(2 intermediate revisions by the same user not shown) |
Line 2: |
Line 2: |
| | number = ML080600303 | | | number = ML080600303 |
| | issue date = 03/03/2008 | | | issue date = 03/03/2008 |
| | title = 03/03/08, Perry, EOC Annual Assessment Letter (Report 05000440-08-001) | | | title = Perry, EOC Annual Assessment Letter (Report 05000440-08-001) |
| | author name = Caldwell J L | | | author name = Caldwell J |
| | author affiliation = NRC/RGN-III/ORA | | | author affiliation = NRC/RGN-III/ORA |
| | addressee name = Allen B S | | | addressee name = Allen B |
| | addressee affiliation = FirstEnergy Nuclear Operating Co | | | addressee affiliation = FirstEnergy Nuclear Operating Co |
| | docket = 05000440 | | | docket = 05000440 |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter: | | {{#Wiki_filter:rch 3, 2008 |
| [[Issue date::March 3, 2008]]
| |
|
| |
|
| Mr. Barry Site Vice President
| | ==SUBJECT:== |
| | ANNUAL ASSESSMENT LETTER - PERRY NUCLEAR PLANT (05000440/2008001) |
|
| |
|
| FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A-PY-290 Perry, OH 44081-0097
| | ==Dear Mr. Allen:== |
| | On February 12, 2008, the NRC staff completed its performance review of the Perry Nuclear Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility. |
|
| |
|
| SUBJECT: ANNUAL ASSESSMENT LETTER - PERRY NUCLEAR PLANT (05000440/2008001)
| | This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the security cornerstone review and resultant inspection plan. |
|
| |
|
| ==Dear Mr. Allen:==
| | Overall, Perry Nuclear Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within the Regulatory Response column of the NRCs Action Matrix, based on the Mitigating Systems Performance Index (MSPI) results for the Emergency AC Power being White since the first quarter of 2007. |
| On February 12, 2008, the NRC staff completed its performance review of the Perry Nuclear Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the security cornerstone review and resultant inspection plan. Overall, Perry Nuclear Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within
| |
|
| |
|
| the Regulatory Response column of the NRC's Action Matrix, based on the Mitigating Systems Performance Index (MSPI) results for the Emergency AC Power being White since the first quarter of 2007. On May 1, 2007, the NRC staff completed an update of our assessment of the Perry Nuclear Power Plant. Our May 2, 2007, letter informed FirstEnergy Nuclear Operating Company that all actions had been completed for Perry to exit the Multiple/Repetitive Degraded Cornerstone column of the NRC's Action Matrix. Therefore, effective the second quarter 2007, the Perry plant exited the Multiple/Repetitive Degraded Cornerstone column and was placed in the Regulatory Response column, based on the White Emergency AC Power System MSPI.
| | On May 1, 2007, the NRC staff completed an update of our assessment of the Perry Nuclear Power Plant. Our May 2, 2007, letter informed FirstEnergy Nuclear Operating Company that all actions had been completed for Perry to exit the Multiple/Repetitive Degraded Cornerstone column of the NRCs Action Matrix. Therefore, effective the second quarter 2007, the Perry plant exited the Multiple/Repetitive Degraded Cornerstone column and was placed in the Regulatory Response column, based on the White Emergency AC Power System MSPI. |
|
| |
|
| Regarding the White Performance Index, Region III conducted Supplemental Inspection 95001, "Inspection for One or Two White Inputs in a Strategic Performance Area," during the week of August 20 to assess the root cause analysis and implementation of corrective actions for the performance index. Based on the results of this inspection, no findings of significance were identified. The staff has identified that the improvements in human performance first noted in our 2006 End-of-Cycle assessment have not been sustained. The performance decline has resulted in the identification of a substantive cross-cutting issue in the area of human performance with a cross-cutting theme in the aspect of work control and planning. There were 12 Green findings with a documented cross-cutting aspect in human performance. Four of the findings shared a common cross-cutting aspect of work control and planning (H.3(a)). In addition, these findings were from more than one cornerstone. This cross-cutting issue will remain open until the number of findings with the same cross-cutting aspect is reduced or when the NRC gains confidence in your actions to address this adverse trend in human performance. | | Regarding the White Performance Index, Region III conducted Supplemental Inspection 95001, |
| | "Inspection for One or Two White Inputs in a Strategic Performance Area," during the week of August 20 to assess the root cause analysis and implementation of corrective actions for the performance index. Based on the results of this inspection, no findings of significance were identified. The staff has identified that the improvements in human performance first noted in our 2006 End-of-Cycle assessment have not been sustained. The performance decline has resulted in the identification of a substantive cross-cutting issue in the area of human performance with a cross-cutting theme in the aspect of work control and planning. There were 12 Green findings with a documented cross-cutting aspect in human performance. Four of the findings shared a common cross-cutting aspect of work control and planning (H.3(a)). In addition, these findings were from more than one cornerstone. This cross-cutting issue will remain open until the number of findings with the same cross-cutting aspect is reduced or when the NRC gains confidence in your actions to address this adverse trend in human performance. |
|
| |
|
| The enclosed inspection plan details the inspections, including baseline and other infrequently conducted inspections, less those related to security, scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review. | | The enclosed inspection plan details the inspections, including baseline and other infrequently conducted inspections, less those related to security, scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review. |
|
| |
|
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| | |
| enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |
|
| |
|
| If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Jamnes Cameron at 630-829-9833 with any questions you may have regarding this letter or the inspection plan. | | If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Jamnes Cameron at 630-829-9833 with any questions you may have regarding this letter or the inspection plan. |
|
| |
|
| Sincerely,/RA/ James L. Caldwell, Regional Administrator Docket No. 50-440 License No. DPR-58 | | Sincerely, |
| | | /RA/ |
| ===Enclosure:===
| | James L. Caldwell, Regional Administrator Docket No. 50-440 License No. DPR-58 Enclosure: Perry Inspection/Activity Plan DISTRIBUTION: |
| Perry Inspection/Activity Plan DISTRIBUTION: | |
| See next page | | See next page |
| }} | | }} |
Similar Documents at Perry |
---|
Category:Inspection Plan
MONTHYEARIR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24088A1922024-03-28028 March 2024 Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 IR 05000440/20230062024-02-28028 February 2024 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2023006) ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) IR 05000440/20220062023-03-0101 March 2023 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2022006) ML23026A2112023-01-26026 January 2023 Notification of Nrc Baseline Inspection and Request for Information Inspection Report 05000440/2023002 ML22336A1222022-12-0505 December 2022 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000440/2023010 IR 05000440/20220052022-08-26026 August 2022 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2022005) ML22234A1482022-08-22022 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-22-052, Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines2022-03-16016 March 2022 Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines IR 05000440/20210062022-03-0202 March 2022 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2021006) ML21257A4602021-09-15015 September 2021 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Perry Nuclear Power Plant IR 05000440/20210052021-09-0101 September 2021 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2021005) ML21168A0662021-06-17017 June 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000440/2021010 ML21099A0872021-04-0808 April 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000440/2021012 IR 05000440/20200062021-03-0404 March 2021 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2020006) ML21020A0392021-01-20020 January 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000440/2021010 ML21004A0922021-01-0404 January 2021 Notification of NRC Baseline Inspection and Request for Information, Inspection Report 05000440/2021001 ML20294A0462020-10-19019 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000440/20200052020-09-0101 September 2020 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2020005) IR 05000440/20190062020-03-0303 March 2020 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2019006) IR 05000440/20190052019-08-28028 August 2019 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2019005) ML19205A4252019-07-23023 July 2019 Ltr. 07/23/19 Perry Nuclear Power Plant, Unit 1 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000440/2019004 (DRS-L.Rodriguez) IR 05000440/20180062019-03-0404 March 2019 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2018006) IR 05000440/20180052018-08-28028 August 2018 Updated Inspection Plan for Perry, Unit 1 (Report 05000440/2018005) IR 05000440/20170062018-03-0202 March 2018 Annual Assessment Letter for Perry Nuclear Power Plant; Report 05000440/2017006 ML18005A6092018-01-0505 January 2018 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000440/20170072017-12-21021 December 2017 NRC Problem Identification and Resolution Inspection Report 05000440/2017007 IR 05000440/20170052017-08-28028 August 2017 Updated Inspection Plan for Perry Nuclear Plant, Unit 1 (Report 05000440/2017005) IR 05000440/20160062017-03-0101 March 2017 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2016006) IR 05000440/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2016005) ML16237A0812016-08-24024 August 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000440/2016004 IR 05000440/20150062016-03-0202 March 2016 Annual Assessment Letter for Perry, Unit 1 (Inspection Report 05000440/2015006) ML16042A1672016-02-10010 February 2016 Ltr. 02/10/16 Perry Nuclear Power Plant - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (MOD/50.59) Baseline Inspection 05000440/2016007 (AAS) IR 05000440/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2015005) ML15204A8292015-07-23023 July 2015 IR 05000440/2015008, 09/21/15, Perry Nuclear Power Plant - Notification of NRC Triennial Fire Protection Baseline ML15062A6042015-03-0404 March 2015 Annual Assessment Letter for Perry Nuclear Power Plant (Report 050003440/2014001) ML14245A3172014-09-0202 September 2014 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant IR 05000440/20130012014-03-0404 March 2014 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2013001) ML13351A3232013-12-16016 December 2013 CDBI Request for Information ML13246A2372013-09-0303 September 2013 2013 Perry Nuclear Power Plant Mid-Cycle Letter Combined IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) ML12248A3122012-09-0404 September 2012 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant ML12166A1902012-06-11011 June 2012 Temporary Instruction 2515/177 Inspection Document Request IR 05000220/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000220/2011001 and 05000440/2011001) IR 05000440/20110072012-03-0505 March 2012 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2011007) IR 05000440/20110062011-09-0101 September 2011 Inspection Plan 05000440-11-006, 9/1/2011 - 12/31/2012, for Perry Nuclear Power Plant ML1106203062011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Activity Plan 2024-08-22
[Table view] Category:Letter
MONTHYEARL-24-179, License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 52024-10-21021 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 5 L-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 05000440/LER-2024-003, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 05000440/LER-2024-002, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models 05000440/LER-2024-001, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency 2024-09-09
[Table view] |
Inspection Report - Perry - 2008001 |
---|
|
|
Text
rch 3, 2008
SUBJECT:
ANNUAL ASSESSMENT LETTER - PERRY NUCLEAR PLANT (05000440/2008001)
Dear Mr. Allen:
On February 12, 2008, the NRC staff completed its performance review of the Perry Nuclear Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Related Information" will include the security cornerstone review and resultant inspection plan.
Overall, Perry Nuclear Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within the Regulatory Response column of the NRCs Action Matrix, based on the Mitigating Systems Performance Index (MSPI) results for the Emergency AC Power being White since the first quarter of 2007.
On May 1, 2007, the NRC staff completed an update of our assessment of the Perry Nuclear Power Plant. Our May 2, 2007, letter informed FirstEnergy Nuclear Operating Company that all actions had been completed for Perry to exit the Multiple/Repetitive Degraded Cornerstone column of the NRCs Action Matrix. Therefore, effective the second quarter 2007, the Perry plant exited the Multiple/Repetitive Degraded Cornerstone column and was placed in the Regulatory Response column, based on the White Emergency AC Power System MSPI.
Regarding the White Performance Index, Region III conducted Supplemental Inspection 95001,
"Inspection for One or Two White Inputs in a Strategic Performance Area," during the week of August 20 to assess the root cause analysis and implementation of corrective actions for the performance index. Based on the results of this inspection, no findings of significance were identified. The staff has identified that the improvements in human performance first noted in our 2006 End-of-Cycle assessment have not been sustained. The performance decline has resulted in the identification of a substantive cross-cutting issue in the area of human performance with a cross-cutting theme in the aspect of work control and planning. There were 12 Green findings with a documented cross-cutting aspect in human performance. Four of the findings shared a common cross-cutting aspect of work control and planning (H.3(a)). In addition, these findings were from more than one cornerstone. This cross-cutting issue will remain open until the number of findings with the same cross-cutting aspect is reduced or when the NRC gains confidence in your actions to address this adverse trend in human performance.
The enclosed inspection plan details the inspections, including baseline and other infrequently conducted inspections, less those related to security, scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Jamnes Cameron at 630-829-9833 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James L. Caldwell, Regional Administrator Docket No. 50-440 License No. DPR-58 Enclosure: Perry Inspection/Activity Plan DISTRIBUTION:
See next page