| {{#Wiki_filter:TQ-AA-151-F10 Revision 0 Page 1 of 1 SRRS: 3D.105 Scenario Outline Station: Dresden Generating Station Scenario No.: | | {{#Wiki_filter:TQ-AA-151-F10 Revision 0 Page 1 of 1 Scenario Outline Station: Dresden Generating Station Scenario No.: ILT-N-1 Class ID: 11-1 (2012-301) |
| ILT-N-1 Class ID: | | Evaluators Operators / crew position |
| Evaluators Operators / crew position 11-1 (2012-301) / ATC / BOP Initial Conditions:
| | / ATC |
| / CRS Initial Power
| | / BOP |
| = Full Power Turnover: Maintain load per TSO direction. | | / CRS Initial Conditions: Initial Power = Full Power Turnover: Maintain load per TSO direction. |
| Event No. Malf. No. Event Type* Event Description 1 NONE C BOP TBCCW - Pump, Swap Due To Degrading Pump 2 B02 C / T ATC RPS - MG Set, Trips / Re | | Event Malf. Event Event No. No. Type* Description 1 NONE C BOP TBCCW - Pump, Swap Due To Degrading Pump 2 B02 C/T ATC RPS - MG Set, Trips / Re-energize From Reserve Power 3 ICTUBLK C/T BOP ISO COND - System, Tube Leak TURBINE AUX - Loss Of All Turbine Seal Oil, With Failure 4 K50 C BOP Of ESOP To Start SER1633 5 C ATC MPT - TR 2 High Temperature Requiring Load Drop E230 6 RLMRFPB I ATC FW - FWLC Controller, FW Flow Indication Fails Upscale 7 I21 M TEAM Manual Scram - Steam Leak in the Drywell. |
| -energize From Reserve Power 3 ICTUBLK C / T BOP ISO COND - System, Tube Leak 4 K50 C BOP TURBINE AUX | | I21 EMERGENCY DEPRESSURIZE - On Exceeding Primary 8 K23 M TEAM Containment Pressure Due To Steam Leak inside the K40 Drywell And Partial Loss of Ability to Spray the Drywell |
| - Loss Of All Turbine Seal Oil, With Failure Of ESOP To Start 5 SER1633 E230 C ATC MPT - TR 2 High Temperature Requiring Load Drop 6 RLMRFPB I ATC FW - FWLC Controller, FW Flow Indication Fails Upscale 7 I21 M TEAM Manual Scram | | * (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec SRRS: 3D.105}} |
| - Steam Leak in the Drywell. | |
| 8 I21 K23 K40 M TEAM EMERGENCY DEPRESSURIZE
| |
| - On Exceeding Primary Containment Pressure Due To Steam Leak inside the Drywell And Partial Loss of Ability to Spray the Drywell | |
| * (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec}}
| |
|
---|
Category:License-Operator
MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A0172021-05-14014 May 2021 Initial License Exam Forms ES-301-2 ML22236A0162021-05-14014 May 2021 Initial License Exam Forms ES-301-1 ML22216A1872021-05-14014 May 2021 April 2021 Proposed JPMs ML22216A1902021-05-14014 May 2021 April 2021 Proposed Written Exam ML22216A1892021-05-14014 May 2021 April 2021 Proposed Scenarios ML22236A0182021-05-14014 May 2021 Initial License Exam Forms ES-401-1 and ES-401-3 rev1 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam 2023-06-09
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22236A6382021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-4 ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam ML22236A6392021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-9 ML22236A0202021-05-14014 May 2021 Initial License Exam Forms ES-D1 ML22236A6372021-05-14014 May 2021 April 2021 Initial License Exam Form ES-301-7 ML22236A6402021-05-14014 May 2021 April 2021 Initial License Exam Operating Test Outline Comments 2023-06-09
[Table view] |
Text
TQ-AA-151-F10 Revision 0 Page 1 of 1 Scenario Outline Station: Dresden Generating Station Scenario No.: ILT-N-1 Class ID: 11-1 (2012-301)
Evaluators Operators / crew position
/ ATC
/ BOP
/ CRS Initial Conditions: Initial Power = Full Power Turnover: Maintain load per TSO direction.
Event Malf. Event Event No. No. Type* Description 1 NONE C BOP TBCCW - Pump, Swap Due To Degrading Pump 2 B02 C/T ATC RPS - MG Set, Trips / Re-energize From Reserve Power 3 ICTUBLK C/T BOP ISO COND - System, Tube Leak TURBINE AUX - Loss Of All Turbine Seal Oil, With Failure 4 K50 C BOP Of ESOP To Start SER1633 5 C ATC MPT - TR 2 High Temperature Requiring Load Drop E230 6 RLMRFPB I ATC FW - FWLC Controller, FW Flow Indication Fails Upscale 7 I21 M TEAM Manual Scram - Steam Leak in the Drywell.
I21 EMERGENCY DEPRESSURIZE - On Exceeding Primary 8 K23 M TEAM Containment Pressure Due To Steam Leak inside the K40 Drywell And Partial Loss of Ability to Spray the Drywell
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec SRRS: 3D.105