June 2002 Monthly Operating Report for H.B. Robinson Steam Electric Co., Unit 2
ML021930080
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 07/10/2002
From: Fletcher B
Carolina Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RNP-RA/02-0102
Download: ML021930080 (4)


Text

TS 5.6.4 TRM 6.2 S'CP&L A Progress Energy Company Serial: RNP-RA/02-0102 JUL 1 0 ZOO2 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 MONTHLY OPERATING REPORT Ladies and Gentlemen:

In accordance with the H. B. Robinson Steam Electric Plant (HBRSEP), Unit No. 2, Technical Specification (TS) Section 5.6.4, "Monthly Operating Reports," and HBRSEP, Unit No. 2, Technical Requirements Manual (TRM) Section 6.2, "Monthly Operating Report," Carolina Power and Light (CP&L) Company submits the enclosed report of operating statistics and shutdown experience for the month of June 2002. In accordance with TS Section 5.6.4, this report is being submitted to the NRC by the 15th day of the month following the calendar month covered by the report.

If you have any questions concerning this matter, please contact Mr. C. T. Baucom.

Sincerely, B. L. Fletcher III Manager - Regulatory Affairs DJS/djs Attachments I. Plant Performance Data System Appendix C - Operating Data Report II. Appendix B - Average Daily Power Level III. Appendix D - Unit Shutdowns and Power Reductions c: NRC Resident Inspector, HBRSEP L. A. Reyes, NRC, Region II R. Subbaratnam, NRC, NRR Robinson Nuclear Plant . " _

3581 West Entrance Road Hartsville, SC 29550

Attachment I to Serial: RNP-RA/02-0102 PLANT PERFORMANCE DATA SYSTEM PAGE 1 of 1 APPENDIX C - OPERATING DATA REPORT RPD36-000 DOCKET NO. 050-0261 UNIT CP&L CO, HBRSEP, UNIT NO. 2 RUN DATE 7/01/02 RUN TIME 16:23:14 COMPLETED BY TOM FREEMAN OPERATING STATUS TELEPHONE (843) 857-1403 UNIT NAME: H. B. ROBINSON STEAM ELECTRIC PLANT (HBRSEP), NOTES:

1.

UNIT NO. 2

2. REPORTING PERIOD: JUNE 2002
3. LICENSED THERMAL POWER (MWT): 2300
4. NAMEPLATE RATING (GROSS MWE): 739.0
5. DESIGN ELECTRICAL RATING (NET MWE): 700.0
6. MAX DEPENDABLE CAPACITY (GROSS MWE): 700.0
7. MAX DEPENDABLE CAPACITY (NET MWE): 683.0
8. IF CHANGES OCCUR IN CAPACITY RATING (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE): None
10. REASONS FOR RESTRICTION, IF ANY:

THIS YR TO CUMULATIVE MONTH DATE

11. HOURS IN REPORTING PERIOD 720.00 4343.00 274679.00
12. NUMBER OF HOURS REACTOR CRITICAL 720.00 4343.00 2081 50.59
13. REACTOR RESERVE SHUTDOWN HRS .00 .00 3314.65
14. HOURS GENERATOR ON LINE 720.00 4343.00 204861.26
15. UNIT RESERVE SHUTDOWN HOURS .00 .00 23.20
16. GROSS THERMAL ENERGY GEN. (MWH) 1655354.16 9848209.92 432777726.24
17. GROSS ELEC. ENERGY GEN. (MWH) 530872.00 3223728.00 140821036.00
18. NET ELEC. ENERGY GENERATED (MWH) 505947.00 3074246.00 133405595.00
19. UNIT SERVICE FACTOR 100.00 100.00 74.58
20. UNIT AVAILABILITY FACTOR 100.00 100.00 74.59
21. UNIT CAP. FACTOR (USING MDC NET) 102.88 103.64 72.32
22. UNIT CAP. FACTOR (USING DER NET) 100.39 101.12 69.38
23. UNIT FORCED OUTAGE RATE .00 .00 11.34
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE DATE AND DURATION OF EACH):

Refueling Outage 21 is scheduled to begin 10/12/02 for a duration of 28 days.

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

Attachment II to Serial: RNP-RA/02-0102 Page 1 of 1 APPENDIX B - AVERAGE DAILY POWER LEVEL RPD39-000 DOCKET NO. 050-0261 UNIT CP&L CO, HBRSEP, UNIT NO. 2 RUN DATE 7/01/02 RUN TIME 16:23:14 CCOMPLETED BY THOMAS FREEMAN TELEPHONE (843) 857-1403 JUNE 2002 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-NET) 1 710* 17 698*

2 705* 18 700*

3 701

  • 19 700*

4 705* 20 701

  • 5 704* 21 702*

6 704* 22 704*

7 702* 23 704*

8 701* 24 703*

9 703* 25 703*

10 703* 26 704*

11 703* 27 704*

12 703* 28 704*

13 703*

29 702

  • 14 703* 30 701
  • 15 699*

16 698*

  • The maximum dependable net capacity is 683 MWE.

Attachment III to Serial: RNP-RA/02-0102 Page 1 of 1 APPENDIX D UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 050-0261 UNIT NAME HBRSEP, UNIT NO. 2 DATE 7/01/02 REPORT MONTH: JUNE 2002 COMPLETED BY THOMAS FREEMAN TELEPHONE (843) 857-1403 No. Date Type Duration Reason' Method of Shutting Down Corrective Actions /

F: Forced (Hours) the Reactor or Reducing Comments 2

S: Scheduled Power L A +/- .J..________ L .1.

2 Reason: Method:

A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Other (Explain)

E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain)

SUMMARY

The unit operated at full power the entire month. There were no challenges to the pressurizer power operated relief valves or the pressurizer safety valves during the month. There were no steam generator inspections during the month.