PNP 2011-061, Voluntary Response to NRC Regulatory Issue Summary 2011-04: Preparation and Scheduling of Operator Licensing Examinations

From kanterella
Jump to navigation Jump to search
Voluntary Response to NRC Regulatory Issue Summary 2011-04: Preparation and Scheduling of Operator Licensing Examinations
ML112060503
Person / Time
Site: Palisades Entergy icon.png
Issue date: 07/22/2011
From: Gustafson O
Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PNP 2011-061, RIS-11-004
Download: ML112060503 (2)


Text

Entergy Nuclear Operations, Inc.

~ I~nter Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043 Tel 269 764 2000 Otto W. Gustafson Licensing Manager PNP 2011-061 July 22, 2011 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Voluntary Response to NRC Regulatory Issue Summary 2011-04:

Preparation and Scheduling of Operator Licensing Examinations Palisades Nuclear Plant Docket 50-255 License No. DPR-20

Dear Sir or Madam:

Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examinations, requests that licensees submit, on a voluntary basis, a NRC Form 536, Operator Licensing Examination Data. Estimates are requested for calendar years 2013 through 2016.

The purpose of these estimates is to assist the NRC in budgeting and scheduling resources.

In response to this request, Entergy Nuclear Operations, Inc. is providing the enclosed NRC Form 536 for the Palisades Nuclear Plant (PNP). PNP currently has examinations scheduled in 2012 for six reactor operators, five senior reactor operators-instant, and four senior reactor operators-upgrade. Examinations begin the week of June 25, 2012.

This letter makes no new commitments or revision to previous commitments.

Sincerely, OWG/bed

Attachment:

1. NRC Form 536 - Operator Licensing Examination Data CC Administrator, Region III, USNRC Project Manager, Palisades, USN RC Resident Inspector, Palisades, USN RC

ATTACHMENT 1 NRC FORM 536 OPERATOR LICENSING EXAMINATION DATA NRC FORM 536 US NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB NO 315 -0131 EXPIRES 10/31/2011 (10-2008) Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), US APERAT(IR

~ I ENSING Nuclear Regulatory 20555-0001, Commission, or by internet email toWashington, DC infocollects@nrc.gov, and EXAMINATION DATA to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid 0MB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY: Palisades Nuclear Plant, 27780 Blue Star Memorial Highway, Covert, MI 49043 NRC REGION III DOCKET 50-255 LICENSE DPR-20 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2013 CY2014 CY2015 CY2016 ESTIMATED NUMBER OF LICENSEE-PREPARED 0 1 0 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2013 CY2014 CY2015 CY2016 NUMBER OF REACTOR 0 0 6 OPERATORS 6 NUMBER OF SENIOR REACTOR 0 3 0 3 OPERATORS-INSTANT NUMBEROFSENIORREACTOR 0 3 0 3 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0 0 0 0 OPERATORS-LIMITED PROPOSED_DATES PRIMARY DATE N/A 6/2/2014 N/A 8/1/2016 ALTERNATE DATE NA 6/30/2014 N/A 9/26/2016 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY2012 CY2013 PROPOSED NUMBER March June September December March June September December ESTIMATED NUMBER OF 0 0 0 0 9 0 0 0 CANDIDATES Page 1 of 1