Issue date | Title | Topic | |
---|---|---|---|
IR 05000070/1999301 | 1 July 1999 | Forwards Insp Repts 50-070/99-301,50-073/99-201 & 50-183/99-201 on 990607-10.No Safety Concern or Noncompliance to NRC Requirements Was Identified | |
ML20206P654 | 7 January 1999 | Forwards Insp Rept 50-070/98-01 on 981116-19.No Violations Noted.Major Activities Reviewed as Part of Insp Focused on Program to Maintain Safstor Condition of General Electric Test Reactor | |
IR 05000070/1998201 | 4 May 1998 | Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-070/98-201, 50-073/98-201 & 50-183/98-201.First Example of Violation 2 Has Been Withdrawn.Actions Examined During Future Insp | |
ML20217B708 | 14 April 1998 | Submits Errata to Annual Rept 29 for ESADA - Vallecitos Experimental Superheat Reactor | |
ML20217C117 | 18 March 1998 | Forwards Insp Repts 50-070/98-201,50-073/98-201 & 50-183/98-201 on 980209-13 & Notice of Violation | |
ML20198K271 | 9 January 1998 | Forwards Insp Repts 50-018/97-01,50-070-97-01 & 50-183/97-01 on 971204.No Violations Noted.One Unresolved Item Identified & Discussed in Section 1.2 of Encl Rept | |
ML20059E384 | 21 December 1993 | Accepts Cost Estimate Related to Licenses DPR-1,R-33,TR-1 & DPR-10,per Review of Documents Provided Via 931013,1202 & 17 Ltrs in Support of 930831 Request for Decrease in Chemical Bank Ltr of Credit Amend & Trust Agreement Amount | |
ML20059E414 | 2 December 1993 | Explains 1993 Cost Estimate for Regulatory Assurance Reduction,W/Respect to GE Ltr of Credit | |
IR 05000183/1993004 | 24 November 1993 | Forwards Insp Rept 50-183/93-04 on 931101-05.No Violations Noted | |
ML20059E402 | 13 October 1993 | Explains 1993 Cost Estimate for Regulatory Assurance Reduction,W/Respect to GE Ltr of Credit | |
ML20127D775 | 4 September 1992 | Forwards USGS Study of Seismic Potential of Northern Calaveras Fault,For Actions Required to Ensure That Safety Analysis Remain Valid | Earthquake |
ML20059F650 | 27 August 1990 | Advises That 900820 Request for Petition for Reconsideration of Denial of Specific Exemption from Financial Assurance Instrument Requirements of 10CFR50 & 70 Under Review.Request for Temporary Extension of 900831 Filing Deadline Granted | |
ML20245B453 | 8 June 1989 | Forwards Encl Listed Info on Decommissioned & Shutdown Reactors Requested During Discussions at Saxton on 890511 | |
ML20150D864 | 18 March 1988 | Informs of Relocation of NRR to Rockville,Md.Official Mailing Address Still Remains Same & Project Managers Have New Locations & Phone Numbers.Ts Michaels Still Lead Project Manager for Facility & a Adams Will Serve as Backup | |
ML20148C385 | 14 January 1988 | Forwards Amend 4 to License DR-10 & Safety Evaluation.Amend Changes Tech Specs to Permit General Radiation Survey Annually Instead of Twice Annually,Per 870816 Request | |
ML20235T243 | 24 September 1987 | Forwards Insp Repts 50-018/87-01,50-070/87-01,50-073/87-01 & 50-183/87-01 on 870901-03 & Notice of Violation | |
ML20236N051 | 3 August 1987 | Forwards Amend 15 to License TR-1 & Safety Evaluation. Amend Changes Tech Specs by Deleting Cooling Tower from Definition of Reactor Facility | |
ML20215C889 | 11 June 1987 | Informs of Recent Reorganization of Nrr.T Michaels Assigned as Project Manager for Facilities | |
ML20214M663 | 22 May 1987 | Forwards Revised NRC Form 398.Rev Reflects Changes to 10CFR55 Effective on 870526.Revised Form Requires New Applications to Complete Each Category Including Educ, Training & Experience.Changes Detailed in Encl 2 | |
ML20210S413 | 26 September 1986 | Further Response to FOIA Request for 16 Categories of Records Re Facilities.Forwards App D & E Documents.Documents Also Available in PDR | Systematic Assessment of Licensee Performance |
ML20206M418 | 25 June 1986 | Forwards Insp Repts 50-018/86-01 & 50-183/86-01 on 860617.No Violation Noted | |
ML20140G721 | 27 March 1986 | Lists Change in Telephone Number for H Bernard,Facility Project Manager,Due to NRR Reorganization.D Tondi New Nonpower Reactors & Safeguards Licensing Section Leader. Correspondence Should Be Sent to Listed Address | |
ML20210H875 | 27 March 1986 | Lists Change in Telephone Number for H Bernard,Facility Project Manager,Due to NRR Reorganization.D Tondi New Nonpower Reactors & Safeguards Licensing Section Leader. Correspondence Should Be Sent to Listed Address | |
ML20195C718 | 21 March 1986 | Responds to FOIA Request for Nine Categories of Records Re Damages Occurring to Nuclear Power Plants Following Earthquakes & 860131 Earthquake Near Perry Site.Forwards Apps a & B Documents.App B Documents Also Available in PDR | Operating Basis Earthquake Earthquake |
ML20137R681 | 5 February 1986 | Forwards Amend 14 to License TR-1,safety Evaluation & Fr Notice.Amend Renews License for Possession Only Until 921001 | |
ML20239A197 | 17 December 1985 | Further Response to 850927 & 1106 FOIA Requests for Documents Re Pressure Suppression Containment,Including Humboldt Bay & Bodega Bay Docket Files.Bodega Bay File Being Placed in Pdr.Review of Addl Documents Continuing | |
ML20138B513 | 8 October 1985 | Forwards Corrected Page 2 to Insp Repts 50-070/85-01 & 50-073/85-02 Per 851007 Telcon Re Presence of Second Individual at Facility Whenever Licensed Operator W/Medical Restrictions Is Performing Licensed Activities | |
ML20133H433 | 1 October 1985 | Forwards Insp Repts 50-070/85-01 & 50-073/85-02 on 850812-15 & Notice of Violation | |
ML20133C212 | 30 September 1985 | Forwards Modified Tech Specs Re Storage & Disposal of Liquid Effluents & Elimination of Area Radiation Monitors for Shutdown of Test Reactor Facility.Info Suppls 850626 Submittal of License Renewal Info | |
ML20128M281 | 15 July 1985 | Forwards Self-Evaluation of NSHC, Supplementing 850625 Application for Amend to License TR-1,changing Tech Specs to Permit Maint of Reactor in Possession/Nonoperating Status | |
ML20128L609 | 26 June 1985 | Forwards Request to Revise 751021 Application to Renew License TR-1,authorizing Possession/Nonoperating Status for Getr,Per Revised Tech Specs | |
ML20058D249 | 20 July 1982 | Requests Extension Until 821103 for Submitting Revised Emergency Plan,Based on Classification as Minor Facility | |
ML20055B460 | 14 July 1982 | Forwards Revised Security Plan for Protection of Reactor Facilities.Plan Withheld (Ref 10CFR2.790) | |
ML20126K549 | 12 May 1981 | Forwards 810507 Fr Notice of Hearing | |
ML20126H259 | 6 April 1981 | Forwards Addl Copies of NRC 810403 Response to Intervenor Dellums Request for Production of Documents.W/O Encl | |
ML20126H077 | 26 March 1981 | Forwards Annual Financial Rept 1980 | |
ML20126F257 | 10 March 1981 | Advises That Notice of Public Hearings on Facility Will Be Forwarded When Issued,In Response to .Explains Procedure for Making Limited Appearance Statement | |
ML20126E721 | 8 February 1981 | Requests Date & Place of Hearing & Procedure to Testify in Support of Facility | |
ML20062J009 | 11 July 1980 | Submits Comments on 800616-17 Meeting on Getr.Requests Copy of Edac 117-253-01,Revision 1.Probabilistic Effects of Presentation of Combining Vibratory Motion W/Uplift Were Unclear | |
ML20149K191 | 7 May 1980 | Generic Ltr 80-38 to All Nonpower Reactor Licensees Re NPR Physical Protection Requirements.Summary of Certain NPR Physical Protection Requirements Encl & Should Aid in Determining Safeguards Requirements Applicable to Facility | |
ML20132A949 | 14 August 1979 | Forwards IE Info Notice 79-20, NRC Enforcement Policy - NRC Licensed Individuals. No Action Required | |
ML20062G847 | 9 February 1979 | Forwards Annual Rept 11 for Deactivated Vallecitos Experimental Superheat Reactor | |
ML20148A275 | 18 December 1978 | Forwards Rept Re 781205-6 Subj Facil Site Visit Re Trenches & Seismic Analysis | |
ML20147H736 | 5 December 1978 | Corrects Error in NRC Staff Answer to Intervenors' Request for Referral & Licensee'S Motion for Imposition of Sanctions, Dtd 781129.On p2 Denied Should Read Granted. Staff Supports Licensee'S Request to Impose Sanctions | |
ML20147C312 | 4 December 1978 | Requests Review of 771107 Preliminary Safety Eval in Light of Possible New Geological Evidence Which May Affect the Safety of Bldg 102,which Houses the Plutonium Labs | Earthquake |
ML20197D900 | 29 November 1978 | Forwards Logs of the Trenches at & Near Subj Facil.Logs Available in Central Files | |
ML20150C611 | 17 November 1978 | Responds to Opposing Reopening of Subj Facil. Explains NRC Lic Process.Recipient Is Incl in Svc List of Those to Receive Notice Ofhearings on Subj.(See:Ano 7811080056) | |
ML20150C580 | 15 November 1978 | Responds to by Forwarding a Copy of Nrc'S Reply to Mrs Delfino'S to Chairman Hendrie | |
ML20148L006 | 13 November 1978 | Responds to to J Hendrie Re Subj Facils.Repts Eval of Both Facils Continues & That Discharges of Tritium Have Been Small Fraction of Reg Limits of 10CFR Part 20. W/Out Encl NRC Eval of Site | |
ML20197C341 | 13 November 1978 | Responds to to Dept of Energy Re Present Status of Subj Facils.Based on Seismology & Site Geology Evaluation Continued Ntr Oper & Activities Authorized by Lic SNM-960 Were Found to Be Acceptable |