position  Applicant's Actions or Behavior Simulator Operator, when contacted as SO, report the following:
* DELETE mf65121574, EMERGENCY SEAL OIL PUMP RUNNING (ANNUNCIATOR ON)
* REPORT Local alarm, EMERG SEAL OIL PUMP RUNNING, (N43-105) has been reset
* Confirms the following by contacting SO locally:
* 2N42-R300, Seal Oil Pump Disch Press, is 100 - 110 psig BOP
* 2N42-R301, Seal Oil / Machine Gas dP, pressure, is being maintained 7 - 9 psig above generator gas pressure.
Simulator Operator, at the Chief Examiners request, PROCEEDS to the next event.


Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Time Position Applicant's Actions or Behavior Simulator Operator, when contacted as SO, report the following:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       2                         Page 4 of 28 Event
DELETE mf65121574, EMERGENCY SEAL OIL PUMP RUNNING (ANNUNCIATOR ON)
REPORT Local alarm, EMERG SEAL OIL PUMP RUNNING, (N43-105) has been reset BOP  Confirms the following by contacting SO locally:
2N42-R300, Seal Oil Pump Disch Press, is 100
- 110 psig  2N42-R301, Seal Oil / Machine Gas dP, pressure, is being maintained 7 - 9 psig above generator gas pressure.
Simulator Operator, at the Chief Examiner's request, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
2 Page 4 of 28 Event


== Description:==
== Description:==
Raise Reactor power to 70% using Recirc.
Raise Reactor power to 70% using Recirc.
Time Position Applicant's Actions or Behavior 10 Min SRO  Directs ATC to increase reactor power to 82% by increasing Recirc flow. Power increases are NOT to exceed 10 MWe/min.
Time     Position Applicant's Actions or Behavior
NOTE: May get the RBM UPSCALE, (603
* Directs ATC to increase reactor power to 82% by increasing Recirc flow.
-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.
10 Min      SRO Power increases are NOT to exceed 10 MWe/min.
May also get Alarm HEATER TROUBLE, (650
NOTE: May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.
-135), alarm. This is expected at this power level.
May also get Alarm HEATER TROUBLE, (650-135), alarm. This is expected at this power level.
ATC  IAW 34SO-B31-001-2 (step 7.1.5) & 34GO
* IAW 34SO-B31-001-2 (step 7.1.5) & 34GO-OPS-005-2, the ATC increases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master (P603 panel) or Individual controls (P602 panel) until reactor power is 82%.
-OPS-005-2, the ATC increases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master (P603 panel) or Individual controls (P602 panel) until reactor power is 82%. If using Individual Controls, pump speed increases will alternate between the "A" & "B" Recirc pumps to prevent excessive flow mismatches.
ATC
Monitors power increase by observing APRM and generator output indications
* If using Individual Controls, pump speed increases will alternate between the A & B Recirc pumps to prevent excessive flow mismatches.
.        ATC  Complies with 34SO
* Monitors power increase by observing APRM and generator output indications.
-B31-001-2 , Limitation 5.2.15, which states:
* Complies with 34SO-B31-001-2 , Limitation 5.2.15, which states:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
  <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating  
ATC
< 70% of rated core flow; AND <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at  
                          *  <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating
> 70% of rated core flow.
                              < 70% of rated core flow; AND
ATC Notifies the SRO that reactor power has been increased to 82%.     Simulator Operator, at the Chief Examiners direction OR after power has been increased by 5%, PROCEEDS to the next event.
                          * <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at
                              > 70% of rated core flow.
ATC     Notifies the SRO that reactor power has been increased to 82%.
Simulator Operator, at the Chief Examiners direction OR after power has been increased by 5%, PROCEEDS to the next event.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       3                       Page 5 of 28 Event
9-02 Event No.:
3 Page 5 of 28 Event


== Description:==
== Description:==
2F Emergency Bus de-energizes due to a hard ground.
2F Emergency Bus de-energizes due to a hard ground.
Time Position Applicant's Actions or Behavior 15 Min  NOTE TO CHIEF EXAMINER
Time     Position Applicant's Actions or Behavior NOTE TO CHIEF EXAMINER:
Event 3 (4160V Emergency Bus 2F loss) and Event 4 (Loss of CRD) will be running concurrently.
15 Min                Event 3 (4160V Emergency Bus 2F loss) and Event 4 (Loss of CRD) will be running concurrently.
Simulator Operator, at direction of the Chief Examiner, ACTIVATE: (RB-3) and ENSURE Event Trigger ET-EGR43-1 ACTIVATES   mfR22_183, "2F" 4160 bus fault ET-EGR43-1   NOTE: With the loss of 2F 4160V bus, the BOP may address 34AB
Simulator Operator, at direction of the Chief Examiner, ACTIVATE: (RB-3) and ENSURE Event Trigger ET-EGR43-1 ACTIVATES
-R22-002-2, Loss of 4160V Emergency Bus", first. Also the following alarms may be addressed in any order.
* mfR22_183, 2F 4160 bus fault
ALL The following alarms associated with 2F 4160V bus will be received:
* ET-EGR43-1 NOTE: With the loss of 2F 4160V bus, the BOP may address 34AB-R22-002-2, Loss of 4160V Emergency Bus, first. Also the following alarms may be addressed in any order.
LOSS OF OFF SITE POWER, (652
The following alarms associated with 2F 4160V bus will be received:
-202) PSW PRESS LOW, (652
* LOSS OF OFF SITE POWER, (652-202)
-210) 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652
* PSW PRESS LOW, (652-210)
-217) 4160V BUS 2F VOLTAGE LOW, (652
ALL
-222) 4160 STA SVC FDR BRKR TRIP, (650
* 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652-217)
-137)           BOP  Responds to annunciators LOSS OF OFF SITE POWER, (652
* 4160V BUS 2F VOLTAGE LOW, (652-222)
-202), 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652
* 4160 STA SVC FDR BRKR TRIP, (650-137)
-217) AND PSW PRESS LOW, (652
* Responds to annunciators LOSS OF OFF SITE POWER, (652-202),
-210).           BOP  Responds to annunciator, LOSS OF OFF SITE POWER, (652
BOP          4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652-217) AND PSW PRESS LOW, (652-210).
-202), Confirms the following on 2H 11-P652: EDG 1B is operating 4160V Bus 2F LOSP Lockout Relay is locked out 4160V Emergency Bus 2F is energized.
* Responds to annunciator, LOSS OF OFF SITE POWER, (652-202),
600V Emergency Buses 2C AND 2D are energized
* Confirms the following on 2H11-P652:
* EDG 1B is operating BOP
* 4160V Bus 2F LOSP Lockout Relay is locked out
* 4160V Emergency Bus 2F is energized.
* 600V Emergency Buses 2C AND 2D are energized


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       3                         Page 6 of 28 Event
9-02 Event No.:
3 Page 6 of 28 Event


== Description:==
== Description:==
2F Emergency Bus de-energizes due to a hard ground.
2F Emergency Bus de-energizes due to a hard ground.
Time Position Applicant's Actions or Behavior BOP  Responds to annunciator 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652
Time     Position Applicant's Actions or Behavior
-217), On 2H11-P652 confirms the following:
* Responds to annunciator 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652-217),
Normal Supply breaker 135574 open Alternate Supply breaker 135564 open 1B EDG Output breaker 135570 open:
* On 2H11-P652 confirms the following:
Dispatches SO/Maintenance to investigate the loss of 4160V Bus 2F BOP  Responds to annunciator, PSW PRESS LOW, (652
BOP
-210),   On 2H11-P652:   Observes 1R24
* Normal Supply breaker 135574 open
-S026 is NOT energized Observes 2P41
* Alternate Supply breaker 135564 open
-C002 Standby PSW pump is NOT energized Observes 2P41
* 1B EDG Output breaker 135570 open:
-C002, "STBY PSW Pump", has no lights illuminated.
* Dispatches SO/Maintenance to investigate the loss of 4160V Bus 2F
Places Feeder to SST 2F1 2S11
* Responds to annunciator, PSW PRESS LOW, (652-210),
-S009 Alt Sply 1R24
* On 2H11-P652:
-S026 Diesel Bldg MCC 1B", to TRIP.
* Observes 1R24-S026 is NOT energized
Observes 2P41
* Observes 2P41-C002 Standby PSW pump is NOT energized BOP
-C002, "STBY PSW Pump", red light illuminates. (This restores cooling water to the 1B DG.)
* Observes 2P41-C002, STBY PSW Pump, has no lights illuminated.
BOP  Enters 34AB
* Places Feeder to SST 2F1 2S11-S009 Alt Sply 1R24-S026 Diesel Bldg MCC 1B, to TRIP.
-R22-002-2. "Loss of 4160V Emergency Bus" Confirm 1B Diesel Generator has auto started Ensure adequate cooling water is available to the 1B Diesel Generator (if NOT previously performed):
* Observes 2P41-C002, STBY PSW Pump, red light illuminates.
Observes 2P41
(This restores cooling water to the 1B DG.)
-C002, "STBY PSW Pump", has no lights illuminated.
* Enters 34AB-R22-002-2. Loss of 4160V Emergency Bus
Places Feeder to SST 2F1 2S11
* Confirm 1B Diesel Generator has auto started
-S009 Alt Sply 1R24
* Ensure adequate cooling water is available to the 1B Diesel Generator (if NOT previously performed):
-S026 Diesel Bldg MCC 1B", to TRIP.
* Observes 2P41-C002, STBY PSW Pump, has no lights BOP                    illuminated.
Observes 2P41
* Places Feeder to SST 2F1 2S11-S009 Alt Sply 1R24-S026 Diesel Bldg MCC 1B, to TRIP.
-C002, "STBY PSW Pump", red light illuminates. (This restores cooling water to the 1B Diesel Generator.)
* Observes 2P41-C002, STBY PSW Pump, red light illuminates.
May dispatch a Systems Operator to locally trip the 1B EDG.
(This restores cooling water to the 1B Diesel Generator.)
* May dispatch a Systems Operator to locally trip the 1B EDG.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       3                         Page 7 of 28 Event
9-02 Event No.:
3 Page 7 of 28 Event


== Description:==
== Description:==
2F Emergency Bus de-energizes due to a hard ground.
2F Emergency Bus de-energizes due to a hard ground.
Time Position Applicant's Actions or Behavior SRO  Directs the BOP to enter 34AB
Time     Position Applicant's Actions or Behavior
-R22-002-2 for the loss of 4160V Emergency Bus Simulator Operator: If called as the SO to trip the 1B DG, enter RB-1 to activate rfR43_162 "Diesel Gen 1B Engine Fuel Rack".
* Directs the BOP to enter 34AB-R22-002-2 for the loss of 4160V SRO Emergency Bus Simulator Operator: If called as the SO to trip the 1B DG, enter RB-1 to activate rfR43_162 Diesel Gen 1B Engine Fuel Rack.
SRO  Addresses Tech Specs 3.8.7 and enters an 8 hour RAS per TS 3.8.7.C.1 to restore AC electrical power distribution subsystem to operable status.
* Addresses Tech Specs 3.8.7 and enters an 8 hour RAS per TS 3.8.7.C.1 to restore AC electrical power distribution subsystem to operable status.
Enters TS 3.8.1 if SRO believes 1B EDG output breaker failed to close or if 1B EDG is ordered tripped locally due to no cooling water, and performs Conditions:
* Enters TS 3.8.1 if SRO believes 1B EDG output breaker failed to close or if 1B EDG is ordered tripped locally due to no cooling water, and performs Conditions:
B.1 in 1 hour perform surveillance on operable required off-site circuits (34SV-SUV-013-0, "Weekly Breaker Alignment Checks")
B.1 in 1 hour perform surveillance on operable required off-site circuits (34SV-SUV-013-0, Weekly Breaker Alignment Checks)
AND  
AND B.2 declare required features supported by the DG inoperable when redundant required features are inoperable (required redundant features ARE operable)
 
SRO AND B.3.1 in 24 hours determines operable DG(s) are NOT inoperable due to common cause failure OR B.3.2 in 24 hours performs surveillance on operable DG(s).
B.2 declare required features supported by the DG inoperable when redundant required features are inoperable (required redundant features ARE operable)  
AND B.4 in 72 hours Restore 1B DG to operable status
 
* May address TS 3.7.2, Plant Service Water Systems & Ultimate Heat Sink, Condition A for the 2C PSW pump.
AND B.3.1 in 24 hours determines operable DG(s) are NOT inoperable due to common cause failure
 
OR B.3.2 in 24 hours performs surveillance on operable DG(s).  
 
AND B.4 in 72 hours Restore 1B DG to operable status May address TS 3.7.2, Plant Service Water Systems & Ultimate Heat Sink, Condition A for the 2C PSW pump.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:         3                         Page 8 of 28 Event
9-02 Event No.:
3 Page 8 of 28 Event


== Description:==
== Description:==
2F Emergency Bus de-energizes due to a hard ground.
2F Emergency Bus de-energizes due to a hard ground.
Time Position Applicant's Actions or Behavior Simulator Operator , A f ter being dispatched , wait 5 minutes and NOTIF Y the U2 SRO and INFORM, as Maintenance Electrical Team Leader
Time     Position Applicant's Actions or Behavior Simulator Operator, After being dispatched, wait 5 minutes and NOTIFY the U2 SRO and INFORM, as Maintenance Electrical Team Leader, there is a fault on 2F Emergency bus and we are still investigating.
, there is a fault on 2F Emergency bus and we are still investigati ng.     NOTE: The 2C PSW pump would be considered inoperable if alarm, PSW PUMP 2C OVLD/LOCKOUT RELAY TRIP, (650
NOTE: The 2C PSW pump would be considered inoperable if alarm, PSW PUMP 2C OVLD/LOCKOUT RELAY TRIP, (650-230), were received, however in this case, the alarm was not received and the pump is just de-energized.
-230), were received, however in this case, the alarm was not received and the pump is just de
* Responds to annunciator 4160 STA SVC FDR BRKR TRIP, (650-137);
-energized.
* On 2H11-P650 confirms that 2C PSW pump amber light is illuminated.
BOP  Responds to annunciator 4160 STA SVC FDR BRKR TRIP, (650
BOP
-137); On 2H11-P650 confirms that 2C PSW pump amber light is illuminated.
* Once cause has been determined and corrected, takes the control switch for 2C PSW pump to off and spring returns to auto to clear amber light.
Once cause has been determined and corrected, takes the control switch for 2C PSW pump to off and spring returns to auto to clear amber light.
* If directed, restarts 2C PSW pump.
If directed, restarts 2C PSW pump.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
 
9-02 Event No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       4                         Page 9 of 28 Event
4 Page 9 of 28 Event


== Description:==
== Description:==
Loss of CRD due to power failure.
Loss of CRD due to power failure.
Time Position Applicant's Actions or Behavior 5 Mins  NOTE to Simulator Operator: NO additional malfunctions need to be entered for this event. This event stems from the loss of 2F 4160V bus.
Time     Position Applicant's Actions or Behavior NOTE to Simulator Operator: NO additional malfunctions need to be entered 5 Mins for this event. This event stems from the loss of 2F 4160V bus.
NOTE: With the loss of CRD, the ATC may address 34AB
NOTE: With the loss of CRD, the ATC may address 34AB-C11-001-2, Loss Of CRD, first. The following alarms may be addressed in any order.
-C11-001-2, "Loss Of CRD", first. The following alarms may be addressed in any order.
The following alarms associated with 2F 4160V bus will be received:
ALL The following alarms associated with 2F 4160V bus will be received:
* CRD PUMP B BREAKER TRIP, (603-129)
CRD PUMP B BREAKER TRIP, (603-129) CRD TEMP HIGH, (603
ALL
-140) CRD ACCUMULATOR PRESS LOW OR LEVEL HIGH, (603
* CRD TEMP HIGH, (603-140)
-148)       ATC Notifies SRO that B CRD pump has tripped.
* CRD ACCUMULATOR PRESS LOW OR LEVEL HIGH, (603-148)
SRO Directs ATC to enter 34AB-C11-001-2, "Loss Of CRD" ATC  Responds to annunciator, CRD PUMP B BREAKER TRIP, (603-129) Check the following indications on 2H11
ATC
-P603: Pump indicating lights.
* Notifies SRO that B CRD pump has tripped.
2C11-R600, CRD Flow controller, indicates zero flow.
SRO     Directs ATC to enter 34AB-C11-001-2, Loss Of CRD
2C11-R605, Cooling Wtr indicator, indicates zero flow.
* Responds to annunciator, CRD PUMP B BREAKER TRIP, (603-129)
2C11-R601, Charging Water Pressure indicator decreasing.
* Check the following indications on 2H11-P603:
2C11-R602, Drive Water DP indicator decreasing.
* Pump indicating lights.
2C11-R603, Cooling Water DP indicator decreasing.
* 2C11-R600, CRD Flow controller, indicates zero flow.
ATC  Responds to annunciators CRD HYD TEMP HIGH, (603-140) and CRD ACCUMULATOR PRESS LOW OR LEVEL HIGH, (603-148);   Enter 34AB
ATC
-C11-001-2, Loss Of CRD.
* 2C11-R605, Cooling Wtr indicator, indicates zero flow.
Dispatches an operator to CRD Temperature Recorder, 2C11
* 2C11-R601, Charging Water Pressure indicator decreasing.
-R018, (130Rx Bldg) and check temperatures.
* 2C11-R602, Drive Water DP indicator decreasing.
Dispatches an operator to determine local accumulator pressures.
* 2C11-R603, Cooling Water DP indicator decreasing.
* Responds to annunciators CRD HYD TEMP HIGH, (603-140) and CRD ACCUMULATOR PRESS LOW OR LEVEL HIGH, (603-148);
* Enter 34AB-C11-001-2, Loss Of CRD.
ATC
* Dispatches an operator to CRD Temperature Recorder, 2C11-R018, (130Rx Bldg) and check temperatures.
* Dispatches an operator to determine local accumulator pressures.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       4                       Page 10 of 28 Event
9-02 Event No.:
4 Page 10 of 28 Event


== Description:==
== Description:==
Loss of CRD due to power failure.
Loss of CRD due to power failure.
Time Position Applicant's Actions or Behavior Simulator Operator after 3 minutes, As the operator sent to the CRD temperature recorder, report that the highest temperature was 270 &deg;F and several CRDs at this temperature.
Time     Position Applicant's Actions or Behavior Simulator Operator after 3 minutes, As the operator sent to the CRD temperature recorder, report that the highest temperature was 270 &deg;F and several CRDs at this temperature.
Also inform that the operator sent to the CRD accumulators, reports that there are several accumulators with pressures less than 940 psig.
* Enters 34AB-C11-001-2, Loss of CRD, or may use CRD Pump Quick Restart Placard located on 2H11-P603
* Places 2C11-R600, CRD Flow Control, in manual and decreases the output to zero.
* Starts the A CRD pump.
* Returns the flow controller to auto and output to the pre-trip position.
ATC
* IF the applicant does NOT start the A CRD pump and the following conditions exist:
* Two or more withdrawn control rod scram accumulators inoperable
* AND
* Charging water header pressure <940 PSIG
* THEN: within 20 minutes restore charging water header pressure >
940 PSIG or inserts a scram.
* As time allows, may address Tech Specs 3.1.5
* By the time the SRO addresses TS 3.1.5; two or more accumulators will have a trouble alarm lit. Once it has been determined that 2 or more SRO          accumulators are inoperable, the SRO begins a 20 minute RAS per TS 3.1.5.B to insert a scram and declares the rods slow or inoperable in one hour.
* Terminates RAS once charging water pressure is restored above 940 psig.
Simulator Operator, After 2F 4160V Emergency bus is energized from 2D SAT AND CRD has been returned to service AND at the direction of the Chief Examiner, PROCEEDS to the next event.


Also inform that the operator sent to the CRD accumulators, reports that there are several accumulators with pressures less than 940 psig.
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       5                       Page 11 of 28 Event
ATC  Enters 34AB-C11-001-2, Loss of CRD, or may use CRD Pump Quick Restart Placard located on 2H11
-P603  Places 2C11
-R600, CRD Flow Control, in manual and decreases the output to zero.
Starts the A CRD pump.
Returns the flow controller to auto and output to the pre-trip position.
IF the applicant does NOT start the A CRD pump and the following conditions exist:
Two or more withdrawn control rod scram accumulators inoperable AND  Charging water header pressure <940 PSIG THEN: within 20 minutes restore charging water header pressure
> 940 PSIG or inserts a scram.        SRO  As time allows, may address Tech Specs 3.1.5 By the time the SRO addresses TS 3.1.5; two or more accumulators will have a trouble alarm lit. Once it has been determined that 2 or more accumulators are inoperable, the SRO begins a 20 minute RAS per TS 3.1.5.B to insert a scram and declares the rods slow or inoperable in one hour. Terminates RAS once charging water pressure is restored above 940 psig.
Simulator Operator , After 2F 4160V Emergency bus is energized from 2D SAT AND CRD has been returned to service AND at the direction of the Chief Examiner , PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
5 Page 11 of 28 Event


== Description:==
== Description:==
2B RFPT Cooling water controller failure. TC repair & return to Automatic.
2B RFPT Cooling water controller failure. TC repair & return to Automatic.
Time Position Applicant's Actions or Behavior 8 Min  At the Chief Examiner's direction, Simulator Operator, INSTRUCT the ATC operator by phone to stay on the line until told to hang up , THEN ENTER:
Time     Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator, INSTRUCT the ATC 8 Min              operator by phone to stay on the line until told to hang up, THEN ENTER:
(RB-5) mfN21_88B, Feedwater Pump Lube Oil Cooling System Failure
(RB-5) mfN21_88B, Feedwater Pump Lube Oil Cooling System Failure.
. ALL The following alarms will annunciate:
The following alarms will annunciate:
RFPT 2B BRG OIL TEMP HIGH, (650
* RFPT 2B BRG OIL TEMP HIGH, (650-315)
-315) RFPT 2B BRG TEMP HIGH, (650
ALL
-333) RFP/COND BRG METAL TEMP HIGH, (650-112), (approximately 1 minute later if 2B RFPT PSW TCV is NOT opened in a timely manner)
* RFPT 2B BRG TEMP HIGH, (650-333)
* RFP/COND BRG METAL TEMP HIGH, (650-112), (approximately 1 minute later if 2B RFPT PSW TCV is NOT opened in a timely manner)
NOTE: The BOP may immediately place the controller in manual IAW 31GO-OPS-021-0, Manipulation and Control of Equipment OR NMP-OS-007-001, Conduct of Operations Standards and Expectations, responding to a failed controller.
NOTE: The BOP may immediately place the controller in manual IAW 31GO-OPS-021-0, Manipulation and Control of Equipment OR NMP-OS-007-001, Conduct of Operations Standards and Expectations, responding to a failed controller.
BOP  Addresses the high temp annunciator, pulling the ARP and confirms temperatures:
* Addresses the high temp annunciator, pulling the ARP and confirms temperatures:
At panel 2H11
* At panel 2H11-P655, checks all temperature indicators on 2N32-R616 to BOP determine actual oil temperatures.
-P655, checks all temperature indicators on 2N32
* Confirms that RFPT 2B Oil Temp controller, 2P41-R606, on panel 2H11-P650 is adjusted for 110 to 130&deg;F.
-R616 to determine actual oil temperatures.
* Recognizes the automatic function of the controller has failed, closing the cooling water valve.
Confirms that RFPT 2B Oil Temp controller, 2P41
BOP
-R606, on panel 2H11
* Places the controller in manual, depresses the open/increase pushbutton, opening the valve. Oil temperatures begin decreasing and the alarm extinguishes.
-P650 is adjusted for 110 to 130&deg;F.
BOP  Recognizes the automatic function of the controller has failed, closing the cooling water valve.
Places the controller in manual, depresses the open/increase pushbutton, opening the valve. Oil temperatures begin decreasing and the alarm extinguishes.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       5                       Page 12 of 28 Event
9-02 Event No.:
5 Page 12 of 28 Event


== Description:==
== Description:==
2B RFPT Cooling water controller failure. TC repair & return to Automatic.
Time    Position  Applicant's Actions or Behavior Notifies maintenance of the 2P41-R606, RFPT temperature controller, SRO problem.
DELETE mfN21_88B.
Simulator Operator, after 5 minutes of being dispatched, uses time compression and reports the automatic function of the temperature controller has been repaired and may be returned to service. As Shift Manager, grant permission to return controller to automatic mode.
SRO      Directs the BOP to return 2P41-R606 to automatic operation.
* Nulls controller and then depresses the automatic pushbutton on controller 2P41-R606.
BOP
* Verifies the controller responds correctly in automatic.
* Notifies the SRO the Lube Oil Temperature Controller has been returned to automatic.
Simulator Operator, at the Chief Examiners request, proceeds to the next event.


2B RFPT Cooling water controller failure. TC repair & return to Automatic.
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       6                       Page 13 of 28 Event
Time Position Applicant's Actions or Behavior SRO Notifies maintenance of the 2P41
-R606, RFPT temperature controller, problem.            DELETE mfN21_88B. Simulator Operator , after 5 minutes of being dispatched, uses time compression and reports the automatic function of the temperature controller has been repaired and may be returned to service.
As Shift Manager, grant permission to return controller to automatic mode.
SRO Directs the BOP to return 2P41
-R606 to automatic operation.
BOP  Nulls controller and then depresses the automatic pushbutton on controller 2P41-R606. Verifies the controller responds correctly in automatic.
Notifies the SRO the Lube Oil Temperature Controller has been returned to automatic.
Simulator Operator, at the Chief Examiner's request, proceeds to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
6 Page 13 of 28 Event


== Description:==
== Description:==
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Pump is secured and isolated.
Time    Position  Applicant's Actions or Behavior Simulator Operator, with Chief Examiners Permission:
12 Min
* Call control room BOP operator and tell them to stay on the phone until directed to hang up.
* ACTIVATE: (RB-6) to start Recirc Pump 2A seal leakage, mfB31_39A.
* Receives Annunciator, PUMP A SEAL STAGING FLOW HIGH/LOW, (602-122)
* Observes and compares 2B31-R603A, Seal A No. 1 pressure indicator, AND 2B31-R602A, Seal A No. 2 pressure indicator, to determine the Inner
(#1) seal has failed (No. 1 pressure normal with No. 2 pressure > normal).
* Notifies SRO that the Inner (#1) Seal on Recirc A has failed ATC
* Directs a System Operator to confirm seal water flow to Pump A is between 1.6 to 2.2 gpm locally (this indication NOT available in the Control Room).
* Assigns an extra operator perform 34SV-SUV-019-2, Surveillance Checks, to determine the magnitude of leakage.
* May monitor Drywell pressure.
Simulator Operator, After the ATC operator has started executing steps in the Pump A Seal Staging Flow High/Low ARP, THEN Instruct the BOP operator to hang up the phone.


Recirc Pump "A" seal leakage causes DW leakage
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       6                       Page 14 of 28 Event
& pressure increase. Pump is secured and isolated
. Time Position Applicant's Actions or Behavior 12 Min  Simulator Operator , with Chief Examiners Permission:
Call control room BOP operator and tell them to stay on the phone until directed to hang up.
ACTIVATE: (RB-6) to start Recirc Pump 2A seal leakage, mfB31_39A.
ATC  Receives Annunciator
, PUMP A SEAL STAGING FLOW HIGH/LOW , (602-122)  Observes and compares 2B31
-R603A, Seal A No. 1 pressure indicator, AND 2B31-R602A, Seal A No. 2 pressure indicator, to determine the Inner (#1) seal has failed (No. 1 pressure normal with No. 2 pressure > normal).
Notifies S RO that the Inner (#1) Seal on Recirc A has failed Directs a System Operator to confirm seal water flow to Pump A is between 1.6 to 2.2 gpm locally (this indication NOT available in the Control Room
). Assigns an extra operator perform 34SV
-SUV-019-2, Surveillance Checks, to determine the magnitude of leakage.
May monitor Drywell pressure
.            Simulator Operator
,  After the ATC operator has started executing steps in the "Pump A Seal Staging Flow High/Low" ARP, THEN Instruct the BOP operator to hang up the phone.
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
6 Page 14 of 28 Event


== Description:==
== Description:==
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Pump is secured and isolated.
Time    Position  Applicant's Actions or Behavior Simulator Operator; After 3 minutes, NOTIFY the Chief Examiner AND then press (RB-2) to ACTIVATE: mfB31_45A (10/20), Recirc A Outer Seal Failure
(**IMPORTANT**)
* Ensure the ATC responds to the OUTER SEAL A LEAK DETECTION FLOW HIGH, (602-116) and performs the next set of actions (Trip and isolate the 2A Recirc Pump).
* Ensure the BOP operator is the person assigned to vent the Drywell.
* Receives Annunciators:
* OUTER SEAL A LEAK DETECTION FLOW HIGH, (602-116)
* DRYWELL/TORUS RCDR R627 TEMP HIGH, (650-204)
All
* PANEL 2H11-P654 SYSTEM TROUBLE, (650-214)
* PANEL 2H11-P657 SYSTEM TROUBLE, (650-224)
* DRYWELL FLOOR DRAINS SUMP LEAK HIGH-HIGH, (602-408)
* Observes and compares 2B31-R603A, Seal A No. 1 pressure indicator AND 2B31-R602A, Seal A No. 2 pressure indicator, to determine the outer seal has now failed (No. 1 and No. 2 seal pressure decreases).
* Notifies SRO that the Outer (#2) Seal on 2A Recirc has also failed.
* Has an extra operator perform 34SV-SUV-019-2, Surveillance Checks, to determine magnitude of leak.
ATC
* Monitors 2D11-R630, Fission Products Monitor recorder, to determine IF primary system coolant is leaking from seals on 2H11-P604.
* Monitors Drywell pressure.
* PANEL 2H11-P657 SYSTEM TROUBLE, (650-224)
* MULTIPOINT TEMPERATURE RCDR 2T47-R626 TEMPERATURE HIGH (657-025).


Recirc Pump "A" seal leakage causes DW leakage
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:         6                       Page 15 of 28 Event
& pressure increase. Pump is secured and isolated
. Time Position Applicant's Actions or Behavior Simulator Operator
;  After 3 minutes, NOTIFY the Chief Examiner AND then press (RB-2) to ACTIVATE: mfB31_45A (1 0/20), Recirc A Outer Seal Failure
(**IMPORTANT**)
Ensure the ATC responds to the OUTER SEAL A LEAK DETECTION FLOW HIGH, (602
-116) and performs the next set of actions (Trip and isolate the "2A" Recirc Pump).
Ensure the BOP operator is the person assigned to vent the Drywell.
All  Receives Annunciators:
OUTER SEAL A LEAK DETECTION FLOW HIGH, (602
-116)  DRYWELL/TORUS RCDR R627 TEMP HIGH, (650
-204)  PANEL 2H 11-P654 SYSTEM TROUBLE, (6 50-214)  PANEL 2H11
-P657 SYSTEM TROUBLE
, (650-224)  DRYWELL FLOOR DRAINS SUMP LEAK HIGH
-HIGH, (602
-408)          ATC  Observes and compares 2B31
-R603A, Seal A No. 1 pressure indicator AND 2B31-R602A, Seal A No. 2 pressure indicator, to determine the oute r seal has now failed (No. 1 and No. 2 seal pressure decreases).
Notifies SRO that the Outer (#2) Seal on "2A" Recirc has also failed
. Has an extra operator perform 34SV
-SUV-019-2, Surveillance Checks, to determine magnitude of leak.
Monitors 2D11
-R630, Fission Products Monitor recorder, to determine IF primary system coolant is leaking from seals on 2H11-P604. Monitors Drywell pressure
. PANEL 2H11
-P 657 SYSTEM TROUBLE, (650
-224)  MULTIPOINT TEMPERATURE RCDR 2 T 47-R626 TEMPERATURE HIGH (657-025).
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
6 Page 15 of 28 Event


== Description:==
== Description:==
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Pump is secured and isolated.
Time    Position  Applicant's Actions or Behavior
* Receives the following alarms
* PRIMARY CONTAINMENT PRESS HIGH, (603-115)
All
* DRYWELL FLOOR DRAINS SUMP LEAK HIGH, (602-408)
* Directs Operator to Check DW Leakage SRO
* Directs the BOP to vent the DW with SBGT, when DW pressure approaches 0.65 psig.
NOTE:      If the crew expeditiously isolates the 2A Recirc pump the following actions for venting the Drywell may not be required.
If necessary, the operator may place SBGT in service by using the Placard that's available or using the appropriate section of the procedure. These steps assume the Placard is used. The 2A or 2B SBGT Train may be used. The following steps are written assuming "2A" Train is used. If "2B" Train is used, substitute "2B" for "2A" for valves and the alarm numbers in parenthesis.
BOP
* Enters 34SO-T46-001-2, Standby Gas Treatment System procedure or uses placard at the 2H11-P657 (P654) panel to start SBGT 2A (2B).
* Opens 2T46-F001A (1B) or 2T46-F003A (3B)
* Places 2A (2B) SBGT Fan control switch to RUN
* Alarm SBGT 2A (2B) SWITCH NOT IN AUTO, 657-091 (654-076),
will be received
* Confirms 2T46-F002A (2B) OPENS
* Confirms SBGT 2A (2B) Heater red light illuminates
* Confirms SBGT 2A (2B) flow on recorder 2T41-R618 Point 5 (2U41-R600 Point 3)


Recirc Pump "A" seal leakage causes DW leakage
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       6                       Page 16 of 28 Event
& pressure increase. Pump is secured and isolated
. Time Position Applicant's Actions or Behavior All  Receives the following alarms PRIMARY CONTAINMENT PRESS HIGH, (603-115)  DRYWELL FLOOR DRAINS SUMP LEAK HIGH, (602
-408)  SRO  Directs Operator to Check DW Leakage Directs the BOP to vent the DW with SBGT, when DW pressure approaches 0.65 psig.
NOTE: If the crew expeditiously isolates the 2A Recirc pump the following actions for venting the Drywell may not be required. 
 
If necessary, the operator may place SBGT in service by using the Placard that's available or using the appropriate section of the procedure. These steps assume the Placard is used. The 2A or 2B SBGT Train may be used. The following steps are written assuming "2A" Train is used. If "2B" Train is used, substitute "2B" for "2A" for valves and the alarm numbers in parenthesis. BOP  Enters 34SO
-T46-001-2, "Standby Gas Treatment System" procedure or uses placard at the 2H11
-P657 (P654) panel to start SBGT 2A (2B).
Opens 2T46
-F001A (1B) or 2T46
-F003A (3B)
Places 2A (2B) SBGT Fan control switch to "RUN" Alarm SBGT 2A (2B) SWITCH NOT IN AUTO, 657
-091 (654-076), will be received Confirms 2T46
-F002A (2B) OPENS Confirms SBGT 2A (2B) Heater red light illuminates Confirms SBGT 2A (2B) flow on recorder 2T41-R618 Point 5 (2U41
-R600 Point 3)
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
6 Page 16 of 28 Event


== Description:==
== Description:==
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Pump is secured and isolated.
Time    Position  Applicant's Actions or Behavior NOTE: The operator may place DW Venting in service by using the Placard that's available or using the appropriate section of the procedure. These steps assume the Placard is used. The 2A or 2B CAD Loop valves will be used first.
BOP
* Opens 2T48-F334A and/or 2T48-F334B
* The following alarms will be received:
* DRYWELL VENT EXHAUST BYPASS VALVES OPEN, (657-008)
* DRWL/TORUS N 2 M/U 2 INCH ISOL VALVES OPEN, (657-042)
* DRYWELL VENT EXHAUST BYPASS VALVES OPEN, (654-002)
* DRWL/TORUS N 2 M/U 2 INCH ISOL VALVES OPEN, (654-035)
* Opens 2T48-F335A and/or 2T48-F335B
* Opens 2T48-F336A and/or 2T48-F336B using 2T48-R615A and/or R615B, Drywell Flow Controller for F336A and/or F336B
* Monitors DW pressure
* Confirms Drywell and Torus O 2 concentration is <4%, on 2P33-R603,Pri Cnmt Oxygen Recorder (P602) OR by lab sample


Recirc Pump "A" seal leakage causes DW leakage
Appendix D                     Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.:       6                       Page 17 of 28 Event
& pressure increase. Pump is secured and isolated
. Time Position Applicant's Actions or Behavior NOTE: The operator may place DW Venting in service by using the Placard that's available or using the appropriate section of the procedure. These steps assume the Placard is used. The 2A or 2B CAD Loop valves will be used first.
BOP  Opens 2T48
-F334A and/or 2T48
-F334B  The following alarms will be received:
DRYWELL VENT EXHAUST BYPASS VALVES OPEN, (657
-008)  DRWL/TORUS N 2 M/U 2 INCH ISOL VALVES OPEN, (657
-042)  DRYWELL VENT EXHAUST BYPASS VALVES OPEN, (654
-002)  DRWL/TORUS N 2 M/U 2 INCH ISOL VALVES OPEN, (654
-035)  Opens 2T48
-F335A and/or 2T48
-F335B  Opens 2T48
-F336A and/or 2T48
-F336B using 2T48
-R615A and/or R615B, Drywell Flow Controller for F336A and/or F336B Monitors DW pressure Confirms Drywell and Torus O 2 concentration is <4%, on 2P33-R603,Pri Cnmt Oxygen Recorder (P602)
OR by lab sample
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
6 Page 17 of 28 Event


== Description:==
== Description:==
 
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Recirc Pump "A" seal leakage causes DW leakage
Pump is secured and isolated.
& pressure increase. Pump is secured and isolated
Time     Position Applicant's Actions or Behavior Simulator Operator; As the operator checking DW leakage, report:
. Time Position Applicant's Actions or Behavior Simulator Operator; As the operator checking DW leakage, report:
* DW Equipment drain leakage is stable at 1.7 gpm
DW Equipment drain leakage is stable at 1.7 gpm Floor drain leakage has increased from 0.8 gpm to 12.1 gpm. SRO  Directs operator to SHUTDOWN and isolate Recirc pump A Enters Tech Specs:
* Floor drain leakage has increased from 0.8 gpm to 12.1 gpm.
3.4 Reactor Coolant System 3.4.1 Recirculation Loops Operating Condition: 3.4.1.A, Requirements of the LCO not met.
* Directs operator to SHUTDOWN and isolate Recirc pump A
* Enters Tech Specs:
* 3.4 Reactor Coolant System
* 3.4.1 Recirculation Loops Operating
* Condition: 3.4.1.A, Requirements of the LCO not met.
(i.e. single loop operations)
(i.e. single loop operations)
Required Action: Satisfy requirements of the LCO.
Required Action: Satisfy requirements of the LCO.
Completion time: 24 hrs.
Completion time: 24 hrs.
Condition: 3.4.4.A, Unidentified leakage not within limit OR total leakage not within limit.
SRO
Required Action: Reduce leakage to within limits.  
* Condition: 3.4.4.A, Unidentified leakage not within limit OR total leakage not within limit.
 
Required Action: Reduce leakage to within limits.
Completion time:
Completion time: 4 hours.
4 hours.
* Condition 3.4.4.B, Unidentified leakage increase not within limit.
Condition 3.4.4.B, Unidentified leakage increase not within limit.
Required Action: Reduce leakage increase to within limits.
Required Action: Reduce leakage increase to within limits.
Completion time:
Completion time: 4 hours.
4 hours.
* Notifies STA or Reactor Engineering that new limits apply for APLHGR, MCPR, LHGR, and APRMs Simulated Thermal power - New Setpoints are required within 24 hours.
Notifies STA or Reactor Engineering that new limits apply for APLHGR, MCPR, LHGR, and APRMs Simulated Thermal power  
- New Setpoints are required within 24 hours.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.:       6                       Page 18 of 28 Event
9-02 Event No.:
6 Page 18 of 28 Event


== Description:==
== Description:==
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Pump is secured and isolated.
Time    Position  Applicant's Actions or Behavior
* Per (602-116) and 34SO-B31-001-2, Recirc System, Performs one of the following to secure the Reactor Recirc Pump:
* Either (actions for Immediate Shutdown)
* Places the ASD A control switch in Pull to Lock (P602)
* Depresses the ASD A Shutdown pushbutton (P602)
* OR (Actions for Shutdown in a Timely Manner)
* Depresses the ASD A Shutdown pushbutton (P602)
* Confirms ASD A speed ramps to ~370 RPM (2B31-R660) or 22%
(2B31-R661)
* Confirms Recirc Pump A goes to 0 RPM (2B31-R660) or 22%
ATC (2B31-R661) and drive coasts to 0 gpm (2B31-R614 or R617)
* Confirms ASD A Start pushbutton illuminates
* Places ASD A control switch 2B31-S002A to Pull-To-Lock (P602)
* Closes 2B31-F031A, Reactor Recirc A Pump Disch Vlv
* Closes 2B31-F023A, Reactor Recirc A Pump Suction Vlv
* Dispatches SO to close Seal Injection To Pump A Header Isolation Valve, 2B31-F008A.
* Enters 34AB-B31-001-2 Reactor Recirculation Pump(s) TRIP, Recirc Loops Flow mismatch, Or ASD Cell Bypass.
* Notifies Plant Management and Load Dispatcher
* Receives and Acknowledges the following Annunciators:
* RECIRC LOOP A OUT OF SERVICE, (602-127)
* ASD A TRIP WARNING, (602-101)
* ASD A TROUBLE, (602-108)
ATC
* ASD A FATAL FAULT, (602-102)
* RBM DOWNSCALE, (603-211)
* ROD OUT BLOCK, (603-238)
* HEATER TROUBLE ALARM, (650-135) (may come in and clear)


Recirc Pump "A" seal leakage causes DW leakage
Appendix D                     Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       6                     Page 19 of 28 Event
& pressure increase. Pump is secured and isolated
. Time Position Applicant's Actions or Behavior ATC  Per (602-116) and 34SO-B31-001-2, Recirc System,  Performs one of the following to secure the Reactor Recirc Pump:
Either (actions for Immediate Shutdown)
Place s the ASD "A" control switch in Pull to Lock (P602)  Depress es the ASD "A" Shutdown pushbutton (P602)
OR (Actions for Shutdown in a Timely Manner)
Depress es the ASD "A" Shutdown pushbutton (P602)
Confirm s ASD A speed ramps to ~370 RPM (2B31
-R660) or 22% (2B31-R661)  Confirm s Recirc Pump A goes to 0 RPM (2B31-R660) or 22% (2B31-R661) and drive coasts to 0 gpm (2B31
-R614 or R617)
Confirm s ASD A Start pushbutton illuminates Place s ASD "A" control switch 2B31
-S002A to Pull
-To-Lock (P602)  Closes 2B31
-F031A, Reactor Recirc A Pump Disch Vlv Closes 2B31
-F023A, Reactor Recirc A Pump Suction Vlv Dispatches SO to close Seal Injection To Pump A Header Isolation Valve, 2B31
-F008A. Enters 34AB
-B31-001-2 "Reactor Recirculation Pump(s) TRIP, Recirc Loops Flow mismatch, Or ASD Cell Bypass."
Notifies Plant Management and Load Dispatcher ATC  Receives and Acknowledges the following Annunciators:
RECIRC LOOP A OUT OF SERVICE
, (602-127)  ASD "A" TRIP WARNING, (602
-101)  ASD "A" TROUBLE, (602
-108)  ASD "A" FATAL FAULT, (602
-102)  RBM DOWNSCALE, (603-211)  ROD OUT BLOCK
, (603-238)  HEATER TROUBLE ALARM
, (650-135) (may come in and clear)
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
6 Page 19 of 28 Event


== Description:==
== Description:==
Recirc Pump A seal leakage causes DW leakage & pressure increase.
Pump is secured and isolated.
Time    Position  Applicant's Actions or Behavior Simulator Operator; AFTER the suction and discharge valves are closed for the 2A Recirc pump, an you are requested to close 2B31-F008, THEN:
* MODIFY mfB31_45A (Final: 100 Ramp: 1000),Recirc A Outer Seal Failure."
AND THEN press (RB-11) to ACTIVATE:
* rfB31_29, Recirc mini purge B31-F016A closure (simulates B31-F008A being closed)
* mf60213160, Outer Seal A Leak Detection Flow High - Annunciator Off (602-116)
Simulator Operator; If another DW leakage check is requested, report:
* Drywell floor drain leakage has decreased to 1.8 gpm.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


Recirc Pump "A" seal leakage causes DW leakage
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       7                       Page 20 of 28 Event
& pressure increase. Pump is secured and isolated
. Time Position Applicant's Actions or Behavior Simulator Operator; AFTER the suction and discharge valves are closed for the "2A" Recirc pump, an you are requested to close 2B31
-F008, THEN:  MODIFY mfB31_45A (Final: 100 Ramp: 1000),"Recirc A Outer Seal Failure."  AND THEN press (RB-1 1) to ACTIVATE:
rfB31_29, Recirc mini purge B31
-F016A closure (simulates B31
-F008A being closed) mf60213160, "Outer Seal A Leak Detection Flow High
- Annunciator Off (602-116)  Simulator Operator;  If another DW leakage check is requested, report:
Drywell floor drain leakage has decreased to 1.8 gpm.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
7 Page 20 of 28 Event


== Description:==
== Description:==
Leak in Drywell causes High Drywell pressure scram.
Leak in Drywell causes High Drywell pressure scram.
Time Position Applicant's Actions or Behavior Simulator Operator, at the direction of the Chief Examiner's, ACTIVATES:
Time     Position Applicant's Actions or Behavior Simulator Operator, at the direction of the Chief Examiners, ACTIVATES:
(RB-7), mfG31_242 RWCU Non
(RB-7), mfG31_242 RWCU Non-Isol Leak in Drywell (final 1.0, ramp 1000).
-Isol Leak in Drywell (final 1.0, ramp 1000).
Recognizes increasing Containment Pressure from the following alarms:
ALL Recognizes increasing Containment Pressure from the following alarms:
* PRIMARY CNMT HIGH PRESSURE TRIP, (603-106),
PRIMARY CNMT HIGH PRESSURE TRIP, (603
ALL
-106), PRIMARY CNMT PRESSURE HIGH, (603
* PRIMARY CNMT PRESSURE HIGH, (603-115),
-115), DRYWELL PRESSURE HIGH, (602
* DRYWELL PRESSURE HIGH, (602-210).
-210).         NOTE: The SRO may direct the BOP to vent the Drywell, but there will NOT be time to complete the task before the LOCA signal is received. SRO  With Drywell pressure increasing and alarms PRIMARY CNMT PRESSURE HIGH, (603
NOTE:     The SRO may direct the BOP to vent the Drywell, but there will NOT be time to complete the task before the LOCA signal is received.
-115) and DRYWELL PRESSURE HIGH, (602
* With Drywell pressure increasing and alarms PRIMARY CNMT PRESSURE HIGH, (603-115) and DRYWELL PRESSURE HIGH, (602-210), alarms being received, directs the ATC enter 34AB-C71-001-2, Scram Procedure, and Scram the reactor.
-210), alarms being received, directs the ATC enter 34AB
SRO
-C71-001-2, Scram Procedure, and Scram the reactor.
* Assigns the ATC to perform RC-1,
Assigns the ATC to perform RC
* Assigns the BOP operator to perform RC-2 and RC-3,
-1 , Assigns the BOP operator to perform RC
* Enters RC & PC EOP flow charts,
-2 and RC-3 , Enters RC & PC EOP flow charts
* Assigns a RWL band between 3 and 50.
Assigns a RWL band between 3" and 50"
Simulator Operator, WHEN the reactor is scrammed, ENSURES ET-EGC71-12 MODIFIES mfG31_242 Final to 1.5 with a ramp of 1000 AFTER 180 seconds.
.            Simulator Operator, WHEN the reactor is scrammed, ENSURES ET-EGC71-12 MODIFIES mfG31_242 Final to 1.5 with a ramp of 1000 AFTER 180 seconds. ATC  Performs RC
* Performs RC-1 consisting of:
-1 consisting of:
* Inserts a manual scram.
Inserts a manual scram.
* Places the mode switch to SHUTDOWN.
Places the mode switch to SHUTDOWN. Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
* Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
Notifies SRO of rod position check.
* Notifies SRO of rod position check.
Places SDV isolation valve switch to "isolate" & confirms close
ATC
: d. If NOT tripped, places the Recirc pumps at minimum speed.
* Places SDV isolation valve switch to "isolate" & confirms closed.
Inserts SRMs and IRMs.
* If NOT tripped, places the Recirc pumps at minimum speed.
Shifts recorders to read IRMS, when required.
* Inserts SRMs and IRMs.
Ranges IRMS to bring reading on scale.
* Shifts recorders to read IRMS, when required.
Notifies the SRO when the above actions are complete.
* Ranges IRMS to bring reading on scale.
* Notifies the SRO when the above actions are complete.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:         7                     Page 21 of 28 Event
9-02 Event No.:
7 Page 21 of 28 Event


== Description:==
== Description:==
Leak in Drywell causes High Drywell pressure scram.
Leak in Drywell causes High Drywell pressure scram.
Time Position Applicant's Actions or Behavior BOP  Performs RC
Time     Position Applicant's Actions or Behavior
-2 actions consisting of:
* Performs RC-2 actions consisting of:
Confirms proper Level Control response:
* Confirms proper Level Control response:
Checks ECCS Injection Systems and secure as necessary.
* Checks ECCS Injection Systems and secure as necessary.
Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value.
BOP
IF set down does NOT auto function, then manually reduces FW Master Controller setpoint to approximately 9 inches.
* Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value.
BOP  Controls HPCI operation for level control by performing one or more of the following:
* IF set down does NOT auto function, then manually reduces FW Master Controller setpoint to approximately 9 inches.
Adjusts 2E41
* Controls HPCI operation for level control by performing one or more of the following:
-R612, HPCI Flow Control, to the desired injection rate Transfers the flow controller to manual and adjust its speed demand output to obtain the desired pump flow Shutdown HPCI by:
* Adjusts 2E41-R612, HPCI Flow Control, to the desired injection rate
Depresses and holds the HPCI Turbine Trip pushbutton When HPCI turbine has stopped, places 2E41
* Transfers the flow controller to manual and adjust its speed demand output to obtain the desired pump flow BOP
-C002-3, HPCI Aux Oil Pump, in Pull
* Shutdown HPCI by:
-To-Lock When HPCI TURBINE BRG OIL PRESS LOW alarm is received, releases the HPCI Turbine Trip push
* Depresses and holds the HPCI Turbine Trip pushbutton
-button.           BOP  When feed flow is less than the capacity o1.5 mlbm/hr), then:
* When HPCI turbine has stopped, places 2E41-C002-3, HPCI Aux Oil Pump, in Pull-To-Lock
Opens 2N21
* When HPCI TURBINE BRG OIL PRESS LOW alarm is received, releases the HPCI Turbine Trip push-button.
-F125. Confirms 2C32
* When feed flow is less than the capacity of the S/U level control valve (
-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
1.5 mlbm/hr), then:
Closes 2N21
* Opens 2N21-F125.
-F110. May attempt to restart the CRD pumps May attempt maximize CRD flow IAW 34SO-C11-005-2 Controls RWL with the HPCI/FW System.
* Confirms 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
Notifies SRO if RWL gets outside assigned band.
BOP
* Closes 2N21-F110.
* May attempt to restart the CRD pumps
* May attempt maximize CRD flow IAW 34SO-C11-005-2
* Controls RWL with the HPCI/FW System.
* Notifies SRO if RWL gets outside assigned band.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       7                       Page 22 of 28 Event
9-02 Event No.:
7 Page 22 of 28 Event


== Description:==
== Description:==
Leak in Drywell causes High Drywell pressure scram.
Leak in Drywell causes High Drywell pressure scram.
Time Position Applicant's Actions or Behavior NOTE to EXAMINER:
Time     Position Applicant's Actions or Behavior NOTE to EXAMINER: SRVs actuate in LLS at 1120 psig and then control pressure between 850 - 990 psig.
SRVs actuate in LLS at 1120 psig and then control pressure between 850  
* Performs RC-3 consisting of:
- 990 psig. BOP  Performs RC
* Monitors RPV pressure.
-3 consisting of:
* If necessary, allows RPV pressure to exceed 1074 psig then cycles any BOP              SRV to initiate LLS.
Monitors RPV pressure.
* If necessary, verifies LLS actuates at 1120 psig
If necessary, allows RPV pressure to exceed 1074 psig then cycles any SRV to initiate LLS.
* Maintains RPV pressure between 1074 and 800 psig.
If necessary, verifies LLS actuates at 1120 psig Maintains RPV pressure between 1074 and 800 psig.
* Notifies SRO of pressure control system operation.
Notifies SRO of pressure control system operation.     NOTE: The SRO will select a reactor pressure band which will lower the driving head of the leak while maintaining EOP limits.
NOTE: The SRO will select a reactor pressure band which will lower the driving head of the leak while maintaining EOP limits.
SRO As time allows, may
As time allows, may; Direct the ATC to decrease reactor pressure to reduce the driving head of SRO          the leak using EHC pressure set, Remove RWCU from service IAW 34AB-T23-002-2, Small Pipe Break in Primary Containment.
; Direct the ATC to decrease reactor pressure to reduce the driving head of the leak using EHC pressure set
Enters Attachment 11 of 34SO-N30-001-2, Main Turbine, or 34GO-OPS-013-2, Normal Plant Shutdown, and at the DEHC panel computer, performs ONE of the following:
, Remove RWCU from service IAW 34AB
: 1. Throttle Pressure Set
-T23-002-2, Small Pipe Break in Primary Containment
* Selects the Control psi- load screen
. ATC Enters Attachment 11 of 34SO-N30-001-2, Main Turbine, or 34GO-OPS-013-2, Normal Plant Shutdown, and at the DEHC panel computer, performs ONE of the following:
* Selects the *Ramp Rate* button ATC
: 1. Throttle Pressure Set Selects the Control     psi- load   screen Selects the *Ramp Rate* button Enters a ramp rate Selects the *Pressure* button Enters desired target pressure
* Enters a ramp rate
: 2. Bypass Valve Jack Positioning Control BPV position by intermittently using the *Raise*   / *Lower* buttons until BYPASS VALVE JACK STATUS changes to   *ACTIVE*   AND desired cooldown rate is established ATC Notifies the SRO that Rx pressure is at the target psig.     Simulator Operator PROCEEDS to the next event at the Chief Examiner's direction.
* Selects the *Pressure* button
* Enters desired target pressure
: 2. Bypass Valve Jack Positioning
* Control BPV position by intermittently using the *Raise* /
                                  *Lower* buttons until BYPASS VALVE JACK STATUS changes to *ACTIVE* AND desired cooldown rate is established ATC     Notifies the SRO that Rx pressure is at the target psig.
Simulator Operator PROCEEDS to the next event at the Chief Examiners direction.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                               Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:         8                       Page 23 of 28 Event
9-02 Event No.:
8 Page 23 of 28 Event


== Description:==
== Description:==
 
1st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.
1 st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.
Time     Position Applicant's Actions or Behavior
Time Position Applicant's Actions or Behavior SRO  Per the PC flowchart, verifies Torus level is <285 inches and directs an operator to place Torus Sprays in service.
* Per the PC flowchart, verifies Torus level is <285 inches and directs an SRO operator to place Torus Sprays in service.
ATC  Sprays the Torus per 34SO
* Sprays the Torus per 34SO-E11-010-2 placard on the 2H11-P601 Panel as follows:
-E11-010-2 placard on the 2H11
* Places Cnmt Spray Vlv Cntl switch in the MANUAL position.
-P601 Panel as follows: Places Cnmt Spray Vlv Cntl switch in the MANUAL position.
ATC
Starts RHR pump(s) in loop A/B, if NOT already running.
* Starts RHR pump(s) in loop A/B, if NOT already running.
Opens 2E11
* Opens 2E11-F028A/B.
-F028A/B. Throttles Open 2E11
* Throttles Open 2E11-F027A/B.
-F027A/B. Notifies SRO that RHR is in Torus Sprays.
* Notifies SRO that RHR is in Torus Sprays.
(One loop of RHR will be placed in Torus Sprays. The flow is only 700 gpm, so it may be difficult to see flow indication from a distance.)
(One loop of RHR will be placed in Torus Sprays. The flow is only 700 gpm, so it may be difficult to see flow indication from a distance.)
SRO  When Torus pressure exceeds 11 psig, verifies that Torus Level is <215 inches, in the safe area of Graph 8 (DWSIL) and Directs an operator to: Place all DW cooling fans to OFF Place both Recirc pumps to PTL OFF
* When Torus pressure exceeds 11 psig, verifies that Torus Level is <215 inches, in the safe area of Graph 8 (DWSIL) and Directs an operator to:
SRO
* Place all DW cooling fans to OFF
* Place both Recirc pumps to PTL OFF


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                             Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:       8                       Page 24 of 28 Event
9-02 Event No.:
8 Page 24 of 28 Event


== Description:==
== Description:==
1st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.
Time    Position  Applicant's Actions or Behavior
* Places both Recirc pumps to the PTL Off on panel 2H11-P602.
* Places the following DW cooling fans control switches in the OFF position.
* 2H11-P654:
* 2T47-B007B
* 2T47-B008B
* 2T47-B009B
* 2T47-B0010B ATC
* 2T47-C001B
* 2T47-C002B
* 2H11-P657:
* 2T47-B007A
* 2T47-B008A
* 2T47-B009A
* 2T47-B0010A
* 2T47-C001A
* 2T47-C002A


1 st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.
Appendix D                       Required Operator Actions                                 Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-02 Event No.:           8                       Page 25 of 28 Event
Time Position Applicant's Actions or Behavior ATC  Places both Recirc pumps to the PTL Off on panel 2H11
-P602. Places the following DW cooling fans control switches in the OFF position. 2H11-P654:  2T47-B007B  2T 47-B008B  2T47-B009B  2T47-B0010B  2T47-C001B  2T47-C002B  2H11-P657:  2T47-B007A  2T47-B008A  2T47-B009A  2T47-B0010A  2T47-C001A  2T47-C002A Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-02 Event No.:
8 Page 25 of 28 Event


== Description:==
== Description:==
 
1st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.
1 st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.
Time     Position Applicant's Actions or Behavior NOTE: If the operator starts with the B Loop of RHR to spray the DW, the 2E11-F016B valve will open AND BOTH RHR pumps in the B Loop will trip, requiring the operator to transition to the A Loop of RHR.
Time Position Applicant's Actions or Behavior NOTE: If the operator starts with the B Loop of RHR to spray the DW, the 2E11-F016B valve will open AND BOTH RHR pumps in the B Loop will trip, requiring the operator to transition to the A Loop of RHR.
If the operator starts with the B Loop of RHR to spray the DW, the 2E11-F016B valve will open AND BOTH RHR pumps in the B Loop will trip, requiring the operator to transition to the A Loop of RHR.
If the operator starts with the B Loop of RHR to spray the DW, the 2E11-F016B valve will open AND BOTH RHR pumps in the B Loop will trip, requiring the operator to transition to the A Loop of RHR.
Simulator Operator, ENSURE Event Triggers EGE11-11 & ET-EGE11-12 trips both RHR pumps in the ASSOCIATED Loop.
Simulator Operator, ENSURE Event Triggers EGE11-11 & ET-EGE11-12 trips both RHR pumps in the ASSOCIATED Loop.
Notifies the SRO that all Drywell cooling fans are off.
* Notifies the SRO that all Drywell cooling fans are off.
Notifies the SRO that both Recirc pumps are off. Sprays the Drywell using 34SO
* Notifies the SRO that both Recirc pumps are off.
-E11-010-2 placard at the 2H11
* Sprays the Drywell using 34SO-E11-010-2 placard at the 2H11-P601 panel.
-P601 panel. Places Cnmt Spray A/B Vlv Cntl switch in the MANUAL position.
* Places Cnmt Spray A/B Vlv Cntl switch in the MANUAL position.
Confirms RHR pump(s) in loop A/B, are running.
* Confirms RHR pump(s) in loop A/B, are running.
Opens 2E11
* Opens 2E11-F021A or B.
-F021A or B
* Opens 2E11-F016A or B (1st VALVE OPEN WILL TRIP BOTH RHR LOOP PUMPS ASSOCIATED WITH THE 1st 2E11-F016 OPENED).
. Opens 2E11
* Informs SRO that the RHR Loop A or B pumps tripped.
-F016A or B (1 st VALVE OPEN WILL TRIP BOTH RHR LOOP PUMPS ASSOCIATED WITH THE 1 st 2E11-F016 OPENED
* Opens 2E11-F021A or B
). Informs SRO that the RHR Loop A or B pumps tripped.
* Throttles Open 2E11-F016A(B) (Critical Task) to >5000 gpm
Opens 2E11
* Confirms Drywell pressure is reducing
-F021A or B Throttles Open 2E11
* Notifies SRO that RHR is in Drywell Sprays
-F016A(B) (Critical Task
* May dispatch SO/Maint to investigate both RHR Loop A (B) pumps tripping, if SRO has not already performed.
) to >5000 gpm Confirms Drywell pressure is reducing Notifies SRO that RHR is in Drywell Sprays May dispatch SO/Maint to investigate both RHR Loop A (B) pumps tripping, if SRO has not already performed.
* As time allows, directs an operator to perform 31EO-EOP-114-2.
SRO  As time allows, directs an operator to perform 31EO
SRO
-EOP-114-2. May dispatch SO/Maint to investigate both RHR Loop A (B) pumps tripping, if ATC has not already performed.
* May dispatch SO/Maint to investigate both RHR Loop A (B) pumps tripping, if ATC has not already performed.
Simulator Operator , After the crew is spraying the Drywell AND with Chief Examiners permission, Terminate the scenario.
Simulator Operator, After the crew is spraying the Drywell AND with Chief Examiners permission, Terminate the scenario.
 
Page 26 of 28 Appendix D                                  Scenario Outline                          Form ES-D-1 NRC FINAL Facility:      E. I Hatch              Scenario No.: 9-02        Op-Test No.:  2015-301 Examiners:                                        Operators:                                            SRO RO BOP Initiating Conditions:      Unit 2 is operating at 75%RTP.
Turnover                    Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82% RTP using the Recirculation System.
Summary:
* Event 1: Normal; The BOP will return Hydrogen Seal Oil to a Normal lineup IAW the system operating procedure.
* Event 2: Reactivity; The ATC will raise Reactor power to ~82% RTP.
* Event 3: Component/TS; 4160 V Emergency Bus 2F will de-energize causing a loss of 2B CRD pump. The SRO addresses Tech Specs for inoperable AC electrical distribution subsystem.
BOP will restore cooling water to the running EDG.
* Event 4: Component/TS; Loss of CRD due to power failure. The ATC will address loss of CRD and start the A CRD pump.
* Event 5: Instrument; Feedwater pump 2B cooling water controller will fail requiring the ATC to maintain cooling water manually. Time Compression repair & return the controller to automatic.
* Event 6: Component/TS; 2A Reactor Recirculation pump seals will sequentially develop a failure that results in reactor coolant leaking into the Drywell (DW). Initially, only the Number 1 seal fails, followed a few minutes later by a Number 2 Seal failure. The ATC operator will trip and isolate the 2A Reactor Recirc pump prior to exceeding the DW pressure LOCA signal.
(Critical Task) The SRO will address TS for coolant leakage and single Recirc loop operation.
* Event 7: Major; The plant experiences a RWCU pipe leak in Drywell causing a High Drywell pressure scram.
* Event 8: Component; The 1st RHR 2E11-F016A/B Containment Spray Valve to be opened will trip the associated Loop RHR pumps requiring the operator to transition to the other loop of RHR to spray the Drywell. (Critical Task)


Page 26 of 28 Appendix D Scenario Outline Form ES-D-1  NRC FINAL Facility: E. I Hatch Scenario No.:
Page 27 of 28 Critical Tasks NRC FINAL Facility:   E. I Hatch           Scenario No.: 9-02       Op-Test No.:     2015-301 Critical Tasks
9-02 Op-Test No.: 2015-301 Examiner s: Operators:
* 2A Reactor Recirculation pump seals will sequentially fail resulting in exceeding the capacity of the CAD loop vents requiring the ATC to trip and isolate the 2A Reactor Recirc pump prior to exceeding the Drywell pressure LOCA signal. (Event 6)
SRO    RO    BOP  Initiating Conditions:
* The 1st RHR 2E11-F016A/B Containment Spray Valve to be opened will trip the associated Loop RHR pumps requiring the operator to transition to the other loop of RHR to spray the Drywell.
Unit 2 is operating at 75%RTP.
(Event 8)
Turnover Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82% RTP using the Recirculation System.
ES 301-4 Attributes    Required    Actual                                Items
Summary: Event 1:  Normal; The BOP will return Hydrogen Seal Oil to a Normal lineup IAW the system operating procedure.
: 1. Total Malfunctions          5-8          6      1. 4160V 2F de-energizes (Event 3)
Event 2:  Reactivity; The ATC will raise Reactor power to ~82% RTP. Event 3: Component/TS; 4160 V Emergency Bus '2F' will de
: 2. Loss of CRD due to power failure (Event 4)
-energize causing a loss of 2B CRD pump. The SRO addresses Tech Specs for inoperable AC electrical distribution subsystem. BOP will restore cooling water to the running EDG. 
: 3. 2B RFPT Clg water controller fails (Event 5)
: 4. 2A Recirc Seal failure (Event 6)
: 5. RWCU pipe leak LOCA (Event 7)
: 6. Loop RHR pumps trip (Event 8)
: 2. Malfunctions After          1-2          1      1. Loop RHR pumps trip (Event 8)
EOP Entry
: 3. Abnormal Events            2-4          3      1. 4160V 2F de-energizes (Event 3)
: 2. Loss of CRD due to power failure (Event 4)
: 3. 2A Recirc Seal failure (Event 6)
: 4. Major Transients            1-2          1      1. RWCU pipe leak LOCA (Event 7)
: 5. EOPs entered,              1-2          2      1. 31EO-EOP-010, RC-Non ATWS (Event 7) requiring substantive                            2. 31EO-EOP-012, PC (Event 7) actions
: 6. EOPs contingencies          0-2          0      1.
requiring substantive actions
: 7. Critical Tasks              2-3          2      1. 2A Recirc Seal failure (Event 6)
: 2. Loop RHR pumps trip (Event 8)


Even t 4: Component/TS
ILT 9 NRC FINAL Scenario 2 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions:      Activities in progress: 34SV-P41-001-1, Plant Service Water Pump Operability.
; Loss of CRD due to power failure. The ATC will address loss of CRD and start the A CRD pump.
UNIT 2 STATUS Plant Conditions:      Unit 2 is operating at 75% RTP.
Protected Train:                                  EOOS:
Division I                          Green                      Orange Division II                          Yellow                      Red Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step Scheduled evolutions:      7.3.3.2.5 of 34SO-N42-001-2.
Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82% RTP using the Recirculation System.
Surveillances due this None shift:
Inop Equipment:            None Active tagouts:            None Rod Configuration:            See RWM


Event 5:  Instrument; Feedwater pump 2B cooling water controller will fail requiring the ATC to maintain cooling water manually. Time Compression repair & return the controller to automatic.
Appendix D                               Scenario Outline                           Form ES-D-1 NRC FINAL Facility:     E. I Hatch             Scenario No.: 9-03        Op-Test No.:   2015-301 Examiners:                                     Operators:                                           SRO RO BOP Initial Conditions. Unit 2 is operating at 59% RTP.
Event 6:  Component/TS; 2A Reactor Recirculation pump seals will sequentially develop a failure that results in reactor coolant leaking into the Drywell (DW). Initially, only the Number 1 seal fails , followed a few minutes later by a Number 2 Seal failure. The ATC operator will trip and isolate the 2A Reactor Recirc pump prior to exceeding the DW pressure LOCA signal
Turnover: RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT 2A in service, starting at step 7.1.11.2.7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System. 2D LLS valve is inop for LLS Function only.
.  (Critical Task
Event       Malf. No.     Event                                       Event No.                      Type*                                     Description Continue startup and place the RFPT 2A in service, starting at step 1  N/A                  N (BOP) 7.1.11.2.7 of 34SO-N21-007-2.
)  The S RO will address TS for coolant leakage and single Recirc loop operation.
2   N/A                 R (ATC)   Raise reactor power with Recirc to 65% power.
Event 7:  Major; The plant experiences a RWCU pipe leak in Drywell causing a High Drywell pressure scram.
mfE41_249 svoE41072 C (ATC) HPCI Steam Line breaks in the Rx bldg.
Event 8:  Component; The 1 st RHR 2E11-F016A/B Containment Spray Valve to be opened will trip the associated Loop RHR pumps requiring the operator to transition to the other loop of RHR to spray the Drywell.
3  svoE41073 TS (SRO) HPCI isolation valves fail to auto close (Critical Task)
(Critical Task
EGE41-3 EGE41-4 4   mf70022416 (ON) C (BOP) Instrument Air System Prefilter dP Hi - swap Prefilters.
)
C (ATC) Recirc Pump 2B High Vibration requiring reducing reactor power 5  mfB31_41B TS (SRO) in an attempt to clear alarm. Alarm remains in until pump is tripped.
Page 27 of 28 Critical Tasks NRC F INAL Facility: E. I Hatch Scenario No.:
mfN43_148A mfN43_158B loN43-S47A3                     Stator Cooling Pump 2B (simulate sheared shaft) 6                        C (BOP) loN43-S47G1                    Standby Stator Cooling pump 2A fails to start (manually started) loN43-S47R2 EGN43-01 mfB21_247A mfB21_247B                     Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual 7                      M (ALL) mfC71_241A                      scram works.
9-02 Op-Test No.: 2015-301  Critical Tasks 2A Reactor Recirculation pump seals will sequentially fail resulting in exceeding the capacity of the CAD loop vents requiring the ATC to trip and isolate the 2A Reactor Recirc pump prior to exceeding the Drywell pressure LOCA signal.  (Event 6)    The 1 st RHR 2E11-F016A/B Containment Spray Valve to be opened will trip the associated Loop RHR pumps requiring the operator to transition to the other loop of RHR to spray the Drywell.  (Event 8)  ES 301-4 Attributes Required Actual Items 1. Total Malfunctions 5-8 6 1. 4160V '2F' de
mfC71_241B 2B SRV fails open, must pull fuses (Critical Task); 2B SRV 8  mfB21_286B          C (ATC)    tailpipe with fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve. (Critical Task)
-energizes  (Event 3) 2. Loss of CRD due to power failure (Event 4) 3. 2B RFPT Clg water controller fails (Event 5) 4. 2A Recirc Seal failure (Event 6) 5. RWCU pipe leak LOCA (Event 7) 6. Loop RHR pumps trip  (Event 8) 2. Malfunctions After EOP Entry 1-2 1 1. Loop RHR pumps trip  (Event 8) 3. Abnormal Events 2-4 3 1. 4160V '2F' de
*       (N)ormal,       (R)eactivity,   (I)nstrument,         (C)omponent,         (M)ajor
-energizes  (Event 3) 2. Loss of CRD due to power failure (Event 4) 3. 2A Recirc Seal failure (Event 6) 4. Major Transients 1-2 1 1. RWCU pipe leak LOCA (Event 7) 5. EOPs entered, requiring substantive actions  1-2 2 1. 31EO-EOP-010, RC-Non ATWS  (Event 7) 2. 31EO-EOP-012, PC  (Event 7) 6. EOPs contingencies requiring substantive actions 0-2 0 1. 7. Critical Tasks 2-3 2 1. 2A Recirc Seal failure (Event 6) 2. Loop RHR pumps trip  (Event 8)
 
ILT 9 NRC FINAL Scenario 2 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Plant Conditions:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:         1                     Page 2 of 26 Event
Unit 1 is operating at 100% power Activities in progress:  34SV-P41-001-1, Plant Service Water Pump Operability.
UNIT 2 STATUS Plant Conditions:
Unit 2 is operating at 75% RTP.
Protected Train:
EOOS:    Division I Division II Green    Yellow  Orange  Red  Scheduled evolutions
:  Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO
-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82% RTP using the Recirculation System. Surveillances due this shift:  None  Inop Equipment:
None  Active tagouts
:  None  Rod Configuration
:  See RWM Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.:
9-0 3 Op-Test No.: 2015-301 Examiners:
Operators:
SRO   RO   BOP Initial Conditions
. Unit 2 is operating at 5 9% RTP. Turnover: RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT '2A' in service, starting at step 7.1.11.2.
7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System.
2D LLS valve is inop for LLS Function only.
Event No. Malf. No. Event Type* Event Description 1 N/A N (BOP) Continue startup and place the RFPT '2A' in service, starting at step 7.1.11.2.7 of 34SO-N21-007-2. 2 N/A R (ATC) Raise reactor power with Recirc to 65% power.
3 mfE 4 1_2 49 svoE41 07 2 svoE41073 EG E4 1-3 EGE41-4 C (ATC) TS (SRO) HPCI Steam Line breaks in the Rx bldg.
HPCI isolation valves fail to auto close (Critical Task
) 4 mf70022416 (ON) C (BOP) Instrument Air System Prefilter dP Hi  
- swap Prefilters.
5 mfB31_41B C (ATC) TS (SRO) Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
6 mfN43_148A mfN43_158B loN43-S47A3 loN43-S47G1 loN43-S47R2  E GN43-01 C (BOP) Stator Cooling Pump '2B' (simulate sheared shaft)
Standby Stator Cooling pump 2A fails to start (manually started) 7 mfB21_247A mfB21_247B mfC71_241A mfC71_241B M (ALL) Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.
8 mfB21_286B C (ATC) 2B SRV fails open, must pull fuses (Critical Task); 2B' SRV tailpipe with fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.
(Critical Task
) * (N)ormal,   (R)eactivity,     (I)nstrument,   (C)omponent, (M)ajor Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
1 Page 2 of 26 Event


== Description:==
== Description:==
Placing the 2A RFPT in service, starting at step 7.1.11.2.9 of 34SO-N21-007-2.
Time      Position  Applicant's Actions or Behavior 15 SRO      Orders Operator to place 2A RFPT in service Mins BOP
* Enters 34SO-N21-007-2 at step 7.1.11.2.7.
* Increases speed with the Speed Setter switch to 2100 rpm (+ 100 rpm)
* Confirms M/A station permissive light illuminates and that the M/A station is tracking actual Speed Setter (RFPT) speed
* Places the TMR Mode switch to M/A
* Confirms the M/A Station green light illuminates
* Slowly changes the M/A station to match input and output while BOP              monitoring RWL, RFPT 2A discharge pressure and RFPT 2A & 2B speed.
Alarm RFP C005A DISCH FLOW LOW, (656-039), will clear when RFPT 2A is placed into service. Alarms HEATER TROUBLE, (650-135), 2H11-P657 SYSTEM TROUBLE, (650-224) and MULTIPOINT TEMP RCDR 2T47-R611 TEMP HIGH, (657-072) may come in and clear. All are expected for this plant condition. If dispatched to RFPT area, SIMULATOR OPERATOR, wait 2 minutes, NOTIFY BOP there are no steam leaks in the RFPT area.
* Places M/A station for RFPT 2A in AUTO
* As required, adjusts RFP 2A Speed Control Bias Setting to maintain BOP              RFPT 2A and 2B speed within 100 RPM
* Confirms RFPT 2A Min Flow valve, 2N21-F117A, closes
* Informs SRO that the 2A RFPT is in service in Automatic control.
SRO
* Informs ATC to increase power with Recirc to 65% power.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


Placing the "2A" RFPT in service, starting at step 7.1.11.2.9 of 34SO-N21-007-2. Time Position Applicant's Actions or Behavior 15 Mins SRO Orders Operator to place 2A "RFPT" in service BOP  Enters 34SO
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301  Scenario No.: 9-03 Event No.:         2                       Page 3 of 26 Event
-N21-007-2 at step 7.1.11.2.7. Increases speed with the Speed Setter switch to 2100 rpm (+ 100 rpm)  Confirms M/A station permissive light illuminates and that the M/A station is tracking actual Speed Setter (RFPT) speed Places the TMR Mode switch to M/A Confirms the M/A Station green light illuminates BOP  Slowly changes the M/A station to match input and output while monitoring RWL, RFPT 2A discharge pressure and RFPT 2A & 2B speed.        Alarm RFP C005A DISCH FLOW LOW, (656
-039), will clear when RFPT 2A is placed into service. Alarm s HEATER TROUBLE, (650
-135), 2H11-P657 SYSTEM TROUBLE, (650
-224) and MULTIPOINT TEMP RCDR 2T47
-R611 TEMP HIGH, (657
-072) may come in and clear. All are expected for this plant condition.
If dispatched to RFPT area, SIMULATOR OPERATOR, wait 2 minutes, NOTIFY BOP there are no steam leaks in the RFPT area.
BOP  Places M/A station for RFPT 2A in AUTO As required, adjusts RFP 2A Speed Control Bias Setting to maintain RFPT 2A and 2B speed within 100 RPM Confirms RFPT 2A Min Flow valve, 2N21
-F117A, closes Informs SRO that the 2A RFPT is in service in Automatic control.
SRO  Informs ATC to increase power with Recirc to 65% power.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-30 1 Scenario No.:
9-0 3 Event No.:
2 Page 3 of 26 Event


== Description:==
== Description:==
Use Recirc to raise reactor power to approximately 65%.
Use Recirc to raise reactor power to approximately 65%.
Time Position Applicant's Actions or Behavior 5 Mins SRO Directs the ATC to increase Rx Power to 65% using Recirc.
Time     Position Applicant's Actions or Behavior 5
NOTE: May get the RBM UPSCALE, (603
SRO     Directs the ATC to increase Rx Power to 65% using Recirc.
-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.  
Mins NOTE:       May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.
 
May also get Alarm HEATER TROUBLE, 650-135 alarm. This is expected at this power level.
May also get Alarm HEATER TROUBLE, 650
IAW 34SO-B31-001-2, the ATC increases Recirc pump speed, NOT to exceed ATC      10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master or Individual controls until reactor power is 65%.
-135 alarm. This is expected at this power level.
Complies with 34SO-B31-001-2 Limitation 5.2.15 which states:
ATC IAW 34SO-B31-001-2, the ATC increases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master or Individual controls until reactor power is 6 5%.       ATC Complies with 34SO-B31-001-2 Limitation 5.2.15 which states:
 
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
 
ATC
< 10% of rated core flow (7.7 E6 lbm/hr) WHEN operating < 70% of rated core flow; AND < 5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at > 70% of rated core flow.
                        < 10% of rated core flow (7.7 E6 lbm/hr) WHEN operating < 70% of rated core flow; AND
ATC Notifies the SRO that reactor power has been increased to 65%.
                        < 5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at > 70% of rated core flow.
ATC     Notifies the SRO that reactor power has been increased to 65%.
Simulator Operator, at the Chief Examiners direction OR after power has been increased by 5%, PROCEEDS to the next event.
Simulator Operator, at the Chief Examiners direction OR after power has been increased by 5%, PROCEEDS to the next event.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       3                       Page 4 of 26 Event
9-03 Event No.:
3 Page 4 of 26 Event


== Description:==
== Description:==
 
HPCI Steam Line breaks in the Rx bldg. with failure to auto isolate the HPCI steam line requiring manual closure of isolation valves Time     Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator operator, ENTER (RB-3) 10 Min mfE41_249, HPCI Steam Line, break 0.75/100.
HPCI Steam Line breaks in the Rx bldg. with failure to auto isolate the HPCI steam line requiring manual closure of isolation valves Time Position Applicant's Actions or Behavior 10 Min  At the Chief Examiner's direction, Simulator operator, ENTER (RB-3) mfE41_249 , HPCI Steam Line, break 0.75/100.
* Receives the following annunciators:
ALL  Receives the following annunciator s: DRYWELL/TORUS RCDR R627 TEMP HIGH, (650
* DRYWELL/TORUS RCDR R627 TEMP HIGH, (650-204)
-204) MULTIPOINT TEMP RCDR 2T41
* MULTIPOINT TEMP RCDR 2T41-R620 TEMP HIGH, (654-004)
-R620 TEMP HIGH, (654
* MULTIPOINT TEMP RCDR 2T41-R626 TEMP HIGH, (657-025)
-004) MULTIPOINT TEMP RCDR 2T41
* Receives the following ~45 seconds later:
-R626 TEMP HIGH, (657
ALL
-025)   Receives the following ~45 seconds later:
* LEAK DET DIFF TEMP HIGH, (601-321)
LEAK DET DIFF TEMP HIGH, (6 01-321) HPCI TURBINE TRIP SOLENOID ENERGIZED, (601
* HPCI TURBINE TRIP SOLENOID ENERGIZED, (601-109)
-109) HPCI ISOLATION TRIP LOGIC A INITIATED, (601
* HPCI ISOLATION TRIP LOGIC A INITIATED, (601-115)
-115) HPCI ISOL TIMER INITIATED, (601
* HPCI ISOL TIMER INITIATED, (601-105)
-105) HPCI ISOLATION TRIP LOGIC B INITIATED, (601
* HPCI ISOLATION TRIP LOGIC B INITIATED, (601-121)
-121) SEC SYSTEM AUTO INITIATION SIGNAL PRESENT, (650
* SEC SYSTEM AUTO INITIATION SIGNAL PRESENT, (650-234)
-234)           ATC Responds to the following annunciators:
Responds to the following annunciators:
HPCI STEAM LINE DIFF PRESS HIGH, (601
* HPCI STEAM LINE DIFF PRESS HIGH, (601-104)
-104) HPCI TURBINE TRIP SOLENOID ENERGIZED, (601
* HPCI TURBINE TRIP SOLENOID ENERGIZED, (601-109)
-109) HPCI ISOLATION TRIP LOGIC A INITIATED, (601
* HPCI ISOLATION TRIP LOGIC A INITIATED, (601-115)
-115) Time:_____________
Time:_____________
Responds to failure of HPCI Auto Isolation:
Responds to failure of HPCI Auto Isolation:
Places 2E41
ATC
-F002 control switch to CLOSE. Places 2E41
* Places 2E41-F002 control switch to CLOSE.
-F003 control switch to CLOSE (Critical Task
* Places 2E41-F003 control switch to CLOSE (Critical Task) is to position 2E41-F002 control switch to close within 5 minutes of receiving 601-115 and/or 601-121 listed above OR may close before alarms are received).
) is to position 2E41
Time:_____________
-F002 control switch to close within 5 minutes of receiving 60 1-115 and/or 60 1-121 listed above OR may close before alarms are received
* Informs SRO of failure of 2E41-F003 to close.
). Time:_____________
Informs SRO of failure of 2E41
-F003 to close
.
Dispatches operator/Maintenance to investigate the leak.
Dispatches operator/Maintenance to investigate the leak.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.:       3                         Page 5 of 26 Event
9-03 Event No.:
3 Page 5 of 26 Event


== Description:==
== Description:==
HPCI Steam Line breaks in the Rx bldg. with failure to auto isolate the HPCI steam line requiring manual closure of isolation valves Time      Position  Applicant's Actions or Behavior
* Orders BOP to evaluate leak detection alarms on 2H11-P601.
* Orders HPCI to be isolated.
SRO
* Orders ATC/BOP to evacuate the Reactor Building.
* May notify Maintenance for assistance in closing HPCI valve if ATC/BOP does NOT.
Reviews TS 3.6.1.3, Primary Containment Isolation Valves, Condition A.1 and A.2 and determines:
* 2E41-F003 INOP
* 2E41-F002 must be closed and deactivated within 4 hours AND
* 2E41-F002/F003 penetration must be verified ISOLATED every 31 days.
* As time allows, contacts the Shift Support Supervisor to draft a Danger SRO            Tagout for 2E41-F002.
Reviews TS 3.5.1, ECCS/RCIC.
* IAW TS 3.5.1 Condition C,
* Declares HPCI inoperable,
* Must verify within one hour that RCIC is operable by administrative means
* Must restore HPCI to operable status within 14 days SIMULATOR OPERATOR; At Chief Examiners direction, PROCEEDS to the next event.


HPCI Steam Line breaks in the Rx bldg. with failure to auto isolate the HPCI steam line requiring manual closure of isolation valves Time Position Applicant's Actions or Behavior SRO  Orders BOP to evaluate leak detection alarms on 2H11
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:         4                       Page 6 of 26 Event
-P601. Orders HPCI to be isolated.
Orders ATC/BOP to evacuate the Reactor Building
. May notify Maintenance for assistance in closing HPCI valve if ATC/BOP does NOT.          SRO Reviews TS 3.6.1.3, Primary Containment Isolation Valves
,  Condition A.1 and A.2 and determines:
2E41-F003 INOP  2E41-F002 must be closed and deactivated within 4 hours AND  2E41-F002/F003 penetration must be verified ISOLATED every 31 days.
As time allows, contacts the Shift Support Supervisor to draft a Danger Tagout for 2E41
-F002. Reviews TS 3.5.1, ECCS/RCIC.
IAW TS 3.5.1 Condition C,  Declares HPCI inoperable,  Must verify within one hour that RCIC is operable by administrative means Must restore HPCI to operable status within 14 days SIMULATOR OPERATOR; At Chief Examiners direction, PROCEEDS to the next event.
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
4 Page 6 of 26 Event


== Description:==
== Description:==
Instrument Air System Prefilter dP Hi - swap Prefilters.
Time      Position  Applicant's Actions or Behavior Simulator Operator at direction of the lead examiner, ACTIVATE: (RB-4) 7 Mins              malfunction mf70022416 - Window 25 INSTRU AIR PREFLTR D103A DIFF PRESS HIGH (ANNUNCIATOR ON)
The following annunciators are received:
All
* PANEL 2H11-P700 SYSTEM TROUBLE, (650-225)
* INSTR AIR PREFLTR D103A DIFF PRESS HIGH, (700-225)
* Acknowledges 2H11-P700 panel alarm on 2H11-P650
* Acknowledges INSTR AIR PREFLTR D103A DIFF PRESS HIGH, (700-225) on 2H11-P700 and notifies the SRO of the alarm BOP
* Dispatches an SO locally to determine Prefilter dP on 2P52-dPIS-N301A, look for air leaks on the filter and to verify that the instrument isolation valve is open.
Simulator Operator: 2 minutes after being dispatched to check Prefilter dP, inform the BOP that 2P52-dpis-N301A indicates 6 psid and that no air leaks exist.
* Notifies Maintenance (if BOP has NOT) to change out the Prefilter SRO          cartridge and initiates a condition report.
* Directs the BOP to swap Prefilters IAW 34AR-700-225-2.


Instrument Air System Prefilter dP Hi
Appendix D                     Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       4                     Page 7 of 26 Event
- swap Prefilters
. Time Position Applicant's Actions or Behavior 7 Mins  Simulator Operator at direction of the lead examiner, ACTIVATE:
(RB-4) malfunction mf700224 16 - Window 25 INSTRU AIR PREFLTR D103A DIFF PRESS HIGH (ANNUNCIATOR ON)
All The following annunciators are received:
PANEL 2H11
-P700 SYSTEM TROUBLE, (650
-225)  INSTR AIR PREFLTR D103A DIFF PRESS HIGH, (700
-225)              BOP  Acknowledges 2H11
-P700 panel alarm on 2H11
-P650    Acknowledges INSTR AIR PREFLTR D103A DIFF PRESS HIGH,  (700-225) on 2H11
-P700 and notifies the SRO of the alarm Dispatches an SO locally to determine Prefilter dP on 2P52-dPIS-N301A, look for air leaks on the filter and to verify that the instrument isolation valve is open.
Simulator Operator: 2 minutes after being dispatched to check Prefilter dP, inform the BOP that 2P52
-dpis-N301 A indicates 6 psid and that no air leaks exist. SRO  Notifies Maintenance (if BOP has NOT) to change out the Prefilter cartridge and initiates a condition report.
Directs the BOP to swap Prefilters IAW 34AR
-700-225-2.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
4 Page 7 of 26 Event


== Description:==
== Description:==
Instrument Air System Prefilter dP Hi - swap Prefilters.
Time      Position  Applicant's Actions or Behavior Simulator Operator, WHEN the BOP swaps Prefilters, ENSURES EVENT TRIGGER EGP52-1 & EGP52-2 ACTIVATES: deleting malfunction mf70022416 - Window 25 INSTRU AIR PREFLTR D103A DIFF PRESS HIGH (ANNUNCIATOR ON) and simulates correct light arrangement.
At 2H11-P700:
* Places control switch to ON for Turb Bldg Inst Air PreFltr/Afterfilter 2P52-D103B/2P52-D102B Inlet Isol, 2P52-F002B/2P52-F011B.
BOP
* Places control switch to OFF for Turb Bldg Inst Air PreFltr/Afterfilter 2P52-D103A/2P52-D102A Inlet Isol, 2P52-F002A/2P52-F011A.
* Notifies the SRO that the Prefilter has been swapped from A to B.
* 700-225 alarm clears.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


Instrument Air System Prefilter dP Hi
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       5                       Page 8 of 26 Event
- swap Prefilters
. Time Position Applicant's Actions or Behavior Simulator Operator, WHEN the BOP swaps Prefilters, ENSURES EVENT TRIGGER EGP52-1 & EGP52-2 ACTIVATES: deleting malfunction mf70022416
- Window 25 INSTRU AIR PREFLTR D103A DIFF PRESS HIGH (ANNUNCIATOR ON) and simulates correct light arrangement.
BOP At 2H11-P7 00:  Places control switch to ON for Turb Bldg Inst Air PreFltr/Afterfilter 2P52-D103B/2P52
-D102B Inlet Isol, 2P52
-F002B/2P52
-F011B. Places control switch to OFF for Turb Bldg Inst Air PreFltr/Afterfilter 2P52-D103A/2P52
-D102A Inlet Isol, 2P52
-F002A/2P52
-F011A. Notifies the SRO that the Prefilter has been swapped from "A" to "B".
700-225 alarm clears.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
5 Page 8 of 26 Event


== Description:==
== Description:==
Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Time      Position  Applicant's Actions or Behavior 18                SIMULATOR OPERATOR; At Chief Examiners direction, press (RB-5) to Min                activate: mfB31_41B, Recirc Pump B High Vibration ALL
* Receives PUMP MOTOR B VIBRATION HIGH, (602-204) alarm ATC
* Enters 602-204
* Depresses the Hi vibration reset pushbutton and determines that the alarm does NOT clear.
* Notifies the SRO that the vibration alarm did NOT clear.
* Notifies the SRO that the ARP requires reducing Recirc flow and attempting to reset the alarm again.
AFTER five minutes has elapsed, if Recirc Pump B is still operating, SIMULATOR OPERATOR; At Chief Examiners direction, press (RB-9) to activate: mfB31_40B, Recirc Pump B Motor High Temp.
* Receives PUMP MOTOR B WINDING COOLING WATER FLOW LOW, (602-218)
* Confirms RBCCW System is in operation as indicated by 2P42-R603, RBCCW Flow to Drwl indicator at 2H11-P650 panel.
ATC
* Confirms winding temperatures are <240&deg;F, on 2B31-R601, Recirc Pump Temp recorder at 2H11-P614.
* IF the winding temperatures cannot be maintained < 240&deg;F, Performs Abnormal SHUT DOWN of the ASD B per 34SO-B31-001-2, subsection 7.2.1.4, Reactor Recirculation System.


Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       5                         Page 9 of 26 Event
Time Position Applicant's Actions or Behavior 18 Min  SIMULATOR OPERATOR; At Chief Examiner's direction, press (RB-5) to activate: mfB31_41B, Recirc Pump B High Vibration ALL  Receives PUMP MOTOR B VIBRATION HIGH , (602-204) alarm            ATC  Enters 602
-2 04    Depresses the Hi vibration reset pushbutton and determines that the alarm does NOT clear. Notifies the S RO that the vibration alarm did NOT clear. Notifies the S RO that the ARP requires reducing Recirc flow and attempting to reset the alarm again.
AFTER five minutes has elapsed, if Recirc Pump B is still operating, SIMULATOR OPERATOR; At Chief Examiner's direction, press (RB-9) to activate: mfB31_4 0B, Recirc Pump B Motor High Temp.
ATC  Receives PUMP MOTOR B WINDING COOLING WATER FLOW LOW, (602-218)  Confirms RBCCW System is in operation as indicated by 2P42
-R603, RBCCW Flow to Drwl indicator at 2H11
-P650 panel.
Confirms winding temperatures are <240&deg;F, on 2B31
-R601,  Recirc Pump Temp recorder at 2H11
-P614. IF the winding temperatures cannot be maintained < 240&deg;F, Performs Abnormal SHUT DOWN of the ASD B per 34SO
-B31-001-2, subsection 7.2.1.4, Reactor Recirculation System. 
      .
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
5 Page 9 of 26 Event


== Description:==
== Description:==
Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Time      Position  Applicant's Actions or Behavior
* Directs the operator to reduce Rx power with Recirc per 34GO-OPS-005 and 34SO-B31-001-2, section 7.1.6, Two Loop Operation From Rated To Minimum Speed, exceeding 10 MWE/minute if necessary.
* Reminds the operator that entry into the Immediate Exit Region of the SRO Power to Flow map is allowed.
* Notifies Plant Management, Load Dispatcher, and Engineering that the power increase has been halted pending investigation of Recirc Pump 2B high vibration condition.
* Enters the following procedures
* 34GO-OPS-005-2, Power Changes
* 34SO-B31-001-2, Recirculation System
* IAW 34SO-B31-001-2, the ATC decreases Recirc pump speed by depressing the Slow, Medium or Fast LOWER pushbuttons on the Master or Individual controls.
* Monitors power decrease by observing APRM and generator output indications.
ATC
* Stops power reduction periodically and depresses the High vibration reset pushbutton.
* The alarm will NOT remain clear until the pump is tripped.
* Continues to decrease BOTH Recirc pump speeds until minimum
* Notifies SRO when BOTH Recirc Pumps are at minimum.
* Notifies the SRO that the vibration alarm DID NOT clear after reducing BOTH Recirc pumps.
* Notifies SRO that the Region of Potential Instabilities/Immediate Exit Region of Power to Flow Map was NOT entered.
Notifies chemistry of 15% power change in 1 hour IAW 34GO-OPS-005-2, BOP Power Changes, Step 5.2.13.


Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       5                       Page 10 of 26 Event
Time Position Applicant's Actions or Behavior SRO  Directs the operator to reduce Rx power with Recirc per 34GO
-OPS-005 and 34SO-B31-001-2, section 7.1.6
, Two Loop Operation From Rated To Minimum Speed, exceeding 10 MWE/minute if necessary.
Reminds the operator that entry into the Immediate Exit Region of the Power to Flow map is allowed.
Notifies Plant Management, Load Dispatcher, and Engineering that the power increase has been halted pending investigation of Recirc Pump 2B high vibration condition.
ATC  Enters the following procedures 34GO-OPS-005-2, Power Changes 34SO-B31-001-2, Recirculation System IAW 34SO-B31-001-2, the ATC decreases Recirc pump speed by depressing the Slow, Medium or Fast LOWER pushbuttons on the Master or Individual controls
. Monitors power decrease by observing APRM and generator output indications.
Stops power reduction periodically and depresses the High vibration reset pushbutton
. The alarm will NOT remain clear until the pump is tripped. Continues to decrease BOTH Recirc pump speeds until minimum Notifies SRO when BOTH Recirc Pumps are at minimum.
Notifies the SRO that the vibration alarm DID NOT clear after reducing BOTH Recirc pumps.
Notifies S RO that the Region of Potential Instabilities/Immediate Exit Region of Power to Flow Map was NOT entered
.            BOP Notifies chemistry of 15% power change in 1 hour IAW 34GO
-OPS-005-2, Power Changes, Step 5.2.13.
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
5 Page 10 of 26 Event


== Description:==
== Description:==
Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Time      Position  Applicant's Actions or Behavior NOTE:      HEATER TROUBLE ALARM, (650-135) may alarm due to plant conditions.
NOTE: 15% power change sample required IAW limitation 5.2.13, 34GO-OPS-005-2.
* Directs the ATC operator to shutdown the B ASD IAW 34SO-B31-001-2 section 7.2.1.4, Abnormal Recirc Pump/ASD B Shutdown.
SRO
* As time allows, directs the BOP operator to secure one Condensate and one Condensate Booster Pump plus one RFPT.
* Places ASD B control switch 2B31-S002B to Pull to Lock OR depresses the ASD B Shutdown pushbutton and places ASD B control switch to Pull to Lock on panel 2H11-P602.
ATC
* Enters 34AB-B31-001-2, Reactor Recirculation Pump(s) Trip, Recirc Loops Flow Mismatch, Or ASD Cell Bypass, for single Recirc pump trip.
* Confirms operating Recirc Pump flow is
                          * <100% rated flow, (45,200 gpm is rated flow) AND
* Core Flow to <38.5 Mlb/hr
________
* Closes 2B31-F031B, Pump Discharge Valve.
TIME
________
* Within 5 minutes, throttles 2B31-F031B, Pump Disch Valve OPEN TIME
* Acknowledges the following annunciators:
* ASD B TRIP WARNING, (602-201)
* ASD B FATAL FAULT, (601-202)
* ASD B TROUBLE, (601-208)
* RECIRC LOOP B OUT OF SERVICE, (601-227)


Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Appendix D                       Required Operator Actions                       Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       5                         Page 11 of 26 Event
Time Position Applicant's Actions or Behavior NOTE: HEATER TROUBLE ALARM, (650
-135) may alarm due to plant conditions.
NOTE: 15% power change sample required IAW limitation 5.2.13,  34GO-OPS-005-2. SRO  Directs the ATC operator to shutdown the B ASD IAW 34SO
-B31-001-2 section 7.2.1.4, Abnormal Recirc Pump/ASD B Shutdown.
As time allows, directs the BOP operator to secure one Condensate and one Condensate Booster Pump plus one RFPT.
ATC  Place s ASD B control switch 2B31
-S002B to Pull to Lock OR  depresses the ASD B Shutdown pushbutton and places ASD B control switch to Pull to Lock on panel 2H11-P602. Enters 34AB
-B31-001-2, Reactor Recirculation Pump(s) Trip, Recirc Loops Flow Mismatch, Or ASD Cell Bypass
, for single Recirc pump trip.
Confirms operating Recirc Pump flow is
  <100% rated flow, (45,200 gpm is rated flow) AND Core Flow to <38.5 Mlb/hr  ________ TIME  Closes 2B31
-F031B, Pump Discharge Valve. ________ TIME  Within 5 minutes, throttles 2B31
-F031B, Pump Disch Valve OPEN Acknowledges the following annunciators:
ASD B TRIP WARNING, (602-201)  ASD B FATAL FAULT , (601-202)  ASD B TROUBLE , (601-208)  RECIRC LOOP B OUT OF SERVICE , (601-227)
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
5 Page 11 of 26 Event


== Description:==
== Description:==
 
Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Time     Position Applicant's Actions or Behavior NOTE:     IAW 34AB-B31-001-2, During single loop operation, WHEN the speed of the running pump decreases below approximately 35%
Time Position Applicant's Actions or Behavior NOTE: IAW 34AB-B31-001-2 , During single loop operation, WHEN the speed of the running pump decreases below approximately 35% speed, positive flow through the idle pump loop due to natural circulation overcomes the negative flow due to reverse flow. The total core flow summing circuitry will continue to subtract this positive idle loop flow from the running loop flow AND give a misleading LOW core flow indication. Total core flow can be calculated by adding the JET PUMP LOOP "A" AND the JET PUMP LOOP "B" flows.
speed, positive flow through the idle pump loop due to natural circulation overcomes the negative flow due to reverse flow. The total core flow summing circuitry will continue to subtract this positive idle loop flow from the running loop flow AND give a misleading LOW core flow indication. Total core flow can be calculated by adding the JET PUMP LOOP "A" AND the JET PUMP LOOP "B" flows.
SRO  Has the operator determine if the plant is in the analyzed region of the Power to Flow map.
* Has the operator determine if the plant is in the analyzed region of the SRO Power to Flow map.
ATC  Determines that the plant is NOT in the Immediate Exit Region of the Power to Flow map.
* Determines that the plant is NOT in the Immediate Exit Region of the ATC Power to Flow map.
Simulator Operator, WHEN the crew determines that the plant is NOT in the Immediate Exit Region of the Power to Flow map, with Chief Examiners permission, PROCEEDS to the next event.
Simulator Operator, WHEN the crew determines that the plant is NOT in the Immediate Exit Region of the Power to Flow map, with Chief Examiners permission, PROCEEDS to the next event.
Simulator Operator, IF the crew makes a conservative decision to shut down the Reactor, with Chief Examiners permission, PROCEEDS to the next event.
Simulator Operator, IF the crew makes a conservative decision to shut down the Reactor, with Chief Examiners permission, PROCEEDS to the next event.
SRO  References Tech Spec 3.4.1.A.1 and has 24 hours to meet requirements for Single Loop Operation.
* References Tech Spec 3.4.1.A.1 and has 24 hours to meet requirements for SRO Single Loop Operation.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                       Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:         5                       Page 12 of 26 Event
9-03 Event No.:
5 Page 12 of 26 Event


== Description:==
== Description:==
Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Time      Position  Applicant's Actions or Behavior
* Removes condensate pumps (CP & CBP) from service prior to CBP discharge pressure < 525 psig OR power <70% OR as soon as practical.
* For removal of CBP
* If 2C is to be removed, removes the Hydrogen Injection System from service
* Sends SO to closed selected pumps discharge valve BOP
* Prior to discharge valve being full closed, trips pump and places control switch in Auto or PTL
* Has SO complete the procedure
* Removal of CP
* Sends SO to closed selected pumps discharge valve
* Trips pump and places control switch in Auto or PTL
* If pump left in Standby, has SO reopen discharge valve NOTE:      IAW 34GO-OPS-005-2, WHEN Feedwater flow is less than 7 mlbm/HR AND two Reactor Feed Pumps are running, one Reactor Feed Pump MAY be shutdown Enters 34SO-N21-007-2, Condensate And Feedwater System, section 7.2.1, BOP First Reactor Feed Pump Shutdown and Leaving in Standby.
* Confirms Feedwater Flow is less than 7 Mlbm / hr.
* Confirms RFPT 2A AND RFPT 2B are in Automatic control on 2C32-R600, Master Controller.
* Places 2C32-R601A (2C32-R601B), RFP A (B) M/A Station, in Manual, by depressing the 'M' pushbutton until it illuminates, panel 2H11-P603.
* Slowly decrease RFPT 2A (2B) speed with RFP A (B) M/A Station until the other RFP is controlling reactor vessel level.
NOTE:      At this point the operator may stop here with the RFPT NOT injecting and continue with this section as time allows.


Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       5                       Page 13 of 26 Event
Time Position Applicant's Actions or Behavior BOP  Removes condensate pumps (CP & CBP) from service prior to CBP discharge pressure < 525 psig OR power <70% OR as soon as practical.
For removal of CBP If 2C is to be removed, removes the Hydrogen Injection System from service Sends SO to closed selected pumps discharge valve  Prior to discharge valve being full closed, trips pump and places control switch in Auto or PTL Has SO complete the procedure Removal of CP Sends SO to closed selected pumps discharge valve Trips pump and places control switch in Auto or PTL If pump left in Standby, has SO reopen discharge valve NOTE: IAW 34GO-OPS-005-2, WHEN Feedwater flow is less than 7 mlbm/HR AND two Reactor Feed Pumps are running, one Reactor Feed Pump MAY be shutdown BOP Enters 34SO
-N21-007-2, Condensate And Feedwater System, section 7.2.1 , First Reactor Feed Pump Shutdown and Leaving in Standby.
Confirms Feedwater Flow is less than 7 Mlbm / hr.
Confirms RFPT 2A AND RFPT 2B are in Automatic control on 2C32
-R600, Master Controller.
Places 2C32
-R601A (2C32
-R601B), RFP A (B) M/A Station, in Manual, by depressing the 'M' pushbutton until it illuminates, panel 2H11-P603. Slowly decrease RFPT 2A (2B) speed with RFP A (B) M/A Station until the other RFP is controlling reactor vessel level
. NOTE: At this point the operator may stop here with the RFPT NOT injecting and continue with this section as time allows.
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
5 Page 13 of 26 Event


== Description:==
== Description:==
Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Time      Position  Applicant's Actions or Behavior
* When the other RFP has control of water level, slowly decrease RFPT 2A (2B) speed with RFP A (B) M/A Station until no speed decrease is observed AND/OR place the RFPT A (B) TMR switch to SS AND confirm Speed Setter yellow light illuminates.
* Slowly lower RFPT 2A (2B) Speed Setter switch until RFPT speed is at 1000 rpm, at 2H11-P650.
* IF desired, reduce the RFPT 2A (2B) speed to minimum AND allow the RFPT to windmill, provided seal water, steam seals, AND lube oil systems remain in service.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


Recirc Pump '2B' High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       6                       Page 14 of 26 Event
Time Position Applicant's Actions or Behavior When the other RFP has control of water level, slowly decrease RFPT 2A (2B) speed with RFP A (B) M/A Station until no speed decrease is observed AND/OR place the RFPT A (B) TMR switch to SS AND confirm Speed Setter yellow light illuminates.
Slowly lower RFPT 2A (2B) Speed Setter switch until RFPT speed is at 1000 rpm, at 2H11
-P650. IF desired, reduce the RFPT 2A (2B) speed to minimum AND allow the RFPT to "windmill", provided seal water, steam seals, AND lube oil systems remain in service.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
6 Pag e 14 of 26 Event


== Description:==
== Description:==
 
Stator Cooling Pump 2B (simulate sheared shaft)
Stator Cooling Pump '2B' (simulate sheared shaft)
Standby Stator Cooling pump 2A fails to start (manually started)
Standby Stator Cooling pump 2A fails to start (manually started)
Time Position Applicant's Actions or Behavior 8 Min  At the Chief Examiner's direction, Simulator operator , INSTRUCT the ATC operator by phone to stay on the line until told to hang up. THEN ENTER:
Time     Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator operator, INSTRUCT the ATC operator by phone to stay on the line until told to hang up. THEN ENTER:
(RB-6) to ACTIVATE: (mfN43_158B , mfN43_148A , loN43-S47A3 (Off), loN43-S47G1 (Off)
8 Min (RB-6) to ACTIVATE: (mfN43_158B, mfN43_148A, loN43-S47A3 (Off),
& loN43-S47R2 (On)
loN43-S47G1 (Off) & loN43-S47R2 (On).
. BOP  When Stator Water Cooling pump 2B is tripped, responds to the following alarms: GENERATOR INLET FLOW LOW, (651
* When Stator Water Cooling pump 2B is tripped, responds to the following alarms:
-201) GENERATOR INLET PRESS LOW, (651
* GENERATOR INLET FLOW LOW, (651-201)
-202) GENERATOR OUTLET TEMP HIGH, (651
* GENERATOR INLET PRESS LOW, (651-202)
-204) STATOR CLG TANK WATER LEVEL HIGH/LOW, (651
BOP
-205) GENERATOR PROTECTION CIRCUIT ENERGIZED, (651
* GENERATOR OUTLET TEMP HIGH, (651-204)
-206) MAIN GENERATOR TEMPERATURE, (651-161) TURBINE TROUBLE, (650
* STATOR CLG TANK WATER LEVEL HIGH/LOW, (651-205)
-105)           BOP  Acknowledges the alarms and informs the SRO that the Stator Cooling system pressure and flow is low and that the "2A" Stator Cooling pump did NOT auto start.
* GENERATOR PROTECTION CIRCUIT ENERGIZED, (651-206)
(2A Stator Cooling may be started manually prior to recognizing failure to auto start.
* MAIN GENERATOR TEMPERATURE, (651-161)
) (There is NOT an obvious reason for the pressure and flow being low.)
* TURBINE TROUBLE, (650-105)
* Acknowledges the alarms and informs the SRO that the Stator Cooling system pressure and flow is low and that the 2A Stator Cooling pump BOP          did NOT auto start. (2A Stator Cooling may be started manually prior to recognizing failure to auto start.) (There is NOT an obvious reason for the pressure and flow being low.)
The BOP may enter the following ARPs in any order:
The BOP may enter the following ARPs in any order:
BOP  Enters 651
* Enters 651-201, Generator Inlet Flow Low, and performs the following:
-201, Generator Inlet Flow Low, and performs the following: Dispatches SO locally to 2N43
* Dispatches SO locally to 2N43-R303, Flow Indicator at 2N43-P001
-R303, Flow Indicator at 2N43
* Manually starts the 2A Stator Cooling pump BOP              (May NOT pull procedure until after the pump has been started.)
-P001   Manually starts the "2A" Stator Cooling pump (May NOT pull procedure until after the pump has been started.)
* Monitors for increasing system flow by 651-201 clearing.
Monitors for increasing system flow by 651
* Dispatches SO/Maint to investigate the cause of Generator Inlet Flow Low.
-201 clearing.
 
Dispatches SO/Maint to investigate the cause of Generator Inlet Flow Low.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       6                     Page 15 of 26 Event
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
6 Pag e 15 of 26 Event


== Description:==
== Description:==
 
Stator Cooling Pump 2B (simulate sheared shaft)
Stator Cooling Pump '2B' (simulate sheared shaft)
Standby Stator Cooling pump 2A fails to start (manually started)
Standby Stator Cooling pump 2A fails to start (manually started)
Time Position Applicant's Actions or Behavior The BOP may NOT enter the following once the standby pump is started.
Time     Position Applicant's Actions or Behavior The BOP may NOT enter the following once the standby pump is started.
BOP  Enters 651
* Enters 651-202, Generator Inlet Press Low, and performs the following:
-202, Generator Inlet Press Low, and performs the following:
* Dispatches SO locally to 2N43-R301, Pressure Indicator at 2N43-P001
Dispatches SO locally to 2N43
* Manually starts the 2A Stator Cooling pump BOP              (May NOT pull procedure until after the pump has been started.)
-R301, Pressure Indicator at 2N43
* Monitors for increasing system pressure by 651-202 clearing.
-P001   Manually starts the "2A" Stator Cooling pump (May NOT pull procedure until after the pump has been started.)
* Dispatches SO/Maint to investigate the cause of Generator Inlet Pressure Low.
Monitors for increasing system pressure by 651
The BOP may NOT enter the following once the standby pump is started.
-202 clearing.
* Enters GENERATOR OUTLET TEMP HIGH, (651-204) and performs the following:
Dispatches SO/Maint to investigate the cause of Generator Inlet Pressure Low
* Monitors Stator Cooling Outlet temp on EHC Control System monitor BOP on 2H11-P650 panel
.            The BOP may NOT enter the following once the standby pump is started.
* Dispatches SO/Maint to investigate GENERATOR OUTLET TEMP HIGH alarm.
BOP  Enters GENERATOR OUTLET TEMP HIGH, (651-204) and performs the following:
The BOP may NOT enter the following once the standby pump is started.
Monitors Stator Cooling Outlet temp on EHC Control System monitor on 2H11-P650 panel Dispatches SO/Maint to investigate GENERATOR OUTLET TEMP HIGH alarm
* Enters STATOR CLG TANK WATER LEVEL HIGH/LOW, (651-202)
.            The BOP may NOT enter the following once the standby pump is started.
BOP and dispatches a SO locally to determine Tank level.
BOP  Enters STATOR CLG TANK WATER LEVEL HIGH/LOW, (651-202) and dispatches a SO locally to determine Tank level.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       6                     Page 16 of 26 Event
9-03 Event No.:
6 Pag e 16 of 26 Event


== Description:==
== Description:==
 
Stator Cooling Pump 2B (simulate sheared shaft)
Stator Cooling Pump '2B' (simulate sheared shaft)
Standby Stator Cooling pump 2A fails to start (manually started)
Standby Stator Cooling pump 2A fails to start (manually started)
Time Position Applicant's Actions or Behavior The BOP may NOT enter the following once the standby pump is started.
Time     Position Applicant's Actions or Behavior The BOP may NOT enter the following once the standby pump is started.
BOP  Enters GENERATOR PROTECTION CIRCUIT ENERGIZED, (651
* Enters GENERATOR PROTECTION CIRCUIT ENERGIZED, (651-206) and performs the following:
-206) and performs the following:
* Starts 2N43-C001A Stator Clg Wtr Pump 2A BOP
Starts 2N43
* IF a Main Turbine Bypass Valve begins opening, enters 34AB-C71-001-2, Scram Procedure, and SCRAM the reactor.
-C001A Stator Clg Wtr Pump 2A IF a Main Turbine Bypass Valve begins opening, enters 34AB
(NOT expected to be required)
-C71-001-2, Scram Procedure, and SCRAM the reactor.
SRO
(NOT expected to be required
* Directs the operator to place the Stator Cooling Pump 2B pump to Trip.
)        SRO Directs the operator to place the Stator Cooling Pump "2B" pump to Trip.
Simulator Operator: ENSURE EVENT TRIGGER ET-EGN43-01 is ACTIVATED, THEN; After 3 minutes of being sent to investigate the Stator Cooling system low flow and pressure AND after the BOP has started 2A Stator Cooling pump, REPORT that the 2B Stator Cooling pump motor is running, but the pump shaft is NOT turning.
Simulator Operator:
* Places 2N43-C001B control switch to Trip position and reports this to the BOP SRO.
ENSURE EVENT TRIGGER ET-EGN43-01 is ACTIVATED, THEN
Simulator Operator, at Chief Examiners direction, starts the Major event.
; After 3 minutes of being sent to investigate the Stator Cooling system low flow and pressure AND after the BOP has started 2 A Stator Cooling pump, REPORT that the "2 B" Stator Cooling pump motor is running, but the pump shaft is NOT turning.
BOP  Places 2N43
-C001B control switch to Trip position and reports this to the SRO.           Simulator Operator, at Chief Examiner's direction, starts the Major event.


Appendix D Required Operator Actio ns Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                    Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       7                         Page 17 of 26 Event
9-03 Event No.:
7 Page 17 of 26 Event


== Description:==
== Description:==
Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.
Time      Position  Applicant's Actions or Behavior Simulator Operator: At the direction of the Chief Examiner, ACTIVATES:
8                (RB-7)
Mins
* mf60321350
* mf60321350 Recognizes annunciators and plant conditions:
ALL
* Group 1 System A/B Trip - Full Group 1, MSIV isolation
* Full reactor scram REQUIRED
* Assigns the ATC to perform RC-1.
* Assigns the BOP operator to perform RC-2 and RC-3.
* If time allows assigns TC-1 to be performed.
SRO
* Enters the RC EOP flow chart, 31EO-EOP-010-2, for a scram condition AND when RWL decreases below 3 inches.
* Directs RWL Band of 3 to 50 inches.
* Performs RC-1 consisting of:
* Inserts a manual scram.
* Places the mode switch to SHUTDOWN.
* Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
* Notifies SRO of rod position check.
ATC
* Places SDV isolation valve switch to "isolate" & confirms closed.
* If NOT tripped, places the Recirc pumps at minimum speed.
* Inserts SRMs and IRMs.
* Shifts recorders to read IRMS, when required.
* Ranges IRMS to bring reading on scale.
* Notifies the SRO when the above actions are complete.
ATC/BOP
* Places MSIV switches to close on 2H11-P602 and P601 panels.


Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works. Time Position Applicant's Actions or Behavi or  8 Mins  Simulator Operator:  At the direction of the Chief Examiner, ACTIVATES: (RB-7)  mf60321350 mf60321350 ALL Recognizes annunciators and plant conditions:
Appendix D                        Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301  Scenario No.: 9-03 Event No.:       7                      Page 18 of 26 Event
Group 1 System A/B Trip
- Full Group 1, MSIV isolation Full reactor scram REQUIRED SRO  Assigns the ATC to perform RC
-1. Assigns the BOP operator to perform RC
-2 and RC-3. If time allows assigns TC
-1 to be performed.
Enters the RC EOP flow chart, 31EO
-EOP-010-2, for a scram condition AND when RWL decreases below 3 inches.
Directs RWL Band of 3 to 50 inches.
ATC  Performs RC
-1 consisting of:
Inserts a manual scram.
Places the mode switch to SHUTDOWN.
Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
Notifies SRO of rod position check.
Places SDV isolation valve switch to "isolate" & confirms closed.
If NOT tripped, places the Recirc pumps at minimum speed.
Inserts SRMs and IRMs.
Shifts recorders to read IRMS, when required.
Ranges IRMS to bring reading on scale.
Notifies the SRO when the above actions are complete.
ATC/BOP  Places MSIV switches to close on 2H11-P602 and P601 panels.


Appendix D Required Operator Actio ns Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
== Description:==
9-03 Event No.:
Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.
7 Page 18 of 26 Event
Time      Position  Applicant's Actions or Behavior Performs RC-2 actions consisting of:
* Confirms proper Level Control response:
* Checks ECCS Injection Systems (HPCI will be ISOLATED from previous steam line break)
* Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value
* If Set down does NOT auto function, manually reduces FW Master Controller setpoint to approximately 9 inches.
* When feed flow is less than the capacity of the S/U level control valve (
BOP 1.5 mlbm/hr), then:
* Confirm/Opens 2N21-F125.
* Confirms 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
* Closes 2N21-F110.
* Will control RWL and with SRO permission will raise RWL to 32 to 42 inches.
* When RFPTs are no longer available, will transition to RCIC to control RWL.
Starts RCIC HPCI for level control by performing the following:
BOP
* RCIC, at 2H11-P602 panel:
* Depresses RCIC Manual Initiation P/B
* Confirms/Opens 2E51-F046
* Confirms/Starts Barom Cndsr Vac Pump
* Confirms/Opens 2E51-F045
* Confirms/Opens 2E51-F019
* Confirms/Closes 2E51-F019 at flow > 79.3 gpm
* Confirms/Opens 2E51-F013
* Adjusts controller for desired flow and with SRO permission will raise RWL to 32 to 42 inches
 
Appendix D                       Required Operator Actions                      Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       7                         Page 19 of 26 Event


== Description:==
== Description:==
Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.
Time      Position  Applicant's Actions or Behavior Simulator Operator When the 2B SRV is open, ENSURE EVENT TRIGGER EGB21-3 activates mfB21_128B, mfB21_130B and mfB21_286B.
* Performs RC-3 consisting of:
* Monitoring RPV pressure.
* Confirms proper operation of pressure control system (SRVs, LLS, etc.) by performing one or more of the following:
* At 2H11-P602 panel, manually cycles SRVs to maintain reactor BOP                  pressure within band of 1074 psig to 800 psig.
* If necessary, allows RPV pressure to exceed 1074 psig then cycles any SRV to initiate LLS.
* Maintains RPV pressure between 1074 and 800 psig until a different band is directed.
* Notifies SRO of pressure control system operation.
Directs operator to enter 34AB-B21-003-2, Failure of Safety/Relief Valves.
SRO Directs operators to verify that the SRV 2B is closed, after the fuses are pulled.
NOTE: The operator may not perform some of the below steps since they are dependent on the status of 2B SRV red light when the operator addresses the open SRV.


Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works. Time Position Applicant's Actions or Behavi or        BOP Performs RC
Appendix D                       Required Operator Actions                    Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       7                       Page 20 of 26 Event
-2 actions consisting of:
Confirms proper Level Control response:
Checks ECCS Injection Systems (HPCI will be ISOLATED from previous steam line break)
Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value If Set down does NOT auto function, manually reduces FW Master Controller setpoint to approximately 9 inches.
When feed flow is less than the capacity of the 1.5 mlbm/hr), then:
Confirm/Opens 2N21
-F125. Confirms 2C32
-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
Closes 2N21
-F110. Will control RWL and with SRO permission will raise RWL to 32 to 42 inches. When RFPTs are no longer available, will transition to RCIC to control RWL.        BOP Starts RCIC HPCI for level control by performing the following:
RCIC, at 2H11
-P602 panel:
Depresses RCIC Manual Initiation P/B Confirms/Opens 2E51
-F046  Confirms/Starts Barom Cndsr Vac Pump Confirms/Opens 2E51
-F045  Confirms/Opens 2E51
-F019  Confirms/Closes 2E51
-F019 at flow > 79.3 gpm Confirms/Opens 2E51
-F013  Adjusts controller for desired flow and with SRO permission will raise RWL to 32 to 42 inches
 
Appendix D Required Operator Actio ns Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
7 Page 19 of 26 Event


== Description:==
== Description:==
Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.
Time      Position  Applicant's Actions or Behavior
* Notifies SRO the 2B SRV failed to close.
* Enters 34AB-B21-003-2, Failure of Safety/Relief Valves.
* Determines SRV 2B is cycling open then close
* Cycles the SRV 2B Control Switch several times
* May depress the ADS Logic A Timer Reset pushbutton (2B21-S2A)
* May depress the ADS Logic B Timer Reset pushbutton (2B21-S2B)
BOP
* May depress the LLS Channel A / C Reset pushbutton (2B21-S15A)
* May depress the LLS Channel B / D Reset pushbutton (2B21-S15B)
* Informs SRO that SRV 2B is still open and the fuses will have to be pulled.
* Notifies the SSS to pull the fuses for SRV 2G. (Critical Task)
Critical Task is to remove the fuses for 2B SRV prior to exceeding >100&deg;F/hr cooldown rate or the unsafe region of the PSP Curve.
Simulator Operator, assuming that a request was made to pull fuses for SRV 2B, wait 4 minutes, then ENTER the following:
ENTER Event Trigger EGB21-6 which will DELETE mfB21_128B and mfB21_130B AND DEPRESSES (RB-8), rfB21_301, to simulate pulling the fuses for SRV 2B.
THEN, Notify the crew that the fuses have been pulled for SRV 2B.
* Confirms that SRV 2B is closed by monitoring one or more of the following:
* SRV tailpipe temperature decrease on P614 panel.
* Torus level stabilizing
* Torus Temp stabilizing
* Rx pressure returns to the pre-event level BOP
* Resets the SRV leak detection by placing the Leak Detection Logic A Reset keylock switch and Leak Detection Logic B Reset keylock switch to RESET position and back to NORMAL position
* Confirms that the Amber SRV indicating lights have extinguished.
* SAFETY BLOWDOWN PRESSURE HIGH, (602-311), clears.
* Informs the SRO that SRV 2B is closed.
Simulator Operator, at Chief Examiners direction, PROCEEDS to the next event.


Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works. Time Position Applicant's Actions or Behavi or            Simulator Operator When the 2B SRV is open, ENSURE EVENT TRIGGER EGB21-3 activates mfB21_128B, mfB21_130B and mfB21_286B.
Appendix D                     Required Operator Actions                    Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       7                       Page 21 of 26 Event
BOP  Performs RC
-3 consisting of:
Monitoring RPV pressure.
Confirms proper operation of pressure control system (SRVs, LLS, etc.) by performing one or more of the following:
At 2H11-P602 panel, manually cycles SRVs to maintain reactor pressure within band of 1074 psig to 800 psig.
If necessary, allows RPV pressure to exceed 1074 psig then cycles any SRV to initiate LLS. Maintains RPV pressure between 1074 and 800 psig until a different band is directed.
Notifies SRO of pressure control system operation.
SRO Directs operator to enter 34AB
-B21-003-2, Failure of Safety/Relief Valves
. Directs operators to verify that the SRV 2B is closed, after the fuses are pulled.
NOTE: The operator may not perform some of the below steps since they are dependent on the status of 2B SRV red light when the operator addresses the open SRV.
 
Appendix D Required Operator Actio ns Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
7 Page 20 of 26 Event


== Description:==
== Description:==
Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.
Time      Position  Applicant's Actions or Behavior


Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works. Time Position Applicant's Actions or Behavi or  BOP  Notifies SRO the 2B SRV failed to close.
Appendix D                       Required Operator Actions                    Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.:         8                        Page 22 of 26 Event
Enters 34AB
-B21-003-2, Failure of Safety/Relief Valves
. Determines SRV 2B is cycling open then close Cycles the SRV 2B Control Switch several times May depress the ADS Logic A Timer Reset pushbutton (2B21
-S2A)  May depress the ADS Logic B Timer Reset pushbutton (2B21
-S2B)  May depress the LLS Channel A / C Reset pushbutton (2B21
-S15A)  May depress the LLS Channel B / D Reset pushbutton (2B21
-S15B)  Informs SRO that SRV 2B is still open and the fuses will have to be pulled. Notifies the SSS to pull the fuses for SRV 2 G. (Critical Task
)  Critical Task is to remove the fuses for 2B SRV prior to exceeding >100&deg;F/hr cooldown rate or the unsafe region of the PSP Curve.
Simulator Operator, assuming that a request was made to pull fuses for  SRV 2 B, wait 4 minutes, then ENTER the following:
ENTER Event Trigger EGB21-6 which will DELETE mfB21_128B and mfB21_130B AND DEPRES SE S (RB-8), rfB21_30 1, to simulate pulling the fuses for SRV 2B. THEN, Notify the crew that the fuses have been pulled for SRV 2 B. BOP  Confirms that SRV 2B is closed by monitoring one or more of the following:
SRV tailpipe temperature decrease on P614 panel. Torus level stabilizing Torus Temp stabilizing Rx pressure returns to the pre
-event level Resets the SRV leak detection by placing the Leak Detection Logic A Reset keylock switch and Leak Detection Logic B Reset keylock switch to RESET position and back to NORMAL position Confirms that the Amber SRV indicating lights have extinguished
. SAFETY BLOWDOWN PRESSURE HIGH, (602
-311), clears
. Informs the SRO that SRV 2B is closed.
Simulator Operator, at Chief Examiner's direction, PROCEEDS to the next event.
Appendix D Required Operator Actio ns Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
7 Page 21 of 26 Event


== Description:==
== Description:==
2B SRV tailpipe fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.
Time      Position  Applicant's Actions or Behavior Recognize increasing Containment Pressure from the following alarms:
ALL
* PRIMARY CNMT HIGH PRESSURE TRIP, (603-106)
* PRIMARY CNMT PRESSURE HIGH, (603-115)
SRO
* Enters 31EO-EOP-012-2, Primary Containment flow chart.
* At panel 2H11-P601, Confirms 4 RHR pumps and 2 Core Spray pumps are BOP running.
* Per the PC flowchart, verifies Torus level is <285 inches and directs an SRO operator to place Torus Sprays in service (Critical Task) - Torus Spray is initiated or the Reactor Emergency Depressurized prior to exceeding Pressure Suppression Pressure, Graph 7.
* Sprays the Torus per 34SO-E11-010-2 placard on the 2H11-P601 Panel as follows:
* Places Cnmt Spray Vlv Cntl switch in the Manual position.
* Verifies RHR pump(s) in loop A (B) running.
* Opens 2E11-F028A or B ATC
* Opens 2E11-F027A or B
* Throttles Open 2E11-F027A(B)
* Notifies SRO that RHR is in Torus Sprays (The flow is only 700gpm, so it may be difficult to see flow indication from a distance.)


Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works. Time Position Applicant's Actions or Behavi or Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-03 Event No.:       8                     Page 23 of 26 Event
9-03 Event No.:
8 Page 22 of 26 Event


== Description:==
== Description:==
2B SRV tailpipe fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.
Time      Position  Applicant's Actions or Behavior NOTE TO EVALUATOR: It is NOT expected that an Emergency Depressurization will be required.
* If Torus pressure cannot be maintained below Pressure Suppression SRO Pressure (PSP) Limits, directs ATC to Emergency Depressurize (ED).
* When directed, places 7 ADS valve switches to the OPEN position on ATC panel 2H11-P602.
* If Emergency Depressurized, direct BOP to ensure RHR and CS injection SRO valves open and injection occurs.
* When directed, monitors RHR and CS and verifies that systems inject BOP when reactor pressure decreases below the system discharge head.
Simulator Operator:
After the crew is spraying the Torus OR Emergency Depressed for PSP concerns AND with Chief Examiners permission, TERMINATE the scenario.


2B' SRV tailpipe fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.
Page 24 of 26 Appendix D                                Scenario Outline                          Form ES-D-1 NRC FINAL Facility:    E. I Hatch            Scenario No.: 9-03          Op-Test No.: 2015-301 Examiners:                                      Operators:                                          SRO RO BOP Initiating Conditions:    Unit 2 is operating at 56% RTP.
Time Position Applicant's Actions or Behavior ALL Recognize increasing Containment Pressure from the following alarms:
Turnover                  RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT 2A in service, starting at step 7.1.11.2.7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System. 2D LLS valve is inop for LLS Function only.
PRIMARY CNMT HIGH PRESSURE TRIP, (603
Summary:
-106) PRIMARY CNMT PRESSURE HIGH, (603
* Event 1: Normal; The 2A RFPT will be placed into service.
-115)          SRO Enters 31EO
* Event 2: Reactivity; After the 2A RFPT is in service, the ATC operator will raise reactor power using the Recirc system to approximately 65% power.
-EOP-012-2, Primary Containment flow chart.
* Event 3: Component/TS; A HPCI steam line will break outside of Primary Containment. The outboard isolation valve is failed open and cannot be closed. Both isolation valves fail to automatically close on an automatic isolation signal and must be manually closed. (Critical Task) The SRO addresses Tech Specs for inoperable Primary Containment Isolation Valve &
BOP  At panel 2H11
ECCS.
-P601, Confirms 4 RHR pumps and 2 Core Spray pumps are running.           SRO  Per the PC flowchart, verifies Torus level is <285 inches and directs an operator to place Torus Sprays in service (Critical Task
* Event 4: Component; Instrument Air System Prefilter dP Hi - swap Prefilters.
) - Torus Spray is initiated or the Reactor Emergency Depressurized prior to exceeding Pressure Suppression Pressure, Graph 7. ATC  Sprays the Torus per 34SO
The operator will dispatch an SO locally to determine dP. Report back will require BOP swapping Prefilters to restore normal system flow/pressure. (OE)
-E11-010-2 placard on the 2H11
* Event 5: Component/TS; Recirc Pump 2B will experience high vibration requiring reducing reactor power in an attempt to clear the alarm. Alarm remains in until pump is tripped. The SRO addresses TS for an inoperable Recirc pump. The plant will NOT be operating in the Immediate Exit Region of the Power-to-Flow map.
-P601 Panel as follows: Places Cnmt Spray Vlv Cntl switch in the Manual position.
* Event 6: Component; Stator Cooling Pump 2B will experience a sheared shaft and the standby Stator Cooling pump will NOT automatically start. The operator will manually start the standby Stator Cooling pump to restore system flow/pressure to normal.
Verifies RHR pump(s) in loop A (B) running.
* Event 7: Major; Inadvertent Group 1 Isolation, Auto fails to close MSIVs but Manual works.
Opens 2E11
* Event 8: Component; A broken SRV B tailpipe causes Torus Pressure to increase with the failed open SRV. Torus Spray is initiated or the Reactor Emergency Depressurized prior to exceeding Pressure Suppression Pressure. (Critical Task)
-F028A or B Opens 2E11
-F027A or B Throttles Open 2E11
-F027A(B)    Notifies S RO that RHR is in Torus Sprays (The flow is only 700gpm, so it may be difficult to see flow indication from a distance.)
 
Appendix D Required Operator Actions Form ES-D-2  Op-Test No.: 2015-301 Scenario No.:
9-03 Event No.:
8 Page 23 of 26  Event


== Description:==
Page 25 of 26 Critical Tasks NRC FINAL Facility:   E. I Hatch          Scenario No.: 9-03        Op-Test No.:      2015-301 Critical Tasks
* Manually isolate the HPCI isolation valves within 5 minutes of receiving 601-115 and 601-121.
(Event 3)
* Pull fuses to SRV 2B. (Event 8)
* Spray the Torus or Emergency Depressurize before exceeding Primary Containment Pressure Suppression Pressure (PSP) curve. (Event 8)
ES 301-4 Attributes      Required      Actual                            Items
: 1. Total Malfunctions          5-8            6      1. HPCI steam line break (Event 3)
: 2. Instrument Air System Prefilter dP Hi (Event 4)
: 3. Recirc Pump 2B high vibration (Event 5)
: 4. Stator Cooling Pump 2B sheared shaft/standby failure to start (Event 6)
: 5. Inadvertent Group 1 Isolation, Auto fails to close MSIV (Event 7)
: 6. Broken SRV B tailpipe (Event 8)
: 2. Malfunctions After          1-2            1      1. Broken SRV B tailpipe (Event 8)
EOP Entry
: 3. Abnormal Events            2-4            3      1. HPCI steam line break (Event 3)
: 2. Instrument Air System Prefilter dP Hi (Event 4)
: 3. Recirc Pump 2B high vibration (Event 5)
: 4. Major Transients            1-2            1      1. Inadvertent Group 1 Isolation, Auto fails to close MSIV (Event 7)
: 5. EOPs entered,              1-2            2      1. 31EO-EOP-010-2, RC Non ATWS, (Event 7) requiring substantive                            2. 31EO-EOP-012-2, PC, (Event 7) actions
: 6. EOPs contingencies          0-2            0      1. None requiring substantive actions
: 7. Critical Tasks              2-3            3      1. HPCI steam line break (Event 3)
: 2. Pull fuses to SRV 2B. (Event 8)
: 3. Broken SRV B tailpipe, spray Torus (Event 8)


2B' SRV tailpipe fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.
ILT 9 NRC FINAL Scenario 3 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions:      Activities in progress: 34SV-P41-001-1, Plant Service Water Pump Operability.
Time Position Applicant's Actions or Behavior NOTE TO EVALUATOR:
UNIT 2 STATUS Plant Conditions:     Unit 2 is operating at 59% RTP.
It is NOT expected that an Emergency Depressurization will be required.
Protected Train:                                    EOOS:
SRO  I f Torus pressure cannot be maintained below Pressure Suppression Pressure (PSP) Limits, directs ATC to Emergency Depressurize (ED).
Division I                           Green                            Orange Division II                          Yellow                          Red RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT 2A in service, starting at step 7.1.11.2.7 of Scheduled evolutions:      34SO-N21-007-2.
ATC  When directed, places 7 ADS valve switches to the OPEN position on panel 2H11
Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System.
-P602.          SRO  If Emergency Depressurized, direct BOP to ensure RHR and CS injection valves open and injection occurs.
Surveillances due this None shift:
BOP  When directed, monitors RHR and CS and verifies that systems inject when reactor pressure decreases below the system discharge head.
Inop Equipment:          2D LLS valve is inop for LLS Function only.
Simulator Operator
Active tagouts:             2D LLS valve is inop for LLS Function only.
: After the crew is spraying the Torus OR Emergency Depressed for PSP concerns AND with Chief Examiners permission, TERMINATE the scenario.
Rod Configuration:            See RWM


Page 24 of 26 Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.:
Appendix D                               Scenario Outline                           Form ES-D-1 NRC FINAL Facility:   E. I Hatch             Scenario No.: 9-04        Op-Test No.:     2015-301 Examiners:                                     Operators:                                           SRO RO BOP Initial Conditions. Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service.
9-03 Op-Test No.: 2015-301 Examiners:
Turnover: Reduce reactor power to 60% RTP for RFPT 2A removal. Leave RFPT 2A operating at ~1000 RPM.
Operators:
Event       Malf. No.     Event                                        Event No.                     Type*                                    Description 1    N/A                R (ATC)     Reduce reactor power to 60% for RFPT 2A removal.
SRO   RO   BOP   Initiating Conditions:
2   N/A               N (BOP)     Remove 2A RFPT from service and leave operating at ~1000 RPM.
Unit 2 is operating at 56% RTP.
mf60131136 aoE21R600A                    2A Loop of Core Spray experiences high discharge pressure (valve C (BOP) 3                                   leakage). When 2E21-F004A is reopened, the valve breaker trips loE21-F004AG1 TS (SRO) when control switch placed to open.
Turnover RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT '2A' in service, starting at step 7.1.11.2.
loE21-F004AR2 CRD 2A pump experiences a Suction Filter hi dP requiring swapping 4   mf60311308        C (ATC) to standby pump.
7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System. 2D LLS valve is inop for LLS Function only. Summary:  Event 1:  Normal; The "2A" RFPT will be placed into service.
C (BOP) RCIC Room fire.
Event 2:  Reactivity
5   N/A TS (SRO)
; After the "2A" RFPT is in service
I (ATC) 6   mfB21_131                      ADS Inadvertent initiation/Inhibit used. (Critical Task)
, the ATC operator will raise reactor power using the Recirc system to approximately 65% power.
TS (SRO)
Event 3:  Component/TS; A HPCI steam line will break outside of Primary Containment. The outboard isolation valve is failed open and cannot be closed. Both isolation valves fail to automatically close on an automatic isolation signal and must be manually closed.
Unisolable HPCI Steam leak in Reactor Building requiring a Reactor 7    mfE41_249          M (ALL)
(Critical Task)  The SRO addresses Tech Specs for inoperable Primary Containment Isolation Valve & ECCS. Event 4:  Component; Instrument Air System Prefilter dP Hi
Manual scram. HPCI Group 3 signal failure.
- swap Prefilters.
M (ALL) Emergency Depress when Max Safe exceeded in more than one area.
T he operator will dispatch an SO locally to determine dP. Report back will require BOP swapping Prefilters to restore normal system flow/pressure.  (OE)
8    N/A                            (Critical Task)
Event 5:  Component/TS; Recirc Pump '2B' will experience high vibration requiring reducing reactor power in an attempt to clear the alarm. Alarm remains in until pump is tripped. The SRO addresses TS for an inoperable Recirc pump. The plant will NOT be operating in the Immediate Exit Region of the Power
SULCV fails closed. Core Spray & RHR Logic failure requiring mfN21_99 manual actions for pumps/valves to inject. RPV level will be 9    mfE11_202B        C (BOP)     controlled either by throttling open 2N21-F110, or by using Core mfE21_202A Spray and/or RHR Systems. (Critical Task)
-to-Flow map.
*        (N)ormal,       (R)eactivity,    (I)nstrument,        (C)omponent,         (M)ajor
Event 6:  Component; Stator Cooling Pump '2 B' will experience a sheared shaft and the standby Stator Cooling pump wil l NOT automatically start. The operator will manually start the standby Stator Cooling pump to restore system flow/pressure to normal.
Event 7:  Major; Inadvertent Group 1 Isolation, Auto fails to close MSIVs but Manual works.
Event 8:  Component; A broken SRV 'B' tailpipe causes Torus Pressure to increase with the failed open SRV. Torus Spray is initiated or the Reactor Emergency Depressurized prior to exceeding Pressure Suppression Pressure.
(Critical Task
)
Page 25 of 26 Critical Tasks NRC FINAL Facility: E. I Hatch Scenario No.: 9-03 Op-Test No.: 2015-301  Critical Tasks Manually isolate th e HPCI isolation valves within 5 minutes of receiving 60 1-115 and 60 1-121.    (Event 3)   Pull fuses to SRV 2B. (Event 8)  Spray the Torus or Emergency Depressurize before exceeding Primary Containment Pressure Suppression Pressure (PSP) curve.
(Event 8)  ES 301-4 Attributes Required Actual Items 1. Total Malfunctions 5-8 6 1. HPCI steam line break (Event 3) 2. Instrument Air System Prefilter dP Hi (Event 4) 3. Recirc Pump '2B' high vibration (Event 5) 4. Stator Cooling Pump '2 B' sheared shaft/standby failure to start  (Event 6) 5. Inadvertent Group 1 Isolation, Auto fails to close MSIV  (Event 7) 6. Broken SRV 'B' tailpipe  (Event 8) 2. Malfunctions After EOP Entry 1-2 1 1. Broken SRV 'B' tailpipe  (Event 8) 3. Abnormal Events 2-4 3 1. HPCI steam line break  (Event 3) 2. Instrument Air System Prefilter dP Hi  (Event 4) 3. Recirc Pump '2B' high vibration  (Event 5) 4. Major Transients 1-2 1 1. Inadvertent Group 1 Isolation, Auto fails to close MSIV  (Event 7) 5. EOPs entered, requiring substantive actions 1-2 2 1. 31EO-EOP-010-2, RC Non ATWS,  (Event 7) 2. 31EO-EOP-012-2, PC,  (Event 7) 6. EOPs contingencies requiring substantive actions 0-2 0 1. None 7. Critical Tasks 2-3 3 1. HPCI steam line break  (Event 3) 2. Pull fuses to SRV 2B.  (Event 8) 3. Broken SRV 'B' tailpipe, spray Torus (Event 8)
ILT 9 NRC FINAL Scenario 3  SHIFT TURNOVER Safety Focus UNIT 1 STATUS Plant Conditions:
Unit 1 is operating at 100% power Activities in progress:  34SV-P41-001-1, Plant Service Water Pump Operability.
UNIT 2 STATUS Plant Conditions:
Unit 2 is operating at 5 9% RTP. Protected Train: EOOS:   Division I Division II Green    Yellow  Orange  Red  Scheduled evolutions
:  RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT '2A' in service, starting at step 7.1.11.2.7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System.
Surveillances due this shift:  None  Inop Equipment:
2D LLS valve is inop for LLS Function only.
Active tagouts
:  2D LLS valve is inop for LLS Function only.
Rod Configuration
:  See RWM 


Appendix D Scenario Outline Form ES-D-1  NRC FINAL  Facility: E. I Hatch Scenario No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:         1                       Page 2 of 27 Event
9-04 Op-Test No.: 2015-301  Examiners:
Operators:
SRO    RO    BOP  Initial Conditions
. Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service. Turnover:  Reduce reactor power to 60% RTP for RFPT 2A removal. Leave RFPT 2A operating at ~1000 RPM.
Event No. Malf. No. Event Type* Event Description 1 N/A R (ATC) Reduce reactor power to 60% for RFPT 2A removal. 2 N/A N (BOP) Remove 2A RFPT from service and leave operating at ~1000 RPM
. 3 mf60131136 aoE21R600A loE21-F004AG1 loE21-F004AR2 C (BOP) TS (SRO) 2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
4 mf60311308 C (ATC) CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
5 N/A C (BOP) TS (SRO) RCIC Room fire.
6 mfB21_131 I (ATC) TS (SRO) ADS Inadvertent initiation/Inhibit used.
(Critical Task
) 7 mfE41_249 M (ALL) Unisolable HPCI Steam leak in Reactor Building requiring a Reactor Manual scram
. HPCI Group 3 signal failure.
8 N/A M (ALL) Emergency Depress when Max Safe exceeded in more than one area.
(Critical Task
) 9 mfN21_99  mfE11_202B mfE21_202A C (BOP) SULCV fails closed. Core Spray & RHR Logic failure requiring manual actions for pumps/valves to inject. RPV level will be controlled either by throttling open 2N21
-F110, or by using Core Spray and/or RHR Systems
.  (Critical Task)    *  (N)ormal,  (R)eactivity,      (I)nstrument,    (C)omponent, (M)ajor Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
1 Page 2 of 27 Event


== Description:==
== Description:==
Reduce reactor power to 60% for RFPT 2A removal.
Reduce reactor power to 60% for RFPT 2A removal.
Time Position Applicant's Actions or Behavior 15 Mins SRO  Directs ATC to decrease reactor power to 60%, to achieve a Feedwater flow <7 mlbm/hr for RFPT removal, by decreasing Recirc flow. Power decreases should be made as recommended by the STA/Reactor Engineering at a rate NOT to exceed 10 MWe/min.
Time     Position Applicant's Actions or Behavior
ATC  IAW 34SO-B31-001-2, the ATC decreases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the LOWER SLOW or LOWER MEDIUM pushbuttons on the Master or Individual controls until reactor power is 6 0%. Monitors power decrease by observing APRM and generator output indications.
* Directs ATC to decrease reactor power to 60%, to achieve a Feedwater 15                      flow <7 mlbm/hr for RFPT removal, by decreasing Recirc flow. Power SRO Mins                    decreases should be made as recommended by the STA/Reactor Engineering at a rate NOT to exceed 10 MWe/min.
Monitors Total Feedwater flow to achieve Feedwater flow <7 mlbm/hr on 2C32-R604A, 2C32
* IAW 34SO-B31-001-2, the ATC decreases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the LOWER SLOW or LOWER MEDIUM pushbuttons on the Master or Individual controls until reactor power is 60%. Monitors power decrease by observing APRM and ATC generator output indications.
-R604B, and 2C32
* Monitors Total Feedwater flow to achieve Feedwater flow <7 mlbm/hr on 2C32-R604A, 2C32-R604B, and 2C32-R607.
-R607. Notifies SRO when Feedwater flow is <7 mlbm/hr.
* Notifies SRO when Feedwater flow is <7 mlbm/hr.
ATC  Complies with 34SO-B31-001-2 , Limitation 5.2.15, which states:
* Complies with 34SO-B31-001-2 , Limitation 5.2.15, which states:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
   <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating  
ATC
< 70% of rated core flow; AND <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at  
                          *   <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating
> 70% of rated core flow.
                              < 70% of rated core flow; AND
NOTE: May get the RBM UPSCALE, (603
                          * <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at
-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.  
                              > 70% of rated core flow.
 
NOTE:     May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.
May also get Alarm HEATER TROUBLE, 650
May also get Alarm HEATER TROUBLE, 650-135 alarm. This is expected at this power level.
-135 alarm. This is expected at this power level.
Simulator Operator, at the Chief Examiners direction OR after power has been decreased by 5%, PROCEEDS to the next event.
Simulator Operator, at the Chief Examiners direction OR after power has been decreased by 5%, PROCEEDS to the next event.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                         Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:         2                     Page 3 of 27 Event
9-04 Event No.:
2 Page 3 of 27 Event


== Description:==
== Description:==
Remove 2A RFPT from service and leave at approximately 1000 rpm.
Remove 2A RFPT from service and leave at approximately 1000 rpm.
Time Position Applicant's Actions or Behavior 10 Mins SRO  Directs the BOP to remove the 2A RFPT from service IAW 34SO-N21-007-2, Section 7.2.1.         BOP  Confirm s Feedwater Flow is less than 7 Mlbm / hr
Time     Position Applicant's Actions or Behavior 10
. Confirm s RFPT 2A AND RFPT 2B are in Automatic control on 2C32-R600, Master Controller
* Directs the BOP to remove the 2A RFPT from service IAW SRO Mins                    34SO-N21-007-2, Section 7.2.1.
. Depresses setpoint increase button on 2C32
* Confirms Feedwater Flow is less than 7 Mlbm / hr.
-R600, Master Controller and raises RWL setpoint to 39 inches. Places 2C32
* Confirms RFPT 2A AND RFPT 2B are in Automatic control on 2C32-R600, Master Controller.
-R601A, RFP A M/A Station, in Manual, by depressing the 'M' pushbutton until it illuminates, panel 2H11
* Depresses setpoint increase button on 2C32-R600, Master Controller and raises RWL setpoint to 39 inches.
-P603. Slowly decreases RFPT 2A speed until RFP 2B is controlling reactor vessel level
* Places 2C32-R601A, RFP A M/A Station, in Manual, by depressing the
. RFP COO5A DISCH LOW FLOW, (656
                          'M' pushbutton until it illuminates, panel 2H11-P603.
-039) will alarm and is expected.
* Slowly decreases RFPT 2A speed until RFP 2B is controlling reactor vessel level.
Depresses setpoint decrease button on 2C32
BOP
-R600, Master Controller and lowers RWL setpoint to 3 7 inches. Slowly decreases RFPT 2A speed until no speed decrease is observed and places RFPT A TMR switch to SS and confirms SPEED SETTER yellow light illuminates.
* RFP COO5A DISCH LOW FLOW, (656-039) will alarm and is expected.
Slowly lowers RFPT 2A Speed Setter switch until RFPT speed is at 1000 rpm, at 2H11
* Depresses setpoint decrease button on 2C32-R600, Master Controller and lowers RWL setpoint to 37 inches.
-P650. Dispatches SO to confirm open OR open RFPT 2A drain valves on Local panel 2H21
* Slowly decreases RFPT 2A speed until no speed decrease is observed and places RFPT A TMR switch to SS and confirms SPEED SETTER yellow light illuminates.
-P244 (steps 7.2.1.9)
* Slowly lowers RFPT 2A Speed Setter switch until RFPT speed is at 1000 rpm, at 2H11-P650.
.        Simulator Operator, if dispatched to confirm RFPT 2A drains, after 5 minutes, report all drain valves per step 7.2.1.9 are open.
* Dispatches SO to confirm open OR open RFPT 2A drain valves on Local panel 2H21-P244 (steps 7.2.1.9).
Simulator Operator, if dispatched to confirm RFPT 2A drains, after 5 minutes, report all drain valves per step 7.2.1.9 are open.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
 
9-04 Event No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       3                         Page 4 of 27 Event
3 Page 4 of 27 Event


== Description:==
== Description:==
2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
Time    Position  Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator enters (RB-3) malfunction mf60131136 Window 28 Core Spray A Disch Pipe Press High 5 Mins (ON) and aoE21-R600A to 465 psig. ENSURE Event Trigger EGE21-1 activates when 2E21-F004A is placed to open position.
ALL      Receives CORE SPRAY A DISCH PIPE PRESS. HIGH, (601-328)
* Enters CORE SPRAY A DISCH PIPE PRESS. HIGH, (601-328)
* Confirms validity of alarm using Disch Press indicator, 2E21-R600A
(~465 psig)
* Confirms the following valves are CLOSED
* 2E21-F037A, Testable Check Bypass Vlv
* 2E21-F005A, Inbd Discharge Vlv
* Closes 2E21-F004A, Outbd Discharge Vlv
* Opens 2E21-F005A BOP
* Closes 2E21-F005A, to reseat
* Places 2E21-F004A to open and alarm CORE SPRAY SYSTEM I VALVES OVERLOAD, (601-316), is received.
* Notifies SRO of alarm (601-316) and that the lights for 2E21-F004A are extinguished.
* Notifies SRO of the following TS 3.5.1 TS 3.5.2 TS 3.6.1.3
* Directs operator to enter 601-316 ARP SRO
* Reviews TS 3.5.1
* Reviews TS 3.6.1.3.A


2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       3                       Page 5 of 27 Event
Time Position Applicant's Actions or Behavior 5 Mins  At the Chief Examiner's direction, Simulator Operator enters (RB-3) malfunction mf60131136 Window 28 Core Spray A Disch Pipe Press High (ON) and aoE21
-R600A to 465 psig. ENSURE Event Trigger EGE21-1 activates when 2E21
-F004A is placed to open position.
ALL Receives CORE SPRAY A DISCH PIPE PRESS. HIGH, (601
-328)        BOP  Enters CORE SPRAY A DISCH PIPE PRESS. HIGH, (601
-328)  Confirm s validity of alarm using Disch Press indicator, 2E21
-R600A (~465 psig)
Confirm s the following valves are CLOSED 2E21-F037A, Testable Check Bypass Vlv 2E21-F005A, Inbd Discharge Vlv Closes 2E21
-F004A, Outbd Discharge Vlv Opens 2E21
-F005A  Closes 2E21
-F005A, to reseat Places 2E21
-F004A to open and alarm CORE SPRAY SYSTEM I VALVES OVERLOAD
, (601-316), is received.
Notifies SRO of alarm (601
-316) and that the lights for 2E21-F004A are extinguished.
Notifies SRO of the following TS 3.5.1 TS 3.5.2 TS 3.6.1.3 SRO  Directs operator to enter 601
-316 ARP  Reviews TS 3.5.1 Reviews TS 3.6.1.3.A Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
3 Page 5 of 27 Event


== Description:==
== Description:==
2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
Time Position Applicant's Actions or Behavior BOP  Enters CORE SPRAY SYSTEM I VALVES OVERLOAD, (601
Time     Position Applicant's Actions or Behavior
-316) Dispatches SO/Maint. to reset the thermal overload for 2E21-F004A at MCC 2R24-S011, Frame 13A Simulator Operator, wait 4 minutes, then as an SO, report that the breaker for 2E21-F004A will NOT reset.
* Enters CORE SPRAY SYSTEM I VALVES OVERLOAD, (601-316)
If asked/directed to manually break 2E21
BOP
-F004A off the closed seat, report this valve will NOT move with the handwheel.
* Dispatches SO/Maint. to reset the thermal overload for 2E21-F004A at MCC 2R24-S011, Frame 13A Simulator Operator, wait 4 minutes, then as an SO, report that the breaker for 2E21-F004A will NOT reset.
SRO Enters TS 3.5.1, ECCS Operating, and determines:
If asked/directed to manually break 2E21-F004A off the closed seat, report this valve will NOT move with the handwheel.
TS 3.5.1.A requires the ECCS pump to restored to operable status in 7 days.
Enters TS 3.5.1, ECCS Operating, and determines:
NOTE: If addressed, 2E21
SRO TS 3.5.1.A requires the ECCS pump to restored to operable status in 7 days.
-F004A is NOT a PCIV and TS 3.6.1
NOTE:     If addressed, 2E21-F004A is NOT a PCIV and TS 3.6.1.3 for PCIVs is not needed.
.3 for PCIVs is not needed.           Simulator Operator, ENSURE Event Trigger EGE21-2 activates when 2E21
Simulator Operator, ENSURE Event Trigger EGE21-2 activates when 2E21-F015A is placed to open position. This will clear CS A Disch Press High alarm & return 2E21-R600A to normal.
-F015A is placed to open position. This will clear CS A Disch Press High alarm & return 2E21-R600A to normal.
* IAW ARP 601-328, may perform the following:
BOP  IAW ARP 601-328, may perform the following:
* Slightly opens 2E21-F015A to lower CS Discharge pressure
Slightly opens 2E21
* Confirms 601-328 clears BOP
-F015A to lower CS Discharge pressure Confirms 601
* When pressure is approximately 100 psig, closes 2E21-F015A.
-328 clears When pressure is approximately 100 psig, closes 2E21
* If CORE SPRAY A JOCKEY PUMP SYS WATER LEVEL LOW, (601-303), is received directs an SO to vent the A Loop of Core Spray IAW 34SV-SUV-017-2.
-F015A. If CORE SPRAY A JOCKEY PUMP SYS WATER LEVEL LOW, (601-303), is received directs an SO to vent the "A" Loop of Core Spray IAW 34SV
* Monitors Core Spray A Loop pressure for subsequent increases.
-SUV-017-2. Monitors Core Spray A Loop pressure for subsequent increases.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       3                         Page 6 of 27 Event
9-04 Event No.:
3 Page 6 of 27 Event


== Description:==
== Description:==
2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
Time      Position  Applicant's Actions or Behavior NOTE:      If pressure is NOT relieved, then a follow-up question on PCIV leakage TS 3.6.1.3.D may be appropriate.
NOTE: If pressure IS relieved on Core Spray Loop A, and pressure is NOT monitored, then a follow-up question on a high pressure condition of the inner system piping may be appropriate.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.
Appendix D                         Required Operator Actions                 Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:     4                       Page 7 of 27 Event
Time Position Applicant's Actions or Behavior NOTE: If pressure is NOT relieved, then a follow
-up question on PCIV leakage TS 3.6.1.3.D may be appropriate.
NOTE: If pressure IS relieved on Core Spray Loop A
, and pressure is NOT monitored, then a follow
-up question on a high pressure condition of the inner system piping may be appropriate
. Simulator Operator, at the Chief Examiners direction, PROCEEDS to the nex t event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
4 Page 7 of 27 Event


== Description:==
== Description:==
CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
Time      Position  Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator ENTERS (RB-4) 10 Min mf60311308, CRD Pump A Suction Filter Diff Press Hi, alarm.
* Receives CRD PUMP A SUCTION FILTER DIFF PRESS HIGH, (603-120), alarm.
ATC
* Confirms CRD system flow is < 59 gpm.
* Dispatches SO locally to check 2C11-dPIS-N015A indicates higher than 9.0 psi Simulator Operator, AFTER 3 minutes from being dispatched, report to the SRO/ATC, as an SO, that 2C11-dPIS-N015A indicates 12.0 psi.
Simulator Operator, AFTER giving report to SRO/ATC, IF SRO directs shifting CRD suction filters INSTEAD of swapping CRD pumps, THEN as Shift Manager, DIRECT the SRO to swap CRD pumps.
* Dispatches Maintenance to investigate 2A CRD Suction Filter dP high.
SRO
* After SO report, directs ATC to shift CRD pumps IAW 34SO-C11-005-2.


CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
Appendix D                         Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:         4                       Page 8 of 27 Event
Time Position Applicant's Actions or Behavior 10 Min  At the Chief Examiner's direction, Simulator Operator ENTERS (RB-4) mf60311308
, CRD Pump A Suction Filter Diff Press Hi, alarm. ATC  Receives CRD PUMP A SUCTION FILTER DIFF PRESS HIGH,  (603-120), alarm.
Confirms CRD system flow is
< 59 gpm. Dispatches SO locally to check 2C11
-dPIS-N015A indicates higher than 9.0 psi Simulator Operator, AFTER 3 minutes from being dispatched, report to the SRO/ATC, as an SO, that 2C11-dPIS-N015A indicates 12.0 psi. Simulator Operator, AFTER giving report to SRO/ATC, IF SRO directs shifting CRD suction filters INSTEAD of swapping CRD pumps, THEN as Shift Manager, DIRECT the SRO to swap CRD pumps.
SRO  Dispatches Maintenance to investigate 2A CRD Suction Filter dP high.
After SO report, directs ATC to shift CRD pumps IAW 34SO
-C11-005-2.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
4 Page 8 of 27 Event


== Description:==
== Description:==
CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
Time Position Applicant's Actions or Behavior NOTE: The ATC may direct the CRD pump room coolers to be swapped or may elect to leave the 2T41
Time     Position Applicant's Actions or Behavior NOTE:       The ATC may direct the CRD pump room coolers to be swapped or may elect to leave the 2T41-B001B cooler in service. Both are acceptable.
-B001B cooler in service. Both are acceptable.
Simulator Operator, After being dispatched to confirm valves listed in step 7.1.3.1.2 are open, report valves are open.
Simulator Operator, After being dispatched to confirm valves listed in step 7.1.3.1.2 are open, report valves are open.
ATC  IAW 34SO-C11-005-2, 7.1.3 , Shifting CRD Pumps, performs the following:
* IAW 34SO-C11-005-2, 7.1.3, Shifting CRD Pumps, performs the following:
Dispatches SO to confirm cooling water valves listed in step 7.1.3.1.2 are open. Confirm s a CRD Room Cooler is in operation per 34SO
* Dispatches SO to confirm cooling water valves listed in step 7.1.3.1.2 are open.
-T41-002-2, CRD Pump Room Ventilation System by performing the following:
* Confirms a CRD Room Cooler is in operation per 34SO-T41-002-2, CRD Pump Room Ventilation System by performing the following:
Confirms 2T41
* Confirms 2T41-B001B is in Run (may direct BOP to confirm)
-B001B is in Run (may direct BOP to confirm)
ATC OR
OR Places control switch for 2T41
* Places control switch for 2T41-B001A, in Run (P657)
-B001A, in Run (P657)
(may direct BOP to perform).
* Places 2T41-B001B, CRD Pump Room Cooler, in Off (P654)
(may direct BOP to perform).
(may direct BOP to perform).
Places 2T41
* Places 2T41-B001B, CRD Pump Room Cooler, in Auto (P654)
-B001B, CRD Pump Room Cooler, in Off (P654)
(may direct BOP to perform).
(may direct BOP to perform).
Places 2T41
-B001B, CRD Pump Room Cooler, in Auto (P654) (may direct BOP to perform).


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                         Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       4                         Page 9 of 27 Event
9-04 Event No.:
4 Page 9 of 27 Event


== Description:==
== Description:==
CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.
Time Position Applicant's Actions or Behavior Simulator Operator, when dispatched to open the below valves and to vent the 2B CRD pump, wait 3 minutes and notify the ATC the below valves are open and the 2B CRD pump has been vented and the vent valves are closed. If asked, INFORM the operator 2C11
Time     Position Applicant's Actions or Behavior Simulator Operator, when dispatched to open the below valves and to vent the 2B CRD pump, wait 3 minutes and notify the ATC the below valves are open and the 2B CRD pump has been vented and the vent valves are closed. If asked, INFORM the operator 2C11-F006 is closed.
-F006 is closed.
Also ENSURE Event Trigger EGC11-5 DELETES 2A CRD Suction Filter dP High alarm when 2A CRD pump is secured.
Also ENSURE Event Trigger EGC11-5 DELETES 2A CRD Suction Filter dP High alarm when 2A CRD pump is secured. ATC  Dispatches SO to confirm open the following valves and to vent the 2B CRD pump: 2C11-F118B, CRD Pump 2B Suction Valve 2C11-F114B, Suction Filter 2B Outlet Isolation 2C11-F115B, Suction Filter 2B Inlet Isolation Starts 2C11-C001B, 2B CRD Pump, at P603.
* Dispatches SO to confirm open the following valves and to vent the 2B CRD pump:
Confirm s flow control valve responds properly by controlling system flow between 30 gpm to 50 gpm
* 2C11-F118B, CRD Pump 2B Suction Valve
. Stops 2C11
* 2C11-F114B, Suction Filter 2B Outlet Isolation
-C001A, 2A CRD Pump, at P603.
* 2C11-F115B, Suction Filter 2B Inlet Isolation
Dispatches SO to confirm closed 2C11
* Starts 2C11-C001B, 2B CRD Pump, at P603.
-F117, CRD Suction Crosstie
* Confirms flow control valve responds properly by controlling system flow ATC            between 30 gpm to 50 gpm.
. Confirms system parameters are in their normal ranges per NOTE in System Startup section of 34SO
* Stops 2C11-C001A, 2A CRD Pump, at P603.
-C11-005-2. May receive MULTIPOINT TEMP RCDR 2T4 1-R6 20 TEMP HIGH, (65 4-0 04). This is expected for this plant condition and will subsequently clear.           SIMULATOR OPERATOR; At Chief Examiners direction, PROCEEDS to the next event.
* Dispatches SO to confirm closed 2C11-F117, CRD Suction Crosstie.
* Confirms system parameters are in their normal ranges per NOTE in System Startup section of 34SO-C11-005-2.
* May receive MULTIPOINT TEMP RCDR 2T41-R620 TEMP HIGH, (654-004). This is expected for this plant condition and will subsequently clear.
SIMULATOR OPERATOR; At Chief Examiners direction, PROCEEDS to the next event.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:       5                       Page 10 of 27 Event
9-04 Event No.:
5 Page 10 of 27 Event


== Description:==
== Description:==
RCIC Room fire.
Time      Position  Applicant's Actions or Behavior Simulator Operator 11                With Chief Examiners direction, NOTIFY the Shift Supervisor, as the SO on Mins              rounds, that smoke is coming from the Unit 2 RCIC room and you cannot see what is actually burning. You are leaving the area.
* Directs BOP to enter 34AB-X43-001-2, Fire Procedure and make the SRO announcement.
* Enters 34AB-X43-001-2, Fire Procedure and performs the following:
* Sounds the fire alarm (SIREN) over the plant PA system, (repeats 2 times - may get U1 operator to handle repeats).
BOP
* Notifies Rad Waste Control room that Reactor Building floor drain sump pumps are in Automatic.
* Notifies Radiation Protection to respond to the fire area.
* Transitions to section 8.0 for Fire in Reactor Bldg.
* Stops the following equipment at Panels 2H11-P654 & P657:
* 2T41-C001A, Rx Bldg Supply Fan.
* 2T41-C001B, Rx Bldg Supply Fan.
* 2T41-C007A, Rx Bldg Exhaust Fan.
* 2T41-C007B, Rx Bldg Exhaust Fan.
* 2T41-C002A, Refuel Flr Vent Supply Fan.
BOP
* 2T41-C002B, Refuel Flr Vent Supply Fan.
* 2T41-C005A, Refuel Flr Vent Exh Fan.
* 2T41-C005B, Refuel Flr Vent Exh Fan.
* Acknowledges annunciators at Panels 2H11-P654 & P657:
* REFUELING FLOOR OUTSIDE AIR DIFF PRESS LOW, (657-001)
* RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW, (654-001)


RCIC Room fire.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:         5                       Page 11 of 27 Event
Time Position Applicant's Actions or Behavior 11 Mins  Simulator Operator With Chief Examiner's direction, NOTIFY the Shift Supervisor, as the SO on rounds, that smoke is coming from the Unit 2 RCIC room and you cannot see what is actually burning. You are leaving the area.
SRO  Directs BOP to enter 34AB
-X43-001-2, 'Fire Procedure' and make the announcement.
BOP  Enters 34AB
-X43-001-2, Fire Procedure and performs the following:
Sounds the fire alarm (SIREN) over the plant PA system,  (repeats 2 times
- may get U1 operator to handle repeats)
. Notifies Rad Waste Control room that Reactor Building floor drain sump pumps are in Automatic
. Notifies Radiation Protection to respond to the fire area
. BOP  Transitions to section 8.0 for Fire in 'Reactor Bldg.'
Stops the following equipment at Panels 2H11
-P654 & P657:
2T41-C001A, Rx Bldg Supply Fan.
2T41-C001B, Rx Bldg Supply Fan.
2T41-C007A, Rx Bldg Exhaust Fan.
2T41-C007B, Rx Bldg Exhaust Fan.
2T41-C002A, Refuel Flr Vent Supply Fan.
2T41-C002B, Refuel Flr Vent Supply Fan.
2T41-C005A, Refuel Flr Vent Exh Fan.
2T41-C005B, Refuel Flr Vent Exh Fan.
Acknowledges annunciators at Panels 2H11
-P654 & P657:
REFUELING FLOOR OUTSIDE AIR DIFF PRESS LOW,  (657-001)  RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW, (654
-001)
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
5 Page 11 of 27 Event


== Description:==
== Description:==
RCIC Room fire.
Time      Position  Applicant's Actions or Behavior
* Transitions to section 8.3 for Fire in North Half of Reactor Bldg below 185 ft.
* Transitions to section 8.3.4 for Fire in RCIC Corner Room
* Places 2T41-B004A RCIC Pump Rm Cooler in Off, P657.
BOP
* Places 2T41-B004B RCIC Pump Rm Cooler in Off, P654.
* Closes the following RCIC Valves on P602
* 2E51-F007
* 2E51-F008 Simulator Operator, ONCE the above RCIC valves are closed, NOTIFY the Shift Supervisor that the fire in the RCIC room is OUT. Various RCIC components are severely damaged. Ventilation can be restored to normal EXCEPT for the RCIC Room Coolers.
* Announces to the crew the fire is out.
* Refers to TS for RCIC inoperability;
* 3.5 ECCS and RCIC System
* 3.5.3 RCIC System SRO            Enters a 1 hour RAS per TS 3.5.3.A.1 to verify by admin means HPCI is operable and per TS 3.5.3.A.2 to restore RCIC to operable status within 14 days.
* As time allows, Refers to TRM 3.7.2.D.1, ECCS and RCIC Room Coolers and immediately declares RCIC INOP.
* Directs BOP to start Rx Bldg Ventilation System and RF Floor Ventilation SRO System.


RCIC Room fire.
Appendix D                     Required Operator Actions               Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:     5                     Page 12 of 27 Event
Time Position Applicant's Actions or Behavior BOP  Transitions to section 8.3 for Fire in 'North Half of Reactor Bldg below 185 ft
.'  Transitions to section 8.
3.4 for Fire in 'RCIC Corner Room'  Places 2T41
-B004A RCIC Pump Rm Cooler in Off, P657.
Places 2T41
-B004B RCIC Pump Rm Cooler in Off, P654.
Closes the following RCIC Valves on P602 2E51-F007  2E51-F008        Simulator Operator , ONCE the above RCIC valves are closed, NOTIFY the Shift Supervisor that the fire in the RCIC room is OUT. Various RCIC components are severely damaged.
Ventilation can be restored to normal EXCEPT for the RCIC Room Coolers
.        SRO  Announces to the crew the fire is out.
Refers to TS for RCIC inoperability; 3.5 ECCS and RCIC System 3.5.3 RCIC System Enters a 1 hour RAS per TS 3.5.3.A.1 to verify by admin means HPCI is operable and per TS 3.5.3.A.2 to restore RCIC to operable status within 14 days.
As time allows, Refer s to TRM 3.7.2.D.1, ECCS and RCIC Room Coolers and immediately declares RCIC INOP.
SRO  Directs BOP to start Rx Bldg Ventilation System and RF Floor Ventilation System.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
5 Page 12 of 27 Event


== Description:==
== Description:==
RCIC Room fire.
Time      Position  Applicant's Actions or Behavior
* Starts Rx Bldg Ventilation IAW 34SO-T41-005-2, Section 7.1
* Momentarily Depresses the following pushbuttons:
BOP
* 2T41-SR1, Rx Bldg Supply Fans Reset.
* 2T41-SR3, Rx Bldg Recirc Fan 2T41-B017 Reset at 2H11-P657.
* 2T41-D005, Reactor Building Filter, Deluge reset at 2H11-P657.
* Requests Unit 1 operator to depress:
* 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr Reset A pushbutton, at BOP          1H11-P657.
* 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr reset B pushbutton, at 1H11-P654.
* Confirms OPEN the following dampers:
* 2T41-F028, Rx Bldg Vent Filter D005 Inlet Damper at 2H11-P657.
* 2T41-F044A, Rx Bldg Inboard Isol Dampers Inaccessible Areas Exhaust Fans Disch at 2H11-P657.
* 2T41-F044B, Rx Bldg Outboard Isol Dampers Inaccessible Areas BOP Exhaust Fans Disch at 2H11-P654.
* Places in RUN 2T41-C007A, Rx Bldg Vent Exhaust Fan at 2H11-P657.
* Places in STBY 2T41-C007B, Rx Bldg Vent Exhaust Fan at 2H11-P657.
* Confirms:
* in RUN 2T41-B017, Fan 1(Fan 2) Rx Bldg Recirc at 2H11-P657.
* in STBY 2T41-B017, Fan 2(Fan 1) Rx Bldg Recirc at 2H11-P657.
BOP
* OPEN/OPEN 2T41-F011A, Rx Bldg Inboard Isol Dampers Supply Fans Disch at 2H11-P657.
* OPEN/OPEN 2T41-F011B, Rx Bldg Outboard Isol Dampers Supply Fans Disch, at 2H11-P654.


RCIC Room fire.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:       5                       Page 13 of 27 Event
Time Position Applicant's Actions or Behavior BOP  Starts Rx Bldg Ventilation IAW 34SO
-T41-005-2, Section 7.1 Momentarily Depresses the following pushbuttons:
2T41-SR1, Rx Bldg Supply Fans Reset.
2T41-SR3, Rx Bldg Recirc Fan 2T41
-B017 Reset at 2H11
-P657. 2T41-D005, Reactor Building Filter, Deluge reset at 2H11
-P657.        BOP  Requests Unit 1 operator to depress:
1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr Reset A pushbutton, at 1H11-P657. 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr reset B pushbutton, at 1H11-P654.        BOP  Confirms OPEN the following dampers:
2T41-F028, Rx Bldg Vent Filter D005 Inlet Damper at 2H11
-P657. 2T41-F044A, Rx Bldg Inboard Isol Dampers Inaccessible Areas Exhaust Fans Disch at 2H11
-P657. 2T41-F044B, Rx Bldg Outboard Isol Dampers Inaccessible Areas Exhaust Fans Disch at 2H11
-P654. Place s in RUN 2T41
-C007 A, Rx Bldg Vent Exhaust Fan at  2H11-P657. Place s in STBY 2T41
-C007 B, Rx Bldg Vent Exhaust Fan at  2H11-P657.        BOP  Confirms:  in RUN 2T41
-B017, Fan 1(Fan 2) Rx Bldg Recirc at 2H11
-P657. in STBY 2T41
-B017, Fan 2(Fan 1) Rx Bldg Recirc at 2H11
-P657. OPEN/OPEN 2T41
-F011A, Rx Bldg Inboard Isol Dampers Supply Fans Disch at 2H11
-P657. OPEN/OPEN 2T41
-F011B, Rx Bldg Outboard Isol Dampers Supply Fans Disch, at 2H11
-P654.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
5 Page 13 of 27 Event


== Description:==
== Description:==
RCIC Room fire.
Time      Position  Applicant's Actions or Behavior
* Aligns fan in:
* RUN 2T41-C001A OR 2T41-C001B, Rx Bldg Supply Fan.
* STBY 2T41-C001B OR 2T41-C001A, Rx Bldg Supply Fan.
BOP
* Verifies Rx Bldg Vent Exhaust Flow approximately 6.5 KCFM as indicated by the green pen on 2T41-R618 located on 2H11-P657.
* Verifies Rx Bldg Vent Supply Flow approximately 5.3 KCFM as indicated by the red pen on 2T41-R618, flow recorder, located on 2H11-P657.
* Verifies flow is maintaining 0.25 inches water pressure on BOP        2T46-DPR-R604A&B.
* Sends SO to verify setpoints of local temperature controllers.
* Verifies in RUN fan:
* 2T41-B007, Rx Bldg Cooler Working Floor EL 130 North
* 2T41-B008, Rx Bldg Cooler Working Floor EL 130 South
* 2T41-B026, Rx Bldg Primary Cooler Mn Steam Pipe Chase
* 2T41-B010, Rx Bldg Cooler Equip Room EL 164
* 2T41-B011, Rx Bldg Cooler Operating Floor EL 185
* 2T41-B014, Rx Bldg Cooler RWCU Pmp/Hx EL 158
* 2T41-B015, Rx Bldg Cooler Operating Floor EL 185
* 2T41-B016, Rx Bldg Cooler Working Floor EL 203
* Verifies in AUTO 2T41-B009, Rx Bldg Secondary Cooler Mn. Steam Pipe Chase.
Starts RF Floor Ventilation IAW 34SO-T41-006-2, Section 7.1
* Requests Unit 1 operator to depress:
* 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr Reset A pushbutton, at 1H11-BOP P657.
* 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr reset B pushbutton, at 1H11-P654.


RCIC Room fire.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:       5                     Page 14 of 27 Event
Time Position Applicant's Actions or Behavior BOP  Aligns fan in:
RUN 2T41-C001A OR 2T41
-C001B, Rx Bldg Supply Fan.
STBY 2T41-C001B OR 2T41
-C001A, Rx Bldg Supply Fan.
Verifies Rx Bldg Vent Exhaust Flow approximately 6.5 KCFM as indicated by the green pen on 2T41
-R618 located on 2H11-P657. Verifies Rx Bldg Vent Supply Flow approximately 5.3 KCFM as indicated by the red pen on 2T41
-R618, flow recorder, located on 2H11
-P657.        BOP  Verifies flow is maintaining 0.25 inches water pressure on 2T46-DPR-R604A&B. Sends SO to verify setpoints of local temperature controllers.
Verifies in RUN fan:
2T41-B007, Rx Bldg Cooler Working Floor EL 130 North 2T41-B008, Rx Bldg Cooler Working Floor EL 130 South 2T41-B026, Rx Bldg Primary Cooler Mn Steam Pipe Chase 2T41-B010, Rx Bldg Cooler Equip Room EL 164 2T41-B011, Rx Bldg Cooler Operating Floor EL 185 2T41-B014, Rx Bldg Cooler RWCU Pmp/Hx EL 158 2T41-B015, Rx Bldg Cooler Operating Floor EL 185 2T41-B016, Rx Bldg Cooler Working Floor EL 203 Verifies in AUTO 2T41
-B009, Rx Bldg Secondary Cooler Mn. Steam Pipe Chase.          BOP Starts RF Floor Ventilation IAW 34SO
-T41-006-2, Section 7.1 Requests Unit 1 operator to depress:
1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr Reset A pushbutton, at 1H11
-
P657. 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr reset B pushbutton, at 1H11
-P654.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
5 Page 14 of 27 Event


== Description:==
== Description:==
RCIC Room fire.
Time      Position  Applicant's Actions or Behavior
* Momentarily Depresses the following pushbuttons:
* 2T41-SR2, RF Floor Vent Reset.
BOP
* 2T41-PB2, Refueling Floor Exh Fil Train 2T41-D007, Deluge reset
* 2T41-PB3, Refueling Floor Exh Fil Train 2T41-D008, Deluge reset
* Dispatches SO to perform steps 7.1.5 through 7.1.9.
* Confirms OPEN 2T41-F004A, Spent Fuel Pool Area Damper
* OPENS 2T41-F004C, Refuel Floor Area Damper.
* Confirms OPEN the following dampers:
BOP
* 2T41-F023A, Flr Isol Dmprs Exhaust Fans Suction, at 2H11-P657.
* 2T41-F023B, Flr Isol Dmprs Exhaust Fans Suction, at 2H11-P654.
* 2T41-F003A, Refuel Flr Isol Dmprs Supply Fans Disch, at 2H11-P657.
* 2T41-F003B, Refuel Flr Supply Fans Disch Outboard Isol Damper, at 2H11-P654.
* Places in RUN 2T41-C005A, Refuel Flr Vent Exh Fan at 2H11-P657.
* Places in RUN 2T41-C002A, Refuel Flr Vent Supply Fan at 2H11-P657.
* Places in STBY 2T41-C005B, Refuel Flr Vent Exh Fan at 2H11-P657.
* Places in STBY 2T41-C002B, Refuel Flr Vent Supply Fan at BOP 2H11-P657.
* Verifies RF Vent Exhaust Flow approximately 30.0 KCFM as indicated by the purple pen on 2T41-R618 located on 2H11-P657.
* Verifies RF Vent Supply Flow approximately 5.3 KCFM as indicated by the blue pen on 2T41-R618, flow recorder, located on 2H11-P657.
* Verifies flow is maintaining 0.25 inches water pressure on 2T46-DPR-R604A&B.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


RCIC Room fire.
Appendix D                       Required Operator Actions                       Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       6                       Page 15 of 27 Event
Time Position Applicant's Actions or Behavior BOP  Momentarily Depresses the following pushbuttons:
2T41-SR 2 , R F Floor Vent Reset. 2T41-PB2, Refueling Floor Exh Fil Train 2T41
-D007, Deluge reset 2T41-PB 3, Refueling Floor Exh Fil Train 2T41
-D00 8, Deluge reset  BOP  Dispatches SO to perform steps 7.1.5 through 7.1.9.
Confirms OPEN 2T41
-F004A, Spent Fuel Pool Area Damper OPENS 2T41
-F004C, Refuel Floor Area Damper
. Confirms OPEN the following dampers
:  2T41-F023A, Flr Isol Dmprs Exhaust Fans Suction, at 2H11-P65 7. 2T41-F023B, Flr Isol Dmprs Exhaust Fans Suction, at 2H11
-P654. 2T41-F003A, Refuel Flr Isol Dmprs Supply Fans Disch ,  at 2H11-P657. 2T41-F003B, Refuel Flr Supply Fans Disch Outboard Isol Damper, at 2H11-P654.        BOP  Places in RUN 2T41
-C005A, Refuel Flr Vent Exh Fan at 2H11-P657. Places in RUN 2T41
-C002A, Refuel Flr Vent Supply Fan at 2H11-P657. Places in STBY 2T41
-C005B, Refuel Flr Vent Exh Fan at 2H11-P657. Places in STBY 2T41
-C002B, Refuel Flr Vent Supply Fan at 2H11-P657. Verifies RF Vent Exhaust Flow approximately 30.0 KCFM as indicated by the purple pen on 2T41
-R618 located on 2H11
-P657. Verifies RF Vent Supply Flow approximately 5.3 KCFM as indicated by the blue pen on 2T41
-R618, flow recorder, located on 2H11
-P657. Verifies flow is maintaining 0.25 inches water pressure on 2T46-DPR-R604A&B.            Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
6 Page 15 of 27 Event


== Description:==
== Description:==
ADS Inadvertent initiation/Inhibit used.
Time      Position  Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator, phone the BOP and 10                instruct the BOP operator to stay on the line until told to hang up, THEN Mins enters (RB-6) malfunction mfB21_131 Inadvertent ADS Initiation.
* Identifies ADS is about to initiate and observe the following alarms:
ALL
* AUTO BLOW DOWN TIMERS INITIATED, (602-306)
* AUTO BLOW DOWN RELAYS ENERGIZED, (602-318)
ATC
* Acknowledges the alarms and reports them to the SRO.
* May observe the ADS timer on SPDS begin counting down.
* Directs ATC to enter the following:
SRO
* AUTO BLOW DOWN TIMERS INITIATED, (602-306)
* AUTO BLOW DOWN RELAYS ENERGIZED, (602-318)
* 34AB-E10-001-2, Inadvertent Initiation of ECCS/RCIC NOTE:      The SRO may direct the ATC to inhibit ADS prior to pulling the 34AB-E10-001-2, Inadvertent Initiation of ECCS/RCIC.
* Enters 34AB-E10-001-2
* Monitors plant parameters to determine extent of ECCS/RCIC ATC              actuations.
* At SRO direction, inhibits ADS using 2B21C-S7A & S7B, ADS Auto Logic Inhibit Switches, on 2H11-P602.


ADS Inadvertent initiation/Inhibit used.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       6                     Page 16 of 27 Event
Time Position Applicant's Actions or Behavior 10 Mins  At the Chief Examiner's direction, Simulator Operator, phone the BOP and instruct the BOP operator to stay on the line until told to hang up, THEN enters (RB-6) malfunction mfB21_131 Inadvertent ADS Initiation.
ALL  Identifies ADS is about to initiate and observe the following alarms:
AUTO BLOW DOWN TIMERS INITIATED, (602
-306)  AUTO BLOW DOWN RELAYS ENERGIZED, (602
-318)          ATC  Acknowledges the alarms and reports them to the SRO.
SRO  May observe the ADS timer on SPDS begin counting down.
Directs ATC to enter the following:
AUTO BLOW DOWN TIMERS INITIATED, (602
-30 6)  AUTO BLOW DOWN RELAYS ENERGIZED, (602
-318)  34AB-E10-001-2, Inadvertent Initiation of ECCS/RCIC NOTE: The SRO may direct the ATC to inhibit ADS prior to pulling the 34AB-E10-001-2, "Inadvertent Initiation of ECCS/RCIC."
ATC  Enters 34AB
-E10-001-2    Monitors plant parameters to determine extent of ECCS/RCIC actuations.
At S RO direction, inhibits ADS using 2B21C
-S7A & S7B,  ADS Auto Logic Inhibit Switches, on 2H11
-P602.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
6 Page 16 of 27 Event


== Description:==
== Description:==
ADS Inadvertent initiation/Inhibit used.
ADS Inadvertent initiation/Inhibit used.
Time Position Applicant's Actions or Behavior SRO Directs ATC to inhibit ADS ATC  If ADS Timer on SPDS is approaching "Zero" (0), the ATC may depress the ADS Logic Timer pushbuttons prior to inhibiting ADS.
Time     Position Applicant's Actions or Behavior SRO
Places ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100&deg;F cooldown rate
* Directs ATC to inhibit ADS
. (Critical Task
* If ADS Timer on SPDS is approaching Zero (0), the ATC may depress the ADS Logic Timer pushbuttons prior to inhibiting ADS.
)          SRO Dispatches Maintenance to determine problem with ADS logic
ATC
.        NOTE: The SRO may enter TS 3.3.5.1. F & G and declare all ADS valves inoperable if the ADS instrumentation is NOT repaired in one hour. Without more information on failed instruments, a follow
* Places ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100&deg;F cooldown rate. (Critical Task)
-up question to the SRO may be required to determin e this TS call. SRO  While determining the extent of ADS failures, enters TS 3.3.5.1
SRO
-1 Item 4 and:   Enters TS 3.5.1.E and declares ALL ADS valves inop immediately.
* Dispatches Maintenance to determine problem with ADS logic.
With all ADS valves inop, be in Mode 3 in 12 hours and <150 psig Rx press in 36 hours.
NOTE:     The SRO may enter TS 3.3.5.1. F & G and declare all ADS valves inoperable if the ADS instrumentation is NOT repaired in one hour.
Without more information on failed instruments, a follow-up question to the SRO may be required to determine this TS call.
* While determining the extent of ADS failures, enters TS 3.3.5.1-1 Item 4 and:
SRO
* Enters TS 3.5.1.E and declares ALL ADS valves inop immediately.
* With all ADS valves inop, be in Mode 3 in 12 hours and <150 psig Rx press in 36 hours.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
 
9-04 Event No.:
Appendix D                     Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:     7                       Page 17 of 27 Event
7 Page 17 of 27 Event


== Description:==
== Description:==
Unisolable HPCI Steam leak in the Reactor Building.
Time      Position  Applicant's Actions or Behavior 10                At the Chief Examiners direction, Simulator operator, ENTER (RB-7)
Min                mfE41_249, HPCI Steam Line, break 20/1.
* Receives the following annunciators (~40 seconds):
* PANEL 2H11-P654 SYSTEM TROUBLE, (650-214)
* DRYWELL/TORUS RCDR R627 TEMP HIGH, (650-204)
* MULTIPOINT TEMP RCDR 2T41-R620 TEMP HIGH, (654-004)
* MULTIPOINT TEMP RCDR 2T41-R626 TEMP HIGH, (657-025)
ALL
* Receives the following ~60 seconds later:
* LEAK DET DIFF TEMP HIGH, (601-321)
* HPCI TURBINE TRIP SOLENOID ENERGIZED, (601-109)
* HPCI ISOLATION TRIP LOGIC A INITIATED, (601-115)
* HPCI ISOL TIMER INITIATED, (601-105)
* HPCI ISOLATION TRIP LOGIC B INITIATED, (601-121)
* Orders BOP to evaluate leak detection alarms on 2H11-P601.
* Orders HPCI to be isolated.
SRO
* Orders BOP to evacuate the Reactor Building.
* May notify Maintenance for assistance in closing HPCI valves if ATC/BOP does NOT.
* Responds to HPCI alarms
* Observes HPCI Isolation valves have failed to close.
* Places 2E41-F002, HPCI Isolation valve switch to Close.
ATC/BOP
* Places 2E41-F003, HPCI Isolation valve switch to Close.
* Notifies SRO of HPCI valve failures.
* May notify Maintenance for assistance in closing HPCI valves if SRO does NOT.


Unisolable HPCI Steam leak in the Reactor Building
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:       7                       Page 18 of 27 Event
. Time Position Applicant's Actions or Behavior 10 Min  At the Chief Examiner's direction, Simulator operator, ENTER (RB-7) mfE41_249 , HPCI Steam Line, break 20/1.
ALL  Receives the following annunciator s (~40 seconds)
:  PANEL 2H11
-P654 SYSTEM TROUBLE, (650
-214)  DRYWELL/TORUS RCDR R627 TEMP HIGH, (650
-204)  MULTIPOINT TEMP RCDR 2T41
-R620 TEMP HIGH, (654
-004)  MULTIPOINT TEMP RCDR 2T41
-R626 TEMP HIGH, (657
-025)  Receives the following ~
60 seconds later:
LEAK DET DIFF TEMP HIGH, (6 01-321)  HPCI TURBINE TRIP SOLENOID ENERGIZED, (601
-109)  HPCI ISOLATION TRIP LOGIC A INITIATED, (601
-115)  HPCI ISOL TIMER INITIATED, (601
-105)  HPCI ISOLATION TRIP LOGIC B INITIATED, (601
-121)          SRO  Orders BOP to evaluate leak detection alarms on 2H11
-P601. Orders HPCI to be isolated.
Orders BOP to evacuate the Reactor Building
. May notify Maintenance for assistance in closing HPCI valves if ATC/BOP does NOT.          ATC/BOP  Responds to HPCI alarms Observes HPCI Isolation valves have failed to close.
Places 2E41
-F002, HPCI Isolation valve switch to Close.
Places 2E41
-F003, HPCI Isolation valve switch to Close.
Notifies SRO of HPCI valve failures.
May notify Maintenance for assistance in closing HPCI valves if SRO does NOT.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
7 Page 18 of 27 Event


== Description:==
== Description:==
Unisolable HPCI Steam leak in the Reactor Building.
Time      Position  Applicant's Actions or Behavior
* Respond to annunciator LEAK DET DIFF TEMP HIGH, (601-321).
* Addresses 2G31-R604 OR 2G31-R608 on 2H11-P614.
* Identifies the following points on R604 increasing:
* 109, HPCI EMER AREA CLR is ~115&deg;F
* 111, RCIC AREA CLR is ~ 89&deg;F
* 113, TORUS NW WALL is ~ 92&deg;F
* 114, TORUS SE WALL is ~ 118&deg;F
* 115, TORUS VENT AIR DIFF is ~ 12&deg;F
* 116, TORUS VENT AIR DIFF is ~ 38&deg;F
* 117, HPCI PIPE PEN RM ~ 135&deg;F BOP
* Identifies the following points on R608 increasing:
* 109, HPCI PMP RM is ~110&deg;F
* 110, HPCI EMER AREA CLR is ~ 110&deg;F
* 115, TORUS WEST WALL is ~ 95&deg;F
* 116, TORUS NE WALL is ~ 120&deg;F
* 117, TORUS VENT AIR DIFF is ~ 15&deg;F
* 118, TORUS VENT AIR DIFF is ~ 38&deg;F
* 121, HPCI PIPE PEN RM ~ 140&deg;F
* Reports temperatures to the SRO.
* Enters the SC flow chart.
* Progresses down each path.
* Proceeds down the SC/T path, directing:
* All available area coolers are operated SRO
* Operate the refueling floor ventilation
* Operate the reactor building ventilation
* Isolate all systems discharging into the area except those needed for ACC, shutdown the reactor, suppress a fire, maintain primary containment


Unisolable HPCI Steam leak in the Reactor Building
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:       7                         Page 19 of 27 Event
. Time Position Applicant's Actions or Behavior BOP  Respond to annunciator LEAK DET DIFF TEMP HIGH, (601-321). Addresses 2G31
-R604 OR 2G31
-R608 on 2H11
-P614. Identifies the following points on R604 increasing:
1 09 , HPCI EMER AREA CLR is ~115&deg;F  11 1 , RCIC AREA CLR is ~ 89&deg;F  113, TORUS NW WALL is ~
92&deg;F  114, TORUS SE WALL is ~
118&deg;F  115, TORUS VENT AIR DIFF is ~
12&deg;F  116, TORUS VENT AIR DIFF is ~
38&deg;F  117, HPCI PIPE PEN RM ~
135&deg;F  Identifies the following points on R608 increasing:
1 09 , HPCI PMP RM is ~110&deg;F  110, HPCI EMER AREA CLR is ~ 110&deg;F 115, TORUS WEST WALL is ~ 95&deg;F 116, TORUS NE WALL is ~ 120&deg;F 117, TORUS VENT AIR DIFF is ~ 15&deg;F 118, TORUS VENT AIR DIFF is ~
38&deg;F  121, HPCI PIPE PEN RM ~ 140&deg;F Reports temperatures to the SRO.
SRO  Enters the SC flow chart.
Progresses down each path.
Proceeds down the SC/T path, directing:
All available area coolers are operated Operate the refueling floor ventilation Operate the reactor building ventilation Isolate all systems discharging into the area except those needed for ACC, shutdown the reactor, suppress a fire, maintain primary containment
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
7 Page 19 of 27 Event


== Description:==
== Description:==
Unisolable HPCI Steam leak in the Reactor Building.
Time      Position  Applicant's Actions or Behavior
* Orders the reactor shutdown due to Max Safe operating temperatures or SRO          delta temps since a primary system (HPCI) is discharging into Secondary Containment.
* Assigns the ATC to perform RC-1.
* Assigns the BOP operator to perform RC-2 and RC-3.
SRO
* Enters 31EO-EOP-010-2, RC EOP flow chart if RWL decreases below 3 inches or if any area exceeds Max Safe.
* Directs RWL Band of 3 to 50 inches.
* Performs RC-1 consisting of:
* Inserts a manual scram.
* Places the mode switch to SHUTDOWN.
* Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
* Notifies SRO of rod position check.
ATC
* Places SDV isolation valve switch to "isolate" & confirms closed.
* If NOT tripped, places the Recirc pumps at minimum speed.
* Inserts SRMs and IRMs.
* Shifts recorders to read IRMS, when required.
* Ranges IRMS to bring reading on scale.
* Notifies the SRO when the above actions are complete.


Unisolable HPCI Steam leak in the Reactor Building
Appendix D                     Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:         7                     Page 20 of 27 Event
. Time Position Applicant's Actions or Behavior SRO  Orders the reactor shutdown due to Max Safe operating temperatures or delta temps since a primary syste m (HPCI) is discharging into Secondary Containment.
SRO  Assigns the ATC to perform RC
-1. Assigns the BOP operator to perform RC
-2 and RC-3. Enters 31EO
-EOP-010-2, RC EOP flow chart if RWL decreases below 3 inches or if any area exceeds Max Safe. Directs RWL Band of 3 to 50 inches.
ATC  Performs RC
-1 consisting of:
Inserts a manual scram.
Places the mode switch to SHUTDOWN. Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
Notifies SRO of rod position check.
Places SDV isolation valve switch to "isolate" & confirms closed.
If NOT tripped, places the Recirc pumps at minimum speed.
Inserts SRMs and IRMs.
Shifts recorders to read IRMS, when required.
Ranges IRMS to bring reading on scale.
Notifies the SRO when the above actions are complete.
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
7 Page 20 of 27 Event


== Description:==
== Description:==
Unisolable HPCI Steam leak in the Reactor Building.
Time      Position  Applicant's Actions or Behavior
* Performs RC-2 actions consisting of:
* Confirms proper Level Control response:
* Checks ECCS Injection Systems (will NOT be in service if RWL >-35 inches)
* Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value
* If Set down does NOT auto function, manually reduces FW Master BOP                Controller setpoint to approximately 9 inches.
* When feed flow is less than the capacity of the S/U level control valve
( 1.5 mlbm/hr), then:
* Confirms/Opens 2N21-F125.
* Confirms/places 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
* Closes 2N21-F110.
* If RFPTs are no longer available, will transition to CBPs.


Unisolable HPCI Steam leak in the Reactor Building
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:         7                       Page 21 of 27 Event
. Time Position Applicant's Actions or Behavior BOP  Performs RC
-2 actions consisting of:
Confirms proper Level Control response:
Checks ECCS Injection Systems (will NOT be in service if RWL >
-35 inches)
Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value If Set down does NOT auto function, manually reduces FW Master Controller setpoint to approximately 9 inches.
When feed flow is less than the capacity of the S/U level control valve  Confirms/Opens 2N21
-F125. Confirms/places 2C32
-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
Closes 2N21
-F110. If RFPTs are no longer available, will transition to CBPs.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
7 Page 21 of 27 Event


== Description:==
== Description:==
Unisolable HPCI Steam leak in the Reactor Building.
Time      Position  Applicant's Actions or Behavior
* Performs RC-3 consisting of:
* Monitoring RPV pressure.
* Confirms proper operation of pressure control system (TBV, LLS, etc.), at 2H11-P650 panel, by confirming TBVs are responding to control reactor pressure at the desired pressure setpoint.
* Maintains RPV pressure between 1074 and 800 psig until a different band is directed.
* Notifies SRO of pressure control system operation.
* If SRO orders a lower reactor pressure band, enters Attachment 11 of 34SO-N30-001-2, Main Turbine, or 34GO-OPS-013-2, Normal Plant Shutdown, and at the DEHC panel computer, performs ONE of the following:
: 1. Throttle Pressure Set
* Selects the Control  psi- load screen
* Selects the *Ramp Rate* button
* Enters a ramp rate
* Selects the *Pressure* button BOP
* Enters desired target pressure
: 2. Bypass Valve Jack Positioning
* Control BPV position by intermittently using the *Raise* /
                                      *Lower* buttons until BYPASS VALVE JACK STATUS changes to *ACTIVE* AND desired cooldown rate is established
* If SRO orders Anticipate Emergency Depress, then the operator will perform the following:
* At P650 HMI screen,
* Selects Control
* Selects Bypass Valve
* Inserts Ramp Rate of 100 then OK
* Inserts BPV position of 100 then OK
* Ensures Bypass Valve Jack Status is Active (controlling)
* Notifies SRO that Bypass Valves are opening NOTE:      Event 8 CRITICAL TASK will be considered MET if the reactor is depressurized through Anticipating Emergency Depress.
* May order a lower than 800 psig Reactor pressure band.
SRO
* May direct an operator to perform Rx Power, Level, and Pressure control, so that the other operator can address Secondary Containment parameters.


Unisolable HPCI Steam leak in the Reactor Building
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.:         8                         Page 22 of 27 Event
. Time Position Applicant's Actions or Behavior BOP  Performs RC
-3 consisting of:
Monitoring RPV pressure.
Confirms proper operation of pressure control system (TBV, LLS, etc.), at 2H11
-P650 panel, by confirming TBVs are responding to control reactor pressure at the desired pressure setpoint.
Maintains RPV pressure between 1074 and 800 psig until a different band is directed.
Notifies SRO of pressure control system operation.
If SRO orders a lower reactor pressure band, enters Attachment 11 of 34SO-N30-001-2, Main Turbine, or 34GO
-OPS-013-2, Normal Plant Shutdown, and at the DEHC panel computer, performs ONE of the following:
: 1. Throttle Pressure Set Selects the Control      psi- load  screen  Selects the  *Ramp Rate* butto n  Enters a ramp rate Selects the  *Pressure* button Enters desired target pressure
: 2. Bypass Valve Jack Positioning Control BPV position by intermittently using the  *Raise*  /  *Lower* buttons until BYPASS VALVE JACK STATUS changes to  *ACTIVE*  AND desired cooldown rate is established If SRO orders "Anticipate Emergency Depress, then the operator will perform the following:
At P650 HMI screen,  Selects "Control" Selects "Bypass Valve" Inserts "Ramp Rate" of 100 then OK Inserts BPV position of 100 then OK Ensures Bypass Valve Jack Status is Active (controlling)
Notifies SRO that Bypass Valves are opening NOTE: Event 8 CRITICAL TASK will be considered MET if the reactor is depressurized through Anticipating Emergency Depress.
SRO  May order a lower than 800 psig Reactor pressure band.
May direct an operator to perform Rx Power, Level, and Pressure control, so that the other operator can address Secondary Containment parameters.
 
Appendi x D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
8 Page 22 of 27 Event


== Description:==
== Description:==
Emergency Depress when Max Safe exceeded in more than one area.
Emergency Depress when Max Safe exceeded in more than one area.
Time Position Applicant's Actions or Behavior ATC  Provides periodic updates on temperature readings and delta temp readings to the SRO
Time     Position Applicant's Actions or Behavior
(~1 4 minutes). Reports R604 points 1 09 & 11 4 are above Max Safe.
* Provides periodic updates on temperature readings and delta temp readings to the SRO (~14 minutes).
Reports R608 points 1 09 & 1 16 are above Max Safe.
* Reports R604 points 109 & 114 are above Max Safe.
When a second temperature or delta temp exceeds Max Safe levels, informs the SRO.
ATC
SRO  May order a lower Reactor pressure band to reduce the driving head.
* Reports R608 points 109 & 116 are above Max Safe.
Transitions to CP
* When a second temperature or delta temp exceeds Max Safe levels, informs the SRO.
-1 and orders 7 ADS valves open for Emergency Depress.           ATC/BOP  Places the switches for 7 ADS valves in the open position.
* May order a lower Reactor pressure band to reduce the driving head.
(Critical Task  
SRO
- Open 7 SRVs when Max Safe exceeded in more than one area. Critical task is met when at least 5 SRVs have been opened)
* Transitions to CP-1 and orders 7 ADS valves open for Emergency Depress.
. This Critical task will be considered met if the reactor is depressurized through Anticipating Emergency Depress from Event 7
* Places the switches for 7 ADS valves in the open position.
. The amber lights for the SRVs will NOT illuminate if pressure has been reduced to below approximately 300 psig. In this case the operator must use 2H11
(Critical Task - Open 7 SRVs when Max Safe exceeded in more than one area. Critical task is met when at least 5 SRVs have been opened).
-P614 recorder indication to monitor tail pipe temperatures for the SRVs to verify the valves actually opened (Recorder 2B21
This Critical task will be considered met if the reactor is depressurized through Anticipating Emergency Depress from Event 7.
-R614). Depending on Reactor Water Level prior to opening ADS valves, RWL may swell to above 60 inches, requiring the operator to enter 34AB-C32-001-2, Reactor Water Level Above 60 inches.
* The amber lights for the SRVs will NOT illuminate if pressure has been reduced to below approximately 300 psig. In this case the ATC/BOP operator must use 2H11-P614 recorder indication to monitor tail pipe temperatures for the SRVs to verify the valves actually opened (Recorder 2B21-R614).
Operator secures all injection other than CRD.
* Depending on Reactor Water Level prior to opening ADS valves, RWL may swell to above 60 inches, requiring the operator to enter 34AB-C32-001-2, Reactor Water Level Above 60 inches.
* Operator secures all injection other than CRD.
Simulator Operator, the NEXT event will be activated as Reactor pressure decreases.
Simulator Operator, the NEXT event will be activated as Reactor pressure decreases.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:     9                       Page 23 of 27 Event
9-04 Event No.:
9 Page 23 of 27 Event


== Description:==
== Description:==
SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a Residual Heat Removal systems.
Time      Position  Applicant's Actions or Behavior Simulator Operator, At the Chief Examiners direction AND AFTER the ADS valves have been opened (Event 8); when Reactor pressure is < 500 psig, ENSURE ET-EGB21-5 INSERTS mfN21_99, SULCV fails closed.
(Critical Task) - Throttle open 2N21-F110 for vessel injection to maintain RWL greater than -185 inches.
If 2N21-F110 is NOT used, then a NEW Critical Task will be to align RHR/Core Spray systems for vessel injection to maintain RWL greater than
                    -185 inches.
EITHER IS ACCEPTABLE.
* The BOP recognizes the SULCV has failed closed.
* Performs ONE or MORE of the following to inject water into the reactor.
BOP
* Throttles open Condensate System, 2N21-F110, and injects water into the reactor (Critical Task).
NOTE: mfE11_202A (LOCA Signal failure) inserted at beginning.
BOP will start 2B Core Spray due to Event 3.
OR
* Starts 2B Core Spray Pump. (Critical Task)
* Confirm discharge pressure >265 psig.
* Confirm 2E21-F031B closes when flow >950 gpm.
* Confirm a CS and RHR room cooler automatically starts.
* When RPV pressure is <425 psig, throttles open 2E21-F005B.


SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a Residual Heat Removal systems. Time Position Applicant's Actions or Behavior Simulator Operator, At the Chief Examiner's direction AND AFTER the ADS valves have been opened (Event 8); when Reactor pressure is < 500 psig, ENSURE ET-EGB21-5 INSERTS mfN21_99, SULCV fails closed.    (Critical Task
Appendix D                     Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-04 Event No.:       9                       Page 24 of 27 Event
) - Throttle open 2N21
-F110 for vessel injection to maintain RWL greater than
-185 inches.
If 2N21-F110 is NOT used, then a NEW Critical Task will be to align RHR/Core Spray systems for vessel injection to maintain RWL greater than
-185 inches.
EITHER IS ACCEPTABLE.
BOP  The BOP recognizes the SULCV has failed closed.
Performs ONE or MORE of the following to inject water into the reactor.
Throttles open Condensate System, 2N21-F110, and injects water into the reactor (Critical Task). NOTE: mfE11_202A (LOCA Signal failure) inserted at beginning.
BOP will start 2B Core Spray due to Event 3. OR  Starts 2B Core Spray Pump.  (Critical Task
)  Confirm discharge pressure >265 psig.
Confirm 2E21
-F031B closes when flow >950 gpm.
Confirm a CS and RHR room cooler automatically starts.
When RPV pressure is <425 psig, throttles open 2E21
-F005B.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-04 Event No.:
9 Page 24 of 27 Event


== Description:==
== Description:==
SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a Residual Heat Removal systems.
Time      Position  Applicant's Actions or Behavior NOTE: mfE11_202B (LOCA Signal failure) inserted at beginning.
OR
* At panel 2H11-P601, Confirms the 4 RHR pumps did NOT auto start and ONLY 2 Core Spray pumps are running.
* Notifies SRO of RHR pump logic failure and starts (Critical Task) is met if one RHR pump is started) the 4 RHR pumps.
* When RPV pressure is <425 psig, throttles open 2E11-F015A (B).
* Reports SULCV problem to the SRO.
With Chief Examiners Permission, the Scenario will be terminated when reactor water is being controlled following the Emergency Depressurization, with reactor pressure below 50 psig or as directed by the Chief Examiner.
Page 25 of 27 Appendix D                                Scenario Outline                        Form ES-D-1 NRC FINAL Facility:    E. I Hatch              Scenario No.: 9-04    Op-Test No.:    2015-301 Examiners:                                      Operators:                                          SRO RO BOP Initiating Conditions:    Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service.
Turnover                  Reduce reactor power to 60% RTP for RFPT 2A removal. Leave RFPT 2A operating at ~1000 RPM.
Summary:
* Event 1: Reactivity: The ATC will reduce reactor power to ~60% RTP via Recirc to achieve
          <7 mlbm/hr for 2A RFPT removal from service.
* Event 2: Normal; After reactor power is reduced, the BOP will remove the 2A RFPT from service and leave rotating at approximately 1000 rpm.
* Event 3: Component/TS; 2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A control switch is placed to open, the valve breaker trips causing the 2A CS Loop to be inop.
* Event 4: Component; The CRD 2A pump experiences a Suction Filter dP High requiring swapping to standby pump IAW System Operating procedure.
* Event 5: Component/TS; RCIC Room fire.
* Event 6: Instrument/TS; The ADS System will experience an inadvertent initiation which will require the ATC to place the ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100&deg;F cooldown rate. (Critical Task) ADS will be inop.
* Event 7: Major; Unisolable HPCI Steam leak in Reactor Building requiring a Reactor Manual scram.
* Event 8: Major; Since a HPCI Group 3 signal failure exists an Emergency Depress when > Max Safe in more than one area. (Critical Task)
* Event 9: Component; SULCV fails closed. Core Spray & RHR Logic failure. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a RHR Systems. (Critical Task)


SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a Residual Heat Removal systems. Time Position Applicant's Actions or Behavior NOTE: mfE11_202B (LOCA Signal failure) inserted at beginning.
Page 26 of 27 Critical Tasks NRC FINAL Facility:    E. I Hatch            Scenario No.: 9-04      Op-Test No.:      2015-301 Critical Tasks
OR  At panel 2H11
* The ADS System will experience an inadvertent initiation which will require the ATC to place the ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100&deg;F cooldown rate. (Event 6)
-P601, Confirms the 4 RHR pumps did NOT auto start and ONLY 2 Core Spray pumps are running.
* Emergency Depress when > Max Safe in more than one area. (Event 8)
Notifies SRO of RHR pump logic failure and starts  (Critical Task
* SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a RHR Systems. (Event 9)
) is met if one RHR pump is started) the 4 RHR pumps.
ES 301-4 Attributes      Required    Actual                            Items
When RPV pressure is <425 psig, throttles open 2E11
: 1. Total Malfunctions          5-8        6        1. CS press high/breaker tripped (Event 3)
-F015A (B).
: 2. CRD 2A Suction Filter dP High (Event 4)
Reports SULCV problem to the S RO.                 With Chief Examiners Permission, the Scenario will be terminated when reactor water is being controlled following the Emergency Depressurization, with reactor pressure below 50 psig or as directed by the Chief Examiner.
: 3. RCIC Room fire. (Event 5)
: 4. ADS System inadvertent initiation (Event 6)
: 5. Unisolable HPCI Steam leak in RB (Event 7)
: 6. SULCV fails closed. Core Spray & RHR Logic failure (Event 9)
: 2. Malfunctions After          1-2         1        1. SULCV fails closed. Core Spray & RHR Logic EOP Entry                                            failure (Event 8)
: 3. Abnormal Events              2-4        3        1. RCIC Room fire. (Event 5)
: 2. ADS System inadvertent initiation (Event 6)
: 3. Unisolable HPCI Steam leak in RB (Event 7)
: 4. Major Transients            1-2        2        1. Unisolable HPCI Steam leak in RB (Event 7)
: 2. Emergency Depress when > one area Max Safe (Event 8)
: 5. EOPs entered,                1-2        2        1. 31EO-EOP-014-2. SC/RR (Event 7) requiring substantive                            2. 31EO-EOP-010-2, RC Non ATWS (Event 7) actions
: 6. EOPs contingencies          0-2        1        1. 31EO-EOP-015-2, CP-1 (Event 8) requiring substantive actions
: 7. Critical Tasks              2-3        3        1. ADS System inadvertent initiation (Event 6)
: 2. Emergency Depress when > one area Max Safe (Event 8)
: 3. SULCV fails closed. Core Spray & RHR Logic failure (Event 9)


Page 25 of 27 Appendix D Scenario Outline Form ES-D-1  NRC FINAL  Facility: E. I Hatch Scenario No.:
ILT 9 NRC FINAL Scenario 4 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions:
9-04 Op-Test No.: 2015-301  Examiners:
Activities in progress: Maintaining Rated Thermal Power UNIT 2 STATUS Unit 2 is operating at 65% RTP making preparations to remove Plant Conditions:
Operators:
2A RFPT from service.
SRO    RO    BOP  Initiating Conditions:
Protected Train:                                   EOOS:
Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service. Turnover Reduce reactor power to 60% RTP for RFPT 2A removal. Leave RFPT 2A operating at ~1000 RPM.
Division I                           Green                      Orange Division II                         Yellow                     Red Reduce reactor power to 60% RTP for RFPT 2A removal.
Summary:  Event 1:  Reactivity: The ATC will reduce reactor power to ~60% RTP via Recirc to achieve
Scheduled evolutions:
<7 mlbm/hr for 2A RFPT removal from service.
Event 2:  Normal; After reactor power is reduced, the BOP will remove the 2A RFPT from service and leave rotating at approximately 1000 rpm.
Event 3:  Component/TS; 2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A control switch is placed to open, the valve breaker trips causing the 2A CS Loop to be inop.
Event 4:  Component; The CRD 2A pump experiences a Suction Filter dP High requiring swapping to standby pump IAW System Operating procedure.
Event 5:  Component/TS; RCIC Room fire.
Event 6:  Instrument/TS; The ADS System will experience an inadvertent initiation which will require the ATC to place the ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100&deg;F cooldown rate.
(Critical Task
)  ADS will be inop.
Event 7:  Major; Unisolable HPCI Steam leak in Reactor Building requiring a Reactor Manual scram. Event 8:  Major; Since a HPCI Group 3 signal failure exists an Emergency Depress when > Max Safe in more than one area.
(Critical Task
)    Event 9:  Component; SULCV fails closed. Core Spray & RHR Logic failure. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a RHR Systems.  (Critical Task
)
Page 26 of 27 Critical Tasks NRC FINAL Facility: E. I Hatch Scenario No.:
9-04 Op-Test No.: 2015-301  Critical Tasks The ADS System will experience an inadvertent initiation which will require the ATC to place the ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100&deg;F cooldown rate.
(Event 6)    Emergency Depress when > Max Safe in more than one area.
(Event 8)    SULCV fails closed. RPV level will be controlled either by throttling open 2N21
-F110, or by using a Core Spray and/or a RHR Systems.  (Event 9)    ES 301-4 Attributes Required Actual Items 1. Total Malfunctions 5-8 6 1. CS press high/breaker tripped (Event 3) 2. CRD 2A Suction Filter dP High (Event 4) 3. RCIC Room fire.
(Event 5) 4. ADS System inadvertent initiation (Event 6) 5. Unisolable HPCI Steam leak in RB  (Event 7) 6. SULCV fails closed. Core Spray & RHR Logic failure  (Event 9) 2. Malfunctions After EOP Entry 1-2 1 1. SULCV fails closed. Core Spray & RHR Logic failure  (Event 8) 3. Abnormal Events 2-4 3 1. RCIC Room fire.
(Event 5) 2. ADS System inadvertent initiation (Event 6) 3. Unisolable HPCI Steam leak in RB  (Event 7) 4. Major Transients 1-2 2 1. Unisolable HPCI Steam leak in RB  (Event 7) 2. Emergency Depress when > one area Max Safe (Event 8) 5. EOPs entered, requiring substantive action s  1-2 2 1. 31EO-EOP-014-2. SC/RR  (Event 7) 2. 31EO-EOP-010-2, RC Non ATWS (Event 7) 6. EOPs contingencies requiring substantive actions 0-2 1 1. 31EO-EOP-015-2, CP-1  (Event 8) 7. Critical Tasks 2-3 3 1. ADS System inadvertent initiation (Event 6)  2. Emergency Depress when > one area Max Safe (Event 8) 3. SULCV fails closed. Core Spray & RHR Logic failure  (Event 9)
ILT 9 NRC FINAL Scenario 4 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Plant Conditions:
Unit 1 is operating at 100% power Activities in progress: Maintaining Rate d Thermal Power UNIT 2 STATUS Plant Conditions:
Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service.
Protected Train:
EOOS:   Division I Division II Green    Yellow   Orange  Red Scheduled evolutions
Reduce reactor power to 60% RTP for RFPT 2A removal.
Leave RFPT 2A operating at ~1000 RPM.
Leave RFPT 2A operating at ~1000 RPM.
Surveillances due this shift: None  Inop Equipment:
Surveillances due this None shift:
None Active tagouts
Inop Equipment:       None Active tagouts:       None Rod Configuration:     See RWM
: None Rod Configuration
 
: See RWM Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.:
Appendix D                               Scenario Outline                           Form ES-D-1 NRC FINAL Facility:   E. I Hatch             Scenario No.: 9-05       Op-Test No.:     2015-301 Examiners:                                     Operators:                                         SRO RO BOP Initial Conditions. Unit 2 is operating at 70% RTP. RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance. 2D LLS valve is inop for LLS Function only.
9-05 Op-Test No.: 2015-301 Examiners:
Turnover: IAW 34SO-E11-010-2, lower Torus water level to 147.5 inches, and then increase reactor power to 75%.
Operators:
Event       Malf. No.     Event                                      Event No.                      Type*                                   Description N/A               N (BOP) Lower Torus level to 147.5 inches using RHR Loop 2B 1                      TS (SRO) IAW 34SO-E11-010-2, Step 7.4.5.1.
SRO   RO   BOP Initial Conditions
2   N/A               R (ATC) Raise Reactor power to 75% using Recirc.
. Unit 2 is operating at 7 0% RTP. RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance.
CRD Flow Controller fails in Auto requiring manual operation to re-3    mfC11_299          C (ATC) establish CRD flow.
2D LLS valve is inop for LLS Function only.
C (BOP) SRV 2B21-F013G opens. The SRV will close after the ATC cycles 4    mfB21_130G TS (SRO) the control switch IAW AB section. (Critical Task)
Turnover: IAW 34SO-E11-010-2, lower Torus water level to 147.5 inches, and then increase reactor power to 75%. Event No. Malf. No. Event Type* Even t Description 1 N/A N (BOP) TS (SRO) Lower Torus level to 147.5 inches using RHR Loop "2B" IAW 34SO-E11-010-2, Step 7.4.5.1.
N/A               C (ATC) System Operator reports Condensate Booster pump B has an oil 5                                  leak, Standby pump must be started, B shutdown.
2 N/A R (ATC) Raise Reactor power to 75% using Recirc.
mfR25_186         C (BOP) Instrument Bus 2B breaker trips open, crosstie to return to service.
3 mfC11_299 C (ATC) CRD Flow Controller fails in Auto requiring manual operation to re
6                      TS (SRO) mfC71_59                      Spurious Reactor scram/ATWS (Power/Level Control, insert control 7                      M (ALL) mfC11_211                      rods and injecting SBLC. (Critical Task) 8 mfC41_240A         C (ALL) SBLC first pump fails to inject, second pump works.
-establish CRD flow.
mfC41_240B diE51_S33 RCIC Manual Initiation PB fails mfE51_109 9                      C (BOP)     RCIC/HPCI fails to Auto start on low level/hi DW pressure. Manual mfE41_235A actions required for injection. (Critical Task) mfE41_235B
4 mfB21_130G C (BOP) TS (SRO) SRV 2B21-F013G opens. The SRV will close after the ATC cycles the control switch IAW AB section.
*       (N)ormal,       (R)eactivity,   (I)nstrument,         (C)omponent,       (M)ajor
(Critical Task
 
)  5 N/A C (ATC) System Operator reports Condensate Booster pump "
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       1                         Page 2 of 29 Event
B" has an oil leak, Standby pump must be started, "
B" shutdown
. 6 mfR25_186 C (BOP) TS (SRO) Instrument Bus 2B breaker trip s open, crosstie to return to service
. 7 mfC71_59 mfC11_211 M (ALL) Spurious Reactor scram/ATWS (Power/Level Control, insert control rods and injecting SBLC. (Critical Task
) 8 mfC41_240A mfC41_240B C (ALL) SBLC first pump fails to inject, second pump works.
9 diE51_S33 mfE51_109 mfE41_235A mfE41_235B C (BOP) RCIC Manual Initiation PB fails RCIC/HPCI fails to Auto start on low level/hi DW pressure. Manual actions required for injection.
(Critical Task)   * (N)ormal,   (R)eactivity,     (I)nstrument,   (C)omponent, (M)ajor Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-05 Event No.:
1 Page 2 of 29 Event


== Description:==
== Description:==
Lower Torus level to 147.5 inches using RHR Loop 2B IAW 34SO-E11-010-2, Step 7.4.5.1.
Time      Position  Applicant's Actions or Behavior 12
* Directs the operator to lower Torus water level to 147.5 using B loop of SRO Min                    RHR.
Simulator Operator, when requested, INFORM as the Radwaste Operator that the Waste Surge Tank level is 6% and is available to receive Torus water level.
* Enters 34SO-E11-010-2, Residual Heat Removal System, at step 7.4.5.1.
* Confirms Radwaste is capable of receiving the water to be transferred.
* Confirms the RHR discharge water temperature is < 200&deg;F, 2T47-R627, point 3.
* Opens 2E11-F049, RHR to Radwaste Valve.
BOP
* Monitors Torus level on 2T48-R607A (B), 2H11-P602 (2H11-P654).
* Throttles OPEN, 2E11-F040, RHR to Radwaste Valve.
* Notifies SRO to refer to:
SPECIAL REQUIREMENT 4.3.2 of 34SO-E11-010-2 and TS 3.5.1, 3.6.2.3, 3.6.2.4, & 3.6.2.5.


Lower Torus level to 147.5 inches using RHR Loop "2B" IAW 34SO-E11-010-2, Step 7.4.5.1.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:         1                         Page 3 of 29 Event
Time Position Applicant's Actions or Behavior 12 Min SRO  Directs the operator to lower Torus water level to 147.5" using "B" loop of RHR.              Simulator Operator, when requested, INFORM as the Radwaste Operator that the Waste Surge Tank level is 6% and is available to receive Torus water level.
BOP  Enters 34SO
-E11-010-2, Residual Heat Removal System, at step 7.4.5.1
. Confirms Radwaste is capable of receiving the water to be transferred.
Confirms the RHR discharge water temperature is < 200&deg;F, 2T47
-R627, point 3. Opens 2E11
-F049, RHR to Radwaste Valve.
Monitors Torus level on 2T48
-R607A (B), 2H11
-P602 (2H11-P654). Throttles OPEN, 2E11
-F040, RHR to Radwaste Valve.
Notifies SRO to refer to
: SPECIAL REQUIREMENT 4.3.2 of 34SO-E11-010-2 and  TS 3.5.1, 3.6.2.3, 3.6.2.4, & 3.6.2.5.
 
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-05 Event No.:
1 Page 3 of 29 Event


== Description:==
== Description:==
Lower Torus level to 147.5 inches using RHR Loop 2B IAW 34SO-E11-010-2, Step 7.4.5.1.
Time      Position  Applicant's Actions or Behavior Reviews SPECIAL REQUIREMENT 4.3.2 of 34SO-E11-010-2 and TS 3.5.1, 3.6.2.3, 3.6.2.4, & 3.6.2.5.
SRO Declares RHR Loop 2B inoperable since 2E11-F040 & 2E11-F049 are open.
* Reviews TS 3.5.1, ECCS/RCIC.
* IAW TS 3.5.1 Condition A,
* Declares one low pressure ECCS inoperable (Loop 2B), and must restore to operable status within 7 days.
* IAW 3.6.2.3 Condition A,
* Declares one RHR Suppression pool cooling system inoperable (Loop 2B), and must restore to operable status within 7 days.
SRO
* IAW 3.6.2.4 Condition A,
* Declares one RHR Suppression pool spray system inoperable (Loop 2B), and must restore to operable status within 7 days.
* IAW 3.6.2.5 Condition A,
* Declares one RHR drywell spray system inoperable (Loop 2B), and must restore to operable status within 7 days.
* Once 2E11-F040 & 2E11-F049 are closed, exits the above RAS.
* Monitors Torus water level and once level has been lowered to approximately 147.5 secures the flow path.
* Closes 2E11-F040, RHR to Radwaste Valve.
* Closes 2E11-F049, RHR to Radwaste Valve.
BOP
* Notifies SRO 2E11-F040 & 2E11-F049 are now closed.
* Reports to the SRO that Torus water level has been lowered to 147.5.
* As time allows, notifies Radwaste Operator that Torus lowering is complete.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


Lower Torus level to 147.5 inches using RHR Loop "2B" IAW 34SO-E11-010-2, Step 7.4.5.1.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       2                         Page 4 of 29 Event
Time Position Applicant's Actions or Behavior SRO Reviews SPECIAL REQUIREMENT 4.3.2 of 34SO-E11-010-2 an d  TS 3.5.1, 3.6.2.3, 3.6.2.4, & 3.6.2.5.
Declares RHR Loop 2B inoperable since 2E11
-F040 & 2E11
-F049 are open.
SRO  Reviews TS 3.5.1, ECCS/RCIC.
IAW TS 3.5.1 Condition A ,  Declares one low pressure ECCS inoperable (Loop 2B), and must restore to operable status within 7 days. IAW 3.6.2.3 Condition A,  Declares one RHR Suppression pool cooling system inoperable (Loop 2B), and must restore to operable status within 7 days. IAW 3.6.2.4 Condition A,  Declares one RHR Suppression pool spray system inoperable (Loop 2B), and must restore to operable status within 7 days. IAW 3.6.2.5 Condition A,  Declares one RHR drywell spray system inoperable (Loop 2B)
, and must restore to operable status within 7 days. Once 2E11-F040 & 2E11
-F049 are closed, exits the above RA S.          BOP  Monitors Torus water level and once level has been lowered to approximately 147.5" secures the flow path.
Closes 2E11
-F040, RHR to Radwaste Valve.
Closes 2E11-F049, RHR to Radwaste Valve.
Notifies SRO 2E11
-F040 & 2E11
-F049 are now closed. Reports to the SRO that Torus water level has been lowered to 147.5".
As time allows, notifies Radwaste Operator that Torus lowering is complete.        Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-05 Event No.:
2 Page 4 of 29 Event


== Description:==
== Description:==
Raise Reactor power to 75% using Recirc.
Raise Reactor power to 75% using Recirc.
Time Position Applicant's Actions or Behavior 10 Min SRO  Directs ATC to increase reactor power to 75% by increasing Recirc flow. Power increases are NOT to exceed 10 MWe/min.
Time     Position Applicant's Actions or Behavior
NOTE: May get the RBM UPSCALE, (603
* Directs ATC to increase reactor power to 75% by increasing Recirc flow.
-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This i s expected and the operator may select a peripheral rod at this time.
10 Min      SRO Power increases are NOT to exceed 10 MWe/min.
May also get Alarm HEATER TROUBLE, (650
NOTE: May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.
-135), alarm. This is expected at this power level.
May also get Alarm HEATER TROUBLE, (650-135), alarm. This is expected at this power level.
ATC  IAW 34SO-B31-001-2 (step 7.1.5) & 34GO
* IAW 34SO-B31-001-2 (step 7.1.5) & 34GO-OPS-005-2, the ATC increases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master (P603 panel) or Individual controls (P602 panel) until reactor power is 75%.
-OPS-005-2, the ATC increases Recirc pump speed
ATC
, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master (P603 panel) or Individual controls (P602 panel) until reactor power is 75%. If using Individual Controls, pump speed increases will alternate between the "A" & "B" Recirc pumps to prevent excessive flow mismatches.
* If using Individual Controls, pump speed increases will alternate between the A & B Recirc pumps to prevent excessive flow mismatches.
Monitors power increase by observing APRM and generator output indications
* Monitors power increase by observing APRM and generator output indications.
. ATC  Complies with 34SO
* Complies with 34SO-B31-001-2 , Limitation 5.2.15, which states:
-B31-001-2 , Limitation 5.2.15, which states:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:
  <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating  
ATC
< 70% of rated core flow; AND <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at > 70% of rated core flow.
                          *  <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating
ATC Notifies the SRO that reactor power has been increased to 75%.     Simulator Operator, at the Chief Examiner's request, PROCEEDS to the next event.
                              < 70% of rated core flow; AND
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
                          * <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at
9-0 5 Event No.:
                              > 70% of rated core flow.
3 Page 5 of 29 Event
ATC       Notifies the SRO that reactor power has been increased to 75%.
Simulator Operator, at the Chief Examiners request, PROCEEDS to the next event.
 
Appendix D                         Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:         3                     Page 5 of 29 Event


== Description:==
== Description:==
CRD Flow Controller fails in Auto requiring manual operation to re-establish CRD flow.
Time      Position  Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator ENTERS (RB-3) 10 Min mfC11_299, CRD Flow Control Fails Low.
* Receives CRD HYD TEMP HIGH, (603-140) alarm.
* Determines that the CRD Flow Control Valve A has closed.
* Determines 2C11-R600, CRD Flow Controller, output is at minimum and ATC has failed downscale.
* Notifies SRO that the CRD Flow Controller has failed downscale.
* Notifies I & C (if SRO does NOT) to investigate 2C11-R600.
* Enters:
* CRD HYD TEMP HIGH, (603-140)
* 34AB-C11-001-2, Loss Of CRD System ATC
* Places 2C11-R600 controller in Manual.
* Increases output of controller until CRD flow is approximately 50 gpm.
* Dispatches I & C to investigate 2C11-R600.
SRO
* Dispatches a SO to monitor CRD drive temperatures.
* Directs operator to perform actions of the ARP and 34AB-C11-001-2.


CRD Flow Controller fails in Auto requiring manual operation to re
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301     Scenario No.: 9-05 Event No.:       3                         Page 6 of 29 Event
-establish CRD flow.
Time Position Applicant's Actions or Behavior 10 Min  At the Chief Examiner's direction, Simulator Operator ENTERS (RB-3) mfC11_299 , CRD Flow Control Fails Low
. ATC  Receives CRD HYD TEMP HIGH, (603
-140) alarm. Determines that the CRD Flow Control Valve A has closed.
Determines 2C11
-R600, CRD Flow Controller, output is at minimum and has failed downscale.
Notifies SRO that the CRD Flow Controller has failed downscale.
Notifies I & C (if SRO does NOT) to investigate 2C11
-R600.          ATC  Enters:  CRD HYD TEMP HIGH, (603
-140)  34AB-C11-001-2, Loss Of CRD System Places 2C11
-R600 controller in Manual.
Increases output of controller until CRD flow is approximately 50 gpm.
SRO  Dispatches I & C to investigate 2C11
-R600. Dispatches a SO to monitor CRD drive temperatures.
Directs operator to perform actions of the ARP and 34AB-C11-001-2.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
3 Page 6 of 29 Event


== Description:==
== Description:==
CRD Flow Controller fails in Auto requiring manual operation to re-establish CRD flow.
Time      Position  Applicant's Actions or Behavior Simulator Operator, if asked, AFTER 3 minutes from being dispatched, report to the SRO, as an SO, that 2C11-R600 FCV does NOT have any air leaks and appears to be functioning properly.
Simulator Operator, if asked, AFTER 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11-R600 FCV appears to be functioning properly with a zero signal going to the FCV and the FCV is closed.
Simulator Operator, if asked to swap FCV, AFTER 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11-R600 FCV is receiving a zero signal from the controller and it appears the flow controller is malfunction.
Simulator Operator, if ATC has placed after 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11-R600 controller has malfunctioned and will need repair.
When requested and if the CRD HYD TEMP HIGH, (603-140) alarm is still illuminated, Simulator Operator, as SO checking CRD Temps, reports that 2 CRD drives are >250&deg;F. 30-11 at 260&deg;F, 22-35 at 265&deg;F and some others are slowly increasing.
If CRD HYD TEMP HIGH, (603-140) alarm is NOT illuminated, Simulator Operator, as SO checking CRD Temps, reports that 2 CRD drives had been
                        >250&deg;F but are now below 250&deg;F and trending down.
Simulator Operator, with Chief Examiners permission, PROCEEDS to Event 4 to run in parallel with Event 3.


CRD Flow Controller fails in Auto requiring manual operation to re
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:     3                         Page 7 of 29 Event
-establish CRD flow.
Time Position Applicant's Actions or Behavior Simulator Operator, if asked, AFTER 3 minutes from being dispatched, report to the SRO, as an SO, that 2C11
-R600 FCV does NOT have any air leaks and appears to be functioning properly.
Simulator Operator, if asked, AFTER 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11
-R600 FCV appears to be functioning properly with a zero signal going to the FCV and the FCV is closed. 
 
Simulator Operator, if asked to swap FCV, AFTER 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11
-R600 FCV is receiving a zero signal from the controller and it appears the flow controller is malfunction.
 
Simulator Operator, if ATC has placed after 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11
-R600 controller has malfunctioned and will need repair.
When requested and if the CRD HYD TEMP HIGH
, (603-140) alarm is still illuminated, Simulator Operator, as SO checking CRD Temps, reports that 2 CRD drives are >250&deg;F. 30
-11 at 260&deg;F, 22
-35 at 265&deg;F and some other s are slowly increasing.
If CRD HYD TEMP HIGH
, (603-140) alarm is NOT illuminated, Simulator Operator, as SO checking CRD Temps, reports that 2 CRD drives had been >250&deg;F but are now below 250&deg;F and trending down.
Simulator Operator, with Chief Examiners permission,  PROCEEDS to Event 4 to run in parallel with Event 3.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
3 Page 7 of 29 Event


== Description:==
== Description:==
CRD Flow Controller fails in Auto requiring manual operation to re-establish CRD flow.
Time      Position  Applicant's Actions or Behavior ONCE Event 4 is complete, DELETE mfC11_299 and notify the SRO that 2C11-R600 is now repaired and as Shift Manager, grant permission to return controller to automatic mode.
SRO
* Directs ATC to return 2C11-R600 to Automatic operation.
* Returns CRD System to normal configuration by performing step 7.1.2.29 of 34SO-C11-005-2 or by performing step 4.9 of 34AB-C11-001-2:
* Manually adjusts 2C11-R600 to match setpoint
* Places 2C11-R600 to Auto ATC
* Confirms system parameters are normal
* Confirms 603-140, CRD Hyd Temp High, alarm is clear
* Reports to SRO that CRD flow controller has been restored to normal configuration.
Simulator Operator, at the Chief Examiners request, PROCEEDS to the next event.


CRD Flow Controller fails in Auto requiring manual operation to re
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:         4                         Page 8 of 29 Event
-establish CRD flow.
Time Position Applicant's Actions or Behavior ONCE Event 4 is complete, DELETE mfC11_299 and notify the SRO that 2C11-R600 is now repaired and as Shift Manager, grant permission to return controller to automatic mode. SRO  Directs ATC to return 2C11
-R600 to Automatic operation.
ATC  Returns CRD System to normal configuration by performing step 7.1.2.29 of 34SO-C11-005-2 or by performing step 4.9 of 34AB
-C11-001-2:  Manually adjusts 2C11
-R600 to match setpoint  Places 2C11
-R600 to Auto Confirms system parameters are normal Confirms 603
-140, CRD Hyd Temp High, alarm is clear Reports to SRO that CRD flow controller has been restored to normal configuration.
Simulator Operator, at the Chief Examiner's request, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-05 Event No.:
4 Page 8 of 29 Event


== Description:==
== Description:==
 
SRV 2G Opens and closes after ATC cycles switch.
SRV "2G" Opens and closes after ATC cycles switch.
Time     Position Applicant's Actions or Behavior Simulator Operator: To insure the BOP operator gets the next malfunction, as Shift Manger, request the ATC to get some Offgas panel reading (Stack Flow)
Time Position Applicant's Actions or Behavior 8 Min  Simulator Operator: To insure the BOP operator gets the next malfunction, as Shift Manger, request the ATC to get some Offgas panel reading (Stack Flow) OR with Chief Examiners permission, perform the following. Simulator Operator: At the direction of the Chief Examiner, ACTIVATE:
OR with Chief Examiners permission, perform the following.
8 Min Simulator Operator: At the direction of the Chief Examiner, ACTIVATE:
(RB-4) mfB21_130G.
(RB-4) mfB21_130G.
ALL  Recognize annunciators:
* Recognize annunciators:
SAFETY BLOWDOWN VALVE LEAKING, (602
ALL
-311) SAFETY BLOWDOWN PRESSURE HIGH, (603
* SAFETY BLOWDOWN VALVE LEAKING, (602-311)
-122)       SRO Directs operator to enter 34 AB-B21-003-2, Failure of Safety/Relief valves Enters a RAS for TS LCO 3.6.1.6.A for 2 or more LLS valves inop, which requires the unit to be in Mode 3 in 12 hours and Mode 4 in 36 hours.
* SAFETY BLOWDOWN PRESSURE HIGH, (603-122)
Directs operator to enter 34AB-B21-003-2, Failure of Safety/Relief valves SRO
* Enters a RAS for TS LCO 3.6.1.6.A for 2 or more LLS valves inop, which requires the unit to be in Mode 3 in 12 hours and Mode 4 in 36 hours.
The ATC may enter the abnormal procedure first before addressing the ARPs.
The ATC may enter the abnormal procedure first before addressing the ARPs.
BOP  Enters 602-311 and 603
* Enters 602-311 and 603-122 annunciators
-122 annunciators Confirm which safety relief valve has opened using the amber valve leakage indicator Confirms green light is OFF Check s back panel tail pipe temperatures BOP  Confirm "2G" is leaking using the indication on 2B21
* Confirm which safety relief valve has opened using the amber valve BOP            leakage indicator
-R614, Auto Blowdown/Safety Vlv Temps recorder.
* Confirms green light is OFF
Reports to the SRO and ATC operator that "2G" SRV is open
* Checks back panel tail pipe temperatures
* Confirm 2G is leaking using the indication on 2B21-R614, Auto BOP          Blowdown/Safety Vlv Temps recorder.
* Reports to the SRO and ATC operator that 2G SRV is open


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       4                       Page 9 of 29 Event
9-05 Event No.:
4 Page 9 of 29 Event


== Description:==
== Description:==
SRV 2G Opens and closes after ATC cycles switch.
Time      Position  Applicant's Actions or Behavior Simulator Operator: When the operator cycles the control switch, ENSURE Event Trigger EGB21-11 activates.
* Executes 34AB-B21-003-2 steps;
* Confirms the green AND amber lights are illuminated for 2G SRV
* Cycles the 2G SRV control switch several times between Open/Close (Critical Task)
BOP
* Notifies SRO that SRV 2G closed when control switch was cycled.
* May request the SSS to pull the fuses for SRV 2G. (SIMULATOR OPERATOR, If requested, wait 4 minutes, DEPRESSES RB-9, rfB21_306, SRV G Fuses) to pull fuses.
* When SRV closes confirms;
* Torus water level increase has stopped.
* Torus temperature increase has stopped.
* Reactor Power is at its original value BOP
* SRV tailpipe temperature decreasing
* Resets the SRV leak detection AMBER SRV indicating lights.
* Notifies SRO the Torus-Drywell Vacuum Breaker surveillance needs to be performed within 12 hours.
* Notifies Chemistry to increase monitoring of vessel moisture carryover.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event AFTER Event 3 & 4 are complete.


SRV "2G" Opens and closes after ATC cycles switch.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       5                       Page 10 of 29 Event
Time Position Applicant's Actions or Behavior Simulator Operator:
When the operator cycles the control switch, ENSURE Event Trigger EGB21-11 activates.
BOP  Executes 34AB-B21-003-2 steps;  Confirms the green AND amber lights are illuminated for 2G SRV Cycles the 2G SRV control switch several times between Open/Close (Critical Task
)  Notifies SRO that SRV "2G" closed when control switch was cycled.
May request the SSS to pull the fuses for SRV 2 G.  (SIMULATOR OPERATOR, If requested, wait 4 minutes, DEPRESSES RB-9, rfB21_306, SRV G Fuses) to pull fuses.
BOP  When SRV closes confirms;  Torus water level increase has stopped.
Torus temperature increase has stopped.
Reactor Power is at its original value SRV tailpipe temperature decreasing Resets the SRV leak detection AMBER SRV indicating lights
. Notifies SRO the Torus
-Drywell Vacuum Breaker surveillance needs to be performed within 12 hours.
Notifies Chemistry to increase monitoring of vessel moisture carryover.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event AFTER Event 3 & 4 are complete
.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
5 Page 10 of 29 Event


== Description:==
== Description:==
 
System Operator reports Condensate Booster pump B has an oil leak, A must be started, B shutdown.
System Operator reports Condensate Booster pump "
Time     Position Applicant's Actions or Behavior Simulator Operator, at the Chief Examiners direction, as a System Operator (SO), reports on rounds, that the 2B Condensate Booster pump has an oil leak.
B" has an oil leak, "A" must be started, "
12                When questioned about the size of the oil leak, report as the SO that the CBP MIN                still has ample oil to operate, but should be shut down as soon as possible.
B" shutdown. Time Position Applicant's Actions or Behavior 12 MIN  Simulator Operator, at the Chief Examiner's direction, as a System Operator (SO), reports on rounds , that the 2 B Condensate Booster pump has an oil leak.
When questioned about the size of the oil leak, report as the SO that the CBP still has ample oil to operate, but should be shut down as soon as possible.
NOTE: The following is written to start the 2A CBP.
NOTE: The following is written to start the 2A CBP.
S RO  Directs Operator to place 2A Condensate Booster pump (CBP) in service and shutdown the 2 B Condensate Booster pump.
* Directs Operator to place 2A Condensate Booster pump (CBP) in service SRO and shutdown the 2B Condensate Booster pump.
ATC Enters 34SO
ATC
-N21-007-2 at step 7.3.6 and performs the following:
* Enters 34SO-N21-007-2 at step 7.3.6 and performs the following:
Has SO: Verify that 2A CBP Oil Reservoir and motor bearing oil levels are WITHIN normal level marks.
* Has SO:
Throttle 2P41
* Verify that 2A CBP Oil Reservoir and motor bearing oil levels are WITHIN normal level marks.
-F364A outlet valve as necessary to maintain the oil temperature between 50&deg;F and 115&deg;F.
* Throttle 2P41-F364A outlet valve as necessary to maintain the oil temperature between 50&deg;F and 115&deg;F.
Confirm / Place CBP 2A Oil Pump control switch in Auto and Confirm pump is running.
* Confirm / Place CBP 2A Oil Pump control switch in Auto and Confirm pump is running.
Confirm Closed/Close 2N21
* Confirm Closed/Close 2N21-F020A, Standby CBP Discharge Valve.
-F020A, Standby CBP Discharge Valve.         Simulator Operator does NOT have to enter the remote function for closing the discharge valve for the CBP, because it has to be throttled prior to pump start and we do NOT have throttle capability.
Simulator Operator does NOT have to enter the remote function for closing the discharge valve for the CBP, because it has to be throttled prior to pump start and we do NOT have throttle capability.
Simulator Operator, as SO, reports that CBP 2A oil levels are normal, oil temperature is at 95&deg;F, the oil pump is running in Auto and that the 2N21-F020A is closed.
Simulator Operator, as SO, reports that CBP 2A oil levels are normal, oil temperature is at 95&deg;F, the oil pump is running in Auto and that the 2N21-F020A is closed.
ATC  Directs SO to: Throttle Open 2N21
* Directs SO to:
-F020A, CBP Discharge Valve, for 15 seconds Observe for indication of a stuck open / leaking discharge check valve as evidenced by increasing pressure on the pump side of the discharge check valve.
* Throttle Open 2N21-F020A, CBP Discharge Valve, for 15 seconds ATC
* Observe for indication of a stuck open / leaking discharge check valve as evidenced by increasing pressure on the pump side of the discharge check valve.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:         5                       Page 11 of 29 Event
9-0 5 Event No.:
5 Page 11 of 29 Event


== Description:==
== Description:==
System Operator reports Condensate Booster pump B has an oil leak, A must be started, B shutdown.
Time      Position  Applicant's Actions or Behavior Simulator Operator, as SO, reports that the 2N21-F020A is opened 15 seconds and the discharge check valve does NOT indicate leakage. (Verify that rfN21_60A is in Open.)
* Starts Condensate Booster Pump 2A, by placing the control switch to Start.
ATC
* Has SO throttle open the Discharge valve and maintain oil temp by throttling PSW to the oil cooler.
Simulator Operator, as SO, reports that the discharge valve is now full open for CBP 2A, and that oil temp is being maintained at 95&deg;F
* When condensate and Feedwater flows and pressures have stabilized, ATC directs the SO to close 2N21-F020B.
Simulator Operator, ACTIVATE: (RB-8): rfN21_61 (CBP B Disch valve close), then as the SO, reports that the discharge valve for CBP 2B is started closed.
* Places CBP 2B control switch to stop within 90 seconds of being told the discharge valve has started closing.
ATC
* Reports to SRO that 2A CBP is operating and that the 2B CBP has been secured. May ask SRO if it is desired to place the 2B CBP in standby. If so the CBP 2B control switch will be placed in Auto.
* May direct the operator to place CBP 2C in PTL Off or Standby and leave SRO oil pump in off.
Simulator Operator, If requested to re-open the discharge valve, TOGGLE:
rfN21_61 (CBP B Disch valve Open) and as SO report that the discharge valve for CBP 2B is Open.
Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


System Operator reports Condensate Booster pump "
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       6                       Page 12 of 29 Event
B" has an oil leak, "A" must be started, "
B" shutdown. Time Position Applicant's Actions or Behavior Simulator Operator, as SO, reports that the 2N21
-F020A is opened 15 seconds and the discharge check valve does NOT indicate leakage.  (Verify that rfN21_60A is in Open.)
ATC  Starts Condensate Booster Pump 2A, by placing the control switch to Start.
Has SO throttle open the Discharge valve and maintain oil temp by throttling PSW to the oil cooler.
Simulator Operator, as SO, reports that the discharge valve is now full open for CBP 2A, and that oil temp is being maintained at 95&deg;F ATC  When condensate and Feedwater flows and pressures have stabilized, directs the SO to close 2N21
-F020 B.        Simulator Operator, ACTIVATE:
(RB-8): rfN21_6 1 (CBP "B" Disch valve close), then as the SO, reports that the discharge valve for CBP 2 B is started closed. ATC  Places CBP 2 B control switch to stop within 90 seconds of being told the discharge valve has started closing.
Reports to SRO that 2A CBP is operating and that the 2 B CBP has been secured. May ask SRO if it is desired to place the 2 B CBP in standby. If so the CB P 2 B control switch will be placed in Auto.
SRO  May direct the operator to place CBP 2C in PTL Off or Standby and leave oil pump in off.
Simulator Operator, If requested to re
-open the discharge valve, TOGGLE: rfN21_6 1 (CBP "B" Disch valve Open) and as SO report that the discharge valve for CBP 2 B is Open. Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
6 Page 12 of 29 Event


== Description:==
== Description:==
Instrument Bus 2B breaker trips open, crosstie to return to service.
Time      Position  Applicant's Actions or Behavior 15                Simulator Operator, at direction of the lead examiner, ACTIVATE: (RB-6)
Mins              malfunction mfR25_186, Loss Of Instrument Bus 2B.
ALL      Various alarms indicating Instrument Bus 2B has lost power.
Directs BOP to enter 34AB-R25-002-2, Loss Of Instrument Buses, for loss of SRO Instrument Bus 2B.
* Enters 34AB-R25-002-2, Loss of Instrument Buses, and performs the following at Panel 2H11-P654,
* Opens 2T46-F001A
* Opens 2T46-F003A
* Places SBGT Fan 2A control switch to "RUN."
* Receives 2A SBGT SWITCH NOT IN AUTO, (657-091), alarm
* Confirms 2T46-F002A OPENS
* Confirms SBGT Heater red light illuminates.
BOP
* Places 2B SBGT Fan control switch to OFF
* Dispatches SO to confirm CLOSE Instrument Bus 2B supply breaker 28 on 2R25-S037, Essential Cabinet 2B by dispatching a SO locally.
* Dispatches SO to confirm Essential Cabinet 2B 2R25-S037 is energized by NO other alarms illuminated at 2H11-P651.
* Per step 4.4, dispatches Maintenance to check fuses R25F209 F01, R25F210 F02, and R25F211 F03, in fuse panel 2R20N P002 located next to Essential Cabinet 2B (power supply to 2R25 S065, Instrument Bus 2B 6).


Instrument Bus 2B breaker trips open, crosstie to return to service.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:         6                       Page 13 of 29 Event
Time Position Applicant's Actions or Behavior 15 Mins  Simulator Operator, at direction of the lead examiner, ACTIVATE:
(RB-6) malfunction mfR25_186, Loss Of Instrument Bus 2B.
ALL Various alarms indicating Instrument Bus 2B has lost power.
SRO Directs BOP to enter 34AB
-R2 5-00 2-2, Loss Of Instrument Buses, for loss of Instrument Bus 2B.        BOP  Enters 34AB
-R25-002-2, Loss of Instrument Buses, and performs the following at Panel 2H11
-P654,  Opens 2T46
-F001A  Opens 2T46-F003A  Places SBGT Fan 2A control switch to "RUN."  Receives 2A SBGT SWITCH NOT IN AUTO, (657
-091), alarm Confirms 2T46
-F002A OPENS Confirms SBGT Heater red light illuminates.
Places 2B SBGT Fan control switch to "OFF" Dispatches SO to confirm CLOSE Instrument Bus 2B supply breaker 28 on 2R25
-S037, Essential Cabinet 2B by dispatching a SO locally.
Dispatches SO to confirm Essential Cabinet 2B 2R25
-S037 is energized by NO other alarms illuminated at 2H11
-P65 1. Per step 4.4, dispatches Maintenance to check fuses R25F209 F01, R25F210 F02, and R25F211 F03, in fuse panel 2R20N P002 located next to Essential Cabinet 2B (power supply to 2R25 S065, Instrument Bus 2B 6).
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
6 Page 13 of 29 Event


== Description:==
== Description:==
Instrument Bus 2B breaker trips open, crosstie to return to service.
Instrument Bus 2B breaker trips open, crosstie to return to service.
Time Position Applicant's Actions or Behavior NOTE: The BOP may consult with the SRO and decide not perform steps 7.2.1.1 through 7.2.4 since these fans only circulate air in Secondary Containment.
Time     Position Applicant's Actions or Behavior NOTE: The BOP may consult with the SRO and decide not perform steps 7.2.1.1 through 7.2.4 since these fans only circulate air in Secondary Containment.
BOP  Secures Rx Bldg Ventilation per 34SO
* Secures Rx Bldg Ventilation per 34SO-T41-005-2, Step 7.2.1 by performing the following; (steps 7.2.1.1 through 7.2.4)
-T41-005-2, Step 7.2.1 by performing the following; (steps 7.2.1.1 through 7.2.4)
May place the following in the STOP position:
May place the following in the STOP position:
Places 2T41
* Places 2T41-B007, Rx Bldg Cooler Working Floor El 130 North
-B007, Rx Bldg Cooler Working Floor El 130 North Places 2T41
* Places 2T41-B008, Rx Bldg Cooler Working Floor El 130 South
-B008, Rx Bldg Cooler Working Floor El 130 South Places 2T41
* Places 2T41-B026, Rx Bldg Primary Cooler Mn Steam Pipe Chase
-B026, Rx Bldg Primary Cooler Mn Steam Pipe Chase Places 2T41
* Places 2T41-B010, Rx Bldg Cooler Equip Room El 164
-B010, Rx Bldg Cooler Equip Room El 164 Places 2T41
* Places 2T41-B011, Rx Bldg Cooler Operating Floor El 185
-B011, Rx Bldg Cooler Operating Floor El 185 Places 2T41
* Places 2T41-B014, Rx Bldg Cooler RWCU Pmp/Hx El 158
-B014, Rx Bldg Cooler RWCU Pmp/Hx El 158 Places 2T41
* Places 2T41-B015, Rx Bldg Cooler Operating Floor El 185
-B015, Rx Bldg Cooler Operating Floor El 185 Places 2T41
* Places 2T41-B016, Rx Bldg Cooler Working Floor El 203 NOTE:     If fans 2T41-B026 and 2T41-B009 are secured, delay proceeding to the next event to evaluate if the SRO will restart Rx Bldg Ventilation BOP or if the Group I signal from High Steam Chase Temperature will be received.
-B016, Rx Bldg Cooler Working Floor El 203
 
NOTE: If fans 2T41-B026 and 2T41
-B009 are secured, delay proceeding to the next event to evaluate if the SRO will restart Rx Bldg Ventilation or if the Group I signal from High Steam Chase Temperature will be received.
May place the following in the OFF position:
May place the following in the OFF position:
2T41-B017, Fan 2 or Fan 1, Rx Bldg Recirc 2T41-B017, Fan 1 or Fan 2, Rx Bldg Recirc 2T41-B009, Rx Bldg Secondary Cooler Mn. Steam Pipe Chase Performs the following:
* 2T41-B017, Fan 2 or Fan 1, Rx Bldg Recirc
Place s in OFF 2T41
* 2T41-B017, Fan 1 or Fan 2, Rx Bldg Recirc
-C001B, Rx Bldg Supply Fan Pl ace s in OFF 2T41
* 2T41-B009, Rx Bldg Secondary Cooler Mn. Steam Pipe Chase Performs the following:
-C001A, Rx Bldg Supply Fan Place s in OFF 2T41
* Places in OFF 2T41-C001B, Rx Bldg Supply Fan
-C007B, Rx Bldg Vent Exhaust Fan Place s in OFF 2T41
* Places in OFF 2T41-C001A, Rx Bldg Supply Fan
-C007A, Rx Bldg Vent Exhaust Fan Close s 2T41-F028, Rx Bldg Vent Filter D005 Inlet Damper.
* Places in OFF 2T41-C007B, Rx Bldg Vent Exhaust Fan
* Places in OFF 2T41-C007A, Rx Bldg Vent Exhaust Fan
* Closes 2T41-F028, Rx Bldg Vent Filter D005 Inlet Damper.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:         6                       Page 14 of 29 Event
9-0 5 Event No.:
6 Page 14 of 29 Event


== Description:==
== Description:==
Instrument Bus 2B breaker trips open, crosstie to return to service.
Instrument Bus 2B breaker trips open, crosstie to return to service.
Time Position Applicant's Actions or Behavior BOP  Secures Refuel Flr Ventilation per 34SO
Time     Position Applicant's Actions or Behavior
-T41-006-2 by performing the following,   Places 2T41
* Secures Refuel Flr Ventilation per 34SO-T41-006-2 by performing the following,
-C002B Refuel Flr Vent Supply Fan, control switch, in OFF. Places 2T41
* Places 2T41-C002B Refuel Flr Vent Supply Fan, control switch, in OFF.
-C002A, Refuel Flr Vent Supply Fan, control switch, in OFF. Places 2T41
* Places 2T41-C002A, Refuel Flr Vent Supply Fan, control switch, in OFF.
-C005B, Refuel Flr Vent Exh Fan, control switch, in OFF.
* Places 2T41-C005B, Refuel Flr Vent Exh Fan, control switch, in OFF.
Places 2T41-C005A, Refuel Flr Vent Exh Fan, control switches, in OFF. Closes 2T41
* Places 2T41-C005A, Refuel Flr Vent Exh Fan, control switches, in BOP              OFF.
-F004C, Refuel Floor Area Damper.
* Closes 2T41-F004C, Refuel Floor Area Damper.
Dispatches a SO locally to perform the following:
* Dispatches a SO locally to perform the following:
Place 2T41
* Place 2T41-B024C, Refueling Floor Unit Heater Fan, control switch, in OFF.
-B024C, Refueling Floor Unit Heater Fan, control switch, in OFF.
* Place 2T41-B024B, Refueling Floor Unit Heater Fan, control switch, in OFF.
Place 2T41
* Place 2T41-B024A, Refueling Floor Unit Heater Fan, control switch, in OFF.
-B024B, Refueling Floor Unit Heater Fan, control switch, in OFF.
Place 2T41
-B024A, Refueling Floor Unit Heater Fan, control switch, in OFF.
Simulator Operator, Once Tech Specs have been addressed, Call the control room, as an Electrician, and report that Instrument Bus 2B supply breaker 28 on 2R25-S037, Essential Cabinet 2B, is damaged and must be replaced. If asked, inform Control Room it will take approximately 6 hours to replace.
Simulator Operator, Once Tech Specs have been addressed, Call the control room, as an Electrician, and report that Instrument Bus 2B supply breaker 28 on 2R25-S037, Essential Cabinet 2B, is damaged and must be replaced. If asked, inform Control Room it will take approximately 6 hours to replace.
Simulator Operator, when directed, ACTIVATE:
Simulator Operator, when directed, ACTIVATE: (RB-9), rfR25_166, Instrument Bus 2B Powered from 2A, THEN NOTIFIES SRO that Instrument Bus 2B is powered from Instrument Bus 2A.
(RB-9), rfR25_166, Instrument Bus 2B Powered from 2A, THEN NOTIFIES SRO that Instrument Bus 2B is powered from Instrument Bus 2A.
Addresses TS 3.8.7, Distribution Systems - Operating and determines that Condition C exists requiring Instrument Bus 2B returned to operable status in 8 hours.
SRO Addresses TS 3.8.7, Distribution Systems  
SRO      Addresses TS 3.4.5. B, requiring grab samples of primary containment atmosphere once per 12 hours and restore within 30 days.
- Operating and determines that Condition C exists requiring Instrument Bus 2B returned to operable status in 8 hours. Addresses TS 3.4.5. B, requiring grab samples of primary containment atmosphere once per 12 hours and restore within 30 days.
After report on local actions, directs the BOP to re-energize Instrument Bus 2B by cross tying with Instrument Bus 2A.
After report on local actions, directs the BOP to re-energize Instrument Bus 2B by cross tying with Instrument Bus 2A
 
.
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:     6                         Page 15 of 29 Event
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
6 Page 15 of 29 Event


== Description:==
== Description:==
Instrument Bus 2B breaker trips open, crosstie to return to service.
Instrument Bus 2B breaker trips open, crosstie to return to service.
Time Position Applicant's Actions or Behavior NOTE: The following steps may be performed out of order, AFTER placing Group Isolation Reset Switch to the Group 1 and Group 2/5 positions, on P601.
Time     Position Applicant's Actions or Behavior NOTE:     The following steps may be performed out of order, AFTER placing Group Isolation Reset Switch to the Group 1 and Group 2/5 positions, on P601.
BOP Directs SO to crosstie Instrument Buses per step 4.5.
Directs SO to crosstie Instrument Buses per step 4.5.
Once Instrument Bus 2B is energized, continues at step 4.7 and performs the following:
Once Instrument Bus 2B is energized, continues at step 4.7 and performs the following:
Following confirmation of any group isolation(s), RESET isolation(s) by placing Group Isolation Reset Switch to the Group 1 and Group 2/5 positions, on P601.
* Following confirmation of any group isolation(s),
Opens the following Fission Product Monitoring isolation valves, panel P700: 2D11-F052 2D11-F053 2D11-F072 Opens 2B31
RESET isolation(s) by placing Group Isolation Reset Switch to the BOP          Group 1 and Group 2/5 positions, on P601.
-F020, Rx Wtr Sample Otbd Isol AOV, on P602.
* Opens the following Fission Product Monitoring isolation valves, panel P700:
IT IS NOT INTENDED FOR THE CREW TO RESTORE ALL OF THE LOADS ASSOCIATED WITH INSTRUMENT BUS 2B. AFTER THE OPERATOR RESTORES 2D11
* 2D11-F052
-F052, F053 & F072
* 2D11-F053
, AT THE CHIEF EXAMINER'S DIRECTION
* 2D11-F072
, SIMULATOR OPERATOR PROCEEDS TO THE NEXT EVENT.
* Opens 2B31-F020, Rx Wtr Sample Otbd Isol AOV, on P602.
BOP  Resets and return Rx Bldg. Ventilation to normal per 34SO-T41-005-2. Resets and return R/F Ventilation to normal per 34SO
IT IS NOT INTENDED FOR THE CREW TO RESTORE ALL OF THE LOADS ASSOCIATED WITH INSTRUMENT BUS 2B.
-T41-006-2 Secures Standby Gas Treatment System and place in standby per 34SO
AFTER THE OPERATOR RESTORES 2D11-F052, F053 & F072, AT THE CHIEF EXAMINERS DIRECTION, SIMULATOR OPERATOR PROCEEDS TO THE NEXT EVENT.
-T46-001-2. Restores Drywell Equipment and Floor Drain Sumps per 34SO-G11-009-2. Returns Steam Packing Exhauster to service per 34SO
* Resets and return Rx Bldg. Ventilation to normal per 34SO-T41-005-2.
-N33-001-2. Notifies Unit 1 NPO to restore Control Room ventilation to the desired mode of operation per 34SO
* Resets and return R/F Ventilation to normal per 34SO-T41-006-2
-Z41-001-1.
* Secures Standby Gas Treatment System and place in standby per 34SO-T46-001-2.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
BOP
9-0 5 Event No.:
* Restores Drywell Equipment and Floor Drain Sumps per 34SO-G11-009-2.
6 Page 16 of 29 Event
* Returns Steam Packing Exhauster to service per 34SO-N33-001-2.
* Notifies Unit 1 NPO to restore Control Room ventilation to the desired mode of operation per 34SO-Z41-001-1.
 
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       6                         Page 16 of 29 Event


== Description:==
== Description:==
Instrument Bus 2B breaker trips open, crosstie to return to service.
Time      Position  Applicant's Actions or Behavior
* At SRO direction returns Rx Water Level Control to 3 element control per 34AR-603-132-2, Feedwater Control System Trouble.
* Restores the Drywell Cooling Fans to normal alignment per 34SO-T47-001-2.
* Alarm 650-204, Drywell/Torus RCDR R627 Temp High, may be received if Drywell Cooling Fans are not restored to a pre-event lineup.
It is NOT intended for the crew to restore all of the loads associated with INSTRUMENT BUS 2B.
AFTER the operator restores 2D11-F052, F053 & F072, AT the Chief Examiners direction, Simulator operator PROCEEDS to the next event.


Instrument Bus 2B breaker trips open, crosstie to return to service.
Appendix D                     Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       7                     Page 17 of 29 Event
Time Position Applicant's Actions or Behavior At SRO direction returns Rx Water Level Control to 3 element control per 34AR-603-132-2, Feedwater Control System Trouble.
Restores the Drywell Cooling Fans to normal alignment per 34SO-T47-001-2. Alarm 650-204, Drywell/Torus RCDR R627 Temp High, may be received if Drywell Cooling Fans are not restored to a pre
-event lineup.
It is NOT intended for the crew to restore all of the loads associated with INSTRUMENT BUS 2B. AFTER the operator restores 2D11
-F052, F053 & F072
, AT the Chief Examiner's direction
, Simulator operator PROCEEDS to the next event
.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
7 Page 17 of 29 Event


== Description:==
== Description:==
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Time Position Applicant's Actions or Behavior Simulator Operator, at direction of the lead examiner, ACTIVATE:
Time     Position Applicant's Actions or Behavior Simulator Operator, at direction of the lead examiner, ACTIVATE: (RB-7) malfunction mfC71_59, Spurious Reactor Scram.
(RB-7) malfunction mfC71_59, Spurious Reactor Scram. SRO Directs ATC to scram the reactor:
Directs ATC to scram the reactor:
Enters RC or RCA EOP Flowcharts.
* Enters RC or RCA EOP Flowcharts.
Directs ATC to perform RC
* Directs ATC to perform RC-1 placard.
-1 placard.
* Directs BOP to perform RC-2 and RC-3 placards.
Directs BOP to perform RC
SRO
-2 and RC-3 placards.
* If time allows assigns TC-1 to be performed.
If time allows assigns TC
* Enters the RCA EOP flow chart, 31EO-EOP-011-2, for a scram condition and reactor power above 5%.
-1 to be performed.
* Enters CP-3 EOP flow chart, 31EO-EOP-017-2, for ATWS level control.
Enters the RCA EOP flow chart, 31EO
Directs ATC to:
-EOP-011-2, for a scram condition and reactor power above 5%.
* Confirm the reactor Mode Switch in Shutdown.
Enters CP-3 EOP flow chart, 31EO
SRO
-EOP-017-2, for ATWS level control.
* Confirm ARI Initiation.
SRO Directs ATC to:
* Confirm Recirc runback to minimum/tripped.
Confirm the reactor Mode Switch in Shutdown.
Confirm ARI Initiation.
Confirm Recirc runback to minimum/tripped.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       7                       Page 18 of 29 Event
9-0 5 Event No.:
7 Page 1 8 of 29 Event


== Description:==
== Description:==
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Time Position Applicant's Actions or Behavior NOTE: Event Trigger C71-15 INSERTS; aiC11-R607-1, CRD Cooling Water dP Controller Failure (f: 25, r: 1000), svoN37225 & svoN3722 6 when the Rx Mode Switch is placed to SHUTDOWN.
Time     Position Applicant's Actions or Behavior NOTE: Event Trigger C71-15 INSERTS; aiC11-R607-1, CRD Cooling Water dP Controller Failure (f: 25, r: 1000), svoN37225 &
ATC (Placard)  Manually SCRAMs the Reactor using the SCRAM pushbuttons.
svoN37226 when the Rx Mode Switch is placed to SHUTDOWN.
Places Rx Mode Switch in SHUTDOWN. Initiates Alternate Rod Insertion (ARI) by rotating the button collars and depressing both ARI pushbuttons at the same time when directed by the SRO. Uses the Full Core Display and Rod Worth Minimizer to determine that all control rods are NOT inserted past position 02.
* Manually SCRAMs the Reactor using the SCRAM pushbuttons.
Informs the SRO that all rods are NOT fully inserted (ATWS).
* Places Rx Mode Switch in SHUTDOWN.
Inserts IRMs and SRMs.
* Initiates Alternate Rod Insertion (ARI) by rotating the button collars and depressing both ARI pushbuttons at the same time when directed by the SRO.
May attempt to inject SBLC depending on RWL/power level (if power is above 5%, the ATC is directed to inject SBLC IAW the RC
* Uses the Full Core Display and Rod Worth Minimizer to determine that all control rods are NOT inserted past position 02.
-1 placard).
* Informs the SRO that all rods are NOT fully inserted (ATWS).
NOTE: See Event 8 for SBLC Failures.
ATC
Places SDV Isol Vlv Switch to "ISOL" and verifies closed.
* Inserts IRMs and SRMs.
Confirms Recirc at minimum speed and since power is above 5%, the ATC trip s Recirc IAW the RC
(Placard)
-1 placard).
* May attempt to inject SBLC depending on RWL/power level (if power is above 5%, the ATC is directed to inject SBLC IAW the RC-1 placard).
ATC Reports to the SRO that:
NOTE:       See Event 8 for SBLC Failures.
The Reactor Mode Switch is in the SHUTDOWN position. ARI has been initiated (ATC may initiate ARI at this time).
* Places SDV Isol Vlv Switch to ISOL and verifies closed.
Recirc is at minimum speed (if power is above 5%, the ATC is directed to trip Recirc IAW the RC
* Confirms Recirc at minimum speed and since power is above 5%, the ATC trips Recirc IAW the RC-1 placard).
-1 placard).
Reports to the SRO that:
* The Reactor Mode Switch is in the SHUTDOWN position.
ATC
* ARI has been initiated (ATC may initiate ARI at this time).
* Recirc is at minimum speed (if power is above 5%, the ATC is directed to trip Recirc IAW the RC-1 placard).


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:         7                       Page 19 of 29 Event
9-0 5 Event No.:
7 Page 19 of 29 Event


== Description:==
== Description:==
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Time Position Applicant's Actions or Behavior BOP Performs actions of placards RC
Time     Position Applicant's Actions or Behavior BOP     Performs actions of placards RC-2 and RC-3 after Reactor SCRAM.
-2 and RC-3 after Reactor SCRAM.
Performs RC-2 actions consisting of:
BOP (Placard) Performs RC
* Confirms proper Level Control response:
-2 actions consisting of:
* Checks ECCS Injection Systems
Confirms proper Level Control response:
* Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value BOP
Checks ECCS Injection Systems Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value When feed flow is less than the capacity of the S/U level c1.5 mlbm/hr), then:
* When feed flow is less than the capacity of the S/U level control valve (
Confirms Open 2N21
(Placard) 1.5 mlbm/hr), then:
-F125. Confirms 2C32
* Confirms Open 2N21-F125.
-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
* Confirms 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
Closes 2N21
* Closes 2N21-F110.
-F110. Will control RWL at 9 inches.
* Will control RWL at 9 inches.
BOP (Placard) Performs RC
Performs RC-3 consisting of:
-3 consisting of: Monitors RPV pressure.
* Monitors RPV pressure.
Confirms proper operation of pressure control system (TBV, LLS, etc.).
* Confirms proper operation of pressure control system (TBV, LLS, etc.).
If necessary, allow RPV pressure to exceed 1074 psig then cycle any SRV to initiate LLS.
BOP
Maintain RPV pressure between 1074 and 800 psig.
* If necessary, allow RPV pressure to exceed 1074 psig then cycle any SRV (Placard) to initiate LLS.
Notify SRO of pressure control system operation.
* Maintain RPV pressure between 1074 and 800 psig.
SRO May direct BOP operator to lower reactor pressure to <845 psig.
* Notify SRO of pressure control system operation.
BOP (Placard)  If directed, lowers pressure setpoint to <845 psig using the DEHC system as described on the following graphic.
SRO
* May direct BOP operator to lower reactor pressure to <845 psig.
BOP
* If directed, lowers pressure setpoint to <845 psig using the DEHC system (Placard)      as described on the following graphic.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                     Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       7                       Page 20 of 29 Event
9-0 5 Event No.:
7 Page 20 of 29 Event


== Description:==
== Description:==
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Time      Position  Applicant's Actions or Behavior BOP
* Notifies SRO that Pressure set has been reduced to <845 psig.
SRO
* Directs ATC to report reactor power or observes reactor power on SPDS.
* Directs ATC to Reset ARI and insert control rods IAW 31EO-EOP-103-2.


Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       7                       Page 21 of 29 Event
Time Position Applicant's Actions or Behavior BOP  Notifies SRO that Pressure set has been reduced to <845 psig.
SRO  Directs ATC to report reactor power or observes reactor power on SPDS.
Directs ATC to Reset ARI and insert control rods IAW 31EO-EOP-103-2.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
7 Page 21 of 29 Event


== Description:==
== Description:==
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Time      Position  Applicant's Actions or Behavior NOTE: If asked, STA will direct the ATC to start in the center of the core and spiral out in a black and white pattern.
SIMULATOR OPERATOR: Once ARI is in TEST & ALL Reactor Scrams signals have been jumpered out, DELETES malfunction mfC71_59, Spurious Reactor Scram.
ATC
* Enters 31EO-EOP-103-2, EOP Control Rod Insertion Methods, section 3.7, Driving Control Rods at panel 2H11-P603.
* Confirms ARI initiation signals are clear and Then depresses ARI Reset pushbutton OR dispatches an operator to place ARI System Test switch, to TEST, on panel 2C11-P001
* Check annunciator ARI INITIATED,603-304, clear
* Attempts to drive rods by:
* Places Reactor Mode switch to REFUEL.
* Places Rod Worth Minimizer bypass switch to BYPASS.
* Obtain recommendations from STA
* Verifies adequate CRD drive water pressure for driving rods and may operate 2C11-R600, CRD Flow Control, to achieve higher drive water DP.
* May start second CRD pump
* Drives rods to at least 02 using the Emerg In or IN (Critical Task)
ATC
* Enters 31EO-EOP-103-2, EOP Control Rod Insertion Methods, section 3.3, Repeating Manual Scram at panel 2H11-P603.
* Bypasses scram discharge volume high level trip at 2H11-P603.
* Dispatches operator to install jumpers to override all automatic scram signals.
* Places Discharge Volume Isolation Test switch to Norm at 2H11-P603.
* Resets Scram when notified that jumpers have been installed.
* Confirm all SDV Vent and Drain Valves are open.


Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       7                     Page 22 of 29 Event
Time Position Applicant's Actions or Behavior NOTE: If asked, STA will direct the ATC to start in the center of the core and spiral out in a "black and white" pattern.
SIMULATOR OPERATOR:
Once ARI is in TEST & ALL Reactor Scrams signals have been jumpered out, DELETES malfunction mfC71_59, Spurious Reactor Scr am. ATC  Enters 31EO
-EOP-103-2, EOP Control Rod Insertion Methods,  section 3.7, Driving Control Rods at panel 2H11-P603. Confirms ARI initiation signals are clear and Then depresses ARI Reset pushbutton OR dispatches an operator to place ARI System Test switch, to TEST, on panel 2C11
-P001  Check annunciator ARI INITIATED, 603-304, clear  Attempts to drive rods by:
Place s Reactor Mode switch to REFUEL.
Place s Rod Worth Minimizer bypass switch to BYPASS.
Obtain recommendations from STA Verifies adequate CRD drive water pressure for driving rods and may operate 2C11
-R600, CRD Flow Control, to achieve higher drive water DP.
May start second CRD pump Drive s rods to at least 02 using the Emerg In or IN (Critical Task
)        ATC  Enters 31EO
-EOP-103-2, EOP Control Rod Insertion Methods,  section 3.3 , Repeating Manual Scram at panel 2H11-P603. Bypasses scram discharge volume high level trip at 2H11
-P603. Dispatches operator to install jumpers to override all automatic scram signals. Places Discharge Volume Isolation Test switch to Norm at 2H11
-P603. Resets Scram when notified that jumpers have been installed.
Confirm all SDV Vent and Drain Valves are open
.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
7 Page 22 of 29 Event


== Description:==
== Description:==
Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Time      Position  Applicant's Actions or Behavior NOTE: 2C11-R607, Press Control Vlv F127, controller is failed to allow only ~25% valve position. A valve position of 25% will NOT allow control rods to insert from Cooling Water DP.
* Enters 31EO-EOP-103-2, EOP Control Rod Insertion Methods, section 3.8, Increasing CRD Cooling Water Dp at panel 2H11-P603.
* Places 2C11-R607, Press Control Vlv F127 Controller, in MAN
* Increases output of 2C11-R607 to 100% at 2H11-P603
* Confirms open OR fully opens 2C11-F003
* Places 2C11-R600, CRD Flow Control, in MANUAL
* Increases output of 2C11-R600 to 100%
* Closes 2C11-F005, Return To Vessel Flow Control Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.


Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.
Appendix D                     Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       8                     Page 23 of 29 Event
Time Position Applicant's Actions or Behavior NOTE: 2C11-R607, Press Control Vlv F127
, controller is failed to allow only ~25% valve position. A valve position of 25% will NOT allow control rods to insert from Cooling Water DP.
Enters 31EO
-EOP-103-2, EOP Control Rod Insertion Methods,  section 3.8, Increasing CRD Cooling Water Dp at panel 2H11-P603. Places 2C11
-R607, Press Control Vlv F127 Controller, in MAN Increases output of 2C11
-R607 to 100% at 2H11
-P603  Confirms open OR fully opens 2C11
-F003  Places 2C11
-R600, CRD Flow Control, in MANUAL Increases output of 2C11
-R600 to 100%
Closes 2C11
-F005, Return To Vessel Flow Control Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
8 Page 23 of 29 Event


== Description:==
== Description:==
SBLC first pump fails to inject, second pump works.
SBLC first pump fails to inject, second pump works.
Time Position Applicant's Actions or Behavior Simulator Operator; ENSURE malfunctions ENSURE EVENT TRIGGERS (EGC41-1 &EGC41-2) THAT WILL PREVENT THE FIRST PUMP STARTING BUT NOT THE SECOND are inserted. They were inserted from the beginning.
Time     Position Applicant's Actions or Behavior Simulator Operator; ENSURE malfunctions ENSURE EVENT TRIGGERS (EGC41-1 &EGC41-2) THAT WILL PREVENT THE FIRST PUMP STARTING BUT NOT THE SECOND are inserted. They were inserted from the beginning.
ATC Injects SBLC (power >5%)
ATC
Unlocks and places SBLC pump select switch in "Start Sys A" or "Start Sys B" position.
* Injects SBLC (power >5%)
Confirms Squib Valve Ready Lights are extinguished.
* Unlocks and places SBLC pump select switch in Start Sys A or Start Sys B position.
Confirms SBLC Loss of Continuity to Squib Valve annunciator is alarmed. Recognizes that the selected SBLC pump DID NOT start.
* Confirms Squib Valve Ready Lights are extinguished.
Places SBLC pump select switch in "Start Sys B" or "Start Sys A" position. (The pump not attempted first.)
* Confirms SBLC Loss of Continuity to Squib Valve annunciator is alarmed.
Confirms the selected second SBLC pump started.
* Recognizes that the selected SBLC pump DID NOT start.
Confirms closed 2G31
* Places SBLC pump select switch in Start Sys B or Start Sys A position. (The pump not attempted first.)
-F004 (RWCU Isolation Valve).
* Confirms the selected second SBLC pump started.
Reports to SRO, SBLC is injecting IAW 34SO
* Confirms closed 2G31-F004 (RWCU Isolation Valve).
-C41-003-2 and the first pump selected failed to start.
* Reports to SRO, SBLC is injecting IAW 34SO-C41-003-2 and the first pump selected failed to start.
Simulator operator proceeds to the next event at the Chief Examiner's direction.
Simulator operator proceeds to the next event at the Chief Examiners direction.


Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
Appendix D                       Required Operator Actions                     Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:         9                     Page 24 of 29 Event
9-0 5 Event No.:
9 Page 24 of 29 Event


== Description:==
== Description:==
RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.
Time      Position  Applicant's Actions or Behavior SRO      Directs an operator to INHIBIT ADS.
ATC/BOP
* 2H11-P602, Places the following switches to INHIBIT:
* ADS Channel A / C Auto Logic Inhibit switch (2B21C-S7A)
* ADS Channel B / D Auto Logic Inhibit switch (2B21C-S7B)
NOTE: Simulator Operator, ENSURE Event Trigger ET-EGB21-7, trips both RFPTs when RWL is <-40.
SRO
* Directs BOP control RWL -60 inches to -90 inches.
* As time allows, directs BOP to verify Isolations and ECCS initiations.
BOP
* Reports failure of HPCI and RCIC to auto initiate at - 35.
* Reports failure of both RFPTs.
* Reduces injection to control RWL -60 inches to -90 inches.
* If HCPI was manually started, the operator will reduce controller output to lower RWL.
* If HCPI was in standby, places 2E41-C002-3, HPCI Aux. Oil Pump, in PULL-TO-LOCK.
* If RCIC were manually started, the operator may depress the RCIC turbine trip push-button or reduce controller output.
BOP      Controls RWL -60 inches to -90 inches using RCIC and/or HPCI.


RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.
Appendix D                     Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.:       9                     Page 25 of 29 Event
Time Position Applicant's Actions or Behavior SRO Directs an operator to "INHIBIT ADS".
ATC/BOP  2H11-P602, Places the following switches to INHIBIT:
ADS Channel A / C Auto Logic Inhibit switch (2B21C
-S7A)  ADS Channel B / D Auto Logic Inhibit switch (2B21C
-S7B)      NOTE: Simulator Operator, ENSURE Event Trigger ET-EGB21-7 , trip s both RFPTs when RWL is <
-40". SRO  Directs BOP control RWL
-60 inches to
-90 inches.
As time allows, directs BOP to verify Isolations and ECCS initiations.
BOP  Reports failure of HPCI and RCIC to auto initiate at
- 35". Reports failure of both RFPTs.
Reduces injection to control RWL
-60 inches to
-90 inches.
If HCPI was manually started, the operator will reduce controller output to lower RWL. If HCPI was in standby, places 2E41
-C002-3, HPCI Aux. Oil Pump, in PULL-TO-LOCK. If RCIC were manually started, the operator may depress the RCIC turbine trip push
-button or reduce controller output.
BOP Controls RWL
-60 inches to
-90 inches using RCIC and/or HPCI.
Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
9 Page 25 of 29 Event


== Description:==
== Description:==
RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.
Time      Position  Applicant's Actions or Behavior BOP      IF RCIC injection is attempted AND RCIC was manually tripped:
* IF RWL is <-35 inches, recognizes and informs the SRO that RCIC failed to auto start
* Transfers 2E51-R612, Turbine Controller, to manual and adjust output to 50%.
* Closes 2E51-F524, Trip & Throttle Valve.
* Opens 2E51-F045, Stm to Turb Valve.
* Opens 2E51-F046, Turb Clg Water Valve.
* Starts 2E51-C002-2, Barom Cndsr Vac Pump.
* Throttle opens 2E51-F524, Trip & Throttle Valve, AND concurrently opens 2E51-F013, Pump Discharge Valve
* Confirms 2E51-F019, Min Flow Valve, Opens, AND subsequently closes, when system flow is greater than 79.3 gpm.
* Continues to throttle 2E51-F524 Open, until turbine speed is limited by 2E51-R612, Turbine Controller, then perform the following:
* Fully opens 2E51-F524, Trip & Throttle Valve.
* Increases 2E51-R612, Turbine Controller, output to achieve 3000 to 4000 rpm.
* Transfers 2E51-R612, Turbine Controller, to auto and adjust to desired flow rate.
* Maintains level -60 to -90 BOP      IF RCIC injection is attempted and RCIC has NOT been tripped:
* Depresses RCIC Manual Initiation P/B (failed)
* Opens 2E51-F046
* Starts Barom Cndsr Vac Pmp
* Opens 2E51-F045
* Confirms open 2E51-F019
* Confirms closed 2E51-F019 at flow > 79.3 gpm
* Opens 2E51-F013
* Adjusts controller for desired flow
* Maintains level -60 to -90


RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.
Appendix D                       Required Operator Actions                   Form ES-D-2 Op-Test No.: 2015-301   Scenario No.: 9-05 Event No.:       9                     Page 26 of 29 Event
Time Position Applicant's Actions or Behavior BOP IF RCIC injection is attempted AND RCIC was manually tripped:
IF RWL is <
-35 inches, recognizes and informs the SRO that RCIC failed to auto start Transfers 2E51
-R612, Turbine Controller, to manual and adjust output to 50%. Closes 2E51
-F524, Trip & Throttle Valve.
Opens 2E51
-F045, Stm to Turb Valve.
Opens 2E51
-F046, Turb Clg Water Valve.
Starts 2E51
-C002-2, Barom Cndsr Vac Pump.
Throttle opens 2E51
-F524, Trip & Throttle Valve, AND concurrently opens 2E51
-F013, Pump Discharge Valve Confirms 2E51
-F019, Min Flow Valve, Opens, AND subsequently closes, when system flow is greater than 79.3 gpm.
Continues to throttle 2E51
-F524 Open, until turbine speed is limited by 2E51-R612, Turbine Controller, then perform the following:
Fully opens 2E51
-F524, Trip & Throttle Valve.
Increases 2E51
-R612, Turbine Controller, output to achieve 3000 to 4000 rpm. Transfers 2E51
-R612, Turbine Controller, to auto and adjust to desired flow rate.
Maintains level
-60" to -90"          BOP IF RCIC injection is attempted and RCIC has NOT been tripped:
Depresses RCIC Manual Initiation P/B (failed)
Opens 2E51
-F046  Starts Barom Cndsr Vac Pmp Opens 2E51
-F045  Confirms open 2E51
-F019  Confirms closed 2E51
-F019 at flow > 79.3 gpm Opens 2E51
-F013  Adjusts controller for desired flow Maintains level
-60" to -90" Appendix D Required Operator Actions Form ES-D-2   Op-Test No.: 2015-301 Scenario No.:
9-0 5 Event No.:
9 Page 26 of 29 Event


== Description:==
== Description:==
RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.
RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.
Time Position Applicant's Actions or Behavior BOP If HPCI injection is attempted the operator:
Time     Position Applicant's Actions or Behavior BOP     If HPCI injection is attempted the operator:
IF RWL is <
* IF RWL is <-35 inches, recognizes and informs the SRO that HPCI failed to auto start
-35 inches, recognizes and informs the SRO that HPCI failed to auto start Opens 2E41
* Opens 2E41-F059, Lube Oil Clg Wtr Valve.
-F059, Lube Oil Clg Wtr Valve.
* Starts 2E41-C002-2, Barom Cndsr Vacuum Pump.
Starts 2E41
* Opens 2E41-F001, Turb Steam Supply Valve.
-C002-2, Barom Cndsr Vacuum Pump.
* Take 2E41-C002-3, Aux Oil Pump, control switch to the START position.
Opens 2E41
* Open 2E41-F006, Pump Discharge Valve.
-F001, Turb Steam Supply Valv
* Confirm 2E41-F012, Min Flow Valve, CLOSES at flow > 790 gpm.
: e. Take 2E41-C002-3, Aux Oil Pump, control switch to the START position. Open 2E41-F006, Pump Discharge Valve.
Confirm 2E41
-F012, Min Flow Valve, CLOSES at flow > 790 gpm.
CONTINUOUS RECHECK:
CONTINUOUS RECHECK:
Simulator Operator, when the following conditions exist: 1. Scram is RESET, 2. RWL is controlled between  
Simulator Operator, when the following conditions exist:
-60 and -90 inches, WITH CHIEF EXAMINERS DIRECTION, the scenario may be terminated.
: 1. Scram is RESET,
: 2. RWL is controlled between -60 and -90 inches, WITH CHIEF EXAMINERS DIRECTION, the scenario may be terminated.
 
Page 27 of 29 Appendix D                                Scenario Outline                          Form ES-D-1 NRC FINAL Facility:    E. I Hatch            Scenario No.: 9-05      Op-Test No.:    2015-301 Examiners:                                    Operators:                                            SRO RO BOP Initiating Conditions:    Unit 2 is operating at 70% RTP. RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance. 2D LLS valve is inop for LLS Function only.
Turnover                  Lower Torus level to 147.5 inches, and then increase reactor power to 75%.
Summary:
* Event 1: Normal; Lower Torus level to 147.5 inches using RHR Loop 2B IAW 34SO-E11-010-2, Step 7.4.5.1.
* Event 2: Reactivity; The ATC will raise Reactor power to ~75% RTP.
* Event 3: Component; The CRD Flow Controller fails closed causing a loss of normal CRD flow. The ATC will place the controller in manual and restore CRD flow.
* Event 4: Component/TS; SRV 2G opens. The ATC operator will attempt to close the SRV IAW the abnormal procedure for an electrically open SRV. After the ATC operator cycles the SRV control switch, the SRV will close. (Critical Task) If Torus temperature exceeds 95&deg;F, the BOP operator will place RHR in Suppression Pool Cooling. SRO addresses TS for inoperable SRV.
* Event 5: Component; System Operator reports Condensate Booster pump B has an oil leak, Standby pump must be started, B shutdown.
* Event 6: Component/TS; Instrument Bus 2B supply breaker from Essential 2B will trip open de-energizing subsequent loads. Once investigated, Instrument Bus 2B will be energized from Instrument Bus 2A and the BOP will return loads to service.
* Event 7: Major; A Spurious Turbine trip will cause a Reactor scram and subsequent ATWS.
The SRO will direct/ensure the ATC inserts control rods within 20 minutes of the scram and inject SBLC prior to leaving RC-1. (Critical Task)
* Event 8: Component; The first SBLC pump fails to start, second pump works injecting SBLC prior to the ATC leaving RC-1.
* Event 9: Component; RCIC and HPCI fail to auto start. RCIC must be manually aligned and started to maintain RWL -60 to -90. (Critical Task)
 
Page 28 of 29 Critical Tasks NRC FINAL Facility:    E. I Hatch          Scenario No.: 9-05        Op-Test No.:    2015-301 Critical Tasks
* Cycles the SRV control switch to close SRV (Event 4)
* Begins inserting control rods within 20 minutes of scram/injects SBLC before leaving RC-1.
(Event 7/8)
* RCIC/HPCI must be manually aligned and started to maintain RWL -60 to -90 (Event 9)
ES 301-4 Attributes    Required      Actual                            Items
: 1. Total Malfunctions          5-8          7      1. ATC uses controller in manual to restore CRD flow (Event 3)
: 2. SRV 2G opens (Event 4)
: 3. Condensate Booster pump B oil leak, Standby pump must be started, B shutdown (Event 5)
: 4. Instrument Bus 2B breaker fails (Event 6)
: 5. Spurious Reactor scram/ ATWS (Event 7)
: 6. SBLC Pump 2A & 2B start failure (1st pump)
(Event 8)
: 7. RCIC/HPCI Auto start failure (Event 9)
: 2. Malfunctions After          1-2          2      1. SBLC Pump 2A & 2B start failure (1st pump)
EOP Entry                                            (Event 8)
: 2. RCIC/HPCI Auto start failure (Event 9)
: 3. Abnormal Events            2-4          3      1. ATC uses controller in manual to restore CRD flow (Event 3)
: 2. SRV 2G opens (Event 4)
: 3. Instrument Bus 2B breaker fails (Event 6)
: 4. Major Transients            1-2          1      1. Spurious Reactor scram/ ATWS (Event 7)
: 5. EOPs entered,              1-2          1      1. 31EO-EOP-011, RCA, (Event 7) requiring substantive actions
: 6. EOPs contingencies          0-2          1      1. 31EO-EOP-017, CP-3, (Event 7) requiring substantive actions
: 7. Critical Tasks              2-3          3      1. SRV 2G opens (Event 4)
: 2. Control Rods & SBLC injection (Event 7/8)
: 3. RCIC/HPCI Auto start failure (Event 9)


Page 27 of 29 Appendix D Scenario Outline Form ES-D-1  NRC FINAL  Facility: E. I Hatch Scenario No.:
ILT 9 NRC FINAL Scenario 5 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions:      Activities in progress: 34SV-P41-001-1, Plant Service Water Pump Operability.
9-05 Op-Test No.: 2015-301  Examiners:
UNIT 2 STATUS Unit 2 is operating at approximately 70% RTP.
Operators:
Plant Conditions:
SRO    RO    BOP  Initiating Conditions:
Activities in progress: RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance..
Unit 2 is operating at 7 0% RTP. RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance.
Protected Train:                                     EOOS:
2D LLS valve is inop for LLS Function only.
Division I                           Green                          Orange Division II                           Yellow                         Red Lower Torus level to 147.5 inches.
Turnover Lower Torus level to 147.5 inches, and then increase reactor power to 75%. Summary:  Event 1:  Normal;  Lower Torus level to 147.5 inches using RHR Loop "2B" IAW 34SO
Scheduled evolutions:
-E11-010-2, Step 7.4.5.1.
After Torus level is lowered increase reactor power to 75%.
Event 2:  Reactivity; The ATC will raise Reactor power to ~
Surveillances due this None shift:
75% RTP. Event 3:  Component; The CRD Flow Controller fails closed causing a loss of normal CRD flow. The ATC will place the controller in manual and restore CRD flow. Event 4:  Component/TS; SRV "2G" opens. The ATC operator will attempt to close the SRV IAW the abnormal procedure for an electrically open SRV. After the ATC operator cycles the SRV control switch, the SRV will close.
Inop Equipment:         2D LLS valve is inop for LLS Function only.
(Critical Task
Active tagouts:       2D LLS valve.
)  If Torus temperature exceeds 95&deg;F, the BOP operator will place RHR in Suppression Pool Cooling. SRO addresses TS for inoperable SRV.
Rod Configuration:       See RWM}}
Event 5:  Component; System Operator reports Condensate Booster pump "
B" has an oil leak, Standby pump must be started, "
B" shutdow n. Event 6:  Component/TS; Instrument Bus 2B supply breaker from Essential 2B will trip open de
-energizing subsequent loads. Once investigated, Instrument Bus 2B will be energized from Instrument Bus 2A and the BOP will return loads to service. Even t 7:  Major; A Spurious Turbine trip will cause a Reactor scram and subsequent ATWS. The SRO will direct/ensure the ATC inserts control rods within 20 minutes of the scram and inject SBLC prior to leaving RC
-1.  (Critical Task
)    Event 8:  Component; The first SBLC pump fails to start, second pump works injecting SBLC prior to the ATC leaving RC
-1. Event 9:  Component; RCIC and HPCI fail to auto start. RCIC must be manually aligned and started to maintain RWL
-60" to -90".  (Critical Task
)
Page 28 of 29 Critical Tasks  NRC FINAL Facility: E. I Hatch Scenario No.:
9-05 Op-Test No.: 2015-301  Critical Tasks  Cycles the SRV control switch to close SRV (Event 4)    Begins inserting control rods within 20 minutes of scram
/injects SBLC before leaving RC
-1.  (Event 7/8)  RCIC/HPCI must be manually aligned and started to maintain RWL
-60" to -90"  (Event 9)  ES 301-4 Attributes Required Actual Items 1. Total Malfunctions 5-8 7 1. ATC uses controller in manual to restore CRD flow  (Event 3) 2. SRV "2G" opens  (Event 4) 3. Condensate Booster pump "
B" oil leak, Standby pump must be started, "
B" shutdown (Event 5) 4. Instrument Bus 2B breaker fails (Event 6) 5. Spurious Reactor scram/ ATWS  (Event 7) 6. SBLC Pump '2A' & '2B' start failure (1 st pump)  (Event 8) 7. RCIC/HPCI Auto start failure  (Event 9) 2. Malfunctions After EOP Entry 1-2 2 1. SBLC Pump '2A' & '2B' start failure (1 st pump)  (Event 8) 2. RCIC/HPCI Auto start failure  (Event 9) 3. Abnormal Events 2-4 3 1. ATC uses controller in manual to restore CRD flow  (Event 3) 2. SRV "2G" opens  (Event 4)  3. Instrument Bus 2B breaker fails  (Event 6) 4. Major Transients 1-2 1 1. Spurious Reactor scram/ ATWS  (Event 7) 5. EOPs entered, requiring substantive actions  1-2 1 1. 31EO-EOP-011, RCA,  (Event 7) 6. EOPs contingencies requiring substantive actions 0-2 1 1. 31EO-EOP-017, CP-3 ,  (Event 7) 7. Critical Tasks 2-3 3 1. SRV "2G" opens  (Event 4) 2. Control Rods & SBLC injection (Event 7/8) 3. RCIC/HPCI Auto start failure  (Event 9)
ILT 9 NRC FINAL Scenario 5 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Plant Conditions:
Unit 1 is operating at 100% power Activities in progress: 34SV
-P41-001-1, Plant Service Water Pump Operability.
UNIT 2 STATUS Plant Conditions:
Unit 2 is operating at approximately 70% RTP.
Activities in progress: RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance.
. Protected Train:
EOOS:   Division I   Division II Green    Yellow   Orange  Red Scheduled evolutions
Lower Torus level to 147.5 inches. After Torus level is lowered increase reactor power to 75%.
Surveillances due this shift: None  Inop Equipment:
2D LLS valve is inop for LLS Function only.
Active tagouts
: 2D LLS valve
. Rod Configuration
: See RWM}}

Latest revision as of 11:50, 5 February 2020

Initial Exam 2015-301 Final Simulator Scenarios
ML15176A543
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 06/22/2015
From:
NRC/RGN-II
To:
Southern Nuclear Operating Co
References
50-321/15-301, 50-366/15-301 50-321/15-301, 50-366/15-301
Download: ML15176A543 (110)


Text

Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-02 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initial Conditions. Unit 2 is operating at 75%RTP.

Turnover: Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82%

RTP using the Recirculation System.

Event Malf. No. Event Event No. Type* Description Restoration To Normal Hydrogen Seal Oil System Lineup starting at 1 N/A N (BOP) step 7.3.3.2.5 of 34SO-N42-001-2.

2 N/A R (ATC) Raise Reactor power to 82% using Recirc.

mfR22_183 4160V Emergency Bus 2F de-energizes due to a hard ground. With mfR22_256 C (BOP) 3 time compression repair and re-energizes. 1B EDG Generator Over mf65223700 TS (SRO) current Alarm (off).

ET-R43-1 4 N/A C (ATC) Loss of CRD due to power failure.

Feedwater pump 2B cooling water controller failure. TC repair and 5 mfN21_88B I (BOP) return to auto.

mfB31_39A mfB31_45A C (ATC) Recirc Pump A Seal Leakage causes DW leakage & pressure 6 mfB31_29 TS (SRO) increase. Pump is secured & isolated. (Critical Task) mf60213160 7 mfG31_242 M (ALL) Leak in Drywell causes High Drywell pressure scram.

ET-E11-11 1st RHR 2E11-F016A/B Containment Spray Valve causes associated 8 C (ATC)

ET-E11-12 RHR pumps to trip. (Critical Task)

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 1 Page 2 of 28 Event

Description:

Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2.

Time Position Applicant's Actions or Behavior Simulator Operator, IF contacted as SO, report the following:

  • Seal Oil Vacuum Pump Separator Tank oil level is between the High AND Low Oil Level on 2N42-LG-R306, Separator Tank Sight Glass 10
  • 2N42-F042, Vacuum Tank Inlet Valve, open Mins
  • Oil level in the Vacuum Tank is above the bottom of the lower observation window
  • Seal Oil Vacuum Pump shaft has been manually rotated.
  • Enters Restoration To Normal Hydrogen Seal Oil System Lineup at step 7.3.3.2.5

Simulator Operator, WHEN contacted as SO, 2N42-R302, Vacuum Tank Pressure, is 26.5 in. Hg and steady.

  • Confirms 2N42-R302, Vacuum Tank Pressure, stabilizes above 26 in. Hg. by contacting SO locally.

BOP

  • Secure 2N42-C002, Emergency Seal Oil Pump, as follows:
  • Holds control switch for ESOP in OFF Pull To Lock position until pump stops as indicated by its extinguished red AND green lights
  • Alarm EMERG SEAL OIL PUMP RUNNING, (651-216) will clear after the SO resets the local panel.
  • AFTER pump stops, releases control switch.
  • Confirm its green light is illuminated.

Simulator Operator, when contacted as SO, report the following:

  • 2N42-R300, Seal Oil Pump Disch Press, is 105 psig
  • 2N42-R301, Seal Oil / Machine Gas dP, pressure, is 8 psig above generator gas pressure.
  • If asked, inform BOP the Emergency Seal Oil Pump shaft has stopped rotating.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 1 Page 3 of 28 Event

Description:

Restoration To Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2.

Time Position Applicant's Actions or Behavior Simulator Operator, when contacted as SO, report the following:

  • DELETE mf65121574, EMERGENCY SEAL OIL PUMP RUNNING (ANNUNCIATOR ON)
  • REPORT Local alarm, EMERG SEAL OIL PUMP RUNNING, (N43-105) has been reset
  • Confirms the following by contacting SO locally:
  • 2N42-R301, Seal Oil / Machine Gas dP, pressure, is being maintained 7 - 9 psig above generator gas pressure.

Simulator Operator, at the Chief Examiners request, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 2 Page 4 of 28 Event

Description:

Raise Reactor power to 70% using Recirc.

Time Position Applicant's Actions or Behavior

  • Directs ATC to increase reactor power to 82% by increasing Recirc flow.

10 Min SRO Power increases are NOT to exceed 10 MWe/min.

NOTE: May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.

May also get Alarm HEATER TROUBLE, (650-135), alarm. This is expected at this power level.

  • IAW 34SO-B31-001-2 (step 7.1.5) & 34GO-OPS-005-2, the ATC increases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master (P603 panel) or Individual controls (P602 panel) until reactor power is 82%.

ATC

  • If using Individual Controls, pump speed increases will alternate between the A & B Recirc pumps to prevent excessive flow mismatches.
  • Monitors power increase by observing APRM and generator output indications.

WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:

ATC

  • <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating

< 70% of rated core flow; AND

  • <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at

> 70% of rated core flow.

ATC Notifies the SRO that reactor power has been increased to 82%.

Simulator Operator, at the Chief Examiners direction OR after power has been increased by 5%, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 3 Page 5 of 28 Event

Description:

2F Emergency Bus de-energizes due to a hard ground.

Time Position Applicant's Actions or Behavior NOTE TO CHIEF EXAMINER:

15 Min Event 3 (4160V Emergency Bus 2F loss) and Event 4 (Loss of CRD) will be running concurrently.

Simulator Operator, at direction of the Chief Examiner, ACTIVATE: (RB-3) and ENSURE Event Trigger ET-EGR43-1 ACTIVATES

  • mfR22_183, 2F 4160 bus fault
  • ET-EGR43-1 NOTE: With the loss of 2F 4160V bus, the BOP may address 34AB-R22-002-2, Loss of 4160V Emergency Bus, first. Also the following alarms may be addressed in any order.

The following alarms associated with 2F 4160V bus will be received:

  • LOSS OF OFF SITE POWER, (652-202)
  • PSW PRESS LOW, (652-210)

ALL

  • 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652-217)
  • 4160V BUS 2F VOLTAGE LOW, (652-222)
  • 4160 STA SVC FDR BRKR TRIP, (650-137)

BOP 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652-217) AND PSW PRESS LOW, (652-210).

  • Responds to annunciator, LOSS OF OFF SITE POWER, (652-202),
  • 4160V Bus 2F LOSP Lockout Relay is locked out
  • 4160V Emergency Bus 2F is energized.
  • 600V Emergency Buses 2C AND 2D are energized

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 3 Page 6 of 28 Event

Description:

2F Emergency Bus de-energizes due to a hard ground.

Time Position Applicant's Actions or Behavior

  • Responds to annunciator 4160V BUS 2F BRKR 135564 TRIPPED/LKDOUT, (652-217),

BOP

  • Normal Supply breaker 135574 open
  • Alternate Supply breaker 135564 open
  • 1B EDG Output breaker 135570 open:
  • Dispatches SO/Maintenance to investigate the loss of 4160V Bus 2F
  • Observes 2P41-C002, STBY PSW Pump, has no lights illuminated.
  • Observes 2P41-C002, STBY PSW Pump, red light illuminates.

(This restores cooling water to the 1B DG.)

  • Confirm 1B Diesel Generator has auto started
  • Ensure adequate cooling water is available to the 1B Diesel Generator (if NOT previously performed):
  • Observes 2P41-C002, STBY PSW Pump, has no lights BOP illuminated.
  • Observes 2P41-C002, STBY PSW Pump, red light illuminates.

(This restores cooling water to the 1B Diesel Generator.)

  • May dispatch a Systems Operator to locally trip the 1B EDG.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 3 Page 7 of 28 Event

Description:

2F Emergency Bus de-energizes due to a hard ground.

Time Position Applicant's Actions or Behavior

  • Directs the BOP to enter 34AB-R22-002-2 for the loss of 4160V SRO Emergency Bus Simulator Operator: If called as the SO to trip the 1B DG, enter RB-1 to activate rfR43_162 Diesel Gen 1B Engine Fuel Rack.
  • Addresses Tech Specs 3.8.7 and enters an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> RAS per TS 3.8.7.C.1 to restore AC electrical power distribution subsystem to operable status.
  • Enters TS 3.8.1 if SRO believes 1B EDG output breaker failed to close or if 1B EDG is ordered tripped locally due to no cooling water, and performs Conditions:

B.1 in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> perform surveillance on operable required off-site circuits (34SV-SUV-013-0, Weekly Breaker Alignment Checks)

AND B.2 declare required features supported by the DG inoperable when redundant required features are inoperable (required redundant features ARE operable)

SRO AND B.3.1 in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> determines operable DG(s) are NOT inoperable due to common cause failure OR B.3.2 in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> performs surveillance on operable DG(s).

AND B.4 in 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Restore 1B DG to operable status

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 3 Page 8 of 28 Event

Description:

2F Emergency Bus de-energizes due to a hard ground.

Time Position Applicant's Actions or Behavior Simulator Operator, After being dispatched, wait 5 minutes and NOTIFY the U2 SRO and INFORM, as Maintenance Electrical Team Leader, there is a fault on 2F Emergency bus and we are still investigating.

NOTE: The 2C PSW pump would be considered inoperable if alarm, PSW PUMP 2C OVLD/LOCKOUT RELAY TRIP, (650-230), were received, however in this case, the alarm was not received and the pump is just de-energized.

  • On 2H11-P650 confirms that 2C PSW pump amber light is illuminated.

BOP

  • Once cause has been determined and corrected, takes the control switch for 2C PSW pump to off and spring returns to auto to clear amber light.
  • If directed, restarts 2C PSW pump.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 4 Page 9 of 28 Event

Description:

Loss of CRD due to power failure.

Time Position Applicant's Actions or Behavior NOTE to Simulator Operator: NO additional malfunctions need to be entered 5 Mins for this event. This event stems from the loss of 2F 4160V bus.

NOTE: With the loss of CRD, the ATC may address 34AB-C11-001-2, Loss Of CRD, first. The following alarms may be addressed in any order.

The following alarms associated with 2F 4160V bus will be received:

  • CRD PUMP B BREAKER TRIP, (603-129)

ALL

  • CRD TEMP HIGH, (603-140)

ATC

  • Notifies SRO that B CRD pump has tripped.

SRO Directs ATC to enter 34AB-C11-001-2, Loss Of CRD

  • Check the following indications on 2H11-P603:
  • Pump indicating lights.

ATC

  • 2C11-R605, Cooling Wtr indicator, indicates zero flow.
  • 2C11-R601, Charging Water Pressure indicator decreasing.
  • 2C11-R602, Drive Water DP indicator decreasing.
  • 2C11-R603, Cooling Water DP indicator decreasing.

ATC

  • Dispatches an operator to CRD Temperature Recorder, 2C11-R018, (130Rx Bldg) and check temperatures.
  • Dispatches an operator to determine local accumulator pressures.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 4 Page 10 of 28 Event

Description:

Loss of CRD due to power failure.

Time Position Applicant's Actions or Behavior Simulator Operator after 3 minutes, As the operator sent to the CRD temperature recorder, report that the highest temperature was 270 °F and several CRDs at this temperature.

Also inform that the operator sent to the CRD accumulators, reports that there are several accumulators with pressures less than 940 psig.

  • Places 2C11-R600, CRD Flow Control, in manual and decreases the output to zero.
  • Starts the A CRD pump.
  • Returns the flow controller to auto and output to the pre-trip position.

ATC

  • IF the applicant does NOT start the A CRD pump and the following conditions exist:
  • AND
  • THEN: within 20 minutes restore charging water header pressure >

940 PSIG or inserts a scram.

  • Terminates RAS once charging water pressure is restored above 940 psig.

Simulator Operator, After 2F 4160V Emergency bus is energized from 2D SAT AND CRD has been returned to service AND at the direction of the Chief Examiner, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 5 Page 11 of 28 Event

Description:

2B RFPT Cooling water controller failure. TC repair & return to Automatic.

Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator, INSTRUCT the ATC 8 Min operator by phone to stay on the line until told to hang up, THEN ENTER:

(RB-5) mfN21_88B, Feedwater Pump Lube Oil Cooling System Failure.

The following alarms will annunciate:

  • RFPT 2B BRG OIL TEMP HIGH, (650-315)

ALL

  • RFP/COND BRG METAL TEMP HIGH, (650-112), (approximately 1 minute later if 2B RFPT PSW TCV is NOT opened in a timely manner)

NOTE: The BOP may immediately place the controller in manual IAW 31GO-OPS-021-0, Manipulation and Control of Equipment OR NMP-OS-007-001, Conduct of Operations Standards and Expectations, responding to a failed controller.

  • Addresses the high temp annunciator, pulling the ARP and confirms temperatures:
  • At panel 2H11-P655, checks all temperature indicators on 2N32-R616 to BOP determine actual oil temperatures.
  • Recognizes the automatic function of the controller has failed, closing the cooling water valve.

BOP

  • Places the controller in manual, depresses the open/increase pushbutton, opening the valve. Oil temperatures begin decreasing and the alarm extinguishes.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 5 Page 12 of 28 Event

Description:

2B RFPT Cooling water controller failure. TC repair & return to Automatic.

Time Position Applicant's Actions or Behavior Notifies maintenance of the 2P41-R606, RFPT temperature controller, SRO problem.

DELETE mfN21_88B.

Simulator Operator, after 5 minutes of being dispatched, uses time compression and reports the automatic function of the temperature controller has been repaired and may be returned to service. As Shift Manager, grant permission to return controller to automatic mode.

SRO Directs the BOP to return 2P41-R606 to automatic operation.

  • Nulls controller and then depresses the automatic pushbutton on controller 2P41-R606.

BOP

  • Verifies the controller responds correctly in automatic.
  • Notifies the SRO the Lube Oil Temperature Controller has been returned to automatic.

Simulator Operator, at the Chief Examiners request, proceeds to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 13 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior Simulator Operator, with Chief Examiners Permission:

12 Min

  • Call control room BOP operator and tell them to stay on the phone until directed to hang up.
  • ACTIVATE: (RB-6) to start Recirc Pump 2A seal leakage, mfB31_39A.
  • Receives Annunciator, PUMP A SEAL STAGING FLOW HIGH/LOW, (602-122)
  • Observes and compares 2B31-R603A, Seal A No. 1 pressure indicator, AND 2B31-R602A, Seal A No. 2 pressure indicator, to determine the Inner

(#1) seal has failed (No. 1 pressure normal with No. 2 pressure > normal).

  • Notifies SRO that the Inner (#1) Seal on Recirc A has failed ATC
  • Directs a System Operator to confirm seal water flow to Pump A is between 1.6 to 2.2 gpm locally (this indication NOT available in the Control Room).
  • Assigns an extra operator perform 34SV-SUV-019-2, Surveillance Checks, to determine the magnitude of leakage.
  • May monitor Drywell pressure.

Simulator Operator, After the ATC operator has started executing steps in the Pump A Seal Staging Flow High/Low ARP, THEN Instruct the BOP operator to hang up the phone.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 14 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior Simulator Operator; After 3 minutes, NOTIFY the Chief Examiner AND then press (RB-2) to ACTIVATE: mfB31_45A (10/20), Recirc A Outer Seal Failure

(**IMPORTANT**)

  • Ensure the ATC responds to the OUTER SEAL A LEAK DETECTION FLOW HIGH, (602-116) and performs the next set of actions (Trip and isolate the 2A Recirc Pump).
  • Ensure the BOP operator is the person assigned to vent the Drywell.
  • OUTER SEAL A LEAK DETECTION FLOW HIGH, (602-116)
  • DRYWELL/TORUS RCDR R627 TEMP HIGH, (650-204)

All

  • DRYWELL FLOOR DRAINS SUMP LEAK HIGH-HIGH, (602-408)
  • Observes and compares 2B31-R603A, Seal A No. 1 pressure indicator AND 2B31-R602A, Seal A No. 2 pressure indicator, to determine the outer seal has now failed (No. 1 and No. 2 seal pressure decreases).
  • Notifies SRO that the Outer (#2) Seal on 2A Recirc has also failed.
  • Has an extra operator perform 34SV-SUV-019-2, Surveillance Checks, to determine magnitude of leak.

ATC

  • Monitors 2D11-R630, Fission Products Monitor recorder, to determine IF primary system coolant is leaking from seals on 2H11-P604.
  • Monitors Drywell pressure.
  • MULTIPOINT TEMPERATURE RCDR 2T47-R626 TEMPERATURE HIGH (657-025).

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 15 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior

  • Receives the following alarms

All

  • DRYWELL FLOOR DRAINS SUMP LEAK HIGH, (602-408)
  • Directs Operator to Check DW Leakage SRO
  • Directs the BOP to vent the DW with SBGT, when DW pressure approaches 0.65 psig.

NOTE: If the crew expeditiously isolates the 2A Recirc pump the following actions for venting the Drywell may not be required.

If necessary, the operator may place SBGT in service by using the Placard that's available or using the appropriate section of the procedure. These steps assume the Placard is used. The 2A or 2B SBGT Train may be used. The following steps are written assuming "2A" Train is used. If "2B" Train is used, substitute "2B" for "2A" for valves and the alarm numbers in parenthesis.

BOP

  • Places 2A (2B) SBGT Fan control switch to RUN
  • Alarm SBGT 2A (2B) SWITCH NOT IN AUTO, 657-091 (654-076),

will be received

  • Confirms SBGT 2A (2B) Heater red light illuminates

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 16 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior NOTE: The operator may place DW Venting in service by using the Placard that's available or using the appropriate section of the procedure. These steps assume the Placard is used. The 2A or 2B CAD Loop valves will be used first.

BOP

  • The following alarms will be received:
  • DRYWELL VENT EXHAUST BYPASS VALVES OPEN, (657-008)
  • DRWL/TORUS N 2 M/U 2 INCH ISOL VALVES OPEN, (657-042)
  • DRYWELL VENT EXHAUST BYPASS VALVES OPEN, (654-002)
  • DRWL/TORUS N 2 M/U 2 INCH ISOL VALVES OPEN, (654-035)
  • Monitors DW pressure
  • Confirms Drywell and Torus O 2 concentration is <4%, on 2P33-R603,Pri Cnmt Oxygen Recorder (P602) OR by lab sample

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 17 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior Simulator Operator; As the operator checking DW leakage, report:

  • DW Equipment drain leakage is stable at 1.7 gpm
  • Floor drain leakage has increased from 0.8 gpm to 12.1 gpm.
  • Directs operator to SHUTDOWN and isolate Recirc pump A
  • Enters Tech Specs:
  • 3.4.1 Recirculation Loops Operating
  • Condition: 3.4.1.A, Requirements of the LCO not met.

(i.e. single loop operations)

Required Action: Satisfy requirements of the LCO.

Completion time: 24 hrs.

SRO

Required Action: Reduce leakage to within limits.

Completion time: 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

Required Action: Reduce leakage increase to within limits.

Completion time: 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

  • Notifies STA or Reactor Engineering that new limits apply for APLHGR, MCPR, LHGR, and APRMs Simulated Thermal power - New Setpoints are required within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 18 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior

  • Per (602-116) and 34SO-B31-001-2, Recirc System, Performs one of the following to secure the Reactor Recirc Pump:
  • Either (actions for Immediate Shutdown)
  • Places the ASD A control switch in Pull to Lock (P602)
  • Depresses the ASD A Shutdown pushbutton (P602)
  • OR (Actions for Shutdown in a Timely Manner)
  • Depresses the ASD A Shutdown pushbutton (P602)

(2B31-R661)

ATC (2B31-R661) and drive coasts to 0 gpm (2B31-R614 or R617)

  • Confirms ASD A Start pushbutton illuminates
  • Closes 2B31-F031A, Reactor Recirc A Pump Disch Vlv
  • Closes 2B31-F023A, Reactor Recirc A Pump Suction Vlv
  • Notifies Plant Management and Load Dispatcher
  • RECIRC LOOP A OUT OF SERVICE, (602-127)
  • ASD A TRIP WARNING, (602-101)
  • ASD A TROUBLE, (602-108)

ATC

  • ASD A FATAL FAULT, (602-102)
  • RBM DOWNSCALE, (603-211)
  • ROD OUT BLOCK, (603-238)
  • HEATER TROUBLE ALARM, (650-135) (may come in and clear)

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 6 Page 19 of 28 Event

Description:

Recirc Pump A seal leakage causes DW leakage & pressure increase.

Pump is secured and isolated.

Time Position Applicant's Actions or Behavior Simulator Operator; AFTER the suction and discharge valves are closed for the 2A Recirc pump, an you are requested to close 2B31-F008, THEN:

  • MODIFY mfB31_45A (Final: 100 Ramp: 1000),Recirc A Outer Seal Failure."

AND THEN press (RB-11) to ACTIVATE:

  • rfB31_29, Recirc mini purge B31-F016A closure (simulates B31-F008A being closed)
  • mf60213160, Outer Seal A Leak Detection Flow High - Annunciator Off (602-116)

Simulator Operator; If another DW leakage check is requested, report:

  • Drywell floor drain leakage has decreased to 1.8 gpm.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 7 Page 20 of 28 Event

Description:

Leak in Drywell causes High Drywell pressure scram.

Time Position Applicant's Actions or Behavior Simulator Operator, at the direction of the Chief Examiners, ACTIVATES:

(RB-7), mfG31_242 RWCU Non-Isol Leak in Drywell (final 1.0, ramp 1000).

Recognizes increasing Containment Pressure from the following alarms:

  • PRIMARY CNMT HIGH PRESSURE TRIP, (603-106),

ALL

  • PRIMARY CNMT PRESSURE HIGH, (603-115),
  • DRYWELL PRESSURE HIGH, (602-210).

NOTE: The SRO may direct the BOP to vent the Drywell, but there will NOT be time to complete the task before the LOCA signal is received.

  • With Drywell pressure increasing and alarms PRIMARY CNMT PRESSURE HIGH, (603-115) and DRYWELL PRESSURE HIGH, (602-210), alarms being received, directs the ATC enter 34AB-C71-001-2, Scram Procedure, and Scram the reactor.

SRO

  • Assigns the ATC to perform RC-1,
  • Assigns the BOP operator to perform RC-2 and RC-3,
  • Enters RC & PC EOP flow charts,
  • Assigns a RWL band between 3 and 50.

Simulator Operator, WHEN the reactor is scrammed, ENSURES ET-EGC71-12 MODIFIES mfG31_242 Final to 1.5 with a ramp of 1000 AFTER 180 seconds.

  • Performs RC-1 consisting of:
  • Places the mode switch to SHUTDOWN.
  • Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
  • Notifies SRO of rod position check.

ATC

  • Places SDV isolation valve switch to "isolate" & confirms closed.
  • If NOT tripped, places the Recirc pumps at minimum speed.
  • Shifts recorders to read IRMS, when required.
  • Ranges IRMS to bring reading on scale.
  • Notifies the SRO when the above actions are complete.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 7 Page 21 of 28 Event

Description:

Leak in Drywell causes High Drywell pressure scram.

Time Position Applicant's Actions or Behavior

  • Performs RC-2 actions consisting of:
  • Confirms proper Level Control response:
  • Checks ECCS Injection Systems and secure as necessary.

BOP

  • Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value.
  • IF set down does NOT auto function, then manually reduces FW Master Controller setpoint to approximately 9 inches.
  • Controls HPCI operation for level control by performing one or more of the following:
  • Adjusts 2E41-R612, HPCI Flow Control, to the desired injection rate
  • Transfers the flow controller to manual and adjust its speed demand output to obtain the desired pump flow BOP
  • When feed flow is less than the capacity of the S/U level control valve (

1.5 mlbm/hr), then:

  • Confirms 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.

BOP

  • May attempt to restart the CRD pumps
  • Controls RWL with the HPCI/FW System.
  • Notifies SRO if RWL gets outside assigned band.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 7 Page 22 of 28 Event

Description:

Leak in Drywell causes High Drywell pressure scram.

Time Position Applicant's Actions or Behavior NOTE to EXAMINER: SRVs actuate in LLS at 1120 psig and then control pressure between 850 - 990 psig.

  • Performs RC-3 consisting of:
  • Monitors RPV pressure.
  • If necessary, allows RPV pressure to exceed 1074 psig then cycles any BOP SRV to initiate LLS.
  • If necessary, verifies LLS actuates at 1120 psig
  • Maintains RPV pressure between 1074 and 800 psig.
  • Notifies SRO of pressure control system operation.

NOTE: The SRO will select a reactor pressure band which will lower the driving head of the leak while maintaining EOP limits.

As time allows, may; Direct the ATC to decrease reactor pressure to reduce the driving head of SRO the leak using EHC pressure set, Remove RWCU from service IAW 34AB-T23-002-2, Small Pipe Break in Primary Containment.

Enters Attachment 11 of 34SO-N30-001-2, Main Turbine, or 34GO-OPS-013-2, Normal Plant Shutdown, and at the DEHC panel computer, performs ONE of the following:

1. Throttle Pressure Set
  • Selects the Control psi- load screen
  • Selects the *Ramp Rate* button ATC
  • Enters a ramp rate
  • Selects the *Pressure* button
  • Enters desired target pressure
2. Bypass Valve Jack Positioning
  • Control BPV position by intermittently using the *Raise* /
  • Lower* buttons until BYPASS VALVE JACK STATUS changes to *ACTIVE* AND desired cooldown rate is established ATC Notifies the SRO that Rx pressure is at the target psig.

Simulator Operator PROCEEDS to the next event at the Chief Examiners direction.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 8 Page 23 of 28 Event

Description:

1st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.

Time Position Applicant's Actions or Behavior

  • Per the PC flowchart, verifies Torus level is <285 inches and directs an SRO operator to place Torus Sprays in service.
  • Places Cnmt Spray Vlv Cntl switch in the MANUAL position.

ATC

  • Starts RHR pump(s) in loop A/B, if NOT already running.
  • Notifies SRO that RHR is in Torus Sprays.

(One loop of RHR will be placed in Torus Sprays. The flow is only 700 gpm, so it may be difficult to see flow indication from a distance.)

  • When Torus pressure exceeds 11 psig, verifies that Torus Level is <215 inches, in the safe area of Graph 8 (DWSIL) and Directs an operator to:

SRO

  • Place all DW cooling fans to OFF
  • Place both Recirc pumps to PTL OFF

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 8 Page 24 of 28 Event

Description:

1st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.

Time Position Applicant's Actions or Behavior

  • Places the following DW cooling fans control switches in the OFF position.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-02 Event No.: 8 Page 25 of 28 Event

Description:

1st RHR 2E11-F016A/B Containment Spray Valve causes associated RHR pumps to trip.

Time Position Applicant's Actions or Behavior NOTE: If the operator starts with the B Loop of RHR to spray the DW, the 2E11-F016B valve will open AND BOTH RHR pumps in the B Loop will trip, requiring the operator to transition to the A Loop of RHR.

If the operator starts with the B Loop of RHR to spray the DW, the 2E11-F016B valve will open AND BOTH RHR pumps in the B Loop will trip, requiring the operator to transition to the A Loop of RHR.

Simulator Operator, ENSURE Event Triggers EGE11-11 & ET-EGE11-12 trips both RHR pumps in the ASSOCIATED Loop.

  • Notifies the SRO that all Drywell cooling fans are off.
  • Notifies the SRO that both Recirc pumps are off.
  • Places Cnmt Spray A/B Vlv Cntl switch in the MANUAL position.
  • Confirms RHR pump(s) in loop A/B, are running.
  • Informs SRO that the RHR Loop A or B pumps tripped.
  • Confirms Drywell pressure is reducing
  • Notifies SRO that RHR is in Drywell Sprays
  • May dispatch SO/Maint to investigate both RHR Loop A (B) pumps tripping, if SRO has not already performed.

SRO

  • May dispatch SO/Maint to investigate both RHR Loop A (B) pumps tripping, if ATC has not already performed.

Simulator Operator, After the crew is spraying the Drywell AND with Chief Examiners permission, Terminate the scenario.

Page 26 of 28 Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-02 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initiating Conditions: Unit 2 is operating at 75%RTP.

Turnover Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step 7.3.3.2.5 of 34SO-N42-001-2. Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82% RTP using the Recirculation System.

Summary:

  • Event 1: Normal; The BOP will return Hydrogen Seal Oil to a Normal lineup IAW the system operating procedure.
  • Event 2: Reactivity; The ATC will raise Reactor power to ~82% RTP.
  • Event 3: Component/TS; 4160 V Emergency Bus 2F will de-energize causing a loss of 2B CRD pump. The SRO addresses Tech Specs for inoperable AC electrical distribution subsystem.

BOP will restore cooling water to the running EDG.

  • Event 4: Component/TS; Loss of CRD due to power failure. The ATC will address loss of CRD and start the A CRD pump.
  • Event 5: Instrument; Feedwater pump 2B cooling water controller will fail requiring the ATC to maintain cooling water manually. Time Compression repair & return the controller to automatic.
  • Event 6: Component/TS; 2A Reactor Recirculation pump seals will sequentially develop a failure that results in reactor coolant leaking into the Drywell (DW). Initially, only the Number 1 seal fails, followed a few minutes later by a Number 2 Seal failure. The ATC operator will trip and isolate the 2A Reactor Recirc pump prior to exceeding the DW pressure LOCA signal.

(Critical Task) The SRO will address TS for coolant leakage and single Recirc loop operation.

  • Event 7: Major; The plant experiences a RWCU pipe leak in Drywell causing a High Drywell pressure scram.
  • Event 8: Component; The 1st RHR 2E11-F016A/B Containment Spray Valve to be opened will trip the associated Loop RHR pumps requiring the operator to transition to the other loop of RHR to spray the Drywell. (Critical Task)

Page 27 of 28 Critical Tasks NRC FINAL Facility: E. I Hatch Scenario No.: 9-02 Op-Test No.: 2015-301 Critical Tasks

  • 2A Reactor Recirculation pump seals will sequentially fail resulting in exceeding the capacity of the CAD loop vents requiring the ATC to trip and isolate the 2A Reactor Recirc pump prior to exceeding the Drywell pressure LOCA signal. (Event 6)
  • The 1st RHR 2E11-F016A/B Containment Spray Valve to be opened will trip the associated Loop RHR pumps requiring the operator to transition to the other loop of RHR to spray the Drywell.

(Event 8)

ES 301-4 Attributes Required Actual Items

1. Total Malfunctions 5-8 6 1. 4160V 2F de-energizes (Event 3)
2. Loss of CRD due to power failure (Event 4)
3. 2B RFPT Clg water controller fails (Event 5)
4. 2A Recirc Seal failure (Event 6)
5. RWCU pipe leak LOCA (Event 7)
6. Loop RHR pumps trip (Event 8)
2. Malfunctions After 1-2 1 1. Loop RHR pumps trip (Event 8)

EOP Entry

3. Abnormal Events 2-4 3 1. 4160V 2F de-energizes (Event 3)
2. Loss of CRD due to power failure (Event 4)
3. 2A Recirc Seal failure (Event 6)
4. Major Transients 1-2 1 1. RWCU pipe leak LOCA (Event 7)
5. EOPs entered, 1-2 2 1. 31EO-EOP-010, RC-Non ATWS (Event 7) requiring substantive 2. 31EO-EOP-012, PC (Event 7) actions
6. EOPs contingencies 0-2 0 1.

requiring substantive actions

7. Critical Tasks 2-3 2 1. 2A Recirc Seal failure (Event 6)
2. Loop RHR pumps trip (Event 8)

ILT 9 NRC FINAL Scenario 2 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions: Activities in progress: 34SV-P41-001-1, Plant Service Water Pump Operability.

UNIT 2 STATUS Plant Conditions: Unit 2 is operating at 75% RTP.

Protected Train: EOOS:

Division I Green Orange Division II Yellow Red Hydrogen Seal Oil System is currently aligned with the Emergency Seal Oil pump in service. After turnover restore to Normal Hydrogen Seal Oil System Lineup starting at step Scheduled evolutions: 7.3.3.2.5 of 34SO-N42-001-2.

Once Hydrogen Seal Oil is returned to Normal lineup, increase reactor power to 82% RTP using the Recirculation System.

Surveillances due this None shift:

Inop Equipment: None Active tagouts: None Rod Configuration: See RWM

Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-03 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initial Conditions. Unit 2 is operating at 59% RTP.

Turnover: RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT 2A in service, starting at step 7.1.11.2.7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System. 2D LLS valve is inop for LLS Function only.

Event Malf. No. Event Event No. Type* Description Continue startup and place the RFPT 2A in service, starting at step 1 N/A N (BOP) 7.1.11.2.7 of 34SO-N21-007-2.

2 N/A R (ATC) Raise reactor power with Recirc to 65% power.

mfE41_249 svoE41072 C (ATC) HPCI Steam Line breaks in the Rx bldg.

3 svoE41073 TS (SRO) HPCI isolation valves fail to auto close (Critical Task)

EGE41-3 EGE41-4 4 mf70022416 (ON) C (BOP) Instrument Air System Prefilter dP Hi - swap Prefilters.

C (ATC) Recirc Pump 2B High Vibration requiring reducing reactor power 5 mfB31_41B TS (SRO) in an attempt to clear alarm. Alarm remains in until pump is tripped.

mfN43_148A mfN43_158B loN43-S47A3 Stator Cooling Pump 2B (simulate sheared shaft) 6 C (BOP) loN43-S47G1 Standby Stator Cooling pump 2A fails to start (manually started) loN43-S47R2 EGN43-01 mfB21_247A mfB21_247B Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual 7 M (ALL) mfC71_241A scram works.

mfC71_241B 2B SRV fails open, must pull fuses (Critical Task); 2B SRV 8 mfB21_286B C (ATC) tailpipe with fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve. (Critical Task)

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 1 Page 2 of 26 Event

Description:

Placing the 2A RFPT in service, starting at step 7.1.11.2.9 of 34SO-N21-007-2.

Time Position Applicant's Actions or Behavior 15 SRO Orders Operator to place 2A RFPT in service Mins BOP

  • Increases speed with the Speed Setter switch to 2100 rpm (+ 100 rpm)
  • Confirms M/A station permissive light illuminates and that the M/A station is tracking actual Speed Setter (RFPT) speed
  • Places the TMR Mode switch to M/A
  • Confirms the M/A Station green light illuminates
  • Slowly changes the M/A station to match input and output while BOP monitoring RWL, RFPT 2A discharge pressure and RFPT 2A & 2B speed.

Alarm RFP C005A DISCH FLOW LOW, (656-039), will clear when RFPT 2A is placed into service. Alarms HEATER TROUBLE, (650-135), 2H11-P657 SYSTEM TROUBLE, (650-224) and MULTIPOINT TEMP RCDR 2T47-R611 TEMP HIGH, (657-072) may come in and clear. All are expected for this plant condition. If dispatched to RFPT area, SIMULATOR OPERATOR, wait 2 minutes, NOTIFY BOP there are no steam leaks in the RFPT area.

  • Places M/A station for RFPT 2A in AUTO
  • As required, adjusts RFP 2A Speed Control Bias Setting to maintain BOP RFPT 2A and 2B speed within 100 RPM
  • Informs SRO that the 2A RFPT is in service in Automatic control.

SRO

  • Informs ATC to increase power with Recirc to 65% power.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 2 Page 3 of 26 Event

Description:

Use Recirc to raise reactor power to approximately 65%.

Time Position Applicant's Actions or Behavior 5

SRO Directs the ATC to increase Rx Power to 65% using Recirc.

Mins NOTE: May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.

May also get Alarm HEATER TROUBLE, 650-135 alarm. This is expected at this power level.

IAW 34SO-B31-001-2, the ATC increases Recirc pump speed, NOT to exceed ATC 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master or Individual controls until reactor power is 65%.

Complies with 34SO-B31-001-2 Limitation 5.2.15 which states:

WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:

ATC

< 10% of rated core flow (7.7 E6 lbm/hr) WHEN operating < 70% of rated core flow; AND

< 5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at > 70% of rated core flow.

ATC Notifies the SRO that reactor power has been increased to 65%.

Simulator Operator, at the Chief Examiners direction OR after power has been increased by 5%, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 3 Page 4 of 26 Event

Description:

HPCI Steam Line breaks in the Rx bldg. with failure to auto isolate the HPCI steam line requiring manual closure of isolation valves Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator operator, ENTER (RB-3) 10 Min mfE41_249, HPCI Steam Line, break 0.75/100.

  • DRYWELL/TORUS RCDR R627 TEMP HIGH, (650-204)
  • MULTIPOINT TEMP RCDR 2T41-R620 TEMP HIGH, (654-004)
  • MULTIPOINT TEMP RCDR 2T41-R626 TEMP HIGH, (657-025)
  • Receives the following ~45 seconds later:

ALL

  • LEAK DET DIFF TEMP HIGH, (601-321)
  • HPCI ISOLATION TRIP LOGIC A INITIATED, (601-115)
  • HPCI ISOL TIMER INITIATED, (601-105)
  • HPCI ISOLATION TRIP LOGIC B INITIATED, (601-121)
  • SEC SYSTEM AUTO INITIATION SIGNAL PRESENT, (650-234)

Responds to the following annunciators:

  • HPCI STEAM LINE DIFF PRESS HIGH, (601-104)
  • HPCI ISOLATION TRIP LOGIC A INITIATED, (601-115)

Time:_____________

Responds to failure of HPCI Auto Isolation:

ATC

  • Places 2E41-F003 control switch to CLOSE (Critical Task) is to position 2E41-F002 control switch to close within 5 minutes of receiving 601-115 and/or 601-121 listed above OR may close before alarms are received).

Time:_____________

Dispatches operator/Maintenance to investigate the leak.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 3 Page 5 of 26 Event

Description:

HPCI Steam Line breaks in the Rx bldg. with failure to auto isolate the HPCI steam line requiring manual closure of isolation valves Time Position Applicant's Actions or Behavior

  • Orders HPCI to be isolated.

SRO

  • Orders ATC/BOP to evacuate the Reactor Building.
  • May notify Maintenance for assistance in closing HPCI valve if ATC/BOP does NOT.

Reviews TS 3.6.1.3, Primary Containment Isolation Valves, Condition A.1 and A.2 and determines:

  • 2E41-F002 must be closed and deactivated within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> AND
  • 2E41-F002/F003 penetration must be verified ISOLATED every 31 days.
  • As time allows, contacts the Shift Support Supervisor to draft a Danger SRO Tagout for 2E41-F002.

Reviews TS 3.5.1, ECCS/RCIC.

  • Must verify within one hour that RCIC is operable by administrative means
  • Must restore HPCI to operable status within 14 days SIMULATOR OPERATOR; At Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 4 Page 6 of 26 Event

Description:

Instrument Air System Prefilter dP Hi - swap Prefilters.

Time Position Applicant's Actions or Behavior Simulator Operator at direction of the lead examiner, ACTIVATE: (RB-4) 7 Mins malfunction mf70022416 - Window 25 INSTRU AIR PREFLTR D103A DIFF PRESS HIGH (ANNUNCIATOR ON)

The following annunciators are received:

All

  • INSTR AIR PREFLTR D103A DIFF PRESS HIGH, (700-225)
  • Acknowledges INSTR AIR PREFLTR D103A DIFF PRESS HIGH, (700-225) on 2H11-P700 and notifies the SRO of the alarm BOP
  • Dispatches an SO locally to determine Prefilter dP on 2P52-dPIS-N301A, look for air leaks on the filter and to verify that the instrument isolation valve is open.

Simulator Operator: 2 minutes after being dispatched to check Prefilter dP, inform the BOP that 2P52-dpis-N301A indicates 6 psid and that no air leaks exist.

  • Notifies Maintenance (if BOP has NOT) to change out the Prefilter SRO cartridge and initiates a condition report.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 4 Page 7 of 26 Event

Description:

Instrument Air System Prefilter dP Hi - swap Prefilters.

Time Position Applicant's Actions or Behavior Simulator Operator, WHEN the BOP swaps Prefilters, ENSURES EVENT TRIGGER EGP52-1 & EGP52-2 ACTIVATES: deleting malfunction mf70022416 - Window 25 INSTRU AIR PREFLTR D103A DIFF PRESS HIGH (ANNUNCIATOR ON) and simulates correct light arrangement.

At 2H11-P700:

  • Places control switch to ON for Turb Bldg Inst Air PreFltr/Afterfilter 2P52-D103B/2P52-D102B Inlet Isol, 2P52-F002B/2P52-F011B.

BOP

  • Places control switch to OFF for Turb Bldg Inst Air PreFltr/Afterfilter 2P52-D103A/2P52-D102A Inlet Isol, 2P52-F002A/2P52-F011A.
  • Notifies the SRO that the Prefilter has been swapped from A to B.
  • 700-225 alarm clears.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 5 Page 8 of 26 Event

Description:

Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.

Time Position Applicant's Actions or Behavior 18 SIMULATOR OPERATOR; At Chief Examiners direction, press (RB-5) to Min activate: mfB31_41B, Recirc Pump B High Vibration ALL

  • Receives PUMP MOTOR B VIBRATION HIGH, (602-204) alarm ATC
  • Enters 602-204
  • Depresses the Hi vibration reset pushbutton and determines that the alarm does NOT clear.
  • Notifies the SRO that the vibration alarm did NOT clear.
  • Notifies the SRO that the ARP requires reducing Recirc flow and attempting to reset the alarm again.

AFTER five minutes has elapsed, if Recirc Pump B is still operating, SIMULATOR OPERATOR; At Chief Examiners direction, press (RB-9) to activate: mfB31_40B, Recirc Pump B Motor High Temp.

  • Receives PUMP MOTOR B WINDING COOLING WATER FLOW LOW, (602-218)

ATC

  • Confirms winding temperatures are <240°F, on 2B31-R601, Recirc Pump Temp recorder at 2H11-P614.
  • IF the winding temperatures cannot be maintained < 240°F, Performs Abnormal SHUT DOWN of the ASD B per 34SO-B31-001-2, subsection 7.2.1.4, Reactor Recirculation System.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 5 Page 9 of 26 Event

Description:

Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.

Time Position Applicant's Actions or Behavior

  • Directs the operator to reduce Rx power with Recirc per 34GO-OPS-005 and 34SO-B31-001-2, section 7.1.6, Two Loop Operation From Rated To Minimum Speed, exceeding 10 MWE/minute if necessary.
  • Reminds the operator that entry into the Immediate Exit Region of the SRO Power to Flow map is allowed.
  • Notifies Plant Management, Load Dispatcher, and Engineering that the power increase has been halted pending investigation of Recirc Pump 2B high vibration condition.
  • Enters the following procedures
  • IAW 34SO-B31-001-2, the ATC decreases Recirc pump speed by depressing the Slow, Medium or Fast LOWER pushbuttons on the Master or Individual controls.
  • Monitors power decrease by observing APRM and generator output indications.

ATC

  • Stops power reduction periodically and depresses the High vibration reset pushbutton.
  • The alarm will NOT remain clear until the pump is tripped.
  • Continues to decrease BOTH Recirc pump speeds until minimum
  • Notifies SRO when BOTH Recirc Pumps are at minimum.
  • Notifies the SRO that the vibration alarm DID NOT clear after reducing BOTH Recirc pumps.
  • Notifies SRO that the Region of Potential Instabilities/Immediate Exit Region of Power to Flow Map was NOT entered.

Notifies chemistry of 15% power change in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> IAW 34GO-OPS-005-2, BOP Power Changes, Step 5.2.13.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 5 Page 10 of 26 Event

Description:

Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.

Time Position Applicant's Actions or Behavior NOTE: HEATER TROUBLE ALARM, (650-135) may alarm due to plant conditions.

NOTE: 15% power change sample required IAW limitation 5.2.13, 34GO-OPS-005-2.

  • Directs the ATC operator to shutdown the B ASD IAW 34SO-B31-001-2 section 7.2.1.4, Abnormal Recirc Pump/ASD B Shutdown.

SRO

  • As time allows, directs the BOP operator to secure one Condensate and one Condensate Booster Pump plus one RFPT.
  • Places ASD B control switch 2B31-S002B to Pull to Lock OR depresses the ASD B Shutdown pushbutton and places ASD B control switch to Pull to Lock on panel 2H11-P602.

ATC

  • Confirms operating Recirc Pump flow is
  • <100% rated flow, (45,200 gpm is rated flow) AND
  • Core Flow to <38.5 Mlb/hr

________

TIME

________

  • Within 5 minutes, throttles 2B31-F031B, Pump Disch Valve OPEN TIME
  • ASD B TRIP WARNING, (602-201)
  • ASD B FATAL FAULT, (601-202)
  • ASD B TROUBLE, (601-208)
  • RECIRC LOOP B OUT OF SERVICE, (601-227)

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 5 Page 11 of 26 Event

Description:

Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.

Time Position Applicant's Actions or Behavior NOTE: IAW 34AB-B31-001-2, During single loop operation, WHEN the speed of the running pump decreases below approximately 35%

speed, positive flow through the idle pump loop due to natural circulation overcomes the negative flow due to reverse flow. The total core flow summing circuitry will continue to subtract this positive idle loop flow from the running loop flow AND give a misleading LOW core flow indication. Total core flow can be calculated by adding the JET PUMP LOOP "A" AND the JET PUMP LOOP "B" flows.

  • Has the operator determine if the plant is in the analyzed region of the SRO Power to Flow map.
  • Determines that the plant is NOT in the Immediate Exit Region of the ATC Power to Flow map.

Simulator Operator, WHEN the crew determines that the plant is NOT in the Immediate Exit Region of the Power to Flow map, with Chief Examiners permission, PROCEEDS to the next event.

Simulator Operator, IF the crew makes a conservative decision to shut down the Reactor, with Chief Examiners permission, PROCEEDS to the next event.

  • References Tech Spec 3.4.1.A.1 and has 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to meet requirements for SRO Single Loop Operation.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 5 Page 12 of 26 Event

Description:

Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.

Time Position Applicant's Actions or Behavior

  • Removes condensate pumps (CP & CBP) from service prior to CBP discharge pressure < 525 psig OR power <70% OR as soon as practical.
  • For removal of CBP
  • If 2C is to be removed, removes the Hydrogen Injection System from service
  • Sends SO to closed selected pumps discharge valve BOP
  • Prior to discharge valve being full closed, trips pump and places control switch in Auto or PTL
  • Has SO complete the procedure
  • Removal of CP
  • Sends SO to closed selected pumps discharge valve
  • Trips pump and places control switch in Auto or PTL
  • If pump left in Standby, has SO reopen discharge valve NOTE: IAW 34GO-OPS-005-2, WHEN Feedwater flow is less than 7 mlbm/HR AND two Reactor Feed Pumps are running, one Reactor Feed Pump MAY be shutdown Enters 34SO-N21-007-2, Condensate And Feedwater System, section 7.2.1, BOP First Reactor Feed Pump Shutdown and Leaving in Standby.
  • Confirms Feedwater Flow is less than 7 Mlbm / hr.
  • Confirms RFPT 2A AND RFPT 2B are in Automatic control on 2C32-R600, Master Controller.
  • Slowly decrease RFPT 2A (2B) speed with RFP A (B) M/A Station until the other RFP is controlling reactor vessel level.

NOTE: At this point the operator may stop here with the RFPT NOT injecting and continue with this section as time allows.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 5 Page 13 of 26 Event

Description:

Recirc Pump 2B High Vibration requiring reducing reactor power in an attempt to clear alarm. Alarm remains in until pump is tripped.

Time Position Applicant's Actions or Behavior

  • When the other RFP has control of water level, slowly decrease RFPT 2A (2B) speed with RFP A (B) M/A Station until no speed decrease is observed AND/OR place the RFPT A (B) TMR switch to SS AND confirm Speed Setter yellow light illuminates.
  • Slowly lower RFPT 2A (2B) Speed Setter switch until RFPT speed is at 1000 rpm, at 2H11-P650.
  • IF desired, reduce the RFPT 2A (2B) speed to minimum AND allow the RFPT to windmill, provided seal water, steam seals, AND lube oil systems remain in service.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 6 Page 14 of 26 Event

Description:

Stator Cooling Pump 2B (simulate sheared shaft)

Standby Stator Cooling pump 2A fails to start (manually started)

Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator operator, INSTRUCT the ATC operator by phone to stay on the line until told to hang up. THEN ENTER:

8 Min (RB-6) to ACTIVATE: (mfN43_158B, mfN43_148A, loN43-S47A3 (Off),

loN43-S47G1 (Off) & loN43-S47R2 (On).

  • GENERATOR INLET FLOW LOW, (651-201)
  • GENERATOR INLET PRESS LOW, (651-202)

BOP

  • GENERATOR OUTLET TEMP HIGH, (651-204)
  • STATOR CLG TANK WATER LEVEL HIGH/LOW, (651-205)
  • GENERATOR PROTECTION CIRCUIT ENERGIZED, (651-206)
  • MAIN GENERATOR TEMPERATURE, (651-161)
  • TURBINE TROUBLE, (650-105)
  • Acknowledges the alarms and informs the SRO that the Stator Cooling system pressure and flow is low and that the 2A Stator Cooling pump BOP did NOT auto start. (2A Stator Cooling may be started manually prior to recognizing failure to auto start.) (There is NOT an obvious reason for the pressure and flow being low.)

The BOP may enter the following ARPs in any order:

  • Enters 651-201, Generator Inlet Flow Low, and performs the following:
  • Manually starts the 2A Stator Cooling pump BOP (May NOT pull procedure until after the pump has been started.)
  • Monitors for increasing system flow by 651-201 clearing.
  • Dispatches SO/Maint to investigate the cause of Generator Inlet Flow Low.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 6 Page 15 of 26 Event

Description:

Stator Cooling Pump 2B (simulate sheared shaft)

Standby Stator Cooling pump 2A fails to start (manually started)

Time Position Applicant's Actions or Behavior The BOP may NOT enter the following once the standby pump is started.

  • Enters 651-202, Generator Inlet Press Low, and performs the following:
  • Manually starts the 2A Stator Cooling pump BOP (May NOT pull procedure until after the pump has been started.)
  • Monitors for increasing system pressure by 651-202 clearing.
  • Dispatches SO/Maint to investigate the cause of Generator Inlet Pressure Low.

The BOP may NOT enter the following once the standby pump is started.

  • Enters GENERATOR OUTLET TEMP HIGH, (651-204) and performs the following:
  • Dispatches SO/Maint to investigate GENERATOR OUTLET TEMP HIGH alarm.

The BOP may NOT enter the following once the standby pump is started.

  • Enters STATOR CLG TANK WATER LEVEL HIGH/LOW, (651-202)

BOP and dispatches a SO locally to determine Tank level.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 6 Page 16 of 26 Event

Description:

Stator Cooling Pump 2B (simulate sheared shaft)

Standby Stator Cooling pump 2A fails to start (manually started)

Time Position Applicant's Actions or Behavior The BOP may NOT enter the following once the standby pump is started.

  • Enters GENERATOR PROTECTION CIRCUIT ENERGIZED, (651-206) and performs the following:

(NOT expected to be required)

SRO

  • Directs the operator to place the Stator Cooling Pump 2B pump to Trip.

Simulator Operator: ENSURE EVENT TRIGGER ET-EGN43-01 is ACTIVATED, THEN; After 3 minutes of being sent to investigate the Stator Cooling system low flow and pressure AND after the BOP has started 2A Stator Cooling pump, REPORT that the 2B Stator Cooling pump motor is running, but the pump shaft is NOT turning.

  • Places 2N43-C001B control switch to Trip position and reports this to the BOP SRO.

Simulator Operator, at Chief Examiners direction, starts the Major event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 7 Page 17 of 26 Event

Description:

Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.

Time Position Applicant's Actions or Behavior Simulator Operator: At the direction of the Chief Examiner, ACTIVATES:

8 (RB-7)

Mins

  • mf60321350

ALL

  • Group 1 System A/B Trip - Full Group 1, MSIV isolation
  • Full reactor scram REQUIRED
  • Assigns the ATC to perform RC-1.
  • Assigns the BOP operator to perform RC-2 and RC-3.
  • If time allows assigns TC-1 to be performed.

SRO

  • Directs RWL Band of 3 to 50 inches.
  • Performs RC-1 consisting of:
  • Places the mode switch to SHUTDOWN.
  • Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
  • Notifies SRO of rod position check.

ATC

  • Places SDV isolation valve switch to "isolate" & confirms closed.
  • If NOT tripped, places the Recirc pumps at minimum speed.
  • Shifts recorders to read IRMS, when required.
  • Ranges IRMS to bring reading on scale.
  • Notifies the SRO when the above actions are complete.

ATC/BOP

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 7 Page 18 of 26 Event

Description:

Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.

Time Position Applicant's Actions or Behavior Performs RC-2 actions consisting of:

  • Confirms proper Level Control response:
  • Checks ECCS Injection Systems (HPCI will be ISOLATED from previous steam line break)
  • Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value
  • If Set down does NOT auto function, manually reduces FW Master Controller setpoint to approximately 9 inches.
  • When feed flow is less than the capacity of the S/U level control valve (

BOP 1.5 mlbm/hr), then:

  • Confirms 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
  • Will control RWL and with SRO permission will raise RWL to 32 to 42 inches.
  • When RFPTs are no longer available, will transition to RCIC to control RWL.

Starts RCIC HPCI for level control by performing the following:

BOP

  • Depresses RCIC Manual Initiation P/B
  • Confirms/Starts Barom Cndsr Vac Pump
  • Adjusts controller for desired flow and with SRO permission will raise RWL to 32 to 42 inches

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 7 Page 19 of 26 Event

Description:

Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.

Time Position Applicant's Actions or Behavior Simulator Operator When the 2B SRV is open, ENSURE EVENT TRIGGER EGB21-3 activates mfB21_128B, mfB21_130B and mfB21_286B.

  • Performs RC-3 consisting of:
  • Monitoring RPV pressure.
  • Confirms proper operation of pressure control system (SRVs, LLS, etc.) by performing one or more of the following:
  • At 2H11-P602 panel, manually cycles SRVs to maintain reactor BOP pressure within band of 1074 psig to 800 psig.
  • If necessary, allows RPV pressure to exceed 1074 psig then cycles any SRV to initiate LLS.
  • Maintains RPV pressure between 1074 and 800 psig until a different band is directed.
  • Notifies SRO of pressure control system operation.

Directs operator to enter 34AB-B21-003-2, Failure of Safety/Relief Valves.

SRO Directs operators to verify that the SRV 2B is closed, after the fuses are pulled.

NOTE: The operator may not perform some of the below steps since they are dependent on the status of 2B SRV red light when the operator addresses the open SRV.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 7 Page 20 of 26 Event

Description:

Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.

Time Position Applicant's Actions or Behavior

  • Notifies SRO the 2B SRV failed to close.
  • Determines SRV 2B is cycling open then close
  • Cycles the SRV 2B Control Switch several times
  • May depress the ADS Logic A Timer Reset pushbutton (2B21-S2A)
  • May depress the ADS Logic B Timer Reset pushbutton (2B21-S2B)

BOP

  • May depress the LLS Channel A / C Reset pushbutton (2B21-S15A)
  • May depress the LLS Channel B / D Reset pushbutton (2B21-S15B)
  • Informs SRO that SRV 2B is still open and the fuses will have to be pulled.
  • Notifies the SSS to pull the fuses for SRV 2G. (Critical Task)

Critical Task is to remove the fuses for 2B SRV prior to exceeding >100°F/hr cooldown rate or the unsafe region of the PSP Curve.

Simulator Operator, assuming that a request was made to pull fuses for SRV 2B, wait 4 minutes, then ENTER the following:

ENTER Event Trigger EGB21-6 which will DELETE mfB21_128B and mfB21_130B AND DEPRESSES (RB-8), rfB21_301, to simulate pulling the fuses for SRV 2B.

THEN, Notify the crew that the fuses have been pulled for SRV 2B.

  • Confirms that SRV 2B is closed by monitoring one or more of the following:
  • SRV tailpipe temperature decrease on P614 panel.
  • Torus level stabilizing
  • Torus Temp stabilizing
  • Rx pressure returns to the pre-event level BOP
  • Resets the SRV leak detection by placing the Leak Detection Logic A Reset keylock switch and Leak Detection Logic B Reset keylock switch to RESET position and back to NORMAL position
  • Confirms that the Amber SRV indicating lights have extinguished.
  • SAFETY BLOWDOWN PRESSURE HIGH, (602-311), clears.
  • Informs the SRO that SRV 2B is closed.

Simulator Operator, at Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 7 Page 21 of 26 Event

Description:

Inadvertent Group 1 Isolation, Reactor Auto scram fails but Manual scram works.

Time Position Applicant's Actions or Behavior

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 8 Page 22 of 26 Event

Description:

2B SRV tailpipe fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.

Time Position Applicant's Actions or Behavior Recognize increasing Containment Pressure from the following alarms:

ALL

  • PRIMARY CNMT HIGH PRESSURE TRIP, (603-106)
  • PRIMARY CNMT PRESSURE HIGH, (603-115)

SRO

  • Per the PC flowchart, verifies Torus level is <285 inches and directs an SRO operator to place Torus Sprays in service (Critical Task) - Torus Spray is initiated or the Reactor Emergency Depressurized prior to exceeding Pressure Suppression Pressure, Graph 7.
  • Places Cnmt Spray Vlv Cntl switch in the Manual position.
  • Verifies RHR pump(s) in loop A (B) running.
  • Notifies SRO that RHR is in Torus Sprays (The flow is only 700gpm, so it may be difficult to see flow indication from a distance.)

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-03 Event No.: 8 Page 23 of 26 Event

Description:

2B SRV tailpipe fails requiring Torus Spray or Emergency Depressurization to maintain safe region PSP curve.

Time Position Applicant's Actions or Behavior NOTE TO EVALUATOR: It is NOT expected that an Emergency Depressurization will be required.

  • If Torus pressure cannot be maintained below Pressure Suppression SRO Pressure (PSP) Limits, directs ATC to Emergency Depressurize (ED).
  • When directed, places 7 ADS valve switches to the OPEN position on ATC panel 2H11-P602.
  • If Emergency Depressurized, direct BOP to ensure RHR and CS injection SRO valves open and injection occurs.
  • When directed, monitors RHR and CS and verifies that systems inject BOP when reactor pressure decreases below the system discharge head.

Simulator Operator:

After the crew is spraying the Torus OR Emergency Depressed for PSP concerns AND with Chief Examiners permission, TERMINATE the scenario.

Page 24 of 26 Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-03 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initiating Conditions: Unit 2 is operating at 56% RTP.

Turnover RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT 2A in service, starting at step 7.1.11.2.7 of 34SO-N21-007-2. Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System. 2D LLS valve is inop for LLS Function only.

Summary:

  • Event 1: Normal; The 2A RFPT will be placed into service.
  • Event 2: Reactivity; After the 2A RFPT is in service, the ATC operator will raise reactor power using the Recirc system to approximately 65% power.
  • Event 3: Component/TS; A HPCI steam line will break outside of Primary Containment. The outboard isolation valve is failed open and cannot be closed. Both isolation valves fail to automatically close on an automatic isolation signal and must be manually closed. (Critical Task) The SRO addresses Tech Specs for inoperable Primary Containment Isolation Valve &

ECCS.

  • Event 4: Component; Instrument Air System Prefilter dP Hi - swap Prefilters.

The operator will dispatch an SO locally to determine dP. Report back will require BOP swapping Prefilters to restore normal system flow/pressure. (OE)

  • Event 5: Component/TS; Recirc Pump 2B will experience high vibration requiring reducing reactor power in an attempt to clear the alarm. Alarm remains in until pump is tripped. The SRO addresses TS for an inoperable Recirc pump. The plant will NOT be operating in the Immediate Exit Region of the Power-to-Flow map.
  • Event 6: Component; Stator Cooling Pump 2B will experience a sheared shaft and the standby Stator Cooling pump will NOT automatically start. The operator will manually start the standby Stator Cooling pump to restore system flow/pressure to normal.
  • Event 7: Major; Inadvertent Group 1 Isolation, Auto fails to close MSIVs but Manual works.
  • Event 8: Component; A broken SRV B tailpipe causes Torus Pressure to increase with the failed open SRV. Torus Spray is initiated or the Reactor Emergency Depressurized prior to exceeding Pressure Suppression Pressure. (Critical Task)

Page 25 of 26 Critical Tasks NRC FINAL Facility: E. I Hatch Scenario No.: 9-03 Op-Test No.: 2015-301 Critical Tasks

  • Manually isolate the HPCI isolation valves within 5 minutes of receiving 601-115 and 601-121.

(Event 3)

  • Pull fuses to SRV 2B. (Event 8)
  • Spray the Torus or Emergency Depressurize before exceeding Primary Containment Pressure Suppression Pressure (PSP) curve. (Event 8)

ES 301-4 Attributes Required Actual Items

1. Total Malfunctions 5-8 6 1. HPCI steam line break (Event 3)
2. Instrument Air System Prefilter dP Hi (Event 4)
3. Recirc Pump 2B high vibration (Event 5)
4. Stator Cooling Pump 2B sheared shaft/standby failure to start (Event 6)
5. Inadvertent Group 1 Isolation, Auto fails to close MSIV (Event 7)
6. Broken SRV B tailpipe (Event 8)
2. Malfunctions After 1-2 1 1. Broken SRV B tailpipe (Event 8)

EOP Entry

3. Abnormal Events 2-4 3 1. HPCI steam line break (Event 3)
2. Instrument Air System Prefilter dP Hi (Event 4)
3. Recirc Pump 2B high vibration (Event 5)
4. Major Transients 1-2 1 1. Inadvertent Group 1 Isolation, Auto fails to close MSIV (Event 7)
5. EOPs entered, 1-2 2 1. 31EO-EOP-010-2, RC Non ATWS, (Event 7) requiring substantive 2. 31EO-EOP-012-2, PC, (Event 7) actions
6. EOPs contingencies 0-2 0 1. None requiring substantive actions
7. Critical Tasks 2-3 3 1. HPCI steam line break (Event 3)
2. Pull fuses to SRV 2B. (Event 8)
3. Broken SRV B tailpipe, spray Torus (Event 8)

ILT 9 NRC FINAL Scenario 3 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions: Activities in progress: 34SV-P41-001-1, Plant Service Water Pump Operability.

UNIT 2 STATUS Plant Conditions: Unit 2 is operating at 59% RTP.

Protected Train: EOOS:

Division I Green Orange Division II Yellow Red RFPT 2A is operating at ~1000 rpm. Continue startup and place the RFPT 2A in service, starting at step 7.1.11.2.7 of Scheduled evolutions: 34SO-N21-007-2.

Once RFPT 2A is in service increase reactor power to 65% RTP using the Recirc System.

Surveillances due this None shift:

Inop Equipment: 2D LLS valve is inop for LLS Function only.

Active tagouts: 2D LLS valve is inop for LLS Function only.

Rod Configuration: See RWM

Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-04 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initial Conditions. Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service.

Turnover: Reduce reactor power to 60% RTP for RFPT 2A removal. Leave RFPT 2A operating at ~1000 RPM.

Event Malf. No. Event Event No. Type* Description 1 N/A R (ATC) Reduce reactor power to 60% for RFPT 2A removal.

2 N/A N (BOP) Remove 2A RFPT from service and leave operating at ~1000 RPM.

mf60131136 aoE21R600A 2A Loop of Core Spray experiences high discharge pressure (valve C (BOP) 3 leakage). When 2E21-F004A is reopened, the valve breaker trips loE21-F004AG1 TS (SRO) when control switch placed to open.

loE21-F004AR2 CRD 2A pump experiences a Suction Filter hi dP requiring swapping 4 mf60311308 C (ATC) to standby pump.

C (BOP) RCIC Room fire.

5 N/A TS (SRO)

I (ATC) 6 mfB21_131 ADS Inadvertent initiation/Inhibit used. (Critical Task)

TS (SRO)

Unisolable HPCI Steam leak in Reactor Building requiring a Reactor 7 mfE41_249 M (ALL)

Manual scram. HPCI Group 3 signal failure.

M (ALL) Emergency Depress when Max Safe exceeded in more than one area.

8 N/A (Critical Task)

SULCV fails closed. Core Spray & RHR Logic failure requiring mfN21_99 manual actions for pumps/valves to inject. RPV level will be 9 mfE11_202B C (BOP) controlled either by throttling open 2N21-F110, or by using Core mfE21_202A Spray and/or RHR Systems. (Critical Task)

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 1 Page 2 of 27 Event

Description:

Reduce reactor power to 60% for RFPT 2A removal.

Time Position Applicant's Actions or Behavior

  • Directs ATC to decrease reactor power to 60%, to achieve a Feedwater 15 flow <7 mlbm/hr for RFPT removal, by decreasing Recirc flow. Power SRO Mins decreases should be made as recommended by the STA/Reactor Engineering at a rate NOT to exceed 10 MWe/min.
  • IAW 34SO-B31-001-2, the ATC decreases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the LOWER SLOW or LOWER MEDIUM pushbuttons on the Master or Individual controls until reactor power is 60%. Monitors power decrease by observing APRM and ATC generator output indications.

WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:

ATC

  • <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating

< 70% of rated core flow; AND

  • <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at

> 70% of rated core flow.

NOTE: May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.

May also get Alarm HEATER TROUBLE, 650-135 alarm. This is expected at this power level.

Simulator Operator, at the Chief Examiners direction OR after power has been decreased by 5%, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 2 Page 3 of 27 Event

Description:

Remove 2A RFPT from service and leave at approximately 1000 rpm.

Time Position Applicant's Actions or Behavior 10

  • Confirms Feedwater Flow is less than 7 Mlbm / hr.
  • Confirms RFPT 2A AND RFPT 2B are in Automatic control on 2C32-R600, Master Controller.
  • Depresses setpoint increase button on 2C32-R600, Master Controller and raises RWL setpoint to 39 inches.
  • Places 2C32-R601A, RFP A M/A Station, in Manual, by depressing the

'M' pushbutton until it illuminates, panel 2H11-P603.

  • Slowly decreases RFPT 2A speed until RFP 2B is controlling reactor vessel level.

BOP

  • RFP COO5A DISCH LOW FLOW, (656-039) will alarm and is expected.
  • Depresses setpoint decrease button on 2C32-R600, Master Controller and lowers RWL setpoint to 37 inches.
  • Slowly decreases RFPT 2A speed until no speed decrease is observed and places RFPT A TMR switch to SS and confirms SPEED SETTER yellow light illuminates.
  • Slowly lowers RFPT 2A Speed Setter switch until RFPT speed is at 1000 rpm, at 2H11-P650.
  • Dispatches SO to confirm open OR open RFPT 2A drain valves on Local panel 2H21-P244 (steps 7.2.1.9).

Simulator Operator, if dispatched to confirm RFPT 2A drains, after 5 minutes, report all drain valves per step 7.2.1.9 are open.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 3 Page 4 of 27 Event

Description:

2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.

Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator enters (RB-3) malfunction mf60131136 Window 28 Core Spray A Disch Pipe Press High 5 Mins (ON) and aoE21-R600A to 465 psig. ENSURE Event Trigger EGE21-1 activates when 2E21-F004A is placed to open position.

ALL Receives CORE SPRAY A DISCH PIPE PRESS. HIGH, (601-328)

  • Enters CORE SPRAY A DISCH PIPE PRESS. HIGH, (601-328)
  • Confirms validity of alarm using Disch Press indicator, 2E21-R600A

(~465 psig)

  • Confirms the following valves are CLOSED
  • Notifies SRO of alarm (601-316) and that the lights for 2E21-F004A are extinguished.
  • Directs operator to enter 601-316 ARP SRO

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 3 Page 5 of 27 Event

Description:

2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.

Time Position Applicant's Actions or Behavior

  • Enters CORE SPRAY SYSTEM I VALVES OVERLOAD, (601-316)

BOP

  • Dispatches SO/Maint. to reset the thermal overload for 2E21-F004A at MCC 2R24-S011, Frame 13A Simulator Operator, wait 4 minutes, then as an SO, report that the breaker for 2E21-F004A will NOT reset.

If asked/directed to manually break 2E21-F004A off the closed seat, report this valve will NOT move with the handwheel.

Enters TS 3.5.1, ECCS Operating, and determines:

SRO TS 3.5.1.A requires the ECCS pump to restored to operable status in 7 days.

NOTE: If addressed, 2E21-F004A is NOT a PCIV and TS 3.6.1.3 for PCIVs is not needed.

Simulator Operator, ENSURE Event Trigger EGE21-2 activates when 2E21-F015A is placed to open position. This will clear CS A Disch Press High alarm & return 2E21-R600A to normal.

  • IAW ARP 601-328, may perform the following:
  • Confirms 601-328 clears BOP
  • When pressure is approximately 100 psig, closes 2E21-F015A.
  • Monitors Core Spray A Loop pressure for subsequent increases.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 3 Page 6 of 27 Event

Description:

2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A is reopened, the valve breaker trips when control switch placed to open.

Time Position Applicant's Actions or Behavior NOTE: If pressure is NOT relieved, then a follow-up question on PCIV leakage TS 3.6.1.3.D may be appropriate.

NOTE: If pressure IS relieved on Core Spray Loop A, and pressure is NOT monitored, then a follow-up question on a high pressure condition of the inner system piping may be appropriate.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 4 Page 7 of 27 Event

Description:

CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.

Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator ENTERS (RB-4) 10 Min mf60311308, CRD Pump A Suction Filter Diff Press Hi, alarm.

  • Receives CRD PUMP A SUCTION FILTER DIFF PRESS HIGH, (603-120), alarm.

ATC

  • Confirms CRD system flow is < 59 gpm.
  • Dispatches SO locally to check 2C11-dPIS-N015A indicates higher than 9.0 psi Simulator Operator, AFTER 3 minutes from being dispatched, report to the SRO/ATC, as an SO, that 2C11-dPIS-N015A indicates 12.0 psi.

Simulator Operator, AFTER giving report to SRO/ATC, IF SRO directs shifting CRD suction filters INSTEAD of swapping CRD pumps, THEN as Shift Manager, DIRECT the SRO to swap CRD pumps.

  • Dispatches Maintenance to investigate 2A CRD Suction Filter dP high.

SRO

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 4 Page 8 of 27 Event

Description:

CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.

Time Position Applicant's Actions or Behavior NOTE: The ATC may direct the CRD pump room coolers to be swapped or may elect to leave the 2T41-B001B cooler in service. Both are acceptable.

Simulator Operator, After being dispatched to confirm valves listed in step 7.1.3.1.2 are open, report valves are open.

  • Dispatches SO to confirm cooling water valves listed in step 7.1.3.1.2 are open.
  • Confirms a CRD Room Cooler is in operation per 34SO-T41-002-2, CRD Pump Room Ventilation System by performing the following:

ATC OR

  • Places control switch for 2T41-B001A, in Run (P657)

(may direct BOP to perform).

(may direct BOP to perform).

(may direct BOP to perform).

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 4 Page 9 of 27 Event

Description:

CRD 2A pump experiences a Suction Filter hi dP requiring swapping to standby pump.

Time Position Applicant's Actions or Behavior Simulator Operator, when dispatched to open the below valves and to vent the 2B CRD pump, wait 3 minutes and notify the ATC the below valves are open and the 2B CRD pump has been vented and the vent valves are closed. If asked, INFORM the operator 2C11-F006 is closed.

Also ENSURE Event Trigger EGC11-5 DELETES 2A CRD Suction Filter dP High alarm when 2A CRD pump is secured.

  • Dispatches SO to confirm open the following valves and to vent the 2B CRD pump:
  • Confirms flow control valve responds properly by controlling system flow ATC between 30 gpm to 50 gpm.
  • Confirms system parameters are in their normal ranges per NOTE in System Startup section of 34SO-C11-005-2.
  • May receive MULTIPOINT TEMP RCDR 2T41-R620 TEMP HIGH, (654-004). This is expected for this plant condition and will subsequently clear.

SIMULATOR OPERATOR; At Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 5 Page 10 of 27 Event

Description:

RCIC Room fire.

Time Position Applicant's Actions or Behavior Simulator Operator 11 With Chief Examiners direction, NOTIFY the Shift Supervisor, as the SO on Mins rounds, that smoke is coming from the Unit 2 RCIC room and you cannot see what is actually burning. You are leaving the area.

  • Sounds the fire alarm (SIREN) over the plant PA system, (repeats 2 times - may get U1 operator to handle repeats).

BOP

  • Notifies Rad Waste Control room that Reactor Building floor drain sump pumps are in Automatic.
  • Notifies Radiation Protection to respond to the fire area.
  • Transitions to section 8.0 for Fire in Reactor Bldg.
  • Stops the following equipment at Panels 2H11-P654 & P657:

BOP

  • REFUELING FLOOR OUTSIDE AIR DIFF PRESS LOW, (657-001)
  • RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW, (654-001)

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 5 Page 11 of 27 Event

Description:

RCIC Room fire.

Time Position Applicant's Actions or Behavior

  • Transitions to section 8.3 for Fire in North Half of Reactor Bldg below 185 ft.
  • Transitions to section 8.3.4 for Fire in RCIC Corner Room

BOP

  • Closes the following RCIC Valves on P602
  • 2E51-F008 Simulator Operator, ONCE the above RCIC valves are closed, NOTIFY the Shift Supervisor that the fire in the RCIC room is OUT. Various RCIC components are severely damaged. Ventilation can be restored to normal EXCEPT for the RCIC Room Coolers.
  • Announces to the crew the fire is out.
  • Refers to TS for RCIC inoperability;
  • As time allows, Refers to TRM 3.7.2.D.1, ECCS and RCIC Room Coolers and immediately declares RCIC INOP.
  • Directs BOP to start Rx Bldg Ventilation System and RF Floor Ventilation SRO System.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 5 Page 12 of 27 Event

Description:

RCIC Room fire.

Time Position Applicant's Actions or Behavior

  • Momentarily Depresses the following pushbuttons:

BOP

  • Requests Unit 1 operator to depress:
  • 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr Reset A pushbutton, at BOP 1H11-P657.
  • 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr reset B pushbutton, at 1H11-P654.
  • Confirms OPEN the following dampers:
  • Confirms:

BOP

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 5 Page 13 of 27 Event

Description:

RCIC Room fire.

Time Position Applicant's Actions or Behavior

  • Aligns fan in:

BOP

  • Verifies Rx Bldg Vent Exhaust Flow approximately 6.5 KCFM as indicated by the green pen on 2T41-R618 located on 2H11-P657.
  • Verifies Rx Bldg Vent Supply Flow approximately 5.3 KCFM as indicated by the red pen on 2T41-R618, flow recorder, located on 2H11-P657.
  • Verifies flow is maintaining 0.25 inches water pressure on BOP 2T46-DPR-R604A&B.
  • Sends SO to verify setpoints of local temperature controllers.
  • Verifies in RUN fan:
  • 2T41-B007, Rx Bldg Cooler Working Floor EL 130 North
  • 2T41-B008, Rx Bldg Cooler Working Floor EL 130 South
  • 2T41-B026, Rx Bldg Primary Cooler Mn Steam Pipe Chase
  • 2T41-B011, Rx Bldg Cooler Operating Floor EL 185
  • 2T41-B015, Rx Bldg Cooler Operating Floor EL 185
  • 2T41-B016, Rx Bldg Cooler Working Floor EL 203
  • Verifies in AUTO 2T41-B009, Rx Bldg Secondary Cooler Mn. Steam Pipe Chase.

Starts RF Floor Ventilation IAW 34SO-T41-006-2, Section 7.1

  • Requests Unit 1 operator to depress:
  • 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr Reset A pushbutton, at 1H11-BOP P657.
  • 1T41/2T41, Rx Bldg/Rf Flr Isol Dmpr reset B pushbutton, at 1H11-P654.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 5 Page 14 of 27 Event

Description:

RCIC Room fire.

Time Position Applicant's Actions or Behavior

  • Momentarily Depresses the following pushbuttons:

BOP

  • Dispatches SO to perform steps 7.1.5 through 7.1.9.
  • Confirms OPEN the following dampers:

BOP

  • Verifies RF Vent Exhaust Flow approximately 30.0 KCFM as indicated by the purple pen on 2T41-R618 located on 2H11-P657.
  • Verifies RF Vent Supply Flow approximately 5.3 KCFM as indicated by the blue pen on 2T41-R618, flow recorder, located on 2H11-P657.
  • Verifies flow is maintaining 0.25 inches water pressure on 2T46-DPR-R604A&B.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 6 Page 15 of 27 Event

Description:

ADS Inadvertent initiation/Inhibit used.

Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator, phone the BOP and 10 instruct the BOP operator to stay on the line until told to hang up, THEN Mins enters (RB-6) malfunction mfB21_131 Inadvertent ADS Initiation.

  • Identifies ADS is about to initiate and observe the following alarms:

ALL

  • AUTO BLOW DOWN TIMERS INITIATED, (602-306)
  • AUTO BLOW DOWN RELAYS ENERGIZED, (602-318)

ATC

  • Acknowledges the alarms and reports them to the SRO.
  • May observe the ADS timer on SPDS begin counting down.
  • Directs ATC to enter the following:

SRO

  • AUTO BLOW DOWN TIMERS INITIATED, (602-306)
  • AUTO BLOW DOWN RELAYS ENERGIZED, (602-318)
  • Monitors plant parameters to determine extent of ECCS/RCIC ATC actuations.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 6 Page 16 of 27 Event

Description:

ADS Inadvertent initiation/Inhibit used.

Time Position Applicant's Actions or Behavior SRO

  • If ADS Timer on SPDS is approaching Zero (0), the ATC may depress the ADS Logic Timer pushbuttons prior to inhibiting ADS.

ATC

  • Places ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100°F cooldown rate. (Critical Task)

SRO

  • Dispatches Maintenance to determine problem with ADS logic.

NOTE: The SRO may enter TS 3.3.5.1. F & G and declare all ADS valves inoperable if the ADS instrumentation is NOT repaired in one hour.

Without more information on failed instruments, a follow-up question to the SRO may be required to determine this TS call.

  • While determining the extent of ADS failures, enters TS 3.3.5.1-1 Item 4 and:

SRO

  • With all ADS valves inop, be in Mode 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and <150 psig Rx press in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 7 Page 17 of 27 Event

Description:

Unisolable HPCI Steam leak in the Reactor Building.

Time Position Applicant's Actions or Behavior 10 At the Chief Examiners direction, Simulator operator, ENTER (RB-7)

Min mfE41_249, HPCI Steam Line, break 20/1.

  • DRYWELL/TORUS RCDR R627 TEMP HIGH, (650-204)
  • MULTIPOINT TEMP RCDR 2T41-R620 TEMP HIGH, (654-004)
  • MULTIPOINT TEMP RCDR 2T41-R626 TEMP HIGH, (657-025)

ALL

  • Receives the following ~60 seconds later:
  • LEAK DET DIFF TEMP HIGH, (601-321)
  • HPCI ISOLATION TRIP LOGIC A INITIATED, (601-115)
  • HPCI ISOL TIMER INITIATED, (601-105)
  • HPCI ISOLATION TRIP LOGIC B INITIATED, (601-121)
  • Orders HPCI to be isolated.

SRO

  • Orders BOP to evacuate the Reactor Building.
  • May notify Maintenance for assistance in closing HPCI valves if ATC/BOP does NOT.
  • Responds to HPCI alarms
  • Observes HPCI Isolation valves have failed to close.

ATC/BOP

  • Notifies SRO of HPCI valve failures.
  • May notify Maintenance for assistance in closing HPCI valves if SRO does NOT.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 7 Page 18 of 27 Event

Description:

Unisolable HPCI Steam leak in the Reactor Building.

Time Position Applicant's Actions or Behavior

  • Respond to annunciator LEAK DET DIFF TEMP HIGH, (601-321).
  • Identifies the following points on R604 increasing:
  • 109, HPCI EMER AREA CLR is ~115°F
  • 111, RCIC AREA CLR is ~ 89°F
  • 113, TORUS NW WALL is ~ 92°F
  • 114, TORUS SE WALL is ~ 118°F
  • 115, TORUS VENT AIR DIFF is ~ 12°F
  • 116, TORUS VENT AIR DIFF is ~ 38°F
  • Identifies the following points on R608 increasing:
  • 110, HPCI EMER AREA CLR is ~ 110°F
  • 115, TORUS WEST WALL is ~ 95°F
  • 116, TORUS NE WALL is ~ 120°F
  • 117, TORUS VENT AIR DIFF is ~ 15°F
  • 118, TORUS VENT AIR DIFF is ~ 38°F
  • Reports temperatures to the SRO.
  • Enters the SC flow chart.
  • Progresses down each path.
  • Proceeds down the SC/T path, directing:
  • All available area coolers are operated SRO
  • Operate the refueling floor ventilation
  • Isolate all systems discharging into the area except those needed for ACC, shutdown the reactor, suppress a fire, maintain primary containment

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 7 Page 19 of 27 Event

Description:

Unisolable HPCI Steam leak in the Reactor Building.

Time Position Applicant's Actions or Behavior

  • Orders the reactor shutdown due to Max Safe operating temperatures or SRO delta temps since a primary system (HPCI) is discharging into Secondary Containment.
  • Assigns the ATC to perform RC-1.
  • Assigns the BOP operator to perform RC-2 and RC-3.

SRO

  • Enters 31EO-EOP-010-2, RC EOP flow chart if RWL decreases below 3 inches or if any area exceeds Max Safe.
  • Directs RWL Band of 3 to 50 inches.
  • Performs RC-1 consisting of:
  • Places the mode switch to SHUTDOWN.
  • Confirms all rods are inserted by observing full in lights, SPDS, or the RWM display.
  • Notifies SRO of rod position check.

ATC

  • Places SDV isolation valve switch to "isolate" & confirms closed.
  • If NOT tripped, places the Recirc pumps at minimum speed.
  • Shifts recorders to read IRMS, when required.
  • Ranges IRMS to bring reading on scale.
  • Notifies the SRO when the above actions are complete.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 7 Page 20 of 27 Event

Description:

Unisolable HPCI Steam leak in the Reactor Building.

Time Position Applicant's Actions or Behavior

  • Performs RC-2 actions consisting of:
  • Confirms proper Level Control response:
  • Checks ECCS Injection Systems (will NOT be in service if RWL >-35 inches)
  • Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value
  • If Set down does NOT auto function, manually reduces FW Master BOP Controller setpoint to approximately 9 inches.
  • When feed flow is less than the capacity of the S/U level control valve

( 1.5 mlbm/hr), then:

  • Confirms/places 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
  • If RFPTs are no longer available, will transition to CBPs.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 7 Page 21 of 27 Event

Description:

Unisolable HPCI Steam leak in the Reactor Building.

Time Position Applicant's Actions or Behavior

  • Performs RC-3 consisting of:
  • Monitoring RPV pressure.
  • Confirms proper operation of pressure control system (TBV, LLS, etc.), at 2H11-P650 panel, by confirming TBVs are responding to control reactor pressure at the desired pressure setpoint.
  • Maintains RPV pressure between 1074 and 800 psig until a different band is directed.
  • Notifies SRO of pressure control system operation.
1. Throttle Pressure Set
  • Selects the Control psi- load screen
  • Selects the *Ramp Rate* button
  • Enters a ramp rate
  • Selects the *Pressure* button BOP
  • Enters desired target pressure
2. Bypass Valve Jack Positioning
  • Control BPV position by intermittently using the *Raise* /
  • Lower* buttons until BYPASS VALVE JACK STATUS changes to *ACTIVE* AND desired cooldown rate is established
  • If SRO orders Anticipate Emergency Depress, then the operator will perform the following:
  • At P650 HMI screen,
  • Selects Control
  • Selects Bypass Valve
  • Inserts Ramp Rate of 100 then OK
  • Inserts BPV position of 100 then OK
  • Ensures Bypass Valve Jack Status is Active (controlling)
  • Notifies SRO that Bypass Valves are opening NOTE: Event 8 CRITICAL TASK will be considered MET if the reactor is depressurized through Anticipating Emergency Depress.
  • May order a lower than 800 psig Reactor pressure band.

SRO

  • May direct an operator to perform Rx Power, Level, and Pressure control, so that the other operator can address Secondary Containment parameters.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 8 Page 22 of 27 Event

Description:

Emergency Depress when Max Safe exceeded in more than one area.

Time Position Applicant's Actions or Behavior

  • Provides periodic updates on temperature readings and delta temp readings to the SRO (~14 minutes).
  • Reports R604 points 109 & 114 are above Max Safe.

ATC

  • Reports R608 points 109 & 116 are above Max Safe.
  • When a second temperature or delta temp exceeds Max Safe levels, informs the SRO.
  • May order a lower Reactor pressure band to reduce the driving head.

SRO

  • Transitions to CP-1 and orders 7 ADS valves open for Emergency Depress.
  • Places the switches for 7 ADS valves in the open position.

(Critical Task - Open 7 SRVs when Max Safe exceeded in more than one area. Critical task is met when at least 5 SRVs have been opened).

This Critical task will be considered met if the reactor is depressurized through Anticipating Emergency Depress from Event 7.

  • The amber lights for the SRVs will NOT illuminate if pressure has been reduced to below approximately 300 psig. In this case the ATC/BOP operator must use 2H11-P614 recorder indication to monitor tail pipe temperatures for the SRVs to verify the valves actually opened (Recorder 2B21-R614).
  • Depending on Reactor Water Level prior to opening ADS valves, RWL may swell to above 60 inches, requiring the operator to enter 34AB-C32-001-2, Reactor Water Level Above 60 inches.
  • Operator secures all injection other than CRD.

Simulator Operator, the NEXT event will be activated as Reactor pressure decreases.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 9 Page 23 of 27 Event

Description:

SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a Residual Heat Removal systems.

Time Position Applicant's Actions or Behavior Simulator Operator, At the Chief Examiners direction AND AFTER the ADS valves have been opened (Event 8); when Reactor pressure is < 500 psig, ENSURE ET-EGB21-5 INSERTS mfN21_99, SULCV fails closed.

(Critical Task) - Throttle open 2N21-F110 for vessel injection to maintain RWL greater than -185 inches.

If 2N21-F110 is NOT used, then a NEW Critical Task will be to align RHR/Core Spray systems for vessel injection to maintain RWL greater than

-185 inches.

EITHER IS ACCEPTABLE.

  • The BOP recognizes the SULCV has failed closed.
  • Performs ONE or MORE of the following to inject water into the reactor.

BOP

  • Throttles open Condensate System, 2N21-F110, and injects water into the reactor (Critical Task).

NOTE: mfE11_202A (LOCA Signal failure) inserted at beginning.

BOP will start 2B Core Spray due to Event 3.

OR

  • Confirm discharge pressure >265 psig.
  • Confirm a CS and RHR room cooler automatically starts.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-04 Event No.: 9 Page 24 of 27 Event

Description:

SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a Residual Heat Removal systems.

Time Position Applicant's Actions or Behavior NOTE: mfE11_202B (LOCA Signal failure) inserted at beginning.

OR

  • Notifies SRO of RHR pump logic failure and starts (Critical Task) is met if one RHR pump is started) the 4 RHR pumps.
  • Reports SULCV problem to the SRO.

With Chief Examiners Permission, the Scenario will be terminated when reactor water is being controlled following the Emergency Depressurization, with reactor pressure below 50 psig or as directed by the Chief Examiner.

Page 25 of 27 Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-04 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initiating Conditions: Unit 2 is operating at 65% RTP making preparations to remove 2A RFPT from service.

Turnover Reduce reactor power to 60% RTP for RFPT 2A removal. Leave RFPT 2A operating at ~1000 RPM.

Summary:

  • Event 1: Reactivity: The ATC will reduce reactor power to ~60% RTP via Recirc to achieve

<7 mlbm/hr for 2A RFPT removal from service.

  • Event 2: Normal; After reactor power is reduced, the BOP will remove the 2A RFPT from service and leave rotating at approximately 1000 rpm.
  • Event 3: Component/TS; 2A Loop of Core Spray experiences high discharge pressure (valve leakage). When 2E21-F004A control switch is placed to open, the valve breaker trips causing the 2A CS Loop to be inop.
  • Event 4: Component; The CRD 2A pump experiences a Suction Filter dP High requiring swapping to standby pump IAW System Operating procedure.
  • Event 5: Component/TS; RCIC Room fire.
  • Event 6: Instrument/TS; The ADS System will experience an inadvertent initiation which will require the ATC to place the ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100°F cooldown rate. (Critical Task) ADS will be inop.
  • Event 7: Major; Unisolable HPCI Steam leak in Reactor Building requiring a Reactor Manual scram.
  • Event 8: Major; Since a HPCI Group 3 signal failure exists an Emergency Depress when > Max Safe in more than one area. (Critical Task)
  • Event 9: Component; SULCV fails closed. Core Spray & RHR Logic failure. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a RHR Systems. (Critical Task)

Page 26 of 27 Critical Tasks NRC FINAL Facility: E. I Hatch Scenario No.: 9-04 Op-Test No.: 2015-301 Critical Tasks

  • The ADS System will experience an inadvertent initiation which will require the ATC to place the ADS Inhibit switches to INHIBIT prior to the valves opening to prevent exceeding >100°F cooldown rate. (Event 6)
  • Emergency Depress when > Max Safe in more than one area. (Event 8)
  • SULCV fails closed. RPV level will be controlled either by throttling open 2N21-F110, or by using a Core Spray and/or a RHR Systems. (Event 9)

ES 301-4 Attributes Required Actual Items

1. Total Malfunctions 5-8 6 1. CS press high/breaker tripped (Event 3)
2. CRD 2A Suction Filter dP High (Event 4)
3. RCIC Room fire. (Event 5)
4. ADS System inadvertent initiation (Event 6)
5. Unisolable HPCI Steam leak in RB (Event 7)
6. SULCV fails closed. Core Spray & RHR Logic failure (Event 9)
2. Malfunctions After 1-2 1 1. SULCV fails closed. Core Spray & RHR Logic EOP Entry failure (Event 8)
3. Abnormal Events 2-4 3 1. RCIC Room fire. (Event 5)
2. ADS System inadvertent initiation (Event 6)
3. Unisolable HPCI Steam leak in RB (Event 7)
4. Major Transients 1-2 2 1. Unisolable HPCI Steam leak in RB (Event 7)
2. Emergency Depress when > one area Max Safe (Event 8)
5. EOPs entered, 1-2 2 1. 31EO-EOP-014-2. SC/RR (Event 7) requiring substantive 2. 31EO-EOP-010-2, RC Non ATWS (Event 7) actions
6. EOPs contingencies 0-2 1 1. 31EO-EOP-015-2, CP-1 (Event 8) requiring substantive actions
7. Critical Tasks 2-3 3 1. ADS System inadvertent initiation (Event 6)
2. Emergency Depress when > one area Max Safe (Event 8)
3. SULCV fails closed. Core Spray & RHR Logic failure (Event 9)

ILT 9 NRC FINAL Scenario 4 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions:

Activities in progress: Maintaining Rated Thermal Power UNIT 2 STATUS Unit 2 is operating at 65% RTP making preparations to remove Plant Conditions:

2A RFPT from service.

Protected Train: EOOS:

Division I Green Orange Division II Yellow Red Reduce reactor power to 60% RTP for RFPT 2A removal.

Scheduled evolutions:

Leave RFPT 2A operating at ~1000 RPM.

Surveillances due this None shift:

Inop Equipment: None Active tagouts: None Rod Configuration: See RWM

Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-05 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initial Conditions. Unit 2 is operating at 70% RTP. RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance. 2D LLS valve is inop for LLS Function only.

Turnover: IAW 34SO-E11-010-2, lower Torus water level to 147.5 inches, and then increase reactor power to 75%.

Event Malf. No. Event Event No. Type* Description N/A N (BOP) Lower Torus level to 147.5 inches using RHR Loop 2B 1 TS (SRO) IAW 34SO-E11-010-2, Step 7.4.5.1.

2 N/A R (ATC) Raise Reactor power to 75% using Recirc.

CRD Flow Controller fails in Auto requiring manual operation to re-3 mfC11_299 C (ATC) establish CRD flow.

C (BOP) SRV 2B21-F013G opens. The SRV will close after the ATC cycles 4 mfB21_130G TS (SRO) the control switch IAW AB section. (Critical Task)

N/A C (ATC) System Operator reports Condensate Booster pump B has an oil 5 leak, Standby pump must be started, B shutdown.

mfR25_186 C (BOP) Instrument Bus 2B breaker trips open, crosstie to return to service.

6 TS (SRO) mfC71_59 Spurious Reactor scram/ATWS (Power/Level Control, insert control 7 M (ALL) mfC11_211 rods and injecting SBLC. (Critical Task) 8 mfC41_240A C (ALL) SBLC first pump fails to inject, second pump works.

mfC41_240B diE51_S33 RCIC Manual Initiation PB fails mfE51_109 9 C (BOP) RCIC/HPCI fails to Auto start on low level/hi DW pressure. Manual mfE41_235A actions required for injection. (Critical Task) mfE41_235B

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 1 Page 2 of 29 Event

Description:

Lower Torus level to 147.5 inches using RHR Loop 2B IAW 34SO-E11-010-2, Step 7.4.5.1.

Time Position Applicant's Actions or Behavior 12

  • Directs the operator to lower Torus water level to 147.5 using B loop of SRO Min RHR.

Simulator Operator, when requested, INFORM as the Radwaste Operator that the Waste Surge Tank level is 6% and is available to receive Torus water level.

  • Confirms Radwaste is capable of receiving the water to be transferred.
  • Confirms the RHR discharge water temperature is < 200°F, 2T47-R627, point 3.

BOP

  • Notifies SRO to refer to:

SPECIAL REQUIREMENT 4.3.2 of 34SO-E11-010-2 and TS 3.5.1, 3.6.2.3, 3.6.2.4, & 3.6.2.5.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 1 Page 3 of 29 Event

Description:

Lower Torus level to 147.5 inches using RHR Loop 2B IAW 34SO-E11-010-2, Step 7.4.5.1.

Time Position Applicant's Actions or Behavior Reviews SPECIAL REQUIREMENT 4.3.2 of 34SO-E11-010-2 and TS 3.5.1, 3.6.2.3, 3.6.2.4, & 3.6.2.5.

SRO Declares RHR Loop 2B inoperable since 2E11-F040 & 2E11-F049 are open.

  • IAW 3.6.2.3 Condition A,
  • Declares one RHR Suppression pool cooling system inoperable (Loop 2B), and must restore to operable status within 7 days.

SRO

  • IAW 3.6.2.4 Condition A,
  • Declares one RHR Suppression pool spray system inoperable (Loop 2B), and must restore to operable status within 7 days.
  • IAW 3.6.2.5 Condition A,
  • Declares one RHR drywell spray system inoperable (Loop 2B), and must restore to operable status within 7 days.
  • Monitors Torus water level and once level has been lowered to approximately 147.5 secures the flow path.

BOP

  • Reports to the SRO that Torus water level has been lowered to 147.5.
  • As time allows, notifies Radwaste Operator that Torus lowering is complete.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 2 Page 4 of 29 Event

Description:

Raise Reactor power to 75% using Recirc.

Time Position Applicant's Actions or Behavior

  • Directs ATC to increase reactor power to 75% by increasing Recirc flow.

10 Min SRO Power increases are NOT to exceed 10 MWe/min.

NOTE: May get the RBM UPSCALE, (603-202) and ROD OUT BLOCK, (603-238) alarm, if a peripheral control rod is NOT selected. This is expected and the operator may select a peripheral rod at this time.

May also get Alarm HEATER TROUBLE, (650-135), alarm. This is expected at this power level.

  • IAW 34SO-B31-001-2 (step 7.1.5) & 34GO-OPS-005-2, the ATC increases Recirc pump speed, NOT to exceed 10 MWE per minute by depressing the RAISE SLOW or RAISE MEDIUM pushbuttons on the Master (P603 panel) or Individual controls (P602 panel) until reactor power is 75%.

ATC

  • If using Individual Controls, pump speed increases will alternate between the A & B Recirc pumps to prevent excessive flow mismatches.
  • Monitors power increase by observing APRM and generator output indications.

WHEN changing Recirc pumps speed while in Two Loop operation maintain pump speeds to limit recirculation loop jet pump mismatch within the following limits:

ATC

  • <10% of rated core flow (7.7 E6 lbm/hr) WHEN operating

< 70% of rated core flow; AND

  • <5% of rated core flow (3.85 E6 lbm/hr) WHEN operating at

> 70% of rated core flow.

ATC Notifies the SRO that reactor power has been increased to 75%.

Simulator Operator, at the Chief Examiners request, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 3 Page 5 of 29 Event

Description:

CRD Flow Controller fails in Auto requiring manual operation to re-establish CRD flow.

Time Position Applicant's Actions or Behavior At the Chief Examiners direction, Simulator Operator ENTERS (RB-3) 10 Min mfC11_299, CRD Flow Control Fails Low.

  • Receives CRD HYD TEMP HIGH, (603-140) alarm.
  • Determines that the CRD Flow Control Valve A has closed.
  • Determines 2C11-R600, CRD Flow Controller, output is at minimum and ATC has failed downscale.
  • Notifies SRO that the CRD Flow Controller has failed downscale.
  • Enters:
  • CRD HYD TEMP HIGH, (603-140)
  • Increases output of controller until CRD flow is approximately 50 gpm.

SRO

  • Dispatches a SO to monitor CRD drive temperatures.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 3 Page 6 of 29 Event

Description:

CRD Flow Controller fails in Auto requiring manual operation to re-establish CRD flow.

Time Position Applicant's Actions or Behavior Simulator Operator, if asked, AFTER 3 minutes from being dispatched, report to the SRO, as an SO, that 2C11-R600 FCV does NOT have any air leaks and appears to be functioning properly.

Simulator Operator, if asked, AFTER 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11-R600 FCV appears to be functioning properly with a zero signal going to the FCV and the FCV is closed.

Simulator Operator, if asked to swap FCV, AFTER 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11-R600 FCV is receiving a zero signal from the controller and it appears the flow controller is malfunction.

Simulator Operator, if ATC has placed after 5 minutes from being dispatched, report to the SRO, as I&C, that 2C11-R600 controller has malfunctioned and will need repair.

When requested and if the CRD HYD TEMP HIGH, (603-140) alarm is still illuminated, Simulator Operator, as SO checking CRD Temps, reports that 2 CRD drives are >250°F. 30-11 at 260°F, 22-35 at 265°F and some others are slowly increasing.

If CRD HYD TEMP HIGH, (603-140) alarm is NOT illuminated, Simulator Operator, as SO checking CRD Temps, reports that 2 CRD drives had been

>250°F but are now below 250°F and trending down.

Simulator Operator, with Chief Examiners permission, PROCEEDS to Event 4 to run in parallel with Event 3.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 3 Page 7 of 29 Event

Description:

CRD Flow Controller fails in Auto requiring manual operation to re-establish CRD flow.

Time Position Applicant's Actions or Behavior ONCE Event 4 is complete, DELETE mfC11_299 and notify the SRO that 2C11-R600 is now repaired and as Shift Manager, grant permission to return controller to automatic mode.

SRO

  • Confirms system parameters are normal
  • Confirms 603-140, CRD Hyd Temp High, alarm is clear
  • Reports to SRO that CRD flow controller has been restored to normal configuration.

Simulator Operator, at the Chief Examiners request, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 4 Page 8 of 29 Event

Description:

SRV 2G Opens and closes after ATC cycles switch.

Time Position Applicant's Actions or Behavior Simulator Operator: To insure the BOP operator gets the next malfunction, as Shift Manger, request the ATC to get some Offgas panel reading (Stack Flow)

OR with Chief Examiners permission, perform the following.

8 Min Simulator Operator: At the direction of the Chief Examiner, ACTIVATE:

(RB-4) mfB21_130G.

ALL

  • SAFETY BLOWDOWN VALVE LEAKING, (602-311)
  • SAFETY BLOWDOWN PRESSURE HIGH, (603-122)

Directs operator to enter 34AB-B21-003-2, Failure of Safety/Relief valves SRO

  • Enters a RAS for TS LCO 3.6.1.6.A for 2 or more LLS valves inop, which requires the unit to be in Mode 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and Mode 4 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The ATC may enter the abnormal procedure first before addressing the ARPs.

  • Confirms green light is OFF
  • Checks back panel tail pipe temperatures
  • Confirm 2G is leaking using the indication on 2B21-R614, Auto BOP Blowdown/Safety Vlv Temps recorder.
  • Reports to the SRO and ATC operator that 2G SRV is open

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 4 Page 9 of 29 Event

Description:

SRV 2G Opens and closes after ATC cycles switch.

Time Position Applicant's Actions or Behavior Simulator Operator: When the operator cycles the control switch, ENSURE Event Trigger EGB21-11 activates.

  • Confirms the green AND amber lights are illuminated for 2G SRV
  • Cycles the 2G SRV control switch several times between Open/Close (Critical Task)

BOP

  • Notifies SRO that SRV 2G closed when control switch was cycled.
  • May request the SSS to pull the fuses for SRV 2G. (SIMULATOR OPERATOR, If requested, wait 4 minutes, DEPRESSES RB-9, rfB21_306, SRV G Fuses) to pull fuses.
  • When SRV closes confirms;
  • Torus water level increase has stopped.
  • Torus temperature increase has stopped.
  • Reactor Power is at its original value BOP
  • SRV tailpipe temperature decreasing
  • Resets the SRV leak detection AMBER SRV indicating lights.
  • Notifies SRO the Torus-Drywell Vacuum Breaker surveillance needs to be performed within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
  • Notifies Chemistry to increase monitoring of vessel moisture carryover.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event AFTER Event 3 & 4 are complete.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 5 Page 10 of 29 Event

Description:

System Operator reports Condensate Booster pump B has an oil leak, A must be started, B shutdown.

Time Position Applicant's Actions or Behavior Simulator Operator, at the Chief Examiners direction, as a System Operator (SO), reports on rounds, that the 2B Condensate Booster pump has an oil leak.

12 When questioned about the size of the oil leak, report as the SO that the CBP MIN still has ample oil to operate, but should be shut down as soon as possible.

NOTE: The following is written to start the 2A CBP.

  • Directs Operator to place 2A Condensate Booster pump (CBP) in service SRO and shutdown the 2B Condensate Booster pump.

ATC

  • Has SO:
  • Verify that 2A CBP Oil Reservoir and motor bearing oil levels are WITHIN normal level marks.
  • Throttle 2P41-F364A outlet valve as necessary to maintain the oil temperature between 50°F and 115°F.
  • Confirm / Place CBP 2A Oil Pump control switch in Auto and Confirm pump is running.

Simulator Operator does NOT have to enter the remote function for closing the discharge valve for the CBP, because it has to be throttled prior to pump start and we do NOT have throttle capability.

Simulator Operator, as SO, reports that CBP 2A oil levels are normal, oil temperature is at 95°F, the oil pump is running in Auto and that the 2N21-F020A is closed.

  • Directs SO to:
  • Observe for indication of a stuck open / leaking discharge check valve as evidenced by increasing pressure on the pump side of the discharge check valve.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 5 Page 11 of 29 Event

Description:

System Operator reports Condensate Booster pump B has an oil leak, A must be started, B shutdown.

Time Position Applicant's Actions or Behavior Simulator Operator, as SO, reports that the 2N21-F020A is opened 15 seconds and the discharge check valve does NOT indicate leakage. (Verify that rfN21_60A is in Open.)

  • Starts Condensate Booster Pump 2A, by placing the control switch to Start.

ATC

  • Has SO throttle open the Discharge valve and maintain oil temp by throttling PSW to the oil cooler.

Simulator Operator, as SO, reports that the discharge valve is now full open for CBP 2A, and that oil temp is being maintained at 95°F

Simulator Operator, ACTIVATE: (RB-8): rfN21_61 (CBP B Disch valve close), then as the SO, reports that the discharge valve for CBP 2B is started closed.

  • Places CBP 2B control switch to stop within 90 seconds of being told the discharge valve has started closing.

ATC

  • Reports to SRO that 2A CBP is operating and that the 2B CBP has been secured. May ask SRO if it is desired to place the 2B CBP in standby. If so the CBP 2B control switch will be placed in Auto.
  • May direct the operator to place CBP 2C in PTL Off or Standby and leave SRO oil pump in off.

Simulator Operator, If requested to re-open the discharge valve, TOGGLE:

rfN21_61 (CBP B Disch valve Open) and as SO report that the discharge valve for CBP 2B is Open.

Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 6 Page 12 of 29 Event

Description:

Instrument Bus 2B breaker trips open, crosstie to return to service.

Time Position Applicant's Actions or Behavior 15 Simulator Operator, at direction of the lead examiner, ACTIVATE: (RB-6)

Mins malfunction mfR25_186, Loss Of Instrument Bus 2B.

ALL Various alarms indicating Instrument Bus 2B has lost power.

Directs BOP to enter 34AB-R25-002-2, Loss Of Instrument Buses, for loss of SRO Instrument Bus 2B.

  • Places SBGT Fan 2A control switch to "RUN."
  • Receives 2A SBGT SWITCH NOT IN AUTO, (657-091), alarm
  • Confirms SBGT Heater red light illuminates.

BOP

  • Places 2B SBGT Fan control switch to OFF
  • Dispatches SO to confirm CLOSE Instrument Bus 2B supply breaker 28 on 2R25-S037, Essential Cabinet 2B by dispatching a SO locally.
  • Dispatches SO to confirm Essential Cabinet 2B 2R25-S037 is energized by NO other alarms illuminated at 2H11-P651.
  • Per step 4.4, dispatches Maintenance to check fuses R25F209 F01, R25F210 F02, and R25F211 F03, in fuse panel 2R20N P002 located next to Essential Cabinet 2B (power supply to 2R25 S065, Instrument Bus 2B 6).

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 6 Page 13 of 29 Event

Description:

Instrument Bus 2B breaker trips open, crosstie to return to service.

Time Position Applicant's Actions or Behavior NOTE: The BOP may consult with the SRO and decide not perform steps 7.2.1.1 through 7.2.4 since these fans only circulate air in Secondary Containment.

  • Secures Rx Bldg Ventilation per 34SO-T41-005-2, Step 7.2.1 by performing the following; (steps 7.2.1.1 through 7.2.4)

May place the following in the STOP position:

  • Places 2T41-B007, Rx Bldg Cooler Working Floor El 130 North
  • Places 2T41-B008, Rx Bldg Cooler Working Floor El 130 South
  • Places 2T41-B026, Rx Bldg Primary Cooler Mn Steam Pipe Chase
  • Places 2T41-B010, Rx Bldg Cooler Equip Room El 164
  • Places 2T41-B011, Rx Bldg Cooler Operating Floor El 185
  • Places 2T41-B015, Rx Bldg Cooler Operating Floor El 185
  • Places 2T41-B016, Rx Bldg Cooler Working Floor El 203 NOTE: If fans 2T41-B026 and 2T41-B009 are secured, delay proceeding to the next event to evaluate if the SRO will restart Rx Bldg Ventilation BOP or if the Group I signal from High Steam Chase Temperature will be received.

May place the following in the OFF position:

  • 2T41-B009, Rx Bldg Secondary Cooler Mn. Steam Pipe Chase Performs the following:
  • Places in OFF 2T41-C007B, Rx Bldg Vent Exhaust Fan
  • Places in OFF 2T41-C007A, Rx Bldg Vent Exhaust Fan

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 6 Page 14 of 29 Event

Description:

Instrument Bus 2B breaker trips open, crosstie to return to service.

Time Position Applicant's Actions or Behavior

  • Secures Refuel Flr Ventilation per 34SO-T41-006-2 by performing the following,
  • Places 2T41-C002B Refuel Flr Vent Supply Fan, control switch, in OFF.
  • Places 2T41-C002A, Refuel Flr Vent Supply Fan, control switch, in OFF.
  • Places 2T41-C005B, Refuel Flr Vent Exh Fan, control switch, in OFF.
  • Places 2T41-C005A, Refuel Flr Vent Exh Fan, control switches, in BOP OFF.
  • Dispatches a SO locally to perform the following:
  • Place 2T41-B024C, Refueling Floor Unit Heater Fan, control switch, in OFF.
  • Place 2T41-B024B, Refueling Floor Unit Heater Fan, control switch, in OFF.
  • Place 2T41-B024A, Refueling Floor Unit Heater Fan, control switch, in OFF.

Simulator Operator, Once Tech Specs have been addressed, Call the control room, as an Electrician, and report that Instrument Bus 2B supply breaker 28 on 2R25-S037, Essential Cabinet 2B, is damaged and must be replaced. If asked, inform Control Room it will take approximately 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> to replace.

Simulator Operator, when directed, ACTIVATE: (RB-9), rfR25_166, Instrument Bus 2B Powered from 2A, THEN NOTIFIES SRO that Instrument Bus 2B is powered from Instrument Bus 2A.

Addresses TS 3.8.7, Distribution Systems - Operating and determines that Condition C exists requiring Instrument Bus 2B returned to operable status in 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

SRO Addresses TS 3.4.5. B, requiring grab samples of primary containment atmosphere once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and restore within 30 days.

After report on local actions, directs the BOP to re-energize Instrument Bus 2B by cross tying with Instrument Bus 2A.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 6 Page 15 of 29 Event

Description:

Instrument Bus 2B breaker trips open, crosstie to return to service.

Time Position Applicant's Actions or Behavior NOTE: The following steps may be performed out of order, AFTER placing Group Isolation Reset Switch to the Group 1 and Group 2/5 positions, on P601.

Directs SO to crosstie Instrument Buses per step 4.5.

Once Instrument Bus 2B is energized, continues at step 4.7 and performs the following:

  • Following confirmation of any group isolation(s),

RESET isolation(s) by placing Group Isolation Reset Switch to the BOP Group 1 and Group 2/5 positions, on P601.

  • Opens the following Fission Product Monitoring isolation valves, panel P700:

IT IS NOT INTENDED FOR THE CREW TO RESTORE ALL OF THE LOADS ASSOCIATED WITH INSTRUMENT BUS 2B.

AFTER THE OPERATOR RESTORES 2D11-F052, F053 & F072, AT THE CHIEF EXAMINERS DIRECTION, SIMULATOR OPERATOR PROCEEDS TO THE NEXT EVENT.

BOP

  • Notifies Unit 1 NPO to restore Control Room ventilation to the desired mode of operation per 34SO-Z41-001-1.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 6 Page 16 of 29 Event

Description:

Instrument Bus 2B breaker trips open, crosstie to return to service.

Time Position Applicant's Actions or Behavior

  • Restores the Drywell Cooling Fans to normal alignment per 34SO-T47-001-2.
  • Alarm 650-204, Drywell/Torus RCDR R627 Temp High, may be received if Drywell Cooling Fans are not restored to a pre-event lineup.

It is NOT intended for the crew to restore all of the loads associated with INSTRUMENT BUS 2B.

AFTER the operator restores 2D11-F052, F053 & F072, AT the Chief Examiners direction, Simulator operator PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 7 Page 17 of 29 Event

Description:

Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.

Time Position Applicant's Actions or Behavior Simulator Operator, at direction of the lead examiner, ACTIVATE: (RB-7) malfunction mfC71_59, Spurious Reactor Scram.

Directs ATC to scram the reactor:

  • Enters RC or RCA EOP Flowcharts.
  • Directs ATC to perform RC-1 placard.
  • Directs BOP to perform RC-2 and RC-3 placards.

SRO

  • If time allows assigns TC-1 to be performed.

Directs ATC to:

  • Confirm the reactor Mode Switch in Shutdown.

SRO

  • Confirm ARI Initiation.
  • Confirm Recirc runback to minimum/tripped.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 7 Page 18 of 29 Event

Description:

Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.

Time Position Applicant's Actions or Behavior NOTE: Event Trigger C71-15 INSERTS; aiC11-R607-1, CRD Cooling Water dP Controller Failure (f: 25, r: 1000), svoN37225 &

svoN37226 when the Rx Mode Switch is placed to SHUTDOWN.

  • Manually SCRAMs the Reactor using the SCRAM pushbuttons.
  • Places Rx Mode Switch in SHUTDOWN.
  • Initiates Alternate Rod Insertion (ARI) by rotating the button collars and depressing both ARI pushbuttons at the same time when directed by the SRO.
  • Informs the SRO that all rods are NOT fully inserted (ATWS).

ATC

(Placard)

  • May attempt to inject SBLC depending on RWL/power level (if power is above 5%, the ATC is directed to inject SBLC IAW the RC-1 placard).

NOTE: See Event 8 for SBLC Failures.

  • Places SDV Isol Vlv Switch to ISOL and verifies closed.
  • Confirms Recirc at minimum speed and since power is above 5%, the ATC trips Recirc IAW the RC-1 placard).

Reports to the SRO that:

  • The Reactor Mode Switch is in the SHUTDOWN position.

ATC

  • ARI has been initiated (ATC may initiate ARI at this time).
  • Recirc is at minimum speed (if power is above 5%, the ATC is directed to trip Recirc IAW the RC-1 placard).

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 7 Page 19 of 29 Event

Description:

Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.

Time Position Applicant's Actions or Behavior BOP Performs actions of placards RC-2 and RC-3 after Reactor SCRAM.

Performs RC-2 actions consisting of:

  • Confirms proper Level Control response:
  • Checks ECCS Injection Systems
  • Ensures FW Master Controller setpoint reduces to 9 inches and output reduces to 25% of previous value BOP
  • When feed flow is less than the capacity of the S/U level control valve (

(Placard) 1.5 mlbm/hr), then:

  • Confirms 2C32-R619, FW S/U level control valve controller, in Auto, set at approximately 9 inches.
  • Will control RWL at 9 inches.

Performs RC-3 consisting of:

  • Monitors RPV pressure.
  • Confirms proper operation of pressure control system (TBV, LLS, etc.).

BOP

  • If necessary, allow RPV pressure to exceed 1074 psig then cycle any SRV (Placard) to initiate LLS.
  • Maintain RPV pressure between 1074 and 800 psig.
  • Notify SRO of pressure control system operation.

SRO

  • May direct BOP operator to lower reactor pressure to <845 psig.

BOP

  • If directed, lowers pressure setpoint to <845 psig using the DEHC system (Placard) as described on the following graphic.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 7 Page 20 of 29 Event

Description:

Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.

Time Position Applicant's Actions or Behavior BOP

  • Notifies SRO that Pressure set has been reduced to <845 psig.

SRO

  • Directs ATC to report reactor power or observes reactor power on SPDS.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 7 Page 21 of 29 Event

Description:

Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.

Time Position Applicant's Actions or Behavior NOTE: If asked, STA will direct the ATC to start in the center of the core and spiral out in a black and white pattern.

SIMULATOR OPERATOR: Once ARI is in TEST & ALL Reactor Scrams signals have been jumpered out, DELETES malfunction mfC71_59, Spurious Reactor Scram.

ATC

  • Confirms ARI initiation signals are clear and Then depresses ARI Reset pushbutton OR dispatches an operator to place ARI System Test switch, to TEST, on panel 2C11-P001
  • Attempts to drive rods by:
  • Places Reactor Mode switch to REFUEL.
  • Obtain recommendations from STA
  • Verifies adequate CRD drive water pressure for driving rods and may operate 2C11-R600, CRD Flow Control, to achieve higher drive water DP.
  • May start second CRD pump
  • Drives rods to at least 02 using the Emerg In or IN (Critical Task)

ATC

  • Dispatches operator to install jumpers to override all automatic scram signals.
  • Places Discharge Volume Isolation Test switch to Norm at 2H11-P603.
  • Resets Scram when notified that jumpers have been installed.
  • Confirm all SDV Vent and Drain Valves are open.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 7 Page 22 of 29 Event

Description:

Spurious Reactor scram/ATWS (Power/Level Control, insert control rods.

Time Position Applicant's Actions or Behavior NOTE: 2C11-R607, Press Control Vlv F127, controller is failed to allow only ~25% valve position. A valve position of 25% will NOT allow control rods to insert from Cooling Water DP.

  • Places 2C11-R607, Press Control Vlv F127 Controller, in MAN
  • Closes 2C11-F005, Return To Vessel Flow Control Simulator Operator, at the Chief Examiners direction, PROCEEDS to the next event.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 8 Page 23 of 29 Event

Description:

SBLC first pump fails to inject, second pump works.

Time Position Applicant's Actions or Behavior Simulator Operator; ENSURE malfunctions ENSURE EVENT TRIGGERS (EGC41-1 &EGC41-2) THAT WILL PREVENT THE FIRST PUMP STARTING BUT NOT THE SECOND are inserted. They were inserted from the beginning.

ATC

  • Injects SBLC (power >5%)
  • Unlocks and places SBLC pump select switch in Start Sys A or Start Sys B position.
  • Confirms Squib Valve Ready Lights are extinguished.
  • Recognizes that the selected SBLC pump DID NOT start.
  • Places SBLC pump select switch in Start Sys B or Start Sys A position. (The pump not attempted first.)
  • Confirms the selected second SBLC pump started.

Simulator operator proceeds to the next event at the Chief Examiners direction.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 9 Page 24 of 29 Event

Description:

RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.

Time Position Applicant's Actions or Behavior SRO Directs an operator to INHIBIT ADS.

ATC/BOP

  • 2H11-P602, Places the following switches to INHIBIT:

NOTE: Simulator Operator, ENSURE Event Trigger ET-EGB21-7, trips both RFPTs when RWL is <-40.

SRO

  • Directs BOP control RWL -60 inches to -90 inches.
  • As time allows, directs BOP to verify Isolations and ECCS initiations.

BOP

  • Reports failure of HPCI and RCIC to auto initiate at - 35.
  • Reports failure of both RFPTs.
  • Reduces injection to control RWL -60 inches to -90 inches.
  • If HCPI was manually started, the operator will reduce controller output to lower RWL.
  • If HCPI was in standby, places 2E41-C002-3, HPCI Aux. Oil Pump, in PULL-TO-LOCK.
  • If RCIC were manually started, the operator may depress the RCIC turbine trip push-button or reduce controller output.

BOP Controls RWL -60 inches to -90 inches using RCIC and/or HPCI.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 9 Page 25 of 29 Event

Description:

RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.

Time Position Applicant's Actions or Behavior BOP IF RCIC injection is attempted AND RCIC was manually tripped:

  • IF RWL is <-35 inches, recognizes and informs the SRO that RCIC failed to auto start
  • Transfers 2E51-R612, Turbine Controller, to manual and adjust output to 50%.
  • Throttle opens 2E51-F524, Trip & Throttle Valve, AND concurrently opens 2E51-F013, Pump Discharge Valve
  • Confirms 2E51-F019, Min Flow Valve, Opens, AND subsequently closes, when system flow is greater than 79.3 gpm.
  • Continues to throttle 2E51-F524 Open, until turbine speed is limited by 2E51-R612, Turbine Controller, then perform the following:
  • Fully opens 2E51-F524, Trip & Throttle Valve.
  • Increases 2E51-R612, Turbine Controller, output to achieve 3000 to 4000 rpm.
  • Transfers 2E51-R612, Turbine Controller, to auto and adjust to desired flow rate.
  • Maintains level -60 to -90 BOP IF RCIC injection is attempted and RCIC has NOT been tripped:
  • Depresses RCIC Manual Initiation P/B (failed)
  • Starts Barom Cndsr Vac Pmp
  • Adjusts controller for desired flow
  • Maintains level -60 to -90

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: 2015-301 Scenario No.: 9-05 Event No.: 9 Page 26 of 29 Event

Description:

RCIC & HPCI fails to auto start with the RCIC manual pushbutton failing.

Time Position Applicant's Actions or Behavior BOP If HPCI injection is attempted the operator:

  • IF RWL is <-35 inches, recognizes and informs the SRO that HPCI failed to auto start
  • Take 2E41-C002-3, Aux Oil Pump, control switch to the START position.
  • Confirm 2E41-F012, Min Flow Valve, CLOSES at flow > 790 gpm.

CONTINUOUS RECHECK:

Simulator Operator, when the following conditions exist:

1. Scram is RESET,
2. RWL is controlled between -60 and -90 inches, WITH CHIEF EXAMINERS DIRECTION, the scenario may be terminated.

Page 27 of 29 Appendix D Scenario Outline Form ES-D-1 NRC FINAL Facility: E. I Hatch Scenario No.: 9-05 Op-Test No.: 2015-301 Examiners: Operators: SRO RO BOP Initiating Conditions: Unit 2 is operating at 70% RTP. RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance. 2D LLS valve is inop for LLS Function only.

Turnover Lower Torus level to 147.5 inches, and then increase reactor power to 75%.

Summary:

  • Event 1: Normal; Lower Torus level to 147.5 inches using RHR Loop 2B IAW 34SO-E11-010-2, Step 7.4.5.1.
  • Event 2: Reactivity; The ATC will raise Reactor power to ~75% RTP.
  • Event 3: Component; The CRD Flow Controller fails closed causing a loss of normal CRD flow. The ATC will place the controller in manual and restore CRD flow.
  • Event 4: Component/TS; SRV 2G opens. The ATC operator will attempt to close the SRV IAW the abnormal procedure for an electrically open SRV. After the ATC operator cycles the SRV control switch, the SRV will close. (Critical Task) If Torus temperature exceeds 95°F, the BOP operator will place RHR in Suppression Pool Cooling. SRO addresses TS for inoperable SRV.
  • Event 5: Component; System Operator reports Condensate Booster pump B has an oil leak, Standby pump must be started, B shutdown.
  • Event 6: Component/TS; Instrument Bus 2B supply breaker from Essential 2B will trip open de-energizing subsequent loads. Once investigated, Instrument Bus 2B will be energized from Instrument Bus 2A and the BOP will return loads to service.

The SRO will direct/ensure the ATC inserts control rods within 20 minutes of the scram and inject SBLC prior to leaving RC-1. (Critical Task)

  • Event 8: Component; The first SBLC pump fails to start, second pump works injecting SBLC prior to the ATC leaving RC-1.
  • Event 9: Component; RCIC and HPCI fail to auto start. RCIC must be manually aligned and started to maintain RWL -60 to -90. (Critical Task)

Page 28 of 29 Critical Tasks NRC FINAL Facility: E. I Hatch Scenario No.: 9-05 Op-Test No.: 2015-301 Critical Tasks

  • Cycles the SRV control switch to close SRV (Event 4)
  • Begins inserting control rods within 20 minutes of scram/injects SBLC before leaving RC-1.

(Event 7/8)

  • RCIC/HPCI must be manually aligned and started to maintain RWL -60 to -90 (Event 9)

ES 301-4 Attributes Required Actual Items

1. Total Malfunctions 5-8 7 1. ATC uses controller in manual to restore CRD flow (Event 3)
2. SRV 2G opens (Event 4)
3. Condensate Booster pump B oil leak, Standby pump must be started, B shutdown (Event 5)
4. Instrument Bus 2B breaker fails (Event 6)
5. Spurious Reactor scram/ ATWS (Event 7)
6. SBLC Pump 2A & 2B start failure (1st pump)

(Event 8)

7. RCIC/HPCI Auto start failure (Event 9)
2. Malfunctions After 1-2 2 1. SBLC Pump 2A & 2B start failure (1st pump)

EOP Entry (Event 8)

2. RCIC/HPCI Auto start failure (Event 9)
3. Abnormal Events 2-4 3 1. ATC uses controller in manual to restore CRD flow (Event 3)
2. SRV 2G opens (Event 4)
3. Instrument Bus 2B breaker fails (Event 6)
4. Major Transients 1-2 1 1. Spurious Reactor scram/ ATWS (Event 7)
5. EOPs entered, 1-2 1 1. 31EO-EOP-011, RCA, (Event 7) requiring substantive actions
6. EOPs contingencies 0-2 1 1. 31EO-EOP-017, CP-3, (Event 7) requiring substantive actions
7. Critical Tasks 2-3 3 1. SRV 2G opens (Event 4)
2. Control Rods & SBLC injection (Event 7/8)
3. RCIC/HPCI Auto start failure (Event 9)

ILT 9 NRC FINAL Scenario 5 SHIFT TURNOVER Safety Focus UNIT 1 STATUS Unit 1 is operating at 100% power Plant Conditions: Activities in progress: 34SV-P41-001-1, Plant Service Water Pump Operability.

UNIT 2 STATUS Unit 2 is operating at approximately 70% RTP.

Plant Conditions:

Activities in progress: RHR Loop B is operating in Torus Cooling Mode due to a recently performed HPCI surveillance..

Protected Train: EOOS:

Division I Green Orange Division II Yellow Red Lower Torus level to 147.5 inches.

Scheduled evolutions:

After Torus level is lowered increase reactor power to 75%.

Surveillances due this None shift:

Inop Equipment: 2D LLS valve is inop for LLS Function only.

Active tagouts: 2D LLS valve.

Rod Configuration: See RWM