ML20043A609
ML20043A609 | |
Person / Time | |
---|---|
Site: | Monticello, Nine Mile Point, Brunswick, River Bend, Clinton, LaSalle |
Issue date: | 04/27/1990 |
From: | Thomas W SULZER BINGHAM PUMPS, INC. |
To: | NRC |
References | |
REF-PT21-90 NUDOCS 9005220307 | |
Download: ML20043A609 (2) | |
Category:DEFICIENCY REPORTS (PER 10CFR50.55E & PART 21)
MONTHYEARML20217N3271999-10-21021 October 1999
[Table view]Part 21 Rept Re non-linear Oxygen Readings with Two (2) Model 225 CMA-X Containment Monitoring Sys at Bsep.Caused by High Gain Produced by 10K Resistor Across Second Stage Amplifier.Engineering Drawings Will Be Revised ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers U-603204, Final Part 21 Rept 21-99-003 Re Deficiency in Commercial Grade Dedication Process Used by Circuit Breaker Refurbishment Supplier Trentec for Westinghouse Breaker 1AP05EH.Issue Determined Not Reportable Per 10CFR211999-04-30030 April 1999 Final Part 21 Rept 21-99-003 Re Deficiency in Commercial Grade Dedication Process Used by Circuit Breaker Refurbishment Supplier Trentec for Westinghouse Breaker 1AP05EH.Issue Determined Not Reportable Per 10CFR21 U-603182, Part 21 Rept Re Deficiency in Commercial Grade Dedication Process Used by Circuit Breaker Refurbishment Supplier, Trentec.Condition Rept 1-99-01-136 Was Initiated to Track Investigation & Resolution of Issue1999-03-12012 March 1999 Part 21 Rept Re Deficiency in Commercial Grade Dedication Process Used by Circuit Breaker Refurbishment Supplier, Trentec.Condition Rept 1-99-01-136 Was Initiated to Track Investigation & Resolution of Issue ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20207E9311999-02-26026 February 1999 Part 21 Rept Re Sprague Model TE1302 Aluminum Electrolytic Capacitors with Date Code of 9322H.Caused by Aluminum Electrolytic Capacitors.Affected Capacitors Replaced ML20199M0891999-01-22022 January 1999 Part 21 Rept Re Failure of Square Root Converters.Caused by Failed Aluminum Electrolytic Capacitory Spargue Electric Co (Model Number TE1302 with Mfg Date Code 9322H).Sent Square Root Converters Back to Mfg,Barker Microfarads,Inc U-603115, Part 21 Interim Rept 21-98-021 Re Deficiencies in Matl Dedication Process Used by Goulds Pumps in Supplying SR Parts to Npps.Issue Is Not Reportable Under 10CFR21. Dedication Process Did Not Affect Ability of Components1998-12-0404 December 1998 Part 21 Interim Rept 21-98-021 Re Deficiencies in Matl Dedication Process Used by Goulds Pumps in Supplying SR Parts to Npps.Issue Is Not Reportable Under 10CFR21. Dedication Process Did Not Affect Ability of Components U-603114, Part 21 Rept 21-98-049 Re W Dhp Circuit Breaker Refurbished by Nuclear Logistics,Inc Which Failed to Operate.Caused by Trip Latch out-of-adjustment & Incorrectly Sized Ratchet Lever Assembly Bushing.Breakers Were Returned to Vendor1998-11-25025 November 1998 Part 21 Rept 21-98-049 Re W Dhp Circuit Breaker Refurbished by Nuclear Logistics,Inc Which Failed to Operate.Caused by Trip Latch out-of-adjustment & Incorrectly Sized Ratchet Lever Assembly Bushing.Breakers Were Returned to Vendor ML20154E2171998-09-28028 September 1998 Follow-up Part 21 Rept Re Defect with 1200AC & 1200BC Recorders Built Under Westronics 10CFR50 App B Program. Westronics Has Notified Bvps,Ano & RBS & Is Currently Making Arrangements to Implement Design Mods ML20153D0191998-09-18018 September 1998 Part 21 Rept Re Defect in Gap Conductance Analyses for co- Resident BWR Fuel.Initially Reported on 980917.Corrective Analyses Performed Demonstrating That Current Operating Limits Bounding from BOC to Cycle Exposure of 8 Gwd/Mtu ML20153C6771998-09-17017 September 1998 Part 21 Rept Re Defect Relative to MCPR Operating Limits as Impacted by Gap Conductance of co-resident BWR Fuel at Facilities.Operating Limit for LaSalle Unit 2 & Quad Cities Unit 2 Will Be Revised as Listed ML20236X2351998-08-0505 August 1998 Part 21 Rept Re Defect Associated W/Westronics 1200AC & 1200BC Recorders Built Under Westronics 10CFR50,App B Program.Beaver Valley,Arkansas Nuclear One & River Bend Station Notified.Design Mod Is Being Developed U-603033, Part 21 Rept 21-98-039 Re Shrinkage of Medium & High Density Silicone Seals Designed & Installed by Bisco Using Dow Corning Sylgard 170 Matl.Caused by Coefficient of Thermal Expansion.Will Inspect & Rework/Repair Suspected Seals1998-07-20020 July 1998 Part 21 Rept 21-98-039 Re Shrinkage of Medium & High Density Silicone Seals Designed & Installed by Bisco Using Dow Corning Sylgard 170 Matl.Caused by Coefficient of Thermal Expansion.Will Inspect & Rework/Repair Suspected Seals ML20236N6751998-07-0909 July 1998 Part 21 & Deficiency Rept Re Notification of Potential Safety Hazard from Breakage of Cast Iron Suction Heads in Apkd Type Pumps.Caused by Migration of Suction Head Journal Sleeve Along Lower End of Pump Shaft.Will Inspect Pumps ML20236E7991998-05-26026 May 1998 Final Part 21 Rept Re W Dhp Circuit Breaker Auxillary Switch Operating Assembly Anomalies.Caused by Loss of Breaker Safety Function.Dhp Circuit Will Be Inspected ML20248F3531998-05-21021 May 1998 Part 21 Rept Re Electronic Equipment Repaired or Reworked by Integrated Resources,Inc from Approx 930101-980501.Caused by 1 Capacitor in Each Unit Being Installed W/Reverse Polarity. Policy of Second Checking All Capacitors Is Being Adopted U-603004, Part 21 Rept Re 980107 Determination That Itt Barton Model 580A Series Differential Pressure Indicating Switches Operating Forces Too Low.Manufacturing Sys Allowed Switches to Be Mixed.Evaluation Concludes Issue Not Reportable1998-05-15015 May 1998 Part 21 Rept Re 980107 Determination That Itt Barton Model 580A Series Differential Pressure Indicating Switches Operating Forces Too Low.Manufacturing Sys Allowed Switches to Be Mixed.Evaluation Concludes Issue Not Reportable ML20216A9601998-05-0808 May 1998 Part 21 Rept Re Failure of 12 Volt DC Inverter Power Supply. Caused by Inadequately Sized Output Transistor Pair Combined W/Degraded Capacitors.Licensee Plans to Replace All Output Transistors & Degraded Capacitors U-602995, Part 21 Interim Rept 21-98-021 Re Deficiencies in Matl Dedication Process Used by Goulds Pumps During Use of Portable Metal Analyzer.Util Identified Discrepancies Which Are Acceptable W/Some Exception of Some Replacement Parts1998-05-0505 May 1998 Part 21 Interim Rept 21-98-021 Re Deficiencies in Matl Dedication Process Used by Goulds Pumps During Use of Portable Metal Analyzer.Util Identified Discrepancies Which Are Acceptable W/Some Exception of Some Replacement Parts U-602994, Part 21 Rept Re Final Rept 21-98-008,on 980113,reliance Electric Motors Supplied by Rockwell International for Hydrogen Recombiner Cooling Fans Do Not Have nameplate- Specified High Temperature Bearings.Fan Motors Acceptable1998-04-29029 April 1998 Part 21 Rept Re Final Rept 21-98-008,on 980113,reliance Electric Motors Supplied by Rockwell International for Hydrogen Recombiner Cooling Fans Do Not Have nameplate- Specified High Temperature Bearings.Fan Motors Acceptable U-602979, Final Part 21 Rept 21-97-059 Re Discrepancies Found During Receipt Insp of Three Refurbished safety-related W Dhp Circuit Breakers.Util Completed Evaluation,Per 10CFR21 & Concludes That Condition Is Not Reportable1998-04-0707 April 1998 Final Part 21 Rept 21-97-059 Re Discrepancies Found During Receipt Insp of Three Refurbished safety-related W Dhp Circuit Breakers.Util Completed Evaluation,Per 10CFR21 & Concludes That Condition Is Not Reportable U-602968, Interim Part 21 Rept 21-97-055 Re Westinghouse Dhp Circuit Breaker Auxiliary Switch Operating Assembly Anomalies. Initially Reported on 980116.Util Currently Evaluating Suppliers Response to Questions Re Issue1998-03-24024 March 1998 Interim Part 21 Rept 21-97-055 Re Westinghouse Dhp Circuit Breaker Auxiliary Switch Operating Assembly Anomalies. Initially Reported on 980116.Util Currently Evaluating Suppliers Response to Questions Re Issue U-602960, Part 21 & Deficiency Rept Re Commerical Grade Dedication Program of Sentry Equipment Corp.Initially Reported on 980217.IP Performed an Addl Assessment at Sentry Facility on 980226.Next Rept Will Be Submitted by 9804111998-03-12012 March 1998 Part 21 & Deficiency Rept Re Commerical Grade Dedication Program of Sentry Equipment Corp.Initially Reported on 980217.IP Performed an Addl Assessment at Sentry Facility on 980226.Next Rept Will Be Submitted by 980411 U-602954, Interim Part 21 rept,21-98-008 Re Identification That Bearings Installed in Hydrogen Recombiner B Cooling Fan Motor 0HG04CB Were Not Same as Bearings Specified on Motor Nameplate.Will Complete Evaluation of Issue by 9805131998-03-0909 March 1998 Interim Part 21 rept,21-98-008 Re Identification That Bearings Installed in Hydrogen Recombiner B Cooling Fan Motor 0HG04CB Were Not Same as Bearings Specified on Motor Nameplate.Will Complete Evaluation of Issue by 980513 U-602952, Part 21 Interim Rept 21-98-001:ITT Barton Model 580A Series Dp Indicating Switch Operating Force Concerns.Initially Reported on 980107.Evaluation of Subj Issue Will Be Completed by 9805301998-03-0606 March 1998 Part 21 Interim Rept 21-98-001:ITT Barton Model 580A Series Dp Indicating Switch Operating Force Concerns.Initially Reported on 980107.Evaluation of Subj Issue Will Be Completed by 980530 U-602939, Part 21 Interim Rept 21-97-060 Re Sentry Equipment Corp Commercial Grade Dedication Program Deficiencies.Evaluation of Issue Will Be Completed by 9804041998-02-17017 February 1998 Part 21 Interim Rept 21-97-060 Re Sentry Equipment Corp Commercial Grade Dedication Program Deficiencies.Evaluation of Issue Will Be Completed by 980404 U-602932, Interim Part 21 Rept 21-97-059 Re Several Discrepancies Found During Receipt Insp of Three safety-related W Dhp Circuit Breakers.Sent Subject Circuit Breakers to Nuclear Logistics Inc for Refurbishment1998-02-13013 February 1998 Interim Part 21 Rept 21-97-059 Re Several Discrepancies Found During Receipt Insp of Three safety-related W Dhp Circuit Breakers.Sent Subject Circuit Breakers to Nuclear Logistics Inc for Refurbishment U-602925, Part 21 Rept 21-97-058 Re Oil Leaking Around Diaphragm of Replacement Pressure Reducing/Dump Valve Installed on Itt Barton Hydromotor Actuator.Caused by Poor Workmanship of Valve at Time of Manufacture.Valves Sent to Vendor1998-02-0606 February 1998 Part 21 Rept 21-97-058 Re Oil Leaking Around Diaphragm of Replacement Pressure Reducing/Dump Valve Installed on Itt Barton Hydromotor Actuator.Caused by Poor Workmanship of Valve at Time of Manufacture.Valves Sent to Vendor U-602920, Part 21 Interim Rept 21-97-044/047/048 Re 970929 Failure of safety-related Battery Charger.Caused by Inadequate Soldered Wire Connections.Util Will Issue Rept of Issues IAW Provisions of 10CFR21 & 10CFR50.73 by 9802171998-01-28028 January 1998 Part 21 Interim Rept 21-97-044/047/048 Re 970929 Failure of safety-related Battery Charger.Caused by Inadequate Soldered Wire Connections.Util Will Issue Rept of Issues IAW Provisions of 10CFR21 & 10CFR50.73 by 980217 U-602910, Part 21 Interim Rept 21-97-055,identified Adverse Trend in Auxiliary Switch Operating Assembly Anomalies in W Dhp Circuit Breakers on 971120.Condition Rept 1-97-11-388 Initiated to Track Investigation & Resolution1998-01-16016 January 1998 Part 21 Interim Rept 21-97-055,identified Adverse Trend in Auxiliary Switch Operating Assembly Anomalies in W Dhp Circuit Breakers on 971120.Condition Rept 1-97-11-388 Initiated to Track Investigation & Resolution ML20198K5081998-01-0606 January 1998 Part 21 Rept Re Transient Analyses at Exposures Prior to End of Cycle.Caused by Component Defect.Notified Commonwealth Edison of Defect & Provided Revised Limits by Siemens Power Corp U-602894, Final Part 21 Rept Re Discrepancies Between GE BWR Reactor Design Requirements Documents & Sys Vendor Manuals.Util Completed Evaluation & Concluded That Issue Is Not Reportable Per 10CFR21 as Reported in 971029 Rept1997-12-18018 December 1997 Final Part 21 Rept Re Discrepancies Between GE BWR Reactor Design Requirements Documents & Sys Vendor Manuals.Util Completed Evaluation & Concluded That Issue Is Not Reportable Per 10CFR21 as Reported in 971029 Rept ML20203H9891997-12-12012 December 1997 Part 21 Rept Re Potential Manufacturing Defect of Enterprise DSR-4 & DSRV-4 Edgs.Cooper Energy Svcs Supplied 1A-7840 Adjusting Screw to Affected Utils & Sites.River Bend Station Replaced W/Acceptable Assemblies ML20203B3691997-12-10010 December 1997 Part 21 Rept Re Potential to Exceed Operating Limits.Cycle 8 Delayed Until Fall 1998 U-602876, Interim Part 21 Rept Re 970929 Discovery of Deviations in safety-related Battery Chargers.Evaluation of Conditions Under Part 21 Continuing.Update on Resolution Progress Will Be Provided by 9801291997-12-0303 December 1997 Interim Part 21 Rept Re 970929 Discovery of Deviations in safety-related Battery Chargers.Evaluation of Conditions Under Part 21 Continuing.Update on Resolution Progress Will Be Provided by 980129 U-602855, Part 21 Rept Re Discrepancies Between GE BWR Design Requirements Documents & Sys Vendor Manuals.Util Does Not Have Firm Date for Resolving Issue But Will Provide Update on Resolution Progress by 9712181997-10-29029 October 1997 Part 21 Rept Re Discrepancies Between GE BWR Design Requirements Documents & Sys Vendor Manuals.Util Does Not Have Firm Date for Resolving Issue But Will Provide Update on Resolution Progress by 971218 U-602823, Part 21 Rept Re Improper Clearance for W Model 50DHP350 Circuit Breaker Arc Chute Rear Arc Horn.Caused by Installation of Arc Chute Having Potential to Cause Line Pole to Deflect.Replace Deficient Arc Chutes1997-08-28028 August 1997 Part 21 Rept Re Improper Clearance for W Model 50DHP350 Circuit Breaker Arc Chute Rear Arc Horn.Caused by Installation of Arc Chute Having Potential to Cause Line Pole to Deflect.Replace Deficient Arc Chutes ML20149F6031997-07-18018 July 1997 Part 21 Rept Re R47 Incorrectly Installed on Electric Power Assembly.Recommends Evaluation of Timing Delay Requirements Applicable to Reactor Protective Sys ML20140A9661997-05-29029 May 1997 Part 21 Rept Re Ksv Emergency Diesel Generator Power Piston Failure.Caused by Jacket Water in Combustion Chamber. Recommends That Users Verify That Crown Thickness at Valve Cutout Be 100 Minimum ML20140A4761997-05-27027 May 1997 Provides Addl Info to 970429 Part 21 Rept Re Potential safety-related Problem W/Asco HV 266000-007J Scram Solenoid Pilot Valves.Corrective Actions Also Listed ML20140G4481997-05-0101 May 1997 Part 21 Rept Re Potential Defect in Component of Dsrv & Dsr Enterprise Standby Diesel Generator Sys.Recommends That Springs Be Inspected on Periodic Basis,Such as During Refueling Outages ML20137G6261997-03-25025 March 1997 Svcs Part 21 Rept Re Emergency Generators Installed at Zion Station Which Developed Significant Drop in Crankcase Lube Oil Level.Caused by Crack in Liner Wall,Allowing Jacket Water to Enter Chamber ML20136D5641997-03-0707 March 1997 Part 21 Rept Re Transformer Not Being Stable in No Load Condition & Tripping When Lightly Loaded U-602704, Part 21 Rept Re Regulated Power Transformer 1AP75ERT Tripping Several Times.Caused by Addition of Step Load from Low or No Load Condition.Will Disconnect Four Potentially Affected Transformers from Div 2 Electrical Sys1997-02-27027 February 1997 Part 21 Rept Re Regulated Power Transformer 1AP75ERT Tripping Several Times.Caused by Addition of Step Load from Low or No Load Condition.Will Disconnect Four Potentially Affected Transformers from Div 2 Electrical Sys ML20133E8001997-01-0808 January 1997 Deficiency Rept Re Nonconformance Related to Masterflow 713 Grout,Which Master Builders,Inc Has Supplied as Nuclear SR Product to 18 Npps.Cause Unknown.Requests That Listed Info Be Provided to Gain Insight as to Scope & Possible Cause U-602677, Part 21 Rept Re Failure of Westinghouse Dhp Circuit Breaker to Close on Demand During Surveillance Test.Inspected, Cleaned,Adjusted & Lubricated Motor cut-off Switch & Spring Charge Indicator Mechanism in Subject Breaker1996-12-20020 December 1996 Part 21 Rept Re Failure of Westinghouse Dhp Circuit Breaker to Close on Demand During Surveillance Test.Inspected, Cleaned,Adjusted & Lubricated Motor cut-off Switch & Spring Charge Indicator Mechanism in Subject Breaker ML20134Q0801996-11-27027 November 1996 Part 21 Rept Re Deficiency of Wkm Model 70-13 Pneumatic Actuators Manufactured by Anchor Darling Valve Company Due to Incorrect Calculation of Bench Set & Supply Air Set Points.All Affected Valves Have Been Reviewed & Evaluated ML20134L1081996-10-10010 October 1996 Part 21 Rept Re Defect in Component of Nordberg Model FS1316HSC Sdg.Nak Engineering,Inc Has Established & Adopted Procedures to Assemble Fuel Oil Lines & Climinate Possible Defective Condition ML20128F5011996-10-0404 October 1996 Part 21 Rept & Deficiency Rept Re Wkm Model 70-13 Pneumatic Actuators Mfg by Anchor Darling Valve Co.All Affected Valves Being Reviewed/Evaluated & Design Changes Are Being Initiated as Required 1999-09-22 Category:TEXT-SAFETY REPORT MONTHYEARML20217N3271999-10-21021 October 1999
[Table view]Part 21 Rept Re non-linear Oxygen Readings with Two (2) Model 225 CMA-X Containment Monitoring Sys at Bsep.Caused by High Gain Produced by 10K Resistor Across Second Stage Amplifier.Engineering Drawings Will Be Revised ML20217G2161999-10-15015 October 1999 Errata Pages 2 & 3 for Safety Evaluation Supporting Amend 168 Issued to FOL DPR-63 Issued on 990921.New Pages Change Description of Flow Control Trip Ref Cards to Be Consistent with Application for Amend ML20217C9121999-10-12012 October 1999 SER Input Authorizing Licensee Proposed Request to Modify Definition of Core Alteration in Section 1.0 of TS & Update Sections 3/4.1,3.4.3 & 3/4.9 to Reflect Proposed Definition Change ML20217F9091999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for LaSalle County Stations,Units 1 & 2.With BSEP-99-0168, Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with ML20217K4631999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Nine Mile Point, Unit 1.With ML20217D1261999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Monticello Nuclear Generating Plant.With ML20216J9251999-09-30030 September 1999 Suppl to Special Rept:On 990621,11 Containment Hydrogen Monitoring Sys Chart Recorder Was Indicating Below Normal Operating Range.Caused by Excessive Wear on Valve Body & Discs of Bypass Pump.Sample Pump Replaced RBG-45144, Monthly Operating Rept for Sept 1999 for River Bend Station. with1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for River Bend Station. with U-603277, Monthly Operating Rept for Sept 1999 for Clinton Power Station,Unit 1.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Clinton Power Station,Unit 1.With ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212F7301999-09-21021 September 1999 Special Rept:On 990907,CR Operators Declared 12 Containment Hydrogen Monitoring Sys Inoperable for Planned Maint.Cause of Low Flow Condition Was Determined to Be Foreign Matl. Replaced Sample Pump Valve Discs ML20212B9081999-09-14014 September 1999 Special Rept:On 990901, 12 Containment Hydrogen Monitoring Sys Was Declared Inoperable for Planned Maint.Caused by Planned Maint Being Performed as Corrective Action.Check Valves with O Rings Were Replaced ML20216G1201999-09-0909 September 1999 Rev 3 to Rbs,Cycle 9 Colr RBG-45110, Monthly Operating Rept for Aug 1999 for River Bend Station, Unit 1.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for River Bend Station, Unit 1.With ML20212C4601999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Nine Mile Point Nuclear Station,Unit 1.With ML20216E7031999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Monticello Nuclear Generating Plant.With ML20212D0431999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Brunswick Steam Electric Plant,Units 1 & 2 ML20216F5141999-08-31031 August 1999 Rept on Status of Public Petitions Under 10CFR2.206 ML20212C4501999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for LaSalle County Station,Units 1 & 2.With U-603267, Monthly Operating Rept for Aug 1999 for Clinton Power Station,Unit 1.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Clinton Power Station,Unit 1.With ML20210P9441999-08-10010 August 1999 Safety Evaluation Accepting Licensee Assessment of Impact on Operation of Plant,Unit 1,with Crack Indications of 2.11, 6.36 & 1.74 Inches in Three Separate Jet Pump Risers ML20210P9181999-08-10010 August 1999 Safety Evaluation Authorizing Request for Reliefs CIP-01,02, 06,07,08,09,10 & 11 (with Certain Exceptions) & 12-18,for Second 10-year ISI Interval.Request CIP-04 & 05 Would Result in hardship,CIP-03 Not Required & CIP-11 Denied in Part RBG-45087, Special Rept:On 990510,LPCI a & LPCS Injected Into Rv for Less than Two Minutes.Caused by Electrical Transient in One of ECCS Power Supplies.Operators Verified Reactor Cavity Level & Closed Injection Valves to Stop Injection1999-08-0606 August 1999 Special Rept:On 990510,LPCI a & LPCS Injected Into Rv for Less than Two Minutes.Caused by Electrical Transient in One of ECCS Power Supplies.Operators Verified Reactor Cavity Level & Closed Injection Valves to Stop Injection ML20210N2341999-08-0505 August 1999 SER Accepting Response to NRC GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issues (USI) A-46 ML20210Q0521999-08-0404 August 1999 Safety Evaluation Approving Relief Request 10 to License DPR-22 Per 10CFR50.55a(g)(6)(i).Inservice Exam for Relief Request 10,Parts A,B,C,D & E Impractical & Reasonable Assurance of Structural Integrity Provided ML20210K4721999-08-0303 August 1999 SER Accepting Licensee 180-day Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves RBG-45091, Monthly Operating Rept for July 1999 for River Bend Station, Unit 1.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for River Bend Station, Unit 1.With ML20210Q6611999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Monticello Nuclear Generating Plant.With ML20210R1191999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Bsep,Units 1 & 2 ML20210U4591999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Nine Mile Point, Unit 1.With U-603245, Monthly Operating Rept for Jul 1999 for CPS Unit 1.With1999-07-31031 July 1999 Monthly Operating Rept for Jul 1999 for CPS Unit 1.With ML20210R0671999-07-31031 July 1999 Monthly Operating Repts for July 1999 for LaSalle County Station,Units 1 & 2.With ML20211C9621999-07-26026 July 1999 ISI Summary Rept U-603232, Special Rept:On 990531 Lpms Was Declared Inoperable Due to Receipt of High Vibration & Loose Parts Alarm Which Did Not Clear.Lpms Was Restored to Operable Status on 990707 After Alignment & Tension on Recorder Tape Drive Was Adjusted1999-07-0909 July 1999 Special Rept:On 990531 Lpms Was Declared Inoperable Due to Receipt of High Vibration & Loose Parts Alarm Which Did Not Clear.Lpms Was Restored to Operable Status on 990707 After Alignment & Tension on Recorder Tape Drive Was Adjusted ML20210C1681999-07-0909 July 1999 Seventh Refueling Outage ASME Section XI Summary Rept ML20210C6391999-07-0202 July 1999 Rev 2 to River Bend Station,Cycle 9 Colr ML20209D0291999-07-0202 July 1999 Special Rept:On 990621,operator Identified That Number 11 Hydrogen Monitoring Sys (Hms) Chart Recorder Was Indicating Below Normal Operating Range.Cause Indeterminate.Licensee Will Complete Troubleshooting of Subject Hms by 990709 ML20209F7901999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Monticello Nuclear Generating Plant.With ML20210R1311999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Bsep,Unit 2 BSEP-99-0118, Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with ML20210B9081999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Nine Mile Point Unit 1.With RBG-45055, Monthly Operating Rept for June 1999 for River Bend Station, Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for River Bend Station, Unit 1.With U-603233, Monthly Operating Rept for June 1999 for Clinton Power Station,Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Clinton Power Station,Unit 1.With ML20209H1501999-06-30030 June 1999 Monthly Operating Repts for June 1999 for LaSalle County Station,Units 1 & 2.With ML20196J8031999-06-24024 June 1999 Rev 1 to Rbs,Cycle 9 Colr ML20209F8811999-06-0808 June 1999 Rev 1 to NMP Unit 1 COLR for Cycle 14 ML20207G2261999-06-0707 June 1999 SER Accepting Proposed Mod to Each of Four Core Shroud Stabilizers for Implementation During Current 1999 Refueling Outage at Plant,Unit 1 ML20195H0351999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Monticello Nuclear Generatintg Plant.With ML20196E2111999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Nmp,Unit 1.With 1999-09-09 |
Text
7v., ; ;; .! +
QSULZER BINEHAM: .196
, 2800 N W. Front Ave
- PO Box 10247
- FAX (503)226-5286
- ITT 4742014
[ 3 i p r G
. t April 27,'1990 i
U.--S. Nuclear. Regulatory Committee ,
Vendor. Program Branch
- Washington, D.'.C. 20555
Dear Sir or Madam:
Per the requirements of :10CFR Part 21, Sulzer Bingham pumps Inc. (formerly Bingham-Willamette Co.) advises of a defect ,
condition on a basic component supplied to Commonwealth Edison LaSalle Units 1 and 2.
1 -The condition was first observed on the Reactor Recirculation :
L pumps ini Unit 1A upon- a - maintenance disassembly during ,'
February:of 1987. The defects observed were axial cracks in the~ pump = shaft in the region immediately above_ the impeller.
Subsequent _ disassembly of the remaining- three (3) Reactor *
,. Recirculation pumps revealed similar conditions. The defects +
L .did not constitute a shaft failure.
Metallurgical evaluation indicated the most common cause of g ' crack growth as. thermal fatigue. At present the root cause of the thermal cycles which appear to be ' producing the cracking is not known.
The 'following list . represents the locations of reactor recirculation pumps supplied with this material.
LaSalle Units.1 and 2 Monticello Nine Mile Point 2 Brunswick 1 and 2 Hanford Unit 2 Clinton Riverbend m
9003220307 900427
/]f-
/
- gDR ADOCK0500g3 e a k !
e '*
SULZER BINGHAM '
N-'- U. S. Nuclear' Regulatory Committee Page 2' 7
Simultaneously. Sulzer Bingham Pumps Inc. will advise the nuclear facilities via our " Technical Advisory Bulletin" 82-9004-001 of this potential condition..
Each plant'.shall.be asked to correspond' directly -with Sulzer Bingham Pumps.Inc., Mr. . Stan Pace - Product Manager - Power Generation, .to evaluate and reach a determination as to further action.
- Regards, SULZER BINGHAM PUMPS f
Wayne D. Thomac
_m ,
Manager Corporate Quality CC: B. Ayres U. Bo11eter T. Morton P. McCullough G. Halas S. Pace G. Parks Joe Wood NRC File WDT:kp