| title = Arkansas Nuclear One - Notification of NRC Triennial Heat Sink Performance Inspection (05000313/2017004 and 05000368/2017004) and Request for Information
| title = Notification of NRC Triennial Heat Sink Performance Inspection (05000313/2017004 and 05000368/2017004) and Request for Information
| author name = Farnholtz T R
| author name = Farnholtz T
| author affiliation = NRC/RGN-IV/DRS/EB-1
| author affiliation = NRC/RGN-IV/DRS/EB-1
| addressee name = Anderson R L
| addressee name = Anderson R
| addressee affiliation = Entergy Operations, Inc
| addressee affiliation = Entergy Operations, Inc
| docket = 05000313, 05000368
| docket = 05000313, 05000368
Line 14: Line 14:
| page count = 6
| page count = 6
}}
}}
See also: [[followed by::IR 05000313/2017004]]
See also: [[see also::IR 05000313/2017004]]


=Text=
=Text=
{{#Wiki_filter:October 19, 2017  
{{#Wiki_filter:October 19, 2017
Mr. Richard L. Anderson, Vice President
Entergy Operations, Inc.
Mr. Richard L. Anderson, Vice President Entergy Operations, Inc.  
1448 S.R. 333
1448 S.R. 333  
Russellville, AR 72802-0967
Russellville, AR 72802-0967  
SUBJECT: ARKANSAS NUCLEAR ONE - NOTIFICATION OF NRC TRIENNIAL HEAT SINK
              PERFORMANCE INSPECTION (05000313/2017004 AND 05000368/2017004)
              AND REQUEST FOR INFORMATION
Dear Mr. Anderson:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)
staff will conduct a triennial heat sink performance inspection at your Arkansas Nuclear One,
Units 1 and Unit 2, from November 13-17, 2017. The inspection will consist of one reactor
inspector from the NRCs Region IV office for one week. The inspection will be conducted in
accordance with NRC Inspection Procedure 71111.07, "Heat Sink Performance."
Experience has shown that this inspection is resource intensive both for the NRC inspectors
and your staff. In order to minimize the impact to your on-site resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to be provided by November 6, 2017. We
request that during the on-site inspection week you ensure that copies of analyses, evaluations,
or documentation regarding the implementation and maintenance of your heat exchanger
program are available. Of specific interest are those documents that establish that your heat
exchanger program satisfies NRC regulatory requirements and conforms to applicable NRC
guidance. Also, appropriate personnel knowledgeable of safety-related heat exchangers should
be available to support the inspector at the site during the inspection.
We have discussed the schedule for this inspection activity with your staff and understand that
our regulatory contact for this inspection will be Michael Hall of your licensing organization. If
there are any questions about this inspection or the material requested, please contact the
inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at chris.smith@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.


R. Anderson                                      2
SUBJECT: ARKANSAS NUCLEAR ONE - NOTIFICATION OF NRC TRIENNIAL HEAT SINK PERFORMANCE INSPECTION (05000313/2017004 AND 05000368/2017004) AND REQUEST FOR INFORMATION
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of
this letter and its enclosure will be available electronically for public inspection in the NRC Public
Dear Mr. Anderson:  
Document Room or from the Publicly Available Records (PARS) component of NRC's document
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
                                                  Sincerely,
                                                  /RA Wayne C. Sifre Acting for/
                                                  Thomas R. Farnholtz, Chief
                                                  Engineering Branch 1
                                                  Division of Reactor Safety
Docket Nos. 50-313, 50-368
License Nos. DPR-51, NPF-6
Enclosure:
Triennial Heat Sink Performance Inspection
  Request for Information
cc: Electronic Distribution


The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff will conduct a triennial heat sink performance inspection at your Arkansas Nuclear One,
Units 1 and Unit 2, from November 13-17, 2017.  The inspection will consist of one reactor
inspector from the NRC's Region IV office for one week.  The inspection will be conducted in
accordance with NRC Inspection Procedure 71111.07, "Heat Sink Performance."
Experience has shown that this
inspection is resource intens
ive both for the NRC inspectors and your staff.  In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. 
Please note that the documents are requested to be provided by November 6, 2017.  We request that during the on-site inspection week you ensure that copies of analyses, evaluations, or documentation regarding the implementat
ion and maintenance of your heat exchanger program are available.  Of specific interest are those documents that establish that your heat
exchanger program satisfies NRC regulatory requirements and conforms to applicable NRC
guidance.  Also, appropriate personnel knowledgeable of safety-related heat exchangers should
be available to support the inspector at the site during the inspection.


  We have discussed the schedule for this inspection activity with your staff and understand that our regulatory contact for this inspection will be Michael Hall of your licensing organization.  If
  ML17292B402
there are any questions about this inspection or the material requested, please contact the
  SUNSI Review         ADAMS:             Non-Publicly Available       Non-Sensitive Keyword:
inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at chris.smith@nrc.gov.    This letter does not contain new or amended information collection requirements subject  to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information
  By: WSifre           Yes No         Publicly Available           Sensitive     NRC-002
collection requirements were approved by the Office of Management and Budget, control
OFFICE       RI:EB1         C:EB1           C:DRP/E         C:EB1
number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to
NAME         CSmith         TFarnholtz       NOKeefe        TFarnholtz
respond to, a request for information or an information collection requirement unless the
SIGNATURE     /RA/           /RA/ WSifre for /RA/           /RA/ WSifre for
requesting document displays a currently valid Office of Management and Budget control
DATE         10/13/17       10/19/17         10/19/17        10/19/17
number.   
                                     
R. Anderson 2
                                      Request for Information
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of
                          Triennial Heat Sink Performance Inspection
this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                      Arkansas Nuclear One
Sincerely,  /RA Wayne C. Sifre Acting for/
Inspection Report:               05000313/2017004 and 05000368/2017004
  Thomas R. Farnholtz, Chief
Inspection Dates:               November 13-17, 2017
Engineering Branch 1
Inspection Procedure:           IP 71111.07, Triennial Heat Sink Performance
 
Inspector:                       Chris Smith, Reactor Inspector
Division of Reactor Safety
Docket Nos. 50-313, 50-368
 
License Nos. DPR-51, NPF-6
 
Enclosure:  Triennial Heat Sink Performance Inspection    Request for Information
 
cc:  Electronic Distribution
 
 
 
  ML17292B402 SUNSI Review   ADAMS:   Non-Publicly Available Non-Sensitive Keyword: By: WSifre  Yes    No Publicly Available Sensitive NRC-002 OFFICE RI:EB1 C:EB1 C:DRP/E C:EB1   NAME CSmith TFarnholtz NO'Keefe TFarnholtz   SIGNATURE /RA/ /RA/ WSifre for /RA/ /RA/ WSifre for   DATE 10/13/17 10/19/17 10/19/1710/19/17  
  Enclosure
Request for Information  
Triennial Heat Sink Performance Inspection Arkansas Nuclear One  
 
Inspection Report:   05000313/2017004 and 05000368/2017004  
 
Inspection Dates: November 13-17, 2017  
 
Inspection Procedure: IP 71111.07, Triennial Heat Sink Performance  
Inspector:   Chris Smith, Reactor Inspector
 
Information Requested for the In-Office Preparation Week
Information Requested for the In-Office Preparation Week
  The following information should be sent to the Region IV office in hard copy or electronic  
The following information should be sent to the Region IV office in hard copy or electronic
format, to the attention of Chris Smith, by November 6, 2017. The inspector will review specific  
format, to the attention of Chris Smith, by November 6, 2017. The inspector will review specific
items from the information requested below and then request from your staff additional documents needed during the on-site inspection week. Also, we request that you categorize the documents in your response with the num
items from the information requested below and then request from your staff additional
bered list below. Please provide requested  
documents needed during the on-site inspection week. Also, we request that you categorize the
documentation electronically if possible. If requested documents are large and only hard copy  
documents in your response with the numbered list below. Please provide requested
formats are available, please inform the inspector, and provide subject documentation during the first day of the on-site inspection. If you have any questions regarding this information  
documentation electronically if possible. If requested documents are large and only hard copy
request, please call the lead inspector as soon as possible.  
formats are available, please inform the inspector, and provide subject documentation during
The following heat exchangers/heat sinks have been selected for inspection:  
the first day of the on-site inspection. If you have any questions regarding this information
 
request, please call the lead inspector as soon as possible.
* Unit 1 Reactor Building Service Water Cooler Coil (Train A), VCC-2A
The following heat exchangers/heat sinks have been selected for inspection:
* Unit 1 Loop Decay Heat Cooler (Train B), E-35B 'B
            *   Unit 1 Reactor Building Service Water Cooler Coil (Train A), VCC-2A
* Unit 2 Component Cooling Water Heat Exchanger (Train A), 2E-28A  
            *   Unit 1 Loop Decay Heat Cooler (Train B), E-35B B
* Unit 2 Emergency Cooling Pond, T-250
            *   Unit 2 Component Cooling Water Heat Exchanger (Train A), 2E-28A
For all samples listed above
            *   Unit 2 Emergency Cooling Pond, T-250
1. Copies of any self-assessments or audits performed in the previous three years
For all samples listed above:
2. Copies of any documents such as a Generic Letter 89-13 heat exchanger program description, heat exchanger program document, etc.  
    1. Copies of any self-assessments or audits performed in the previous three years
3. List of commitments (with descriptions) to the Generic Letter 89-13 program  
    2. Copies of any documents such as a Generic Letter 89-13 heat exchanger program
4. Copies of system health reports and maintenance rule system notebooks  
        description, heat exchanger program document, etc.
5. Copies of design bases documents, updated final safety analysis report pages, technical specification (and bases) pages, and technical requirements manual (and bases) pages  
    3. List of commitments (with descriptions) to the Generic Letter 89-13 program
6. List of corrective action program documents (with descriptions) for the past three years  
    4. Copies of system health reports and maintenance rule system notebooks
7. List of any design changes (with descriptions) implemented during the past three years  
    5. Copies of design bases documents, updated final safety analysis report pages, technical
8. List of preventive maintenance tasks (with descriptions) and frequency  
        specification (and bases) pages, and technical requirements manual (and bases) pages
 
    6. List of corrective action program documents (with descriptions) for the past three years
  2  9. Copies of simplified piping and instrum
    7. List of any design changes (with descriptions) implemented during the past three years
entation drawings or diagrams and operator
    8. List of preventive maintenance tasks (with descriptions) and frequency
training manuals, if available
                                                                                  Enclosure
For the specific heat exchangers selected:
Testing Documents
10. Copies of the two most recent completed tests confirming thermal performance for those heat exchangers which are performance tested 
11. Instrument uncertainties of the instruments used during testing
12. Copy of any operability determinations or other documentation of degradation associated with the heat exchangers or the systems that support the operation for the
selected heat exchangers 
13. Documents that show the as-found results are recorded, evaluated, and appropriately dispositioned such that the as-left condition is acceptable
Cleaning Documents
14. The cleaning and inspection maintenance schedule for each heat exchanger for the next
five years 
15. Copy of the document describing the inspection results for the last two cleaning and inspection activities completed on each heat exchanger 
16. Cleaning procedures with acceptance criteria for the selected heat exchangers
17. Copies of the documents that verify the structural integrity of the heat exchanger (e.g., eddy current summary sheets, ultrasonic testing results, and visual inspection results) 
18. Copies of those documents that describe the methods taken to control water chemistry in the heat exchangers 
Design Documents
19. Provide a list of calculations (with descriptions) which currently apply to each heat
exchanger 
 
20. Copies of vendor data sheets and design basis data for the selected heat exchangers 
21. Copy of the calculation which establishes the limiting (maximum) design basis heat load which is required to be removed by each of these heat exchangers 
22. Copy of the calculation which correlates surveillance testing results from these heat exchangers with design basis heat removal capability (e.g., basis for surveillance test
acceptance criteria)
23. Copy of the calculations or documents which evaluate the potential for water hammer or excessive tube vibration in the heat exchanger or associated piping 
 
  3  24. Copy of the document which identifies the current number of tubes in service for each heat exchanger and the supporting calculation which establishes the maximum number
of tubes which can be plugged in each heat exchanger 
25. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes which are identified in each heat exchanger
  For the ultimate heat sink or safety-related service water system: 
26. Dam inspections that monitor the integrity of the ultimate heat sink (if applicable)
27. Copies of calculations and surveillances that determine the ultimate heat sink reservoir capacity and heat transfer capability (if applicable)
28. Copies of procedures for a loss of ultimate heat sink or safety-related service water system  29. Copies of inspections and/or maintenance related to macrofouling (silt, mussel shells, debris, etc.) and aquatic life
30. Copies of inspections and/or maintenance related to preventing biotic fouling 
31. Copies of procedures and/or test results to survey or monitor interface valves between the safety-related section of the service water system and the nonsafety-related section 
32. Copy of the most recent service water flow balance test results, both as-found and as-
left  33. History of any thru-wall pipe leaks on the safety-related service water system 
Inspector Contact Information:
Chris Smith


Reactor Inspector
  9. Copies of simplified piping and instrumentation drawings or diagrams and operator
 
      training manuals, if available
817-200-1095
For the specific heat exchangers selected:
  Testing Documents
  10. Copies of the two most recent completed tests confirming thermal performance for those
      heat exchangers which are performance tested
  11. Instrument uncertainties of the instruments used during testing
  12. Copy of any operability determinations or other documentation of degradation
      associated with the heat exchangers or the systems that support the operation for the
      selected heat exchangers
  13. Documents that show the as-found results are recorded, evaluated, and appropriately
      dispositioned such that the as-left condition is acceptable
  Cleaning Documents
  14. The cleaning and inspection maintenance schedule for each heat exchanger for the next
      five years
  15. Copy of the document describing the inspection results for the last two cleaning and
      inspection activities completed on each heat exchanger
  16. Cleaning procedures with acceptance criteria for the selected heat exchangers
  17. Copies of the documents that verify the structural integrity of the heat exchanger
      (e.g., eddy current summary sheets, ultrasonic testing results, and visual inspection
      results)
  18. Copies of those documents that describe the methods taken to control water chemistry
      in the heat exchangers
  Design Documents
  19. Provide a list of calculations (with descriptions) which currently apply to each heat
      exchanger
  20. Copies of vendor data sheets and design basis data for the selected heat exchangers
  21. Copy of the calculation which establishes the limiting (maximum) design basis heat load
      which is required to be removed by each of these heat exchangers
  22. Copy of the calculation which correlates surveillance testing results from these heat
      exchangers with design basis heat removal capability (e.g., basis for surveillance test
      acceptance criteria)
  23. Copy of the calculations or documents which evaluate the potential for water hammer or
      excessive tube vibration in the heat exchanger or associated piping
                                              2


    24. Copy of the document which identifies the current number of tubes in service for each
        heat exchanger and the supporting calculation which establishes the maximum number
        of tubes which can be plugged in each heat exchanger
    25. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
        which are identified in each heat exchanger
For the ultimate heat sink or safety-related service water system:
    26. Dam inspections that monitor the integrity of the ultimate heat sink (if applicable)
    27. Copies of calculations and surveillances that determine the ultimate heat sink reservoir
        capacity and heat transfer capability (if applicable)
    28. Copies of procedures for a loss of ultimate heat sink or safety-related service water
        system
    29. Copies of inspections and/or maintenance related to macrofouling (silt, mussel shells,
        debris, etc.) and aquatic life
    30. Copies of inspections and/or maintenance related to preventing biotic fouling
    31. Copies of procedures and/or test results to survey or monitor interface valves between
        the safety-related section of the service water system and the nonsafety-related section
    32. Copy of the most recent service water flow balance test results, both as-found and as-
        left
    33. History of any thru-wall pipe leaks on the safety-related service water system
Inspector Contact Information:
Chris Smith
Reactor Inspector
817-200-1095
Chris.Smith@nrc.gov
Chris.Smith@nrc.gov
 
Mailing Address:
Mailing Address:  
U.S. NRC, Region IV
 
ATTN: Chris Smith
1600 East Lamar Blvd.
U.S. NRC, Region IV ATTN: Chris Smith  
Arlington, TX 76011-4511
1600 East Lamar Blvd.  
                                              3
Arlington, TX 76011-4511
}}
}}

Latest revision as of 13:00, 29 October 2019

Notification of NRC Triennial Heat Sink Performance Inspection (05000313/2017004 and 05000368/2017004) and Request for Information
ML17292B402
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 10/19/2017
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Richard Anderson
Entergy Operations
References
IR 2017004
Download: ML17292B402 (6)


See also: IR 05000313/2017004

Text

October 19, 2017

Mr. Richard L. Anderson, Vice President

Entergy Operations, Inc.

1448 S.R. 333

Russellville, AR 72802-0967

SUBJECT: ARKANSAS NUCLEAR ONE - NOTIFICATION OF NRC TRIENNIAL HEAT SINK

PERFORMANCE INSPECTION (05000313/2017004 AND 05000368/2017004)

AND REQUEST FOR INFORMATION

Dear Mr. Anderson:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)

staff will conduct a triennial heat sink performance inspection at your Arkansas Nuclear One,

Units 1 and Unit 2, from November 13-17, 2017. The inspection will consist of one reactor

inspector from the NRCs Region IV office for one week. The inspection will be conducted in

accordance with NRC Inspection Procedure 71111.07, "Heat Sink Performance."

Experience has shown that this inspection is resource intensive both for the NRC inspectors

and your staff. In order to minimize the impact to your on-site resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

Please note that the documents are requested to be provided by November 6, 2017. We

request that during the on-site inspection week you ensure that copies of analyses, evaluations,

or documentation regarding the implementation and maintenance of your heat exchanger

program are available. Of specific interest are those documents that establish that your heat

exchanger program satisfies NRC regulatory requirements and conforms to applicable NRC

guidance. Also, appropriate personnel knowledgeable of safety-related heat exchangers should

be available to support the inspector at the site during the inspection.

We have discussed the schedule for this inspection activity with your staff and understand that

our regulatory contact for this inspection will be Michael Hall of your licensing organization. If

there are any questions about this inspection or the material requested, please contact the

inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at chris.smith@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

R. Anderson 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of

this letter and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's document

system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA Wayne C. Sifre Acting for/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-313, 50-368

License Nos. DPR-51, NPF-6

Enclosure:

Triennial Heat Sink Performance Inspection

Request for Information

cc: Electronic Distribution

ML17292B402

SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: WSifre Yes No Publicly Available Sensitive NRC-002

OFFICE RI:EB1 C:EB1 C:DRP/E C:EB1

NAME CSmith TFarnholtz NOKeefe TFarnholtz

SIGNATURE /RA/ /RA/ WSifre for /RA/ /RA/ WSifre for

DATE 10/13/17 10/19/17 10/19/17 10/19/17

Request for Information

Triennial Heat Sink Performance Inspection

Arkansas Nuclear One

Inspection Report: 05000313/2017004 and 05000368/2017004

Inspection Dates: November 13-17, 2017

Inspection Procedure: IP 71111.07, Triennial Heat Sink Performance

Inspector: Chris Smith, Reactor Inspector

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format, to the attention of Chris Smith, by November 6, 2017. The inspector will review specific

items from the information requested below and then request from your staff additional

documents needed during the on-site inspection week. Also, we request that you categorize the

documents in your response with the numbered list below. Please provide requested

documentation electronically if possible. If requested documents are large and only hard copy

formats are available, please inform the inspector, and provide subject documentation during

the first day of the on-site inspection. If you have any questions regarding this information

request, please call the lead inspector as soon as possible.

The following heat exchangers/heat sinks have been selected for inspection:

  • Unit 1 Reactor Building Service Water Cooler Coil (Train A), VCC-2A
  • Unit 1 Loop Decay Heat Cooler (Train B), E-35B B
  • Unit 2 Component Cooling Water Heat Exchanger (Train A), 2E-28A
  • Unit 2 Emergency Cooling Pond, T-250

For all samples listed above:

1. Copies of any self-assessments or audits performed in the previous three years

2. Copies of any documents such as a Generic Letter 89-13 heat exchanger program

description, heat exchanger program document, etc.

3. List of commitments (with descriptions) to the Generic Letter 89-13 program

4. Copies of system health reports and maintenance rule system notebooks

5. Copies of design bases documents, updated final safety analysis report pages, technical

specification (and bases) pages, and technical requirements manual (and bases) pages

6. List of corrective action program documents (with descriptions) for the past three years

7. List of any design changes (with descriptions) implemented during the past three years

8. List of preventive maintenance tasks (with descriptions) and frequency

Enclosure

9. Copies of simplified piping and instrumentation drawings or diagrams and operator

training manuals, if available

For the specific heat exchangers selected:

Testing Documents

10. Copies of the two most recent completed tests confirming thermal performance for those

heat exchangers which are performance tested

11. Instrument uncertainties of the instruments used during testing

12. Copy of any operability determinations or other documentation of degradation

associated with the heat exchangers or the systems that support the operation for the

selected heat exchangers

13. Documents that show the as-found results are recorded, evaluated, and appropriately

dispositioned such that the as-left condition is acceptable

Cleaning Documents

14. The cleaning and inspection maintenance schedule for each heat exchanger for the next

five years

15. Copy of the document describing the inspection results for the last two cleaning and

inspection activities completed on each heat exchanger

16. Cleaning procedures with acceptance criteria for the selected heat exchangers

17. Copies of the documents that verify the structural integrity of the heat exchanger

(e.g., eddy current summary sheets, ultrasonic testing results, and visual inspection

results)

18. Copies of those documents that describe the methods taken to control water chemistry

in the heat exchangers

Design Documents

19. Provide a list of calculations (with descriptions) which currently apply to each heat

exchanger

20. Copies of vendor data sheets and design basis data for the selected heat exchangers

21. Copy of the calculation which establishes the limiting (maximum) design basis heat load

which is required to be removed by each of these heat exchangers

22. Copy of the calculation which correlates surveillance testing results from these heat

exchangers with design basis heat removal capability (e.g., basis for surveillance test

acceptance criteria)

23. Copy of the calculations or documents which evaluate the potential for water hammer or

excessive tube vibration in the heat exchanger or associated piping

2

24. Copy of the document which identifies the current number of tubes in service for each

heat exchanger and the supporting calculation which establishes the maximum number

of tubes which can be plugged in each heat exchanger

25. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes

which are identified in each heat exchanger

For the ultimate heat sink or safety-related service water system:

26. Dam inspections that monitor the integrity of the ultimate heat sink (if applicable)

27. Copies of calculations and surveillances that determine the ultimate heat sink reservoir

capacity and heat transfer capability (if applicable)

28. Copies of procedures for a loss of ultimate heat sink or safety-related service water

system

29. Copies of inspections and/or maintenance related to macrofouling (silt, mussel shells,

debris, etc.) and aquatic life

30. Copies of inspections and/or maintenance related to preventing biotic fouling

31. Copies of procedures and/or test results to survey or monitor interface valves between

the safety-related section of the service water system and the nonsafety-related section

32. Copy of the most recent service water flow balance test results, both as-found and as-

left

33. History of any thru-wall pipe leaks on the safety-related service water system

Inspector Contact Information:

Chris Smith

Reactor Inspector

817-200-1095

Chris.Smith@nrc.gov

Mailing Address:

U.S. NRC, Region IV

ATTN: Chris Smith

1600 East Lamar Blvd.

Arlington, TX 76011-4511

3