Text
TQ-AA-151-F10 Revision 0 Page 1 of 1 SRRS: 3D.105 Scenario Outline Station: Dresden Generating Station Scenario No.: ILT-N-4 Class ID:
Evaluators Operators
/ crew position 11-1 (2012-301)
/ ATC
/ BOP Initial Conditions:
/ CRS Initial Power = 50%
Turnover:
Maintain load per TSO direction.
Event No.
Malf.
No.
Event Type*
Event Description 1
NONE C
BOP TBCCW - Pump, Swap Due To Degrading Pump 2
B02 C / T ATC RPS - MG Set, Trips / Re-energize From Reserve Power 3
NII12POT NIA2POT I / T ATC NI - APRM, Fails With Partial Half Scram 4
H21 C
ATC FW - Cond/Bstr Pump, Trips Due To Overcurrent 5
ICTUBLK C / T BOP ISO COND - System, Tube Leak 6
K50 C
BOP TURBINE AUX - Loss Of All Turbine Seal Oil, With Failure Of ESOP To Start 7
I21 M
TEAM Manual Scram - Steam Leak in the Drywell.
8 I21 K23 K40 M
TEAM EMERGENCY DEPRESSURIZE - On Exceeding Primary Containment Pressure Due To Steam Leak inside the Drywell And Partial Loss of Ability to Spray the Drywell
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec