April 2003 Monthly Operating Report for H.B. Robinson Steam Electric Plant, Unit No.2
ML031290065
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 05/06/2003
From: Baucom C
Progress Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RNP-RA/03-0062, TRM 6.2, TS 5.6.4
Download: ML031290065 (3)


Text

TS 5.6.4 TRM6.2 C Progress Energy Serial: RNP-RA/03-0062 MAY 0 6 2003 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 MONTHLY OPERATING REPORT Ladies and Gentlemen:

In accordance with the H. B. Robinson Steam Electric Plant (HBRSEP), Unit No. 2, Technical Specifications (TS) Section 5.6.4, "Monthly Operating Reports," and HBRSEP, Unit No. 2, Technical Requirements Manual (TRM) Section 6.2, "Monthly Operating Report," Progress Energy Carolinas, Inc., also known as Carolina Power & Light Company, submits the attached report of operating statistics and shutdown experience for the month of April 2003.

If you have any questions concerning this matter, please contact me.

Sincerely, Oat 7 C. T. Baucom Supervisor - Licensing/Regulatory Programs CTB/jmg Attachment c: NRC Resident Inspector, HBRSEP L. A. Reyes, NRC, Region II C. P. Patel, NRC, NRR Progress Energy Carolinas, Inc.

3581 West Entrance Road Hartsville, SC 295500

Attachment to Serial: RNP-RA/03-0062 Page 1 of 2 MONTHLY OPERATING REPORT DOCKET NO. 050-0261 UNIT H. B. ROBINSON STEAM ELECTRIC PLANT (HBRSEP), UNIT NO. 2 DATE 05/02/03 COMPLETED BY TIMOTHY SURMA TELEPHONE (843) 857-1086 REPORTING PERIOD: APRIL 2003

1. DESIGN ELECTRICAL RATING (NET MWE): 765
2. MAX DEPENDABLE CAPACITY (NET MWE): 710 THIS YR TO MONTH DATE CUMMULATIVE
3. NUMBER OF HOURS REACTOR CRITICAL 719.00 2879.00 214676.99
4. HOURS GENERATOR ON LINE 719.00 2879.00 211357.26
5. UNIT RESERVE SHUTDOWN HOURS 0.00 0.00 23.20
6. NET ELEC. ENERGY GENERATED (MWH) 533475 2150149.00 138087607.00

Attachment to Serial: RNP-RA/03-0062 Page 2 of 2 DOCKET NO. 050-0261 UNIT NAME HBRSEP. UNIT NO. 2 DATE 05/02/03 COMPLETED BY TIMOTHY SURMA TELEPHONE (843) 857-1086 REPORTING PERIOD: APRIL 2003 UNIT SHUTDOWNS No. Date Type Duration Reason' Method of Shutting Down Cause / Corrective Actions / Comments 2

F Forced (Hours) the Reactor S scheduled 2

Reason: Method A-Equipment Failure (Explain) I-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Continuation E-Operator Training & Ucense Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

SUMMARY

The unit operated at approximately full power for the entire month. There were no challenges to the pressurizer power operated relief valves or the pressurizer safety valves during the month.