| {{#Wiki_filter:Southern Nuclear Operating Company (SNC) Standard Emergency Plan (SEP) | | {{#Wiki_filter:Southern Nuclear Operating Company (SNC) Standard Emergency Plan (SEP) |
| SNC/Nuclear Regulatory Commission (NRC) Pre | | SNC/Nuclear Regulatory Commission (NRC) Pre-submittal Interaction April, 22, 2015 |
| -submittal Interaction April, 22, 2015 Agenda July 2014 Interaction Recap Change in Submittal Scope Status of Fleet SEP Construction/Testing Schedule Milestones Update License Amendment Scope and Schedule Key Features of the Submittal Effect on EP Inspection Tests Analyses and Acceptance Criteria (ITAAC) Licensing Considerations Questions/Feedback 2 | | |
| July 2014 Interaction Recap Described current status of and history of Vogtle 3-4 emergency plan Discussed options for combining the two Vogtle emergency plans into a single plan Agreed that the option of adopting the fleet SEP on a limited basis to include Vogtle only was the option of choice Agreed that future interactions would be desirable 3 | | Agenda |
| Change in Submittal Scope Initial submittal to include SNC SEP base for all SNC plants, and annexes for Farley, Hatch, Vogtle 1 | | * July 2014 Interaction Recap |
| -2 and Vogtle 3 | | * Change in Submittal Scope |
| -4 Vogtle 1-2 annex will be submitted using the current Technical Support Center (TSC) and Operations Support Center (OSC) | | * Status of Fleet SEP |
| Vogtle 3-4 will be submitted using the Vogtle common TSC and OSC When approved and SNC personnel trained on new SNC Fleet SEP then Farley, Hatch, Vogtle 1 | | * Construction/Testing Schedule Milestones Update |
| -2 and Vogtle 3 | | * License Amendment Scope and Schedule |
| -4 will implement Impacts to Emergency Operations Facility (EOF) and EOF staffing require all SNC plants to implement concurrently, with exception of Vogtle 3 | | * Key Features of the Submittal |
| -4 A separate License Amendment Request (LAR) will be submitted for Vogtle 1 | | * Effect on EP Inspection Tests Analyses and Acceptance Criteria (ITAAC) |
| -2 to transition to the common TSC and OSC The LAR for use of the common Vogtle TSC and OSC by all Vogtle units will be implemented prior to 10 CFR 52.103(g) 4 Status of Fleet SEP Fleet SEP drafted | | * Licensing Considerations |
| -Includes all emergency plan information common to SNC plants (Farley, Hatch and Vogtle)
| | * Questions/Feedback 2 |
| EOF Communication plan Annexes for Farley, Hatch, Vogtle 1 | | |
| -2 and Vogtle 3 | | July 2014 Interaction Recap |
| -4 drafted | | * Described current status of and history of Vogtle 3-4 emergency plan |
| -Include EP information unique to each site
| | * Discussed options for combining the two Vogtle emergency plans into a single plan |
| -Much information for each Vogtle annex identical, but separate information for treatment of Emergency Action Level (EALs) and associated technical bases 5
| | * Agreed that the option of adopting the fleet SEP on a limited basis to include Vogtle only was the option of choice |
| VEGP 3 and 4 EP Related Construction/Testing Schedule Milestones VEGP 3 fuel load VEGP 10 CFR 52.103(g) finding | | * Agreed that future interactions would be desirable 3 |
| - EP required to be followed and effectiveness maintained (10 CFR 50.54(q)(2)) | | |
| VEGP 3 exercise | | Change in Submittal Scope |
| - completion of EP ITAAC VEGP TSC and OSC available for training/drills Final EALs submitted for approval | | * Initial submittal to include SNC SEP base for all SNC plants, and annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 |
| - 180 days before fuel load | | * Vogtle 1-2 annex will be submitted using the current Technical Support Center (TSC) and Operations Support Center (OSC) |
| - License Condition (Following SCANA approach)
| | * Vogtle 3-4 will be submitted using the Vogtle common TSC and OSC |
| Staffing assessment submitted | | * When approved and SNC personnel trained on new SNC Fleet SEP then Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 will implement |
| - 180 days before fuel load | | * Impacts to Emergency Operations Facility (EOF) and EOF staffing require all SNC plants to implement concurrently, with exception of Vogtle 3-4 |
| - License Condition (Staffing analysis completed December 2014) | | * A separate License Amendment Request (LAR) will be submitted for Vogtle 1-2 to transition to the common TSC and OSC |
| Implementing procedures submitted | | * The LAR for use of the common Vogtle TSC and OSC by all Vogtle units will be implemented prior to 10 CFR 52.103(g) 4 |
| - 180 days before fuel load | | |
| - ITAAC 6 License Amendment Scope and Schedule Amend all eight licenses to incorporate a SNC SEP with site specific annexes Applies the common TSC and OSC to Vogtle 3
| | Status of Fleet SEP |
| -4 Includes conforming changes to affected EP ITAAC Submittal planned for June 2015 Requesting approval by June 2016 Submit LAR for Vogtle site common TSC and OSC in June 2016 immediately following approval of SNC SEP Implement SNC SEP for entire SNC Fleet (except Vogtle 3 | | * Fleet SEP drafted |
| -4) in June 2017 Implement Common TSC and OSC for Vogtle site at or near the 103(g) for Unit 3 7 | | - Includes all emergency plan information common to SNC plants (Farley, Hatch and Vogtle) |
| Key Features of the Submittal Conforms to NUREG 0654 Rev. 1 Removes unnecessary detail Leverages fleet standard procedures and processes Requests a 90 minute augmentation time Revises EOF organization to include Emergency Director Standardizes on | | * EOF |
| -shift and augmented ERO for the SNC fleet with minor exceptions for Vogtle 3 | | * Communication plan |
| -4 8 Effect on EP ITAAC Some conforming changes to EP ITAAC required | | * Annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 drafted |
| -90 minute augmentation time
| | - Include EP information unique to each site |
| -Use of tone alert radio as back
| | - Much information for each Vogtle annex identical, but separate information for treatment of Emergency Action Level (EALs) and associated technical bases 5 |
| -up notification method SEP refers to implementing procedures as Emergency Plan Implementing Procedure (EPIPs) | | |
| Existing emergency plan uses the term Emergency Implementing Procedure (EIP) | | VEGP 3 and 4 EP Related Construction/Testing Schedule Milestones |
| EP ITAAC will retain the EIP nomenclature 9 | | * VEGP 3 fuel load |
| Licensing Considerations Submittal contents LAR Considerations | | * VEGP 10 CFR 52.103(g) finding - EP required to be followed and effectiveness maintained (10 CFR 50.54(q)(2)) |
| -One letter with separate enclosures for Farley, Hatch, Vogtle 1
| | * VEGP 3 exercise - completion of EP ITAAC |
| -2 and Vogtle 3 Separate enclosures with change justification matrices for Farley, Hatch, Vogtle 1 | | * VEGP TSC and OSC available for training/drills |
| -2 and Vogtle 3-4 -Separate enclosures with ERO Augmentation Technical Document for Farley, Hatch, Vogtle 1 | | * Final EALs submitted for approval - 180 days before fuel load - |
| -2 and Vogtle 3-4 Separate LAR for Vogtle site common TSC and OSC submitted after NRC approval of SNC SEP 10 Questions/Feedback 11}} | | License Condition (Following SCANA approach) |
| | * Staffing assessment submitted - 180 days before fuel load - License Condition (Staffing analysis completed December 2014) |
| | * Implementing procedures submitted - 180 days before fuel load - |
| | ITAAC 6 |
| | |
| | License Amendment Scope and Schedule |
| | * Amend all eight licenses to incorporate a SNC SEP with site specific annexes |
| | * Applies the common TSC and OSC to Vogtle 3-4 |
| | * Includes conforming changes to affected EP ITAAC |
| | * Submittal planned for June 2015 |
| | * Requesting approval by June 2016 |
| | * Submit LAR for Vogtle site common TSC and OSC in June 2016 immediately following approval of SNC SEP |
| | * Implement SNC SEP for entire SNC Fleet (except Vogtle 3-4) in June 2017 |
| | * Implement Common TSC and OSC for Vogtle site at or near the 103(g) for Unit 3 7 |
| | |
| | Key Features of the Submittal |
| | * Conforms to NUREG 0654 Rev. 1 |
| | * Removes unnecessary detail |
| | * Leverages fleet standard procedures and processes |
| | * Requests a 90 minute augmentation time |
| | * Revises EOF organization to include Emergency Director |
| | * Standardizes on-shift and augmented ERO for the SNC fleet with minor exceptions for Vogtle 3-4 8 |
| | |
| | Effect on EP ITAAC |
| | * Some conforming changes to EP ITAAC required |
| | - 90 minute augmentation time |
| | - Use of tone alert radio as back-up notification method |
| | * SEP refers to implementing procedures as Emergency Plan Implementing Procedure (EPIPs) |
| | * Existing emergency plan uses the term Emergency Implementing Procedure (EIP) |
| | * EP ITAAC will retain the EIP nomenclature 9 |
| | |
| | Licensing Considerations Submittal contents |
| | * LAR Considerations |
| | - One letter with separate enclosures for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 |
| | - Separate enclosures with change justification matrices for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 |
| | - Separate enclosures with ERO Augmentation Technical Document for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 |
| | * Separate LAR for Vogtle site common TSC and OSC submitted after NRC approval of SNC SEP 10 |
| | |
| | Questions/Feedback 11}} |
Letter Sequence Request |
---|
|
|
MONTHYEARML15106A2042015-04-22022 April 2015 April 22, 2015, Meeting with Southern Nuclear Company, Slide Presentation Project stage: Request ML15103A0602015-04-30030 April 2015 April 22, 2015, Summary of Meeting with Southern Nuclear Operating Company to Discuss a Future Fleet Standard Emergency Plan Submittal Project stage: Meeting ML15128A0062015-05-0808 May 2015 May 12, 2015, Meeting with Southern Nuclear Company, Draft Table B-1, Vogtle Electric Generating Plant, Units 1 and 2, Site On-Shift Table Comparison Project stage: Request ML15128A0032015-05-0808 May 2015 May 12, 2015, Meeting with Southern Nuclear Company, Draft Vogtle Electric Generating Plant, Units 1 & 2, On-Shift and Augmented Emergency Response Organization Summary Project stage: Request ML15128A0022015-05-0808 May 2015 May 12, 2015, Meeting with Southern Nuclear Company, Draft Emergency Response Organization Augmentation Plan for the Vogtle Electric Generating Plant Project stage: Request ML15125A0872015-05-26026 May 2015 May 12, 2015 Summary of Meeting with Southern Nuclear Operating Company to Discuss a Future Fleet Standard Emergency Plan Submittal Project stage: Meeting 2015-04-30
[Table View] |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24022A1192024-01-24024 January 2024 Slides - SNC Slides - Pre-Submittal Meeting on January 24, 2024 - Vogtle 3 & 4 Explosively Actuated Valves Relief Request ML23361A0812024-01-0808 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR ML23361A1092024-01-0808 January 2024 SNC Slides for Public Meeting on 1-8-24 to Discuss Hatch LAR - Revise TS Table 1.1-1 (Modes) to Relax Required No. of Fully Tensioned RPV Head Closure Studs ML24004A1852024-01-0404 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR Revised ML23257A2322023-09-28028 September 2023 SNC Presentation - Pre-Submittal Meeting on September 28, 2023 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML23137A1162023-06-0202 June 2023 Draft Slides for Advisory Committee on Reactor Safeguards Subcommittee Meeting Regarding Use of Accident Tolerant Fuel Lead Test Assemblies ML23139A2462023-05-19019 May 2023 Annual Assessment Public Meeting Slides (May 23, 2023) ML23094A1402023-04-0404 April 2023 4 -- 2022 Aam Slides ML23079A2362023-03-20020 March 2023 Annual Assessment Meeting Presentation Slides ML23055A0402023-02-24024 February 2023 VEGP, Unit 4, Potential License Amendment Request for Prior to Initial Criticality Overview Presentation ML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22329A0192022-12-0101 December 2022 Southern Nuclear Company Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request 1 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22332A0012022-11-28028 November 2022 SNC Slides - Pre-Submittal Meeting on November 30, 2022 - Vogtle TS 5.5.11 License Amendment Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ML22319A1232022-11-15015 November 2022 Kozak Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22319A0052022-11-15015 November 2022 NEI Slides for November 15 2022 Public Meeting on Part 52 Lessons Learned ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22251A0002022-09-30030 September 2022 Pre-Submittal Meeting on September 13, 2022 - Vogtle Online Monitoring LAR ML22265A0972022-09-22022 September 2022 Southern Nuclear Company Slides on Lessons Learned from Part 52 Implementation for Public Meeting on 9/27/2022 ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML22209A1872022-07-28028 July 2022 Pre-Submittal Meeting on August 1, 2022 Re Plant Hatch LAR: Relaxation of Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs (EPID L-2022-LRM-0052) (Slides) ML22167A1402022-06-22022 June 2022 Pre-Submittal Public Meeting Slides for Rewrite TS-3.7.2 License Amendment ML22138A3952022-05-24024 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 24, 2022 - Vogtle RR RWST Suction Check Valves ML22137A2812022-05-23023 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 23, 2022 - Vogtle TS 3.8.1 and TSTF-163 LAR ML22126A0102022-05-11011 May 2022 Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemption Requests - Licensing Questions ML22123A3332022-05-10010 May 2022 Pre-Submittal Meeting 2: TSTF-51, TSTF-471, TSTF-490, and Alternative Source Term License Amendment Request - May 10, 2022 (EPID L-2022-LRM-0033)(slides) ML22110A1702022-04-20020 April 2022 4 2022 Annual Assessment Meeting.Final ML22080A0192022-03-18018 March 2022 Annual Assessment Meeting Presentation ML22021B6472022-01-27027 January 2022 Pre-Submittal for Westinghouse Increased Enrichment Accident Tolerant Fuel Lead Test Assemblies (EPID L-2022-LRM-0003) (Slides) ML21306A0242021-11-30030 November 2021 SNC Pre-Submittal Meeting for LAR to Relocate Augmented Piping Inspection Program Details from TSs to a Licensee Controlled Document for Farley Nuclear Plant, Units 1 & 2; and Vogtle Electric Generating Plant, Units 1 & 2 (EPID L-2021-LRM-0 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21280A0012021-10-31031 October 2021 Pre-Submittal Meeting Presentation from SNC to Discuss a Future LAR Regarding Change TS to Increase Containment Peak Pressure to Address Several NSALs ML21225A0312021-08-31031 August 2021 Pre-Submittal Meeting - Request to Eliminate the Requirement for Automatic Main Steam Isolation on High Turbine Building Area Temperature ML21230A2842021-08-18018 August 2021 SNC Slides - Vogtle MSIV Elimination LAR - Pre-submittal Meeting Part 2 - 08-25-2021 ML21222A0342021-08-16016 August 2021 SNC Slides - Hatch TSTF-505 LAR - Pre-Submittal Meeting - 08-16-2021 ML21187A0972021-07-0808 July 2021 Late Filed Allegations (Lfa) Process ML21193A0762021-07-0808 July 2021 ITAAC Related to Incore Instrument Thimble Assembly (Iita) ML21172A1312021-07-0101 July 2021 Pre-Submittal Meeting Alternate Source Term and TSTF-490 ML21193A0772021-06-24024 June 2021 Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses, 6-24-21 Pre-submittal Meeting ML21173A0632021-06-24024 June 2021 Pre-Application SNC Presentation Slides - Removal of Encapsulations from Recirculation Suction Valves ML21085A4902021-05-19019 May 2021 Risk-informed Resolution of Generic Letter 2004-02 ML21064A3652021-03-0101 March 2021 Dashboard Report 3-1-2021 ML21027A2062021-02-28028 February 2021 Fixed 8-Hour Emergency Light Deviation Pre-Submittal Meeting, February 2021 (Slides) ML21057A0182021-02-26026 February 2021 Pre-Submittal Meeting Revise Technical Specification 3.2.1 Heat Flux Hot Channel Factor (Fq(Z)) (EPID L-2021-LRM-0023) (Slides) ML21036A1172021-02-0505 February 2021 SNC Slides - Pre-Submittal Meeting on February 16, 2021 - Beacon LAR ML20343A0742020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20318A1032020-11-12012 November 2020 SNC ERO Staffing LAR RAI Responses ML20314A0962020-11-0202 November 2020 Dashboard Report 11/02/2020 ML20217L4312020-08-13013 August 2020 Edwin I Hatch, Units 1 and 2; and Vogtle Electric Plant, Units 1, 2, 3, and 4 - Meeting Slides a License Amendment Request for the Emergency Plan (EPID Nos L-2020-LLA-0150 and L-2020-LLA-051 2024-01-08
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24022A1192024-01-24024 January 2024 Slides - SNC Slides - Pre-Submittal Meeting on January 24, 2024 - Vogtle 3 & 4 Explosively Actuated Valves Relief Request ML23361A0812024-01-0808 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR ML23361A1092024-01-0808 January 2024 SNC Slides for Public Meeting on 1-8-24 to Discuss Hatch LAR - Revise TS Table 1.1-1 (Modes) to Relax Required No. of Fully Tensioned RPV Head Closure Studs ML24004A1852024-01-0404 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR Revised ML23304A2682023-11-0707 November 2023 License Amendment Request to Revise the Ultimate Heat Sink Mission Time Pre Submittal Meeting on November 7, 2023 ML23311A2452023-11-0707 November 2023 Pre-Submittal Meeting on November 7, 2023 - License Amendment Request to Revise the Ultimate Heat Sink Mission Time (Slides) ML23293A0052023-10-20020 October 2023 Lessons Learned from the ITAAC Hearing Process for Vogtle 3 and 4 ML23257A2322023-09-28028 September 2023 SNC Presentation - Pre-Submittal Meeting on September 28, 2023 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML23206A0412023-08-0202 August 2023 SNC Slides - Public Pre-Submittal Meeting on Aug 02, 2023 - Request for 45-Day Limited Extension of Risk Informed Completion Time (RICT) Program Backstop for TS 3.7.1 & 3.7.2 ML23137A1162023-06-0202 June 2023 Draft Slides for Advisory Committee on Reactor Safeguards Subcommittee Meeting Regarding Use of Accident Tolerant Fuel Lead Test Assemblies ML23139A2462023-05-19019 May 2023 Annual Assessment Public Meeting Slides (May 23, 2023) ML23094A1402023-04-0404 April 2023 4 -- 2022 Aam Slides ML23088A2362023-03-28028 March 2023 SNC Presentation - Public Meeting - 03-28-2023 - Page from ML22231B055 ML23079A2362023-03-20020 March 2023 Annual Assessment Meeting Presentation Slides ML23072A1802023-03-13013 March 2023 2023 RIC Powerpoint Slide Presentation, Vogtle 3: Journey from Construction to Operations ML23055A0402023-02-24024 February 2023 VEGP, Unit 4, Potential License Amendment Request for Prior to Initial Criticality Overview Presentation ML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22335A5542022-12-0101 December 2022 Slides - SNC Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request - ML22329A0192022-12-0101 December 2022 Southern Nuclear Company Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request 1 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22332A0012022-11-28028 November 2022 SNC Slides - Pre-Submittal Meeting on November 30, 2022 - Vogtle TS 5.5.11 License Amendment Request ML22319A1232022-11-15015 November 2022 Kozak Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22319A0052022-11-15015 November 2022 NEI Slides for November 15 2022 Public Meeting on Part 52 Lessons Learned ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML22251A0002022-09-30030 September 2022 Pre-Submittal Meeting on September 13, 2022 - Vogtle Online Monitoring LAR ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML22265A0972022-09-22022 September 2022 Southern Nuclear Company Slides on Lessons Learned from Part 52 Implementation for Public Meeting on 9/27/2022 ML22209A1872022-07-28028 July 2022 Pre-Submittal Meeting on August 1, 2022 Re Plant Hatch LAR: Relaxation of Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs (EPID L-2022-LRM-0052) (Slides) ML22206A1712022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22206A1682022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22201A0442022-07-20020 July 2022 Voices Dashboard Report for Vogtle Unit 3 as of July 20, 2022 ML22167A1402022-06-22022 June 2022 Pre-Submittal Public Meeting Slides for Rewrite TS-3.7.2 License Amendment ML22144A0502022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22144A0492022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22138A3952022-05-24024 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 24, 2022 - Vogtle RR RWST Suction Check Valves ML22137A2812022-05-23023 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 23, 2022 - Vogtle TS 3.8.1 and TSTF-163 LAR ML22126A0102022-05-11011 May 2022 Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemption Requests - Licensing Questions ML22123A3332022-05-10010 May 2022 Pre-Submittal Meeting 2: TSTF-51, TSTF-471, TSTF-490, and Alternative Source Term License Amendment Request - May 10, 2022 (EPID L-2022-LRM-0033)(slides) ML22126A0012022-05-0606 May 2022 SNC Slides - Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemptions ML22110A1702022-04-20020 April 2022 4 2022 Annual Assessment Meeting.Final ML22080A0192022-03-18018 March 2022 Annual Assessment Meeting Presentation ML22060A0062022-02-28028 February 2022 4Q 2021 Performance Summary U3 ML22021B6472022-01-27027 January 2022 Pre-Submittal for Westinghouse Increased Enrichment Accident Tolerant Fuel Lead Test Assemblies (EPID L-2022-LRM-0003) (Slides) ML22026A0582022-01-26026 January 2022 Dashboard Report 1-26-2022 ML21306A0242021-11-30030 November 2021 SNC Pre-Submittal Meeting for LAR to Relocate Augmented Piping Inspection Program Details from TSs to a Licensee Controlled Document for Farley Nuclear Plant, Units 1 & 2; and Vogtle Electric Generating Plant, Units 1 & 2 (EPID L-2021-LRM-0 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21280A0012021-10-31031 October 2021 Pre-Submittal Meeting Presentation from SNC to Discuss a Future LAR Regarding Change TS to Increase Containment Peak Pressure to Address Several NSALs ML21271A2022021-10-0505 October 2021 Pre-Submittal Meeting on October 5, 2021 - Hatch NFPA 805 Supplement LAR (SNC Slides) ML21225A0312021-08-31031 August 2021 Pre-Submittal Meeting - Request to Eliminate the Requirement for Automatic Main Steam Isolation on High Turbine Building Area Temperature 2024-01-08
[Table view] |
Text
Southern Nuclear Operating Company (SNC) Standard Emergency Plan (SEP)
SNC/Nuclear Regulatory Commission (NRC) Pre-submittal Interaction April, 22, 2015
Agenda
- July 2014 Interaction Recap
- Change in Submittal Scope
- Construction/Testing Schedule Milestones Update
- License Amendment Scope and Schedule
- Key Features of the Submittal
- Effect on EP Inspection Tests Analyses and Acceptance Criteria (ITAAC)
July 2014 Interaction Recap
- Discussed options for combining the two Vogtle emergency plans into a single plan
- Agreed that the option of adopting the fleet SEP on a limited basis to include Vogtle only was the option of choice
- Agreed that future interactions would be desirable 3
Change in Submittal Scope
- Initial submittal to include SNC SEP base for all SNC plants, and annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Vogtle 3-4 will be submitted using the Vogtle common TSC and OSC
- When approved and SNC personnel trained on new SNC Fleet SEP then Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 will implement
- Impacts to Emergency Operations Facility (EOF) and EOF staffing require all SNC plants to implement concurrently, with exception of Vogtle 3-4
- A separate License Amendment Request (LAR) will be submitted for Vogtle 1-2 to transition to the common TSC and OSC
Status of Fleet SEP
- Includes all emergency plan information common to SNC plants (Farley, Hatch and Vogtle)
- Annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 drafted
- Include EP information unique to each site
- Much information for each Vogtle annex identical, but separate information for treatment of Emergency Action Level (EALs) and associated technical bases 5
VEGP 3 and 4 EP Related Construction/Testing Schedule Milestones
- Final EALs submitted for approval - 180 days before fuel load -
License Condition (Following SCANA approach)
- Staffing assessment submitted - 180 days before fuel load - License Condition (Staffing analysis completed December 2014)
- Implementing procedures submitted - 180 days before fuel load -
ITAAC 6
License Amendment Scope and Schedule
- Amend all eight licenses to incorporate a SNC SEP with site specific annexes
- Applies the common TSC and OSC to Vogtle 3-4
- Includes conforming changes to affected EP ITAAC
- Submittal planned for June 2015
- Requesting approval by June 2016
- Submit LAR for Vogtle site common TSC and OSC in June 2016 immediately following approval of SNC SEP
- Implement SNC SEP for entire SNC Fleet (except Vogtle 3-4) in June 2017
- Implement Common TSC and OSC for Vogtle site at or near the 103(g) for Unit 3 7
Key Features of the Submittal
- Removes unnecessary detail
- Leverages fleet standard procedures and processes
- Requests a 90 minute augmentation time
- Revises EOF organization to include Emergency Director
- Standardizes on-shift and augmented ERO for the SNC fleet with minor exceptions for Vogtle 3-4 8
Effect on EP ITAAC
- Some conforming changes to EP ITAAC required
- 90 minute augmentation time
- Use of tone alert radio as back-up notification method
- Existing emergency plan uses the term Emergency Implementing Procedure (EIP)
- EP ITAAC will retain the EIP nomenclature 9
Licensing Considerations Submittal contents
- One letter with separate enclosures for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Separate enclosures with change justification matrices for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Separate enclosures with ERO Augmentation Technical Document for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Separate LAR for Vogtle site common TSC and OSC submitted after NRC approval of SNC SEP 10
Questions/Feedback 11