Interim Deficiency Rept DR-105 Re Electrical Separation Between Reactor Protection Sys & Nuclear Steam Supply Shutoff Wiring within Power Generation Control Complex. Investigation in Progress.Next Rept by 831219
ML20078R537
Person / Time
Site: River Bend Entergy icon.png
Issue date: 11/01/1983
From: Booker J
GULF STATES UTILITIES CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
DR-105, RBG-16-275, NUDOCS 8311150189
Download: ML20078R537 (1)


Text

Gh

. GULF STATES UTILITIES COMPANY POSTOFFtCEBOX 29S1

  • DEAUMONT. TEXAS 77704 AREA CODE 409 838 6631 November 1, 1983 RBG-16,275 File Nos. G9.5, G9.25.1.1 Mr.-John T. Collins, Regional Administrator U. S. Nuclear Regulatory Commission Region IV, Office of Inspection and Enforcement 3jh 3 ]" ~% h3

- - - ~

611 Ryan Plaza Drive, Suite 1000 i Arlington, Texas 76011  ! NOV 3 3 i

Dear Mr. Collins:

River Bend Station Unit 1 Docket No. 50-458 Interim Report /DR-105 Gulf States Utilities Company has not completed its investigation of DR-105 concerning the electrical separation between the Reactor Protection System and the Nuclear Steam Supply Shutoff wiring within the Power Generation Control Complex. An interim or final status report will be provided by December 19, 1983.

Sincerely,

. I, t-J. E. Booker Manager-Engineering, Nuclear Fuels & Licensing River Bend Nuclear Group cc: Director of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 NRC Resident Inspector-Site 8311150189 831101 PDR ADOCK 05000450 S PDR I 0 j & c27