NPL-97-0087, Forwards Updated Unit 2 Startup Commitment List & Restart Commitment Summary .Documents Provide Progress Summary Update for Unit 2 Restart,Identified in

From kanterella
Jump to navigation Jump to search
Forwards Updated Unit 2 Startup Commitment List & Restart Commitment Summary .Documents Provide Progress Summary Update for Unit 2 Restart,Identified in
ML20136H036
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 03/13/1997
From: Dante Johnson
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NPL-97-0087, NPL-97-87, NUDOCS 9703190035
Download: ML20136H036 (175)


Text

Wisconsin Electnc POWER COMPANY Point Beoch Nuclear Plant (414) 755-2321 6610 Nuclear Rd., Two Rivers. WI 54241 NPL 97-0087 March 13,1997 Document Control Desk U. S. NUCLEAR REGULATORY COMMISSION Mail Station Pl-137 Washington, DC 20555 Ladies / Gentlemen:

DOCKET 50-301 RESTART DOCUMENTATION POINT BEACH NUCLEAR PI ANT. UNIT 2 We are enclosing copies of our updated PBNP Unit 2 Startup Commitment List and PBNP Unit 2 Restart Commitment Summary dated March 12,1997. These documents provide a progress summary update for the PBNP Unit 2 restart i.ssues which we identified in our December 12,1996 letter.

Sincerely, M

Douglas F. Johnson Manager -

Regulatory Services & Licensing hds i Enclosures /&hO l

cc: NRC Regional Administrator 9703190035 PDR 970313 ADOCK 05000301 P pop 180089 515555555555 um on-n a >ws, a

r POINT BEACH NUCLEAR PLANT UNIT 2 STARTUP COMMITMENT LIST March 12,1997 Status Update IDENTIFICATION AND RESOLUTION OF ISSUES PERTINENT TO REACTOR SAFETY The following actions will be taken prior to Unit 2 criticality, except as specifically noted. The scope of reviews will be examining the identified documents or items for accuracy and compliance with requirements. Should any reviews identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of those reviews will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Commitment Description Status ID Number Complete a detailed Unit 2 Containment Materiel Condition Assessment, addressing in progress.

I housekeeping, system walkdowns, materiel condition, and instrumentation. Extensive work inside Containment was conducted this outage due to the Steam Generator replacement project.

2 Walkdown all accessible Unit 2 and common Maintenance Rule systems for adequate visual In progress.

material condition.

Walkdown all accessible Unit 2 and common systems for outstanding work order tags. Work and independent 3 Note: The scope was expanded to include all accessible Unit I systems. closeout verification

, completed.

I Conduct as ouilt inspections of the electrical and I&C components on the Unit 2 CVCS and Work and independent I 4 CCW systems (Work Orders 9607322,9611140,9606548, and 9611139). closeout verification completed.

Complete Work Orders 9513222 through 9513225 to conduct inspections of Appendix R Work and independent 5 alternate power transfer switches. closecut verification completed.

Complete Work Order 9604151 to perform foreign material exclusion inspections on the Work and independent 6 Unit 2 4160V safeguards hus 2A-06 and breakers. closeout verification completed.

Complete a review ofI' nit 2 administrative controls implementing or referencing 'i ethnical in closecut verification 7 Specifications to ensure Technical Specification requirements are appropriately reflected in process.

tha administrative controls.

PageI

Review 20% of the Operations Technical Specification, insenice Test, and Operations In progress. Scheduled Refueling Test related surveillance procedures, with concentration on those involving major completion date is Mar. 28, 8 equipment. Upgrade as necessary to include appropriate initial conditions, return to senice 1997.

lineups, preperly specified independent verification, reviewing acceptance criteria, and Technical Specification implementation.

Review the In Senice Testing (IST) acceptance criteria for the remaining IST pumps to Work and independent 9 ensure that the IST acceptance criteria meets the design basis / accident analysis requirements. closeout verification Make any changes necessary as a result of this review. completed.

Review the In Senice Testing acceptance criteria for all IST valves to ensure that the IST Work and independent 10 acceptance criteria meets the design basis / accident analysis requirements. Complete closcout verification necessary operability evaluations, revise procedures, and resolve Unit 2 equipment completed.

discrepancies.

Complete the following regarding installed instrumentation used in the IST program: Work and independent closcout verification

. Identify the Unit 2 installed instruments used in the IST program. completed.

I1 . Review the performance of the identified instruments over the last 3 years.

. Review the suitability of the instrumentation for use in the IST program.

. Review all IST pump hydraulic data over the past y ear fbr adverse trends.

As necessary, make changes as a result of these actions.

Review 20% of the surveillance procedures associated with safety significant non-pump and in progress Scheduled valve components (such as heat exchangers and fans) to ensure that the surveillance completion date is Mar. 21.

12 acceptance criteria satisfy the requirements of the plant design basis / accident analysis. Make 1997.

changes as necessary as a result of this review.

Note: This has been expanded to a 100% review.

13 Review other operating procedures that contain maintenance activities and revise as In closcout verification necessary to ensure PMT and QC are properly addressed by those procedures. process.

Review equipment return to senice testing requirements prior to the following U2R22 mode Will occur approximately one change readiness reviews to ensure the required equipment is operable prior to changing week prior to each of the mode 14 modes: core reload, leaving cold shutdown, and the approach to criticality. changes.

Resieu 20% of the work orders performed since January 1.1995 on Unit 2 or common PSA in progress. Scheduled 15 safety significant systems (AFW, SW, EDG, I A,4.16 ks. gas turbine. and CCW) to verify completion date is Mar 13.

adequate PMT was performed to ensure system / component saf ety timetion. 1997.

rme2

=- _

_ _ . ~ _ _ - - . - _ _- - _. .. .. -. .- -.- -. . .. .- - - . . . .

16 Complete all Unit 2 Maintenance Rule related work order post-work, pre-PMT reviews prior On-going reviews in progress.

to the approach to criticality.

Review 50.59 screenings conducted in 1996. Upgrade those determined to require a 50.59 Review completed. Upgrading 17 evaluation. in progress. Scheduled  !

completion date is Mar. 31, 1997.

Review outstanding JCO's. Perform operability determinations and 50.59 evaluations In progress. Scheduled 18 needed to address the issues. completion date is Mar. 27, 1997.

Conduct a review of 50.59 evaluations from this outage. Ensure all conditions of the Initial review completed.

evaluations have been completed. Reviews of emergent 50.59 19 evaluations in progress.

Tracking completion of ,

conditions through the outage.

Review items from existing open item lists (e.g., NUTRK) to identify potentially degraded In progress. Scheduled ,

20 equipment. completion date is Mar.17, 1997.

Review open items from the Design Basis Document development program. In progress. Scheduled 21 completic 1 date is Mar.17, 1997.

All open operability evaluations Ihr Unit 2 and common equipment will be reviewed for In progress. This will continue 22 acceptable closure of the degraded equipment issue. Disposition outstanding issues in through the outage.

l accordance with 10CFR50.59 and Generic Letter 91-18.  ;

Review 20% of the Condition Reports closed since January 1,1995 which are associated In closecut verification with PSA safety significant systems for degraded equipment operability issues to ensure that process.

23 we have adequately identified and dispositioned operability issues.

Note: This has been expanded to a 100% review of PSA safety significant systems.

Complete an additional Outage Safety Review for the startup phase of the outage. In progress. Scheduled 24 completion date is Mar. 31, 1997.

Conduct an integrated review of all outage licensing commitments (50.59's. enthreement in progress. Scheduled 25 conference items, Technical Specification Change Requests. and Reload Safety Analysis) completion date is Mar. 31, Ensure all requirements are met. 1997.

Revise ORT-3 and DCS 3.1.11 to ensure Technical Specification 15.4.6.A.2 testing includes l Work and independent 26 dynamic loading of the EDG uith sequenced loads. p closcout verification

[ completed.

Page 3 I

27 Test all EDGs in accordance with revised ORT-3 and DCS-3.1.11. Return the electrical In closeout verification systems to normal alignment ,rior to leaving cold shutdown. process.

Resolve the containment penetration commitments, including: In progress. Scheduled 28 completion date is Mar. 31,

. CP-32 (Containment penetration for Auxiliary Charging line). 1997.

. Penetration thermal reliefissue.

29 Complete a 50.59 evaluation for the existing CCW supply to the RCP seals as a safety In closeout verification function. process.

Update the diesel generator loading calculation N-91-016 te properly reflect the loading of In progress. Scheduled 30 the Containment Fan Coolers. completion date is April 1, 1997.

Evaluate the adequacy of coordination on the 120 VAC instrument bus system through a in progress. Scheduled 31 50.59 or operability review. completion date is April 4, 1997.

Implement interim improvements for the Condition Reporting process, based on a review of In progress. Scheduled 32 assessments and identified recommendations for improving that process. completion datt. is Mar. 31, 1997.

33 Implement interim improvements for the 50.59 process to require that all screenings be either In closecut verification authored or reviewed by a member of the multi-disciplinary review team. process.

34 Upgrade Unit 2 operations checklists to include requirements for initials, time, and date. In closcout verification During the review, verify that the checklists are technically correct. process.

Revise applicable IST program documents to prevent equipment from being returned to in closcout verification  ;

35 service (declared operable) with vibrations in the alert range. process.

Revise NP 8.1.1, Work Order Processing, and NP 8.1.3, Post-Maintenance Testing to ensure in closecut verification 36 post-maintenance testing , operability testing, and surveillance test requirements are properly process.

addressed.

37 include return to service testing in the plant schedule, both outage and nonoutage. In clostout verification process.

Page4

CfQMPLETE PHYSICAL WORK WHICH SUPPORTS SAFE STARTUP A.ND POWER OPERATIONS  :

l Modifications which Point Beach Nuclear Plant has identified as being significant to safety and scheduled for compleiion in U2R22 will be in an accepted status (i.e., the applicable physical work completed, post-maintenance testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications. These modifications are. i Commitment Description Status  ;

ID Number 38 Modification 96-033 - replace control power transformers on Motor Control Centers in progress.

I 2B32 and 2B42.

Modification 90-048 - replace Boric Acid rind Reactor Makeup Water totalizers, replace Awaiting PMT. Scheduled 39 the CVCS control switch, replace flow indicators, and refurbish flow controllers. This completion date is Mar. 21, resolves an Operator workaround issue. 1997.

Modification 94-097 - remove six RCS loop drain valves. Awaiting PMT. Scheduled 40 completion date is Mar. 31, 1997.

l 41 Modification 92-141 - relocate the RilR flow control valve controllers on 2CO3 for in closcout verification human factoring. process.

Modification 96-073 - seismically upgrade CCW, SI, RiiR, and RHR/ letdown piping Work and independent 42 supports and remove an AFW snubber. closcout verification completed.

Modification 94-066 - install a soft seat in containment isolation valve 2SI-834D, and in closcout verification 43 add a re"ef valve and pressure regulator in the nitrogen supply line to the SI process.

accumulators. This resolves an Operator workaround issue.

44 Modification 96-065B - seismically upgrade the Refueling Water Storage Tank in closecut verification recirculation line. process.

Modification 96-054 - install pressure gauges in the service water return header from the in progress. . Scheduled 45 Emergency Diesel Generator GOl and GO2 glycol coolers, and reset the throttle valves completion date is Mar. 28, in that line. 1997.

Modification 96-022 - install a new 125 VDC feed to 480V safeguards bus 2B03. Erk and independent 46 closeout verification completed.

Modification 94-055 - add seismic supports to the raceway between risers 56 and 62 on Lik and independent 47 C04 (Reactor and Primary Plant Control lioard). t hweout verification completed.

Page 5

! Modification 96-068B - eliminate containment heating steam and condensate return in progress. Scheduled 48 containment isolation valves. completion date is Mar.14, 1997.

Modification 96-053 - replace an elbow in the west service water header. In progress. Scheduled 49 completion date is Apr. 4, 1997.

50 Modification 95-070 - seismically upgrade the containment cooling fans and filters. In closeout verification process.

51 Modification 96-026 - install, delete, and modify supports for feedwater, main steam, and In closeout verification Si system piping for the 79-14 project. process.

Modification 96-058 - move Power Plant Computer System alarms to the exterior of C- Work and independent 52 20 panels, closeout verification completed.

Modification 94-095 - replace 8 Main Steam Condenser steam dump valves with Awaiting PMT (PMT will be 53 improved design. completed following reactor startup).

Modification 95-029 - replace Si accumulator level transmitters. Awaiting PMT. Scheduled 54 completion date is Apr.1, 1997 t 55 Modification 95-035 - modify Containment Spray additise tank controller circuit. In closcout verification process.

Modification 96-063 - replace 345 KV breakers (3-4,4-5, and 142). Awaiting PMT (PMT will not 56 be completed until Unit 2 is on-line).

Modification 96-069 - replace four breakers (1 Y-06-01,1 Y-06-03,1 Y-06-05, and 1 Y In closcout verification  !

57 11) associated with instrument bus lY-06. process.

Modification 95-058'O - repair Steam Generator intennediate leg supports. This may be Awaiting PMT (will not be 58 resolved through analysis. completed until the unit is heated-up).

59 Modification 96-070 - replace molded case circuit breakers associated with instrument In closecut verification <

buses 2Y-05 and 2Y-06. process.

Page 6

The work and testing associated with these Work Orders will be completed prior to the associated component / system being declared operable.

Emergent Work Orders associated with Maintenance Rule Risk Significant Systems which Point Beach Nuclear Plant defines as priority level 1 to 4 will be completed prior to Unit 2 criticality.

Commitment Description Status ID Number Work Orders 9601506,9602502,9603921,9611267,9611278, and 9611755 - replace in progress. Scheduled 60 proximity switches and targets with an improved design and overhaul the Fuel Transfer completion date is Mar. 21, Cart to enhance control system operation. This resolves an Operator workaround issue. 1997.

Work Orders 9613568 and 9613569 - provide bonnet pressure locking relief for the SI- Work complete. Determining 857A and SI-857B valves (interface valves between RIIR and High Ilead SI) on Unit 2. additional PMT, and procedures 61 are being revised. Scheduled completion date is Mar.15, 1997.

Work Order 9611757 - correct the leakage which leads to boric acid buildup in the Awaiting PMT. Scheduled 62 cylinder blocks of"B" Charging Pump. completion date is May 15, 1997.

Work Order 9603532 - repair the handswitch f or 2P-2A, the "A" Charging Pump. Anaiting PMT. Scheduled 63 completion date is Mar. 28, 1997.

Work Orders 9611624 through 9611626 - replace existing pneumatic turbine generator Work is scheduled. The f 64 circuitry time delay relays with plug-in, electronic time delay relays. scheduled completion date is Mar. 31,1997.

Work Order 9606626 - reinstall switches on the Unit 2 Containment hatch third door to Work and independent closeout 65 allow monitoring of door status. verification completed.

l l 66 Work Order 9611052 - replace the 2P-10B switch. the "B" RllR Pump control switch. In closcout serification process.

Work Orders 9611198 and 9611199 - repair the body-to-bonnet boric acid leak on CV- Awaiting PMT. Scheduled 67 307 B (lowside tap for "B" RCP #1 seal d'p) and CV-308B (lap seal d/p for "B" RCP). completion date is May 12.

1997.

l Page 7

The following actions will be completed to correct Operator workarounds prior to Unit 2 csiticality, except as specifically noted:

Commitment Description Status ID Number Repair valve AR-3511 per Work Order 9513340. The Unit 2 priming air ejector is blank Awaiting PMT. Scheduled 68 flanged due to air in-leakage through the condenser air removal isolation valve, AR- completion date is May 15, 3511. 1997.

Repair the drain valve for the heating steam moisture separator per Work Order 9613451. Work is scheduled. Scheduled 69 The Unit 2 heating steam moisture separator level has been difficult to maintain during completion date is Apr. 7.1997.

normal operations, and frequent alarms were received due to low level. This will be tested following Unit 2 startup.

Install a new level control system for the brine tank (T-118) per Modification 92-008*Q. In closecut verification process.

70 The tank overflows because the installed automatic level control system is not effective, and there is no high level alarm for the tank.

Repair MS-249, the Unit 2 steam line sample valve, per Work Order 9603128. The Awaiting PMT. Scheduled 71 valve had a packing leak which required steam header sampling to be shifted to the Il completion da :is May 15, steam header. 1997.

Repair alarm switch 21 S-2511 per Work Order 9605711. The Unit 2 D MSR level was Awaiting PMT. Scheduled 72 being maintained low in the band due to level oscillations and a steam leak from the completion date is May 17, alarm switch. 1997.

Repair 2P116, the Unit 2 lloric Acid Recirculation Pump, per Work Order 9603130. It Work is scheduled. Scheduled 73 has a significant seal leak. completion date is Mar. 21, 1997.

e e

Page 8

f PERSONNEL AND LICENSING READINESS-The following actions will be completed prior to Unit 2 criticality:

Commitment Description Status ID Number Each operating crew will receive simulator training to gain proficiency in casualty in progress. Scheduled 74 response, the expected response of the newly installed steam generators and reactor core, completion date is Mar.15, and placing the turbine on-line. 1997.

Revise the initial and requalification operator training plans to include a review of the Conducting independent 75 administrative procedures identified as significant to daily operation of the plant during closcout verification.

each two year operations training plan.

Conduct roundtable discussions with all MSS \SS\DTA personnel regarding conservative in progress. Scheduled 76 decisionmaking, Technical Specification interpretations. and lessons learned from recent completion date is Mar.14, regulatory communications and perspectives. Review outlier Technical Specification 1997.

interpretations for interim applications.

Comnlete the procedure changes and training associated with the new Technical in progress. Scheduled 77 Specification on ECCS regarding the new Containment integrity Analysis. completion date is Mar. 28, I997.

Communicate specific expectations regarding AFW rnd EDG status control to Operators. In progress. Scheduled 78 completion date is Mar.15.

1997.

79 Restore a proceduralized capability to operate the Containment Spray Pumps in the in progress. Scheduled recirculation mode of the ECCS. completion date is Apr.1.1997.

Obtain amendments requested by Change Requests 188 and 189 related to Steam in progress. Scheduled Generator replacement; 192 related to Service Water operability; and 194 related to 1.ow completion date is Mar. 25, 80 Temperature Overpressurization limits. This will include resolution ofissues related to 1997.

Control Room and offsite dose evaluations fbr the analped events.

n,yc "

7 Submit the following requests for license amendments resulting from the review of In progress. Schetiuled existing Technical Specification interpretations: completion date is Mar. 25, 1997.

. Revise the maximum acceptable power level when crossover steam dumps are inoperable (TS 15.3.4.E).

81 e Revise requirements for offsite power lines availability to address adequacy (TS I 5.3.7. A.1.a).

. Remove allowances in TS 15.3.1.A.I.a for single reactor coolant pump operation.

. Appropriately modify the minimum required boron concentration in the Refueling Water Storage Tanks.

Status Exnlanation:

In closeout verification process - work and PMT, as applicable, have been reported as complete. The independent review by Duke Engineering is either in progress or issues from that review are being addressed.

Work and independent closecut verification completed - the issue is ready for NRC review.

Page 10

4 l

Point Beach Nuclear Plant Unit 2 Restart Commitment l

$ Summary (March 12,1997) l l

l Commitment ID#: 1  ;

Commitment Descriptium Complete a detailed Unit 2 Containment Materiel Condition

, Assessment, addressing housekeeping, system walkdowns, materiel condition, and

! instrumentation. Extensive work inside Containment was conducted this outage due to l the Steam Generator replacement project, so this warrants increased scrutiny during l Containment closecut.  !

Should this assessment identify either generic issues or significant discrepancies which l could negatively impact reactor safety, the scope of the assessment will be expanded. i l' Where discrepancies are identified, appropriate corrective and preventive actions will be j taken commensurate with their safety significance. I l

Completion Timingt This should be completed prior to Unit 2 leaving cold shutdown. I If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.  !

. Criteria to Closcout This Item:

1. Completion of the assessment defined in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart Issues Coordinator:
  • A summary of the scope of the materiel condition assessment and when it was conducted (report using the NUTRK system - NUTRK U2R22 RESTART Action
  1. 1).
  • A copy of documentation used to conduct the assessment.
  • A summary which addresses significant items / issues identified during conduct of the assessment and how they were resolved (can simply reference Condition j'

Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART i Action # 1). )

- 3. The Restart Issues Coordinator has verified that the:

T e Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the assessment are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

I

c l

l l

4. Completion of an independent verification. l f Statils l

l This commitment addresses the conditions of systems and components inside Unit 2 containment. This is being accomplished through 4 mechanisms:

  • Use of the System Restoration Procedure (NP 2.3.4), which formalizes a systematic approach to restoring 25 systems following extensive work and outages. I8 have been completed. 2 (Containment and Fuel llandling) of the remaining 7 must be completed prior to core loading.
  • The thorough inspection for inateriel condition and operational readiness as part of the proceduralized, normal startup sequence (using Checklist 20L
  • Steam Generator Replacement Project walkdown and closeout 01 containment. I his has been completed.
  • Sargent and Lundy's detailed walkdown of the Instrument Air System. This has been completed.

Discrepancies identified are being resolved through the Condition Reporting and work order processes.

A new scheduled completion date is being developed.

I i

2

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 2 Commitment

Description:

Walkdown all accessible Unit 2 and common Maintenance Rule systems for adequate visual materiel condition.

i Should these walkdowns identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the walkdowns will be expanded.

Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

1 Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown. I If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Item;

1. Completion of the walkdowns defined in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart Issues Coordinator:

. A summary of the scope of the walkdowns and when they were conducted (report using the NUTRK system - NUTRK U2R22 RESTART Action # 2).

l

. A copy of documentation used to conduct the walkdowns.

. A summary which addresses significant items / issues identified during conduct of the walkdowns and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 2).

3. The Restart Issues Coordinator has verified that the:

l

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately abos e).

. Significant items / issues identified during conduct of the walkdowns are being tracked in a tracking system which is being reviewed per Restart Commitment st22. 1

4. Completion of an independent verification.

I 3

I

l l

Status:

The Maintenance Rule systems (68 of them) have been identified, and this conunitment is l being accomplished through two means: )

1 e 25 Maintenance Rule systems are being walked-down using the System Restoration Procedure (NP 2.3.4) outside containment.

. The remaining Maintenance Rule systems will be independently walked-down for l visgal assessment of materiel condition by the associated system engineers. 1 Discrepancies identified will be resolved through the Condition Reporting and work order l processes.

l l

A new scheduled completion date is being developed. j l

l 4 I l

)

i

1 Point Beach Nuclear Plant Unit 2 Restart Commitment i Summary (March 12,1997) i l

Commitment ID#: 3 i Commitment Descrintiam Walkdown all accessible Unit 2 and common systems for outstanding work order tags.

Should these walkdowns identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the walkdowns will be expanded.

Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Item:

1. Completion of the walkdowns defined in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart issues Coordinator:
  • A summary of the scope of the walkdowns, when they were conducted, and what i was found (report using the NUTRK system - NUTRK U2R22 RESTART Action )
  1. 3).

. A summary which addresses significant items / issues identified during conduct of the walkdowns and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) .QR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 3).

3. The Restart issues Coordinator has verified that the:
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately abm e).
  • Significant items / issues identified during conduct of the walkdowns are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

5

. , _ . _ _ _. . . -..u. __ __. _ . _._ . _ _ _ . . ____ _ _ _ _ _ _ _ . m.___u _ 2.,-. .. __. . _ _ . . . _ 4 ._ . .. .

Status:

The walkdowns were completed from January 20-30,1997, and the scope was to identify i every work order tag / sticker in the plant and verify its status (restricted to work orders {

initiated prior to January 1,1997). This effort was expanded to include aII Unit 1 l systems, except for those in Containment (work order tags / stickers are not hung in Containment).

Condition Reports 97-0386 through 97-0391 were written to document discrepancie.s.

Verified closed. The associated documentation was provided to the NRC.

l l

1 l

l l

l l

6

4 Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) 4 2

Commitment ID#: 4 Commitment

Description:

Conduct as-built inspections of the electrical and I&C components on the Unit 2 CVCS and CCW systems (Work Orders 9607322,9611140, 9606548, and 9611139). This will ensure that the associated drawings will be accurate.

Should these as-built inspections identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the as-built

inspections will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

Critcha to Closcout This Item:

1. Completion of the as-built inspections associated with the listed work orders.
2. Tha Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the closed work orders.
  • A summary of the significant items / issues identified during conduct of the work orders and how they were resolved (can simply reference Condition Report l numbers or other tracking mechanisms) DR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # .

4).

3 The Restart Issues Coordinator has verified that the:

  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work orders.

]

. Significant items / issues identified during conduct of the work orders are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

7

l Statuu Verified closed. The associated documentation was provided to the NRC on February 10 and 12,1997.

There were no safety significant issues or discrepancies identified during conduct of the activity.

l I

8

Point Beach Nuclear Plant Unit 2 Restart Commitment '

Summary (March 12,1997) .

I l

Commitment ID#: 5 Commitment Descriptioru Complete Work Orders 9513222 through 9513225 to conduct inspections of Appendix R alternate power transfer switches.

The inspections will determine whether an E shaped retaining ring on the arcing contact assembly of some ASCO switches is missing. Condition Report 95 602 documents the missing E clip issue. Seismic qualification testing has shown that the switches pass the baseline functional testing even without the E shaped retaining rings installed.

Should these inspections identify either generic issues or significant discrepancies which i' could negatively impact reactor safety, the scope of the inspections will be expanded.

Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

r Completion Timine This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

r Criteria to Closcout This Item:

1. Completion of the work associated with the listed work orders.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the closed work orders.

  • A summary of the significant items / issues identified during conduct of the work orders and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

5).

i

3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is  ;

required to forward to the Restart issues Coordinator (see immediately above).

i 9

1 I

e Duty Shift Supervisor's signature and date is on the " Equipment iteturn to Service" section on page 2 of the associated work orders.

  • Significant items / issues identified during conduct of the work orders are being l tracked in a tracking system which is being reviewed per Restart Commitment n22.
4. Completion of an independent verification.

Status:

1 i

Verified closed. The associated documentation was provided to the NRC on February 12.

1997.

l There were no safety significant issues or discrepancies identified by the Responsible j Person. No E-clips were found to be missing. l l

l i

l l

l 10

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) ,

l Commitment ID#16 Commitment

Description:

Complete W ork Order %04151 to perform foreign material exclusion inspections on the Unit 2 4160V safeguards bus 2A-06 and breakers. Debris found in switchgear prompted these inspections.

)

Should these inspections identify either generic issues or significant discrepancies u hich could negatively impact reactor safety, the scope of the inspections uill be expanded Where discrepancies are identified, appropriate corrective and presentive actions will be taken commensurate with their safety significance.

Guttpletion Timing: This should be completed prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work order.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

l

. A copy of the closed work order.

  • A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identitled (report using the NUTRK system - NUTRK U2R22 RESTART Action # 6).
3. The Restart issues Coordinator has verified that the:

e Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.

. Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Ii

Status:

1 Verified closed. The associated documentation was provided to the NRC. l I

f l

1 J

I l I

1 4

i 1

j i i

l

\

)

]

s I

l 1

12

1 Point Beach Nuclear Plant Unit 2 Restart Commitment  !

Summary (March 12,1997) l l

1 l

Commitment ID#: 7 l l

Commitntent Description 1 Complete a review of Unit 2 administralise controk implementing or referencing Technical Specifications to ensure Technical Specilication requirements are appropriately reflected in the administrative controls.

The scope of this review will be examining the identified documents for accuracy and l compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

This commitment is also a subset of Enforcement Conference Commitment item # 3.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference Commitments Coordinator which addresses (report using the NUTRK system): 1 e When the review occurred. l e Whete the Technical Specification requirements are reflected in the administrative controls (i.e., a matrix or equivalent).
  • Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those j documents sent to the Enforcement Conference Commitments Coordinator.
  • Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified.

13

__ _ ._ ~ _ . - - . _ _ .

l

3. The Restart issues Coordinator or the Enforcement Conference Commitments Coordinator have verilled that the-
  • Restart issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see ,

immediately above).

. Significant items / issues identified during conduct of the review are being tracked I in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Slatus This is in the closecut verification phase.12 Condition Reports are being written on possible procedural inadequacies and other administrative deficiencies.

This involves ensuring that all surveillances in Technical Specifications section 15 A are implemented by plant procedures. In addition, this review ensures that each surveillance has an associated LCO (from Techn.ical Specifications section 15.3). ,

1 I

14

l l

i Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) 1 l

Commitment ID#: 8 i

Cmmnitment

Description:

Review 20% of the Operations Technical Specification.

l Inservice Test, and Operations Refueling Test related surveillance procedures. with concentration on those involving major equipment. Upgrade as accessary to include appropriate initial conditions, return to service lineups, properly specified independent verification, reviewing acceptance criteria, and Technical Specification implementation.

The population considered for this commitment will be the Unit 2 and common Operations Technical Specification, inservice Test, and Operations Refueling Test related surveillance procedures.

The scope of this review will be examining the identified documents for accuracy and compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies which could negatively

~

impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

The Restart Issues Coordinator will work with the Responsible Person to ensure the sampling methodology creates a 20% population which is both random and representatis e of the entire population.

This commitment is also a subset of Enforcement Conference Commitment item # 17.

Cmnpletion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criterin to Closcout This Item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference Commitments Coordinator which addresses (report using the NUTRK system):

. When the review occurred.

  • The total number of Operations Technical Specification, Inservice Test. and Operations Refueling Test related surveillance procedures.

15

. Which specific surveillances were reviewed (i.e., the 20%). The surveillance procedure number for each of these must be included in this summary. Also, provide a copy of each changed or created procedure to the Enforcement  !

Conference Commitments Coordinator. 1

  • Surveillances which were changed or created as a result of this review. The surveillance procedure number for each of these must be included in this summary.

Also, provide a copy of each changed or created procedure to the Enforcement Conference Commitments Coordinator.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified.

3. The Restart issues Coordinator or the Enforcement Conference Commitments Coordinator have:

. Verified that the Restart issues File includes the summary which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator.

. Collected and included in the Restart issues File a copy of each surveillance changed or created as a result of this review.

. Verified that the significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status The upgrading of the 20% sampling is in progress; those procedures are in the review and approval process. No safety significant issues have been identified.

The scheduled completion date is March 28,1997.

16

l Point Ileach Nuclear Plant Unit 2 Restart Commitment Sum mary (March 12,1997) i Commitment ID#: 9 i Commitment

Description:

Review the In Service Testing (IST) acceptance criteria for the remaining IST pumps (CCW, Charging, Boric Acid Transfer, CR Chill Water, CSR Chill Water, SFP Cooling, and FO Transfer pumps) to ensure that the IST acceptance criteria meets the design basis / accident analysis requirements. Make any changes necessary as a result of this review.

The work has already been completed for the SI, RHR, AFW. SW, and Containment Spray pumps (the original group), so they are not included in this commitment.

The scope of this review will be ensuring that the IST acceptance criteria meets the design basis / accident analysis requirements. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

This commitment is also Enforcement Conference Commitment item # 39.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference Commitments Coordinator which addresses (report using the NUTRK system):

e When the review occurred.

. Which specific documents were reviewed. The document number for each of these must be included in this summary.

  • Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Enforcement Conference Commitments Coordinator.

17

ea

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) M a statement that there were none identified.

3. The Restart issues Coordinator or the Enforcement Conference Commitments Coordinator have verified that the:

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).

. Significant items / issues identified during conduct of the review are being tracked 4

in a tracking system which is being reviewed per Restart Commitment u22.

4. Completion of an independent verification.

Status:

)' Verified closed by the Enforcement Conference Commitments Coordinator. The pumps were all operating satisfactorily. The associated documentation was provided to the NRC in the January 24,1997 weekly management meeting.

5 i

18

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 10' Commitment

Description:

Review the in Service Testing acceptance criteria for all IST valves to ensure that the IST acceptance criteria meets the design basis / accident analysis requirements. Complete necessary operability evaluations, revise procedures, and resolve Unit 2 equipment discrepancies.

The scope of this review will be examining the associated documents for accuracy and compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

This commitment is also Enforcement Conference Commitment item u 40.

Completion Timing: This will be completed prior to January 17,1997. If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications. the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference Commitments Coordinator which addresses (report using the NUTRK system):

. When the review occurred.

. Identification of which valves which are in the IST Program. l

. Which specific documents were reviewed. The decument number for each of these must be included in this summary. j

. Documents initiated or changed as a result of this review The identification number for each of these must be included in this summary, and a copy of those documents sent to the Enforcement Conference Commitments Coordinator.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) DR a statement that there were none identified.

19 i

3. The Restart Issues Coordinator or the Enforcement Conference Commitments Coordinator have verified that the :
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).
  • Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment 2122.
4. Completion of an independent verification.

Status:

Verified closed by the Enforcement Conference Commitments Coordinator. The associated documentation was provided to the NRC in the January 24,1997 weekly management meeting.

1 l

l 4

l 20

i Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 11 Commitment

Description:

Complete the following regarding installed instrumentation used in the IST program:

. Identify the Unit 2 installed instruments used in the IST program.

. Review the performance of the identified instruments over the last 3 years.

  • Review the suitability of the instrumentation for use in the IST program.

. Review all IST pump hydraulic data over the past year ihr adverse trends.

As necessary, make changes as a result of these actions. l Should these reviews identify either generic issues or significant discrepancies w hich  ;

could negatively impact reactor safety, the scope of the reviews will be expanded. Where i discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

This commitment is also Enfbreement Conference Commitment Item # 43.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Item:

1. Completion of the reviews defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference Commitments Coordinator which addresses (report using the NUTRK system):

. When the reviews occurred.

. Identification of the Unit 2 installed instruments used in the IST program.

. Documents initiated or changed as a result of these reviews. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Enforcement Conference Commitments Coordinator.

. Results of the reviews.

21

e l Significant items / issues identified during conduct of the reviews and how they '

were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified.

3. The Restart issues Coordinator or the Enforcement Conference Commitments Coordinator have verified that the:

e Restart Issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).

  • Significant items / issues identified during conduct of the reviews are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

Status:

1 1

Verified closed by the Enforcement Conference Commitments Coordinator. The associated documentation was provided to the NRC in the January 24,1997 weekly l

management meeting. '

l l

22

i

)

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 12 Commitment Descriptiorn Review 20% of the surveillance procedures associated with safety significant non-pump and valve components (such as heat exchangers and fans) to ensure that the surveillance acceptance criteria satisfy the requirements of the plant design basis / accident analysis. Make changes as necewary as a result of this review.

The population considered for this commitment will be the Unit 2 and common surveillance procedures associated with safety significant non-pump and vais e components (such as heat exchangers and fans).

The scope of this review will be examining the identified documents fbr accuracy and compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

The Restart issues Coordinator will work with the Responsible Person to ensure the sampling methodology creates a 20% population which is both random and representative of the entire population.

This commitment is also Enforcement Conference Commitment Item # 47. ,

i Completion Timinga This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference Commitments Coordinator which addresses (report using the NUTRK system):

. When the review occurred.

. The total number of surveillance procedures associated with safety significant non-pump and valve components (such as heat exchangers and fans). The surveillance procedure number for each of these must be included in this summary.

23

l

. Which specific surveillances were reviewed (i.e., the 20%). The surveillance i procedure number for each of these must be included in this summary. l

. Surveillances which were changed or created as a result of this review The surveillance procedure number fbr each of these must be included m this summm y l

. Significant items / issues identified daring conduct of the review and how they weie resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified.

3. The Restart Issues Coordinator or the Enforcement Conference Commitments Coordinator have:

1

. Verified that the Restart issues File includes the summary which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).

  • Collected and included in the Restart Issues File a copy of each surveillance changed or created as a result of this review.

. Verified that the significant items / issues identified during conduct of the review are be:ng tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Sinhts This is in progress. The scope of this effort has increased to where 47 total Unit 1 and Unit 2 surveillance procedures (100% of the surveillance procedures associated with safety significant non-pump and valve components) are being reviewed prior to the scheduled completion date. Four Condition Reports have been initiated as a result of this review (97-0166,97-0548,97-0573, and 97-0575).

The scheduled completion date is March 21.1997.

24

d i

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 13 Commitment

Description:

Review other operating procedures that contain maintenance activities and revise as necessary to ensure PMT and QC are properly addressed by those

procedures. This will be done for Unit 2 operating procedures.

The scope of this review will be examining the identified documents ihr accuracy and

, compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies uhich could negatis eh j '

impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with i their safety significance.

This commitment is also Enforcement Conference Commitment item # 51.

Completion Timing: This will be completed prior to January 31,1997. Ifsome i systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

! Criteria to Closcout This item:

i

1. Completion of the review delined in the " Commitment Description" section.

l 2. The Responsible Person has forwarded a summary to John Palmer (the Entbreement Conference Commitments Coordinator) which addresses (report using the NUTRK system):

. When the review occurred.

i . Which specific operating procedures were reviewed. The operating procedure

) number for each of these must be included in this summary. Send a copy of the index review checklists to the Enforcement Conference Commitments Coordinator.

>

  • Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those

. documents sent to the Enforcement Conference Commitments Coordinator.

  • Significant items / issues identified during conduct of the review and how they were resoived (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified.

25

3. The Restart Issues Coordinator or the Enforcement Conference Conunitments Coordinator have verified that the:

. Restart issues File includes the documents which the Responsible Person is required to fonvard to Enforcement Conference Commitments Coordinator (see immediately above). )

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

1 Stainst I

This is in the closeout verification process.

781 procedures were reviewed for maintenance activities. Of these, a total of 70 procedures were determined to require immediate, permanent revision (67 for PMT; 15 for QC). Condition Reports have been submitted for the 70 procedures to address ,

operability determinations. Another 81 procedures will be controlled sia a temporary l change process which ensures that the procedures will not be used until resiewed f or (p and PMT. I 1

1

. All of the following procedure types were reviewed: 01. OP, TS, IT. PC, and RF e RP series procedures excepting RP-7 and RP-8 were reviewed (those will be so reviewed and revised prior to the next ISFSI cask load). Procedure holds have been placed on these to ensure they are not used before.

. Unit 1 ORT procedures excepting 3. 3A,3B,3C,9 (and appendices),10, and 17 (those will be so reviewed and revised prior to the next use). Procedure holds have been placed on these to ensure they are not used before.

. Unit 2 ORT procedures excepting ORT 3 A and 3B (those will be so reviewed and revised prior to the next use) and ORT 9 (and appendices),10, and 17 (those will be so reviewed and revised prior to Unit 2 restart). Procedure holds have been placed on these to ensure they are not used before.

Two condition reports have been written as a result of this activity: CR 97-0238 and CR 97-0255.

26

.. .. .= - . - . - .- .-- - -- - - -- .- -

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) 1 l

Commitinent ID#: 14 Commitment

Description:

Review equ:pment return to service testing requirements l prior to the following U2R22 mode change readiness reviews to ensure the required equipment is operable prior to changing the following modes: core reload. leasing cold 1 shutdown, and the approach to criticality.

4 Should this review identify either generic issues or significant discrepancies which could 4

negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken l commensurate with their safety significance.

This commitment is also Enforcement Conference Commitment item # 53.

Completion Timing: This will be completed approximately one week prior to core i loading, prior to leaving cold shutdown, and prior to the approach to criticality.

Criteria to Closcout This Itenu

1. Completion of the three reviews defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Enforcement Conference
Commitments Coordinator which addresses (report using the NUTRK system): 1 1

.

  • When the reviews occurred,

! . Copies of documents used to perform the reviews. I

. Results of the reviews.

e Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking l mechanisms) QR a statement that there were none identified.

3. The Restart Issues Coordinator or the Enforcement Conference Commitments 1

Coordinator have verified that the:

e Restart Issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see

immediately above).

1 e Significant items / issues identified during conduct of the reviews are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

a 27

i

4. Completion of an independent verification.

Status:

The readiness reviews will occur shortly belbre each of the three major mode changes (core loading, leaving cold shutdown, and the approach to criticality). These reviews are scheduled activities in the Major Item Work List and are " predecessors" to each plant '

condition.

l t

l 4 i 4 l 1

1 l

i i

1 i

28

l Point Ileach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l Comntitment ID#: 15 l Commitment Descriplimu Review 20% of the work orders peribrmed since January I.

l' 1995 on Unit 2 or common PSA safety significant systems ( AFW, SW. EDG, I A,4.16 kv, gas turbine, and CCW) t ' verify adequate PMT was performed to ensure system / component safety function.

i Approximately 80% of the work orders at Point Beach Nuclear Plant are maintenance

! work orders, and the original commitment focused on maintenance work orders alone.

The scope of this review has been expanded to address the non-maintenance work orders i 2 also.  :

4 l

i i The scope of this review will be examining the identified documents for accuracy and compliance with requirements, per the criteria in the above paragraph. Should this j review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

The Restart Issues Coordinator will work with the Responsible Person to ensure the sampling methodology creates a 20% population which is both random and representatis e of the entire population.

Completion Timingt This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Ittml

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 15):

. When the review occurred.

. The total number of work orders performed since January 1,1995 on Unit 2 or common PSA safety significant systems (AFW, SW, EDG, I A,4.16 kv, gas 29

turbine, and CCW). The work order number for each of these must be included in this summary.

  • Which specific work orders were reviewed (i.e., the 20%). The work order number ihr each of these must be included in this summary.

. Work orders and other documents initiated or changed as a result of this review.

The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart Issues Coordinator fbr inclusion in the Restart Issues File (fbr the work orders, only fbrward pages 1 and 2).

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none idemitied.

3. The Restart issues Coordinator has verified that the
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately abos e).
  • Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

Status:

The review of the 20% sample has been completed, with the following results:

. 10 Quality Condition Reports and 9 Observations were written to address issues  !

identified in the reviews.

  • Inadequate PMT was identified in 14 of the 409 work orders inspected. l Based on the results of operability determinations for the Quality Condition Reports (no operability concerns were identified) and an assessment of the re.mitications of the i discrepancies identified, the sample size is not planned to be expanded.

Documentation of this effort is scheduled to be completed by March 13.1997.

i l

30 A

t Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) i Commitment ID#: 16 Commitment

Description:

Complete J Unit 2 Maintenance Rule related work order post-PMT (i.e., post-work, pre-PMT) reviews prior to the approach to criticality.

l l

The scope of this review will be examining the identifid documents for accuracy and compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to the i nit 2 approach to criticality.

Criteria to Closcout T. bis Item:

1. Completion of the reviews defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 16):
  • When the reviews occurred.
  • Documents initiated or changed as a result of these reviews. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart Issues Coordinator for inclusion in the Restart Issues File.

. Significant items / issues identified during conduct of the reviews and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) DJ1 a statement that there were none identified.

3. The Restart Issues Coordinator has verified that the :

. Restart issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the reviews are being tracked I in a tracking system which is being reviewed per Restart Commitment #22.

f 4. Completion of an independent verification.

31 l

1 l

f i

1 Status:

The review is in progress, occurring as work orders become available. As this is a )

continuous process, the scheduled completion date for this commitment will coincide I with the approach to criticality.

'. These reviews occur between the time maintenance is reported complete and w hen the l PMT is actually accomplished (so as to ensure the proper PMT is done for the work performed). I s

i 1

i i

i i

I 32

.-;.4 W. 4 -.di. w. M. 4 m._md. + w mm..__i4-a_a.a _&4._,a a ..e _ hau A * - . - ~ . . . - . M. .a.A -. m..1M A m. :n a.a . -. Jam + a.--.a.aA m I

Point Beach Nuclear Plant Unit 2 Restart Commitment Sum mary (March 12,1997)

Commitment ID#: 17 i

Commitmen!

Description:

Review 50.59 screenings conducted in 1996. Upgrade those l determined to require a 50.59 cvaluation. This will be done for all 50.59 screenings, not j 4 just those involving Unit 2. )

, 1 During November 1996, QA auditors reviewed the 50.59 and 72.48 safety evaluation  ;

processes per QA audit A-P-96-17. The auditors reviewed two hundred 50.59 screenings l and identified six which required a full 50.59 evaluation and another six which were

questionable. None of these were found to involve an Unreviewed Safety Question.

The scope of this review will be examining the identified documents for accuracy and compliance with requirements. Should this review identify either generie issues or l significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate correctis e and preventive actions will be taken commensurate with their safety significance. 1 l Completion Timing: This should be completed prior to the Unit 2 approach to ,

i criticality. If some systems / components addressed per this commitment are required to be operable before that mode change per Technica Specifications, the applicable portions of this commitment should be completed earlier.

4 Criteria to Closcout This Item:

! 1. Completion of the review defined in the " Commitment Description" section.

1

2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator

! which addresses (report using the NUTRK system - NUTRK U2R22 RESTART i Action # 17):

l . When the review occurred.

1

  • How many screenings were reviewed.

. Documents initiated or changed as a result of this review (this includes 50.59

evaluations). The identification number for each of these must be included in this
summary, and a copy of those documents sent to the Restart issues Coordinator for inclusion in the Restart issues File.

3

. Significant items / issues identified during conduct of the review and how they were j resolved (can simply reference Condition Report numbers or other tracking

mechanisms) OR a statement that there were none identified.

33 i

3. The Restart Issues Coordinator has veritied that the:

. Restart issues File includes the documents w hich the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

  • Significant items / issues identified during conduct of the review are bemg tracked in a tracking system which is being reviewed per Restart Commitment u22.
4. Completion of an independent verification.

Status:

The review has been completed of all screenings done from January 1.1996 to present (about 420 screenings). 21 screenings (all tracked under QCR 96-092 in NUTRK) are being upgraded to 50.59 evaluations, and 4 screenings are being re-written due to lack of detail. No USQs have been identified.

This is scheduled to be complete by March 31,1997, 1

1 1

34

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 18 Cnmmitment

Description:

Review outstanding JCOs. Perform operability determinations and 50.59 evaluations needed to address the issues. This applies to all outstanding JCOs, notjust the ones associated with Unit 2.

The scope of this review will be examining the outstanding JCOs for accuracy and compliance with requirements. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety. the scope of the review will be expanded. Where discrepancies are identified. appropriate correctis e and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to Unit 2 leaving cold shutdms n.

i Criteria to Closcout This Item:

1

1. Completion of the review defined in the " Commitment Description" section.  ;

l

2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator j which addresses (report using the NUTRK system - NUTRK U2R22 RESTART l Action # 18): )

. When the review occurred.

. Which specific JCOs were reviewed.

. Documents initiated or changed as a result of this review (including operability determinations and 50.59 evaluations). The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart issues Coordinator for inclusion in the Restart issues File.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified.

3. The Restart issues Coordinator has verified that the:

1

. Restart issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

35

l

4. Completion of an independent verification.

Slauls There are two outstanding JCOs:

. JCO #94-03 -involves DC Molded Case Circuit Breakers. A 50.59 is being written to address this. There was one operability issue identified with wire separation which could impact molded case circuit breakers. That operability issue is being dispositioned through the CR and operability determination processes.

  • JCO #94-07 -involves the Containment Accident Fan motor unshielded bearings. A 50.59 evaluation has been drafted and is being reviewed.

This is scheduled to be complete by March 27,1997.

I l

l 1

l l

I l

l l

l I

36

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 19 Commitment Descriptient Conduct a review of 50.59 evaluations from this outage.

Ensure all conditions of the evaluations have been completed. This review will address the 50.59 evaluations for Unit 2.

The scope of this review will be examining the identified documents for accurae) and compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies uhich could negatis ely impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 19):

. When the review occurred.

. A listing of the 50.59 evaluations which were reviewed.

. Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart Issues Coordinator for inclusion in the Restart issun File.

. Results of the review.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) 2 a statement that there were none identified.

37

3. The Restart Issues Coordinator has verilied that the:

. Restart issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator tsee immediately ahos e).

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

This is in progress. There are two aspects of this:

1 e To identify existing outage related 50.59 evaluations, all 50.59 evaluations approved l since January 1,1996 (to 97-007-01) were reviewed to identify the outage related l population. From that population, I8 commitments were identified, which are being tracked to completion through the outage.  ;

. As emerging outage related 50.59 evaluations are developed, commitments are being identified and tracked to completion through the outage.

As this is a continuous process, the scheduled completion date ihr this commitment uill coincide with the approach to criticality.

38

4 l

3 Point Beach Nuclear Plant Unit 2 Restart Commitment l Summary (March 12,1997) i Commitment ID#: 20  ;

J Commitment

Description:

Review items from existing open item lists (e.g.. NI i Rh i j j- to identify potentially degraded equipment. Other lists which could identity potentially degraded equipment must also be reviewed per this commitment. including inlio mal lish in peoples' desks, etc.

7 Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to the Unit 2 core loading. If some systems / components addressed per this commitment are required to be operable belbre )

that mode change per Technical Specifications, the applicable portions of this l commitment should be completed earlier.

Criteria to CloscoutThis Item;

1. Completion of the review defined in the " Commitment Description" section.
2. Each Group Head has infonned the Restart issues Coordinator:

. That the review described in the " Commitment Description" section has been' completed for their group.

. What potentially degraded equipment was identified from their review (reference a NUTRK identification number, etc. to uniquely identify the document addressing the issue).

3. The Restart Issues Coordinator has:

. Verified that the Group IIeads have reported the data listed immediately above (in item 2).

. Distributed a listing of the documents reponed to him which identify potentially degraded equipment, so that the issues can be addressed.

4. Completion of an independent verificatien.

39

1 l

. Statur l

1 This review is in progress. '

l l The scheduled completion date is March 17,1997.

1 1

4 1 3

a l

40

+

I a

f Point Beach Nuclear Plant Unit 2 Restart Commitment

Summary (March 12,1997)

! Commitment ID#: 21

Commitment

Description:

Review open items from the Design Basis Document j development program, i

The scope of this review will be examining the identified documents for accuracy and j compliance with requirements. Should this review identify either generic issues or

significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 21):

. When the review occurred.

. Which specific open DDD items were reviewed.

. Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart Issues Coordinator for inclusion in the Restart issues File.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) DR a statement that there were none identified.

3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately abose).

i 41 l

l l

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

This is in progress. One issue arising from the independent verification activity is still being addressed.

The scheduled completion date is March 17,1997.

i 1

l i

i 1

4 1

1 I

l

-12

i l

Point 13each Nuclear Plant Unit 2 Restart Commitment i Summary (March 12,1997) l Commitment ID#: 22 Commitment

Description:

All open operability evaluations fbr Unit 2 and common equipment will be reviewed for acceptable closure of the degraded equipment issue.

Disposition outstanding issues in accordance with 10CFR50.59 and Generic Letter 91-18.

l The scope of this review will be examining the identified documents for accuracy and I compliance with requirements, per the criteria in the above paragraph. Should this l review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with  !

their safety significance. '

Completion Timine: This should be completed prior to the Unit 2 approach to criticality. If some systems / components addressed per this commitment are required to I be operable before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 22):
  • When the review occurred.

.- Which specific open operability evaluations were reviewed.

. Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those  ;

documents sent to the Restart Issues Coordinator for inclusion in the Restart issues File.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified.

3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

l 43

. Significant items / issues identified during conduct of the review are being tracked l in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

This review is in progress.

All open condition reports through mid-January 1997(1065 records) has e been res ieu ea by a multidisciplinary team (an NSSS Mechanical Engineering Supers isor. a semor Electrical / I&C Engineer, and a DSS) to identify open operability determinations.

Emergent condition reports since mid-January 1997 are being reviewed to identity additional startup issues.

For those condition reports determined to constitute startup issues, the issues will either be completely resolved, a 50.59 evaluation will be completed documenting acceptability of the situations prior to the associated mode changes, or it will be addressed as a USQ.

As this is a continuous process, the scheduled completion date for this commitment will coincide with the approach to criticality. l 44

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitinent ID#: 23 Commitment Descriplimu Review 20% of the Condition Reports closed since January 1,1995 which are associated with PSA safety significant systems for degraded equipment operability issues to ensure that we have adequately identified and dispositioned operability issues. This commitment applies to all Condition Reports, not simply those l applicable to Unit 1.

The scope of this review will be examining the identified documents for accuracy and compliance with requirements, per the criteria in the above paragraph. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are l

identified, appropriate corrective and preventive actions will be taken commensarate with their safety significance.

The Restart Issues Coordinator will work with the Responsible Person to ensure the sampling methodology creates a 20% population which is both random and representative j of the entire population.

Completion Timine: This should be completed prior to Unit 2 leaving cold shutdown.

If some systems / components addressed per this commitment are required to be operable l before that mode change per Technical Specifications, the applicable portions of this commitment should be completed earlier.

Criteria to Closcout This Item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 23):

. When the review occurred.

  • The total number of Condition Reports closed since January 1,1995 which are associated with PSA safety significant systems.

. Which specific Condition Reports were reviewed (i.e., the 20%). The Condition Report number for each of these must be included in this summary.

. Documents initiated or changed as a result of this review. The identification number for each of these must be included m this summary, and a copy of those 45

q documents sent to the Restart issues Coordmator fbr inclusion in the Restart Issues File.

  • Significant items / issues identified during conduct of the review and how they were I

resolved (can simply reference Condition Report numbers or other tracking l mechanisms) OR a statement that there were none identitled.

3. The Restart issues Coordinator has verified that the:

1 1

  • Restart Issues File includes the documents which the Responsible Person is l required to Ibrward to the Restart Issues Coordinator (see immediately abos et

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment il22.

4. Completion of an independent verification.

1 Stat 1111 i This is in the closcout verification process. The review has been completed, and more than 50 Condition Reports are being re-opened.

This review was expanded to a 100% review of the PSA safety significant systems, due to issues identified in the 20% review (14 of 48 Condition Reports were re-opened due t.o operability questions).

46

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 24 Commitment

Description:

Complete an additional Outage Safety Review for the startup phase of the outage. This will evaluate the remainder of the outage schedule from a nuclear safety perspective, not a scheduling perspective.

Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded. Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART 1 Action # 24):

i . When the review occurred.

  • A description of what was reviewed.
. Documents initiated or changed as a result of this review. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart Issues Coordinator for inclusion in the Restart issues 4

File.

  • Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified.
3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).
  • Significant items / issues identified during conduct of the review are being tracked l in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

47

Etatus:

This review was conducted on February 5.1997. Comments from that resiew are being addressed. New comments based on emergent work will be addressed prior to core load This is scheduled to be completed by N1 arch 31.1997.

i l

i l

l 48 I

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (Mareh 12,1997)

Commitment ID#: 25 Commitment Desetiption: Conduct an integrated review of all outage licensing commitments (50.59's, enforcement conference items, Technical Specification Change Requests, and the Reload Safety Analysis). Ensure ali requirements are met.

The scope of this review will be to identify outstanding licensing commitment issues which need to be resolved prior to mode changes. Those issues will then be appropriatek resolved. Should this review identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the review will be expanded Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. Completion of the review defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 25):
  • When the review occurred.

. A description of what was reviewed.

. A list of the outstanding licensing commitment issues that need to be resolved prior to mode changes.

. Significant items / issues identified during conduct of the review and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified.

3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

49

l Statia; A review of additional outage related licensing documentation is being res iewed in conjunction with this commitment. The original review has been conducted, and the Responsible Person is currently resolving issues from that review.

This is scheduled to be complete by March 31,1997.

50

Point Beach Nuclear Plant Unit 2 Restart Commitment l Summary (March 12,1997)

Commitment ID#: 26 Commitment

Description:

Revise ORT-3 and DCS 3.1.11 to ensure Technical Specification !5.4.6.A.2 testing includes dynamic loading of the EDG with sequenced loads.

Completion Timine: This should be completed prior to the tJnit 2 core loading.

Criteria to Closeintt Ihisitenu

1. Completion of the actions defined in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart Issues Coordinator:

. A copy of the revised ORT-3 and DCS 3.1.11. ,

. A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OJ1 a statement that there were none 1

identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 26). i l
3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately abos el.  !

. Significant items / issues identified during conduct of the task are being tracked in a i tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

Verified closed. The associated documentation was provided to the NRC on February 6, 1997.

5i

i i

4 i

i 52

- . .... - . vm+-. ...-, , _ .wep p, N " trT T

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l Commitment ID#: 27 Commitment

Description:

Test all EDGs in accordance with revised OR I-3 and I Wo 3.1.11. Return the electrical systems to normal alignment prior to leaving cold shutdown Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to the Unit 2 core loading.

Criteria to Closcout This Item: l l

1. Completion of the actions defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart issues Coordinator I which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 27): l

. When the actions detined in the " Commitments Description" section were completed.

  • Significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified.
3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documents whkn the Responsible Person is required to forward to the Restart Issues Coardinator (see immediately above).
  • Significant items / issues identified during ;onduct of the task are being tracked in a tracking system which is being reviewed. per Restart Commitment #22.
4. Completion of an independent verification.

Statun This is in the closcout verification phase.

53

m W, er 14.hemm _Je .F J.-$. ea rdM AJb a .h"ar.. asp -se. Ne4a U= & 4 h,0.Ja h- 4 4 4,' '$4 J e W.W A4W hM'r$ 4 Ae %W 2,44 SMMM h6= uhW@ AN _sh &md. AM & As3AnM d M AAM M -' ' E A Me mm,4,anwd ,

.{

- ll d j i

j .:

6 4<

d ni I

4" j

4

\ l 4 I 4-M 4

A 4

4 s

?

I i t

I k

[

d 1

L f.

f l .

e-1

(~

j-i.

1 4

j-I~

1 1

i e

h I

i I

d r

a e

I 4

4 1

i'

.i -

i

+

!- 54 v

l

., ,_,-r ,. -,- ., _,m..... , ,, - _.. ,,, . ..m.,. m , , .,- ,,,, ,, -. . - - , _ _m ,

\

d I

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l Commitment LDR 28 )

I Commitment

Description:

Resolve the containment penetration commitments.

4 meluding:

. CP-32c (Containment penetration for auxiliary cha,ging line). A small leak (4 drops per minute at 1900 psig) was found in the 3/4 inch Si test line (CPP-32b). This was docurnented on Condition Report 97-0003

. Penetration thermal reliefissue. This issue concerns the potential for overpressurization of piping passing through containment, the result causing a loss of containment integrity. For this to be a concern, the piping must be water-solid and l isolated by two non-relieving containment isolation valves. Condition Report 96-470 was initiated regarding this fbilowing an industry operating experience item from Maine Yankee, which was followed-up by IN 96-049 and Generic Letter 96-06. The PBNP initial response to the Generic Letter was sent to the NRC under VPNPD 090.

Should generic issues or significant discrepancies be identified during this resolution which could negatively impact reactor safety, the scope of this effort will be expanded.

Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Completion Timine: This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. Resolution of the containment penetration commitments defined in the " Commitment Description" section.
2. The Responsible Person has forwarded a summary to the Restart Issues Coordinator which addresses (report using the NUTRK system - NUTRK U2R22 RESTART Action # 28):

. When the actions described in the " Commitments Description" section were completed.

  • What specifically was done to resolve the containment penetration commitments.
  • Documents initiated or changed as a result of this task. The identification number for each of these must be included in this summary, and a copy of those documents sent to the Restart issues Coordinator for inclusion in the Restart Issues File.

55

  • Significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) .QR a statement that there were none identified.
3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment h22.

4. Completion of an independent verification.

Stattis ,

l CP-32c (Containment penetration for auxiliary charging line) - this line is protected by air l operated CV-1296, so no modification is required. It was tested per ORT-46. j CP-32b (3/4 inch Si test line)- this work is complete. Similar Unit 2 containment penetrations were inspected and found to be intact, so this is not considered a generic problem. A work order has been initiated to perform these same inspections during UIR24 i l

Penetration thermal reliefissue - the concern is being evaluated under Condition Report l 96 470 (also identified by IN 96-049 and GL 96-06). The following lines were identified as concerns by the evaluation-l

. P-11 (RCP seal water retum line)- operability for Unit I required 2 inches of callsil insulation inside containment. Insulation was installed per Work Order 9 /00318. A four-hour NRC event notification was made concerning this on Unit 1. and an I liR is being submitted. P-!I is being modified per MR 96-057* B to install a check vah e around ICV-313 A inside containment to provide an overpressure protection flow path. Diaphram 1CV-1406 is being replaced with a Whitey valve to address the temperature concern. Installation is planned for the week of March 10,1997.

  • Potential overpressure concerns exist fbr the pressurizer liquid sample line (P-28b).

Penetration P-28b will require pressure relief by MR 96-057*D, which will occur following completion of MR 96-057*B. The parts have been ordered, but work documentation has not been prepared.

. P-12a (DI water supply line)- The Unit 1 DI water supply line has been drained three times. Three gallons drained out the first time, four ounces was drained one week later, and three ounces was drained several weeks later. This confirms that the line will not become water solid during the operating cycle due to valve leak-by. For Unit 2, CL-lb has been revised on February 11,1997, to ensure the D1 water supply line does not become water-solid during power operation. This will result in one PAR DI 56

hose station being removed from service. As a long-term solution. modifications will be required to allow isolating P-12a piping without causing a loss ol' DI water to othei components.

. P-30c (Pressurizer relief tank makeup)- this line is piotected by air operated diaphram valves, so no modification is necessary.

  • P-53 (Ileating steam condensate return) - this line was verified not water-solid on Unit 1. For Unit 2, this line is being cut and weld-capped per MR 96-068 during U2R22.

This is scheduled to be completed by March 31,1997.

l l

57

eMame dMag

--" - " " " " " " " " * ^ ^ "

  1. -ra Famv e.44..aema awm.N-*PmN.r-NJ NN-" '----'-- 5 64 h 5 470. LMB ad.Eh*S W.4 @ Wed& M44 M CM- ' " ' " - "t.@-

. - - - - "" "'-"-' "- W A44m I

1 I

l l:

a i

f l

i i

I i

i I

l i

1 i

l l

I 8 I

l i-l i

p i

58

?

Point Beach Nuclear Plant Unit 2 Restart Commitment .

Summary (March 12,1997) l l

l Commitment ID#: 29 4 1

Commitment

Description:

Complete a 50.59 evaluation for the existing CCW supply to the RCP seals as a safety function. In 1992, Point Beach Nuclear Plant committed to making this configuration consistent with the classification of that function as a safety l function. This is already classified as safety related frem a pressure boundary standpoint, but not for the flow function.

l Should this evaluation identify either generic issues or significant discrepancies which j could negatively impact reactor safety, the scope of this effort will be expanded. Where i discrepancies are identified, appropriate corrective and preventive actions will be taken l commensurate with their safety significance. l l

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdtmn.

Criteria to Closcout This Item:

1. Completion of the 50.59 evaluation.
2. The Resper.sible Person has forwarded to the Restart Issues Coordinator:

. A copy of the completed 50.59 evaluation.

. A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 29).
3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

59

Status:

This is in the closecut verification process. A document has been completed which provides a history ofissues associated with system functional reclassification, proposed physical system configuration modifications, and an evaluation of the conformance of the present configuration with the FSAR.

1 60

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

G11unitment ID#: 30 Commitment

Description:

Update the diesel generator loading calculation N-91-016 to properly reDect the loading of the Containment Fan Coolers.

Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

Gmpletion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item;

1. Completion of the diesel generator loading calculation task update defined in the

" Commitment Description" section.

2. The Responsible Person has forwarded to the Restart Issues Coordinator:
  • A copy of the revised coverpage to the diesel generator loading calculation N 016 and the page showing the new reference (#61).

. A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 30).
3. The Restart issues Coordinator has verified that the: )

e Restart issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately abos e).

. Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

61

l Status:

This is in progress.

  • An original calculation could not be located, so it was thought that thi.s task was necessary. That calculation has since been found, so the diesel generator loading l calculation only needs to be revised to add that reference calculation.
  • The loading calculation has been updated to add that reference calculation. Ilones er.

questions have arisen concerning the validity of the CFC loading values used, and that will be resolved during the ILRT, where the data will be used to complete draft calculation 97-0038," Containment Accident Fan Motor Electrical Power Requirements Following a LOCA"

  • Calculation N-91-016,"PBNP EDG Loading Analysis", will then be updated.

This is scheduled to be completed by April 1,1997.

1

{.

62

i Point Beach Nuclear Plant Unit 2 Restart Commitment  !

Summary (March 12,1997) I 1

l Commitment ID#: 31 Commitment

Description:

Evaluate the adequacy of coordination on the 120 VAC instrument bus system through a 50.59 evaluation or operability detennination.

Should this evaluation identify either generic issues or significant discrepancies u hich could negatively impact reactor safety, the scope of the evaluation will be expanded.

Where discrepancies are identified, appropriate corrective and pres entis e actions will be taken commensurate with their safety significance.

Completion Timing: This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This item:

1. Completion of the evaluation / operability review defmed in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart issues Coordinator:

e' A copy of the 50.59 evaluation or operability determination.

. A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 31).

- 3. The Restart issues Coordinator has verified that the:

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

63

i Stallin j This is in progress.

  • MR 97-005 has been initiated to re-supply non-safety related panels 2Y I 1,2Y21, 2Y31, and 2Y41 from non-safety related supplies. Moving the non-safety related panels off the safety related panels will ensure that no single fault will cause multiple channels ofinstrumentation to fail.
  • A formal short circuit calculation is being perfonned to determine the fault currents at the inverters to evaluate whether the current limit will be reached. Following this, an operability determination will be completed.
  • New circuits supplied from all four Unit 1 instrument channels were fbund installed on adjacent manually operated breakers in IC04. A condition report and prompt operability detennination was created fbr these circuits. The Unit 2 circuits will be reviewed to determine if there is a corresponding problem with those manually operated breakers in 2C04.

This is scheduled to be completed by April 4,1997.

l l;

I i

l l

64 I

a I

1

)

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

I l

Commitment ID#: 32 '

Commitment Descriplimu implement interim improvements for the Condition i Reporting process, based on a review of assessments and identified recommendations Ihr improving that process.

l fnmpletion Timing: This will be completed prior to the Unit 2 approach to criticality.

Criteria to Closcout This item:

1. Completion of the implementation ofinterim improvements for the Condition Reporting process defined in the " Commitment Description" section.

1

2. The Responsible Person has forwarded to the Restart issues Coordinator-1 e A copy of the interim improvements for the Condition Reporting process.

. A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 32). ,
3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documents uhich the Responsible Person is required to forward to the Restart Issues Ccordinator (see immediately abovet
  • Significant items / issues identified during conduct of the task are being tracked in a ,

tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status This is in progress.

  • A staff review of current Condition Reports has been instituted immediately following the morning update.
  • The Condition Report review and the Operating Experience review have been coupled into a single, daily meeting which is attended by personnel from several disciplines.

Some staff members will also attend.

65

I l

e During the week of March 3. a process impros ement team will mett to address the Corrective Action process. Following implementation ofinterim actions from this team, this Restart Issue will be closed.

This is scheduled to be completed by March 31,1997.

1 4

l l

1 I

k 1

66

Point lleach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment II)#: 33 Commitment Dncription: Implement interim improvements for the 50.59 process to require that all screenings be either authored or reviewed by a member of the multi-disciplinary review team.

Completion Timine: This will be completed prior to the Unit 2 approach to criticality .

Criteria to Closcout This Itenu

1. Completion of the implementation ofinterim improvements for the 50.59 process defined in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart issues Coordinator:

. A copy of the interim improvements for the 50.59 process.

  • A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action
  1. 33).
3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent veritication.

Status:

This is in the closecut verification process.

  • Members for the multi-disciplinary review team have been designated.

. Training for these personnel has been conducted to ensure consistency in their approach. Required reading was completed by existing members.

67

  • This wili assure that no-evaluation screenings are in fact no-evaluation screenings.

l The existing full,in-line review team will still exist. The interim improvements were included in NP 10.3.1.

l l

l l I i

l l

l l

4 l

l I

l 68

1 Point lleach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 34 Commitment Descriptiom Upgrade Unit 2 operations checklists to include requirements for initials, time, and date. During the review, verify that the checklists are technically correct.

Should this upgrade identify either generic issues or significam discrepancies uhich could negatively impact reactor safety, the scope of the upgrade will be expanded. Where j

discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

This is also a subset of Enforcement Conference Commitment item # 18.

Comnletion Timine: This should be completed prior to Unit 2 leaving cold shutdown, if some systems / components addressed per this commitment are required to be operable before that mode change per Technical Specifications, the applicable portions of this I commitment should be completed earlier.

Criteria to Closcout This Iteun

1. Completion of the actions defined in the " Commitment Description" section.

I

2. The Responsible Person has forwarded to the Entbreement Conference Commitments  ;

Coordinator:

  • A listing of which Unit 2 operations checklists were reviewed, with an indication l of which were revised (report using the NUTRK system).
  • A copy of each revised Unit 2 operations checklist.
  • A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system).
3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).
  • Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

69

4. Completion of an independent verification. .

Status: i l

This is in the closecut verification process, i

i l

l l

I l

t 70 i

(

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment II)#: 35 Commitment Descriplium Revise applicable IST program documents to prevent equipment from being returned to service (declared operable) with vibrations in the alert range.

Should this revision effort identify either generic issues or significant discrepancies which could negatively impact reactor safety, the scope of the efTort will be expanded.

Where discrepancies are identified, appropriate corrective and preventive actions will be taken commensurate with their safety significance.

This commitment is also Enforcement Conference Commitment Item # 41.

1 Completion Timine: This should be completed prior to Unit 2 leaving cold shutdown. l l

Criteria to Closcout This Item:

l. Completion of the actions defined in the " Commitment Description" section.

l

2. The Responsible Person has forwarded to the Enforcement Conferenet. Comr.iltments Coordinator:

1

. A copy of the revised IST program documents.

. A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system).

3. The Restart Issues Coordinator has verified that the:

. The Restart Issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).

. Significant items / issues identified during conduct of the task are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

71

Status:

This is in the closecut verification process.

The revision to OM 4.2.2 provides guidance for returning a Section XI pump back to service following maintenance. Specifically, no pump will be returned to service following maintenance with a vibration greater than 0.325 ips.

1

,1 t

d s

i

')

i  ;

1 4 j

' I 4

i s

k l 1

2 72 a

Point lleach Nuclear Phint Unit 2 Restart Commitment i Summary (March 12,1997) I Commitment ID#: 36 ,

1 l

Commitntent

Description:

Revise NP 8.1.1, Work Order Processing, and NP 8.1.3. l Post-Maintenance Testing, to ensure post-maintenance testing, operability testing, and l

surveillance testing requirements are properly addressed.

l This commitment is also Enforcement Conference Commitment item # 57.

Completion Timing: This should be completed prior to the Unit 2 approach to  ;

criticality. l Criteria to Closcout This Item:

1. Comple: ion of the actions defined in the " Commitment Description" section
2. The Responsible Person has forwarded to the Enforcement Conference Commitments Coordinator:

. A copy of the revised documents.

. . A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report i numbers or other tracking mechanisms) OR a statement that there were none  ;

identified (report using the NUTRK system).

3. The Restart issues Coordinator has verified that the:

. Restart issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see j immediately above). j

. Significant items / issues identified during conduct of the task are being tracked in a i tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

This is in the closecut verification process, i

NP 8.1.1 was revised, but changes to NP 8.1.3 were deemed not necessary, as this procedure references NP 8.1.1 for content.

73

d 1

1

,Y, t

i l

t i No significant issues were identified during the conduct of this task. _t i

E i

f a

n il

+

J 4

t s

1 I

4 4

f i

i 4

4 1

4 4

d I

a

?

74

1 1

3 Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l Commitment ID#: 37 .

l i

[ Commitment D.cscription: Include return to service testing in the plant schedule, both 2

outage and nonoutage.  !

, This commitment is also Enforcement Conference Commitment Item # 59.

. Completion Timing: This should be completed prior to the Unit 2 core loading.

! Criteria to Closcout This Item: I

1. Completion of the actions defined in the " Commitment Description" section.

4

2. The Responsible Person has forwarded to the Enforcement Conference Commitments Coordinator:

. A copy of a plant schedule with the return to service testing included.

. A copy of plant procedures changed to implement these.

j . The date this task was accomplished (report using the NUTRK system). I I . A summary which addresses significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report i numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system).

, 3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documents which the Responsible Person is

! required to forward to the Enforcement Conference Commitments Coordinator tsee

) immediately above).

. Significant items / issues identified during conduct of the task are being tracked in a j tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

i htus 1

This is in the closeout verification process.

l

} 75 t

1 I

i l

I

'I l

i i

f i

i I

1 l

i J

l l

1 1

I i

76

\

Point Beach Nuclear Plant Unit 2 Restart Commitment

Summary (March 12,1997) 4 Commitment ID#
38 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 96-033 - replace control power transformers on Motor Control Centers 2B32 and 2B42.

These control power transformers were identified as being relatively undersized. I his modification will replace the approximately 60 existing Unit 2 control power transformers with larger ones to increase the margin for performing their function.

There are approximately 30 common control power transformers associated with this modification which will be replaced after U2R22, during a system outage or when the equipment is not required.

Completion Timine: This should be in an accepted status prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

38).

3. The Restart Issues Coordinator has verified that:

. The Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. The Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

77

i i

l

  • The significant items / issues identified durug conduct of the modification are being tracked in a tracking system uhich is being reviewed per Restart Commitment :22
4. Completion of an independent veritication.

SlalE This is in progress. Of the 67 control power transformers originally scheduled to be installed this outage (60 in use,7 spares), one remains to be installed. All others have been installed and passed their PMT.

4 1

e i

l 4

i 78

l l

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l l

Commitment ID#: 39 1 1

Commitment

Description:

The following modification will be in an accepted status ]

(i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Tc:hnical Specifications:

Modification 90-048 - replace lloric Acid and Reactor Niakeup Water totalizers. replace the CVCS control switch, replace flow indicators. and refurbish flow controllers.  !

Due to their unreliability when operating in automatic, these controls have been used in the manual mode. This resolves a workaround issue.

Completion Timine: This should be in a conditionally accepted status prior to the Unit 2 core loading (only awaiting PMT). It should be in an accepted status prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

e A copy of the completed Installation Work Package.

. A summary of the significant items / issues identitied during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action u 39).

3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

79

. - . . . . . - . - . . - - - . -- - .. .- . _ _ -. - . .. . ..~

l

4. Completion of an independent verification. l 1

4 i Sla1115; .

I i

This modification has been conditionally accepted (based on flow testing to the "11"

' l Iloidup Tank). Final acceptance will require in-service testing or additional PNIT aller the VCT is returned to service while the unit is in cold shutdown. 1 Two condition reports (CR 96-1530 and CR 97-0360) have been initiated during conduct of this task.

The scheduled completion (acceptance) date is March 21,1997.

l l

1 l

a l 1

4 l

l 5 '

l 1

e i

d i

4 4

l 80 t

I Point lleach Nuclear Plant Unit 2 Restart Commitment l Summary (March 12,1997)

Commitment ID#: 40 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 94-097 - remove six RCS loop drain valves.

These valves are radiological hot spots and potential leakage paths. Due to leakage from one of these valves, the unit was forced to shutdown. Maintenance draindowns can be performed from other loop drain valves.

Completion Timing: This will be in an accepted status immediately after the RCS leak check, per Technical Specification 15.4.3.

Criteria to Closcout This item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package. 1

  • A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QS a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

40).

3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

  • Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification 81

1 1

Stattis The physical work has been completed. and the modification is awaiting PMT (completion of the RCS leak test). .

1 The scheduled completion (acceptance) date is March 31,1997.  ;

l I

i I

J l

l 1

82

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 41 Commitment

Description:

The following modification will be in an accepted stattn (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 92-141 - relocate the RllR flow control valve controllers on 2CO3 for human factoring.

Train "A" and train "B" main control board controls typically have a left to right convention on Unit I and a right to left convention on Unit 2. This convention was not followed for the RHR controllers 2HC-624 and 2HC-625, and this modification corrects that. Also, the common flow controller 2HC-626 will be positioned between these two RHR controllers to improve their separation.

Cumpletion Timing: This should be in an accepted status prior to the Unit 2 core loading.

Criteria to Closcout This Itenu

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

41).

3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

I 83

4. Completion of an independent verification Status:

This is in the closeout verification process. The work was compicted under Work Order 9605772.

W i

l 4

Y U

l 4

1

.l a

1 j 1

4 84

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment IDJ.; 42 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed. post-maintenance and return to sersice testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 96-073 - seismically upgrade CCW, SI, RIIR. and RilIUletdown piping supports and remove an AFW snubber.

Completion Timine: This should be in an accepted status prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action v 42).

3. The Restart issues Coordinator has verified that the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

85

Status:

Verified closed. The associated documentation was provided to the NRC on 1 ebruary 10 and 12,1997.

4 4

d i

k 86

l Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l Commitment ID#_; 43 Commitment

Description:

The fbliowing modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Tc.:hnical Specifications:

Modification 94-066* A - install a soft seat in containment isolation valve 2SI-834D. and add a relief valve and pressure regulator in the nitrogen supply line to the SI l accumulators.

The soft seat is being installed to improve leakage performance. The relief valve and ,

pressure regulator are being installed to ensure the piping is not overpressurized. This resolves a workaround issue.

Cnmpletion Timing: This should be in an accepted status prior to Unit 2 leaving cold I shutdown.  ;

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the completed Installation Work Package.
  • A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

43).

3. The Restart !ssues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to Ibrward to the Restart Issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.
  • Significant items / issues identified during conduct of the modification are being tracked in a trteking system which is being reviewed per Restart Commitment #22. '

87

1

4. Completion of an independent veriGeation.

Status: l This is in the closecut veriGeation process.

l

\

I l

l l

J l

l i

i l

l

\

88

1 Point Beach Nuclear Plant Unit 2 Restart Commitment c Summary (March 12,1997) i Commitment ID#: 44 Qunmitment

Description:

The following modification will be in an accepted status 4

(i.e., the applicable physical work completed, post-maintenance and return to senice testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

i' Modification 96-065*B - seismically upgrade the Refueling Water Storage Tank recirculation line.

l Completion Timine: This should be in an accepted status prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. The modification is in an accepted status.

a

2. The Responsible Person has fbrwarded the fbliowing documentation to the Restart issues Coordinator:

4 i e A copy of the completed Installation Work Package, e A summary of the significant itemshssues identified during conduct of the

, modification and how they were resolved (can simply reference Condition Report l numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

44).

3. The Restart issues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

This is in the closcout verification process.

89

i I

90

Point Beach Nuclear Phmt Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 45 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 96-054 - install pressure gauges in the service water return header from the Emergency Diesel Generator GOl and GO2 glycol coolers, and reset the throttle valves ,

in that line. I GOl and GO2 throttle valves must be reset to meet the assumptions made in the new service water flow model. Prior to the modification. valves were set using an assumed l

" worst case" service water return header pressure. The new gauges will allow s ah es to i be set with actual pressure. This will better balance the service water system flows and I enhance service water system performance.

Completion Timine: This should be in an accepted status prior to Unit 2 leaving cold shutdown.

I Criteria to Closcout This item: I l

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator:
  • A copy of the completed Insta!!ation Work Package.
  • A summary of the sLnificant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) .02 a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action h  :

45). l

3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

91

Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment fi22.

4. Completion of an independent verification.

Stallis Outstanding concerns about the seismic mounting of gauges and high flow through the diesel coolers are delaying project release for installation.

i The scheduled conipletion date is March 28.1997.

l i

I l

92

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) 1 Commitment ID#: 46 Commitment

Description:

The following modification will be in an accepted status

(i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared
operable) prior to being required to be operable per Technical Specifications

Modification 96-022 - install a new 125 VDC feed (for DC Control Power) to 480V safeguards bus 2003.

This supports the effort to align DC systems which supply ')C control pimer to the 4No \

buses 4160 V buses, and the normally aligned EDGs.

Completion Timine: This should be in an accepted status prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

A copy of the completed Installation Work Package.

A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) DJ1 a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

46).

3. The Restart Issues Coordinator has verified that the:

Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

93

I I

Status: I i

Verified closed. The associated documentation was provided to the NRC on Februarv 10 and 12,1997. '

One discrepancy with the test procedure was addressed through Condition Report 9t>-

1153. This issue has been resolved per the Condition Reporting System. and the test 1 I

procedure was revised to reDect that resolution.

i i

i 1

94

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 47 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service l testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 94-055 - add seismic supports to the raceway between risers 56 and 62 on 2C04 (Reactor and Primary Plant Control Board).

The cable tray was sagging due to weakening caused by a sidewall wireway being cut into the cable tray to allow the exit of some wiring. The addition of these supports restores the full integrity of the cable tray.

Completion Timing This should be in an accepted status prior to Unit 2 leaving cold shutdown.

f.riteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the completed Installation Work Package.
  • A summary of the significant items / issues identified during conduct of the j modification and how they were resolved (can simply reference Condition Repon numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action ;

47).

3. The Restart issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

95  ;

_ . . = . . - - . - _ .

4. Completion of an independent verification.

Status Verified closed. The associated documentation was provided to the NRC.

I 4

I l

96 j

l

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 48 Commitment Descriplimu The fbliowing modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service

, . testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 96-068B - eliminate containment heating steam and condensate return containment isolation valves.

These were determined to be unnecessary to support plant operations. Removal i eliminates a potential containment leakage path and reduces the need to conduct future i

Appendix J testing on these.

, Completion Timine: This should be in an accepted status prior to Unit 2 leaving cold

, shutdown.

i Criteria to Closcout This Item:

1. The modification is in an accepted status.

. 2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator:

. A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report i numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action d

, 48).

i

3. The Restart Issues Coordinator has verified that the:

) . Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

97

.. . . - _ = . .. - -. .- . - . ,_ . . _ . . . _ . -

4 Statits 2

The work is in progress.

This is scheduled to be completed (accepted) by March 14.1997.

i j

2 1

5 1

I 98

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 49 l

l Commitment Descriptimu The following modification will be in an accepted status j (i.e., the applicable physical work completed, post-maintenance testing and return to l

service completed satisfactorily, and the associated component / system being declared l operable) prior to being required to be operable per Technical Specifications:

Modi 0 cation 96-053 - replace an elbow in the west service water header.

A temporary, non-code repair was performed in July 1996 on the service water 6 inch elbow per temporary modification TM 96-014. There is an NRC commitment to perform  !

the code repair prior to the exit from the next refueling outage. Further pipe inspections revealed a second elbow with wall thinning (no leak yet). Both elbows are normally unisolable from the west service water header.

Completion Titning; This should be in an accepted status prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has fbrwarded the ibilowing documentation to the Restart Issues Coordinator:
  • A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) Q11 a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

49).

3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documentation which the Responsible Person is required to forwr.rd to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

  • Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

99

l l

J f

4. Completion of an independent verification ,

- Status:

The work is in progress. j The scheduled completion (acceptance) date is April 4,1997.

)

l l

I I

I l

j 1

l l

100

i

)

3 4

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Canunitment ID#: 50 Commitment

Deaription:

The following modiHeation will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) piior to being required to be operable per Technical Specincations:

Modification 95-070 - seismically upgrade the containment cooling fans and filters.

Completion Timine: This should be in an accepted status prior to Unit 2 leaving cold shutdown. 4 Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator:
  • A copy of the completed Installation Work Package.
  • A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

50).

3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the moditication are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent veriHeation.

Status:

This is in the closecut verification process.

101

  • 4 *4 ha 1

I i

I l

i l

i i

l 1

1

~

l l

i l

i l

102

s Point 13each Nuclear Plant Unit 2 Restart Commitment- l Summary (March 12,1997)

Commitment ID#: 51 l l

Commitment

Description:

The following modification will be in an accepted status l

) (i.e., the applicable physical work completed, post-maintenance and return to service i te:, ting completed satisfactorily, and the associated component / system being declared i operable) prior to being required to be operable per Te:hnical Specifications:

Modification 96-026 - install, delete, and modify supports for feedwater, main steam, and SI system piping for the 79-14 project.

The piping and pipe supports for these systems have been evaluated for their ability to withstand design basis loads and stresses. Analysis shows that these piping systems are 1 operable in their present configuration and prior to these modifications. Ilowever, various transients have been postulated that could result in stresses above code allowances, and these modifications will reduce these stresses to below code allowable.

l Completion Timing: This should be in an accepted status prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

51).

3. The Restart issues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.
  • Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

103

_ . _ . .- .~. - . - . .. . . _ _ -_ - - _ ..

I

4. Completion of an independent verification.

Statun This is in the closecut verification process. l l

1 l

l I

l 104 i

l

1 Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 52 Commitment

Description:

The following modification will be in an accepted status I (i.e., the applicable physical work completed, post-maintenance and return to service

testing completed satisfactorily, and the associated component / system being declared

! operable) prior to being required to be operable per Technical Specifications:

?

Modification 96-058 - move Power Plant Computer System alarms to the exterior of C-20 '

, panels. This will enhance the alarm sound levels.

i 3

.Cnmpletion Timing: This should be in an accepted status prior to Unit 2 leaving cold i shutdown.

a Criteria to Closcout This Iterm

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator
  • A copy of the completed Installation Work Package.

l

  • A summary of the significant items / issues identified during conduct of the l modification and how they were resolved (can simply reference Condition Report

, numbers or other tracking mechanisms) OR a statement that there were none l identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

j 52).

l

3. The Restart Issues Coordinator has verified that the:

i

e Restart Issues File includes the documentation which the Responsible Person is j required to forward to the Restart issues Coordinator (see immediately above),

l

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work

, Package page.

I e Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

1 4. Completion of an independent verification.

J J

105

S1;itus:

Veri.Ged closed. The associated documentation was provided to the NRC on February 10 und 12,1997.

No issues were identified during the conduct of the modification.

d d

4 n

W 106

Point Beach Nuclear Plant Unit 2 Restart Commitment i Summary (March 12,1997) i Commitment ID#: 53 Commitment

Description:

The followi:'g modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

l Modification 94-095 - replace 8 Main Steam Condenser steam dump valves with improved design.

This will resolve a workaround issue, as the performance of these valves has not been satisfactory.

Completion Timing: The physical should be in an accepted status prior to Unit 2 leaving cold shutdown. The PMT will be completed fbliowing reactor startup.

Criteria to Closcout This Itenu

1. The modification is in an accepted status.  ;
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the completed Installation Work Package.  !
  • A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

53).

3. The Restart issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

  • Significant items / issues identified during conduct of the modification are being tracked in a tracking system which ir being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

107

l Status:

This is awaiting PMT, which involves acceptance testing with steam (need to complete PC-11, Part 3, which references 01-13). The PNIT will be completed following reactor startup. No Condition Reports have been issued during conduct of the actisit).

l t

i l

l J

108

)

l 1

l Point Beach Nuclear Plant Unit 2 Restart Commitment  !

Summary (March 12,1997) l i

Commitment ID#: 54 Commitment 1)escription: The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 95-029 - replace Si accumulator level transmitters.

The purpose of this modification is to provide a more accurate and reliable level indication system for the Si accumulators. The current capacitance probe ty pe level indicators are being replaced with Rosemount differential pressure transmitters.

Completion Timine: This should be in an accepted status prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package. I e A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action n 54).

3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work l Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

109

I Shilus This is awaiting completion of PMT. The remaining testing includes a leak test and f

functional testing, both of which cannot be done until the accumulators are restored.

which is presently scheduled for after the Integrated Leak Rate Test (ll.RT).

l The scheduled completion (acceptance) date is April 1.1997.

l l

l l

4 J

l 5

5 3

i d

i.

d 4

4 110

i Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

~

l l

Commitment ID#: 55 i Commitment Descriptiom The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared  ;

operable) prior to being required to be operable per Tc.hnical Specifications: l l Modification 95-035 - modify Containment Spray additive tank controller circuit.

j Completion Timinya This should be in an accepted status prior to linit 2 leasing cold l shutdown. I 4

t Criteria to Closcout This Item:

1 4

1. The modification is in an accepted status. I
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the completed Installation Work Package.

  • A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action n 55).
3. The Restart issues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Ii1

%s .m a - * - , - , . , - ,. 4 A c a e Status:

'"" r um identified as defectig e

  1. dtirin ( ct )f1) n) 1 I on at -

pl .,

l l

1 112

l Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 56 l l

l

! Cunusitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service i testing completed satisfactorily, and the associated component /sy stem being declared operable) prior to being required to be operable per Technical Specifications:

Modification 96-063 - replace 345 kv breakers (3-4. 4-5, and 142).

During extremely cold winter conditions, these switchyard breakers experienced air loss.

making them difficult to operate. This replacement will ensure their operability during l these conditions.

Completion Timine: The physical work associated with this modification should be l completed prior to criticality. To conduct the PMT (which involves relaying checks), the  !

unit must be on-line.

Criteria to Closcout This item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

l e A copy of the completed Installation Work Package. l

. A summary of the significant item's/ issues identified during conduct of the l modification and how they were resolved (can simply reference Condition Report  ;

numbers or other tracking mechanisms) OR a statement that there were none  !

identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # l l

56).

3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work l Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

I13

1 S.tatus:

The physical work is completed, and the modification is awaiting PMT. To conduct the

PMT (which involves relaying checks with the generator breaker closed and energized),

the unit must be on-line. A procedure update to PC-21 must also be made to allow acceptance of this modification.

a

?

h i

4 a

t I

4 i

.i l14

Point Beach Nuclear Plaint Unit 2 Restart Commitment 4

Summary (March 12,1997)

Commitment ID#: 57 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 96-069 - replace four breakers (l Y-06-01,1 Y-06-03,1 Y-06-05, and 1 Y 11) associated with instrument bus 1 Y-06.

This will resolve an issue where these breakers are oversized for the wiring they are protecting, creating a potential delay or lack of breaker tripping situation should a fault occur.

Completion Timine: This should be in an accepted status prior to Unit 2 leaving cold I shutdown. ,

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

57).

3. The Restart Issues Coordinator has verified that the:

. Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment n22.

I15 w-r

4. Completion of an independent verification.

Statits This is in the closcout verification process.

l 1

l l

1 l

\

116

Point Beach Nuclear Plant Unit 2 Restart Commitment Sum mary (March 12,1997)

Commitmsnt ID#: 58 Commitment 1)escription: The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

Modification 95-058*O - repair Steam Generator intermediate leg supports. These were found degraded, and this issue may be resolved through analysis.

Completion Timing 1 This should be in an accepted status prior to the Unit 2 approach to criticality.

Criteria to Closcout This Item:

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator:
  • A copy of the completed Installation Work. Package.
  • A summary of the significant items / issues identified during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

58).

3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documemation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.
  • Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4.- Completion of an independent verification.

I i

i17

Status:

This is awaiting PMT (hot gap measurements), which will occur when the unit is heated-up and prior to criticality.

118

i i

! Point lleach Nuclear Plant Unit 2 Restart Commitment l Summary (March 12,1997) i 4

Commitment ID#: 59 Commitment

Description:

The following modification will be in an accepted status (i.e., the applicable physical work completed, post-maintenance and return to service testing completed satisfactorily, and the associated component / system being declared operable) prior to being required to be operable per Technical Specifications:

i Modification 96-070 - replace molded case circuit breakers associated with instrument buses 2Y-05 and 2Y-06.

This will resolve an issue where these breakers are oversized for the wiring they are 4

protecting, creating a potential delay or lack of breaker tripping situation should a fault occur.

Completion Timing: This should be in an accepted status prior to linit 2 leasing cold

. shutdown, 3

l Criteria to Closcout This Iteam

1. The modification is in an accepted status, i
2. The Responsible Person has forwarded the fbilowing documentation to the Restart j Issues Coordinator:

i e A copy of the completed Installation Work Package.

  • A summary of the significant items / issues identitied during conduct of the modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) DR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #

59).

3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately abos et

. Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.

. Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

I19

a

4. Completion of an independent verification.

Status:

This is in the closecut verification process.

I 120

i i Point Beach Nuclear Plant Unit 2 Restart Commitment

[ Summary (March 12,1997) 1 Commitment IDJ1 60 1 Commitment

Description:

The work and testing associated with these work orders will be completed prior to the associated component / system being declared operable: Work Orders 9601506,9602502,9603921,9611267,9611278, and 9611755 - replace ,

proximity switches and targets with an improved design and overhaul the Fuel Transfer j i Cart to enhance control system operation. l 1

l j The original equipment manufacturer had provided switches not designed tbr underwater  !

service, causing a history of recurring failures. This will resolve a workaround issue. l l Comnletion Timinnt This should be completed prior to the Unit 2 core loading.

s i 1

' Criteria to Closcout This Item:

l. Completion of the work associated with the listed wmk orders.  ;

i j

' The Responsible Person has forwarded the lbliowing documentation to the Restart I Issues Coordinator:

)

  • A copy of the closed work orders.
  • A summary of the significant items / issues identified during conduct of the work

, orders and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 60).
3. The Restart Issues Coordinator has verified (Sat the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" sectio.n on page 2 of the associated work orders.

. Significant items / issues identified during conduct of the work orders are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independ:nt verification.

121

l l

Status:

This is in progress. Work Order 97-02020 has been initiated to perform a visual inspection of portions of the Fuel Transfer System.

The scheduled completion date is March :1,1997.

1 1

1 i

I t i

! j I

l l

1 l

l .

l l

l i

122 l

1

d Point 13each Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 61 I

Commitment

Description:

The work and testing associated with these work orders will be completed prior to the associated component /sy stem being declared operable: Work Orders 9613568 and 9613569 - provide bonnet pressure locking relief for the SI-857A j and SI-857B valves (interface valves between RilR and liigh llead SI) on Unit 2. These are critical, manually operated valves.

Completion Timing: This should be completed prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work orders.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the closed work orders.
  • A summary of the signiGeant items / issues i tentined during conduct of the work I orders and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action
  1. 61).
3. The Restart Issues Coordinator has veri 0ed that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work orders.
  • SigniGcant items / issues identified during conduct of the work orders are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

123

I i

Statils-i The physical work has been satisfhetorily completed. liOP 1.3 must be permanently I revised and additional PMT completed for this to be considered complete.

The scheduled completion date is March 15,1997.  !

1 I

l 1

124

Point Beach Nuclear Plant Un t 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 62 Commitment

Description:

The work and testing associated with this work order will be completed prior to the associated component / system being declared operable: Work Order 9611757 - correct the leakage which leads to boric acid buildup in the cylinder blocks of"B" Charging Pump.

This is a housekeeping issue, not an operability issue. Resolution will bring this into ,

compliance with Maintenance Department housekeeping standards. ,

Completion Timine: The physical work will be completed prior to Unit 2 leaving cold shutdown. PMT requires that the pump be run prior to turbine roll-up.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work order.
2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator:

. A copy of the closed work order.

. A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action n62).

3. The Restart Issues Coordinator has verified that the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above),

e Duty Shift Supervisor's signature and date is on the " Equipment Return to '

Service" section on page 2 of the associated work order.

  • Significant items / issues identified during conduct of the work order are being  !

tracked in a tracking system which is being reviewed per Restart Commitment #22.  !

4. Completion of an independent verification.

125

Status:

The physical work associated with this work order has been completed. and it is awaiting PMT (run the pump prior to turbine roll-up). ,

The scheduled completion date is May 15.1997. ,

l l

l l

l l

l l

i i

126

f i

j Point Beach Nuclear Plant Unit 2 Restart Commitment 3

Summary (March 12,1997)

Commitment ID#: 63 Commitment

Description:

The work and testing associated with this work order will be l

completed prior to the associated component / system being declared operable: Work Order 9603532 - repair the handswitch Ibr 2P-2A, the "A" Charging Pump.

) This handswitch has a history of not operating smoothly, and this was addressed in the past through the use oflubricants. A change in maintenance philosophy prompted the i replacement of this component.

Completion Timine This should be completed prior to Unit 2 leaving cold shutdown.

4 i

3 Criteria to Closcout This Item:

! 1. Completion of the work associated with the listed work order.

, 2. The Responsible Person has thrwarded the following documentation to the Restart 1 Issues Coordinator:

i I 1

. A copy of the closed work order.

. A summary of the significant items / issues identified during conduct of the uork l order and how they were resolved (can simply reference Condition Report numbers l

or other tracking mechanisms) GE a statement that there were none identified I (report using the NUTRK system - NUTRK U2R22 RESTART Action #63).

3. The Restart issues Coordinator has verified that the:

Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.

Significant items / issues identified during conduct of the work order are being J tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

127

l 4

Status: 1 i

The physical work is complete, and the work order is awaiting PMT (running the pump during OP-4 A).

The scheduled completion date is March 28,1997.

1 I l

)

i l

l l

l 128

f Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) 4 Commitment ID#: 64 Commitment J)escription: The work and testing associated with these work orders will be completed prior to the associated component / system being declared operable: Work

Orders 9611624 through 9611626 - replace existing pneumatic turbine generator circuitry
i. time delay relays with plug-in, electronic time delay relays.

i

, The case of calibration and cycle drift will be improved through this change.

Completion Timing; This shot.ld be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

, 1. Completion of the work associated with the listed work orders.

2. The Responsible Person has forwarded the following documentation to the Restart
Issues Coordinator

J

. A copy of the closed work orders. ]

{

  • A summary of the significant items / issues identified during conduct of the work j orders and how they were resolved (can simply reference Condition Report i i numbers or other tracking mechanisms) DE a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action l I
  1. 64).

f l 3. The Restart Issues Coordinator has verified that the:

i e Restart Issues File includes the documentation which the Responsible Person is

]'

required to forward to the Restart issues Co'ordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the " Equipment Return to
Service" section on page 2 of the associated work orders.

. . Significant items / issues identified during conduct of the work orders are being

tracked in a tracking system which is being reviewed per Restart Commitment #22.

1

4. Completion of an independent verification.

2

} 129 1

i

I i

Sallul The work plans have men prepared, and the work order is scheduled.

The scheduled completion date is March 31.1997. j l

I f

I l

l l 130 l

I

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 65 Commitment

Description:

The work and testing associated with this work order will be completed prior to the associated component / system being declared operable: Work Order 9606626 - reinstall switches on the Unit 2 Containment hatch third door to allow monitoring of door status.

There have been recurring human performance errors associated with this door, as people would block it open during refueling operations to transfer equipment. To ensure the operability of this door, switches are being installed to allow remote monitoring ofits status.

Completion Timing: This should be completed prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work order.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator: J e A copy of the closed work order.

l

  • A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) DR a statement that there were none identified  !

(report using the NUTRK system - NUTRK U2R22 RESTART Action #65). l

3. The Restart Issues Coordinator has verified that the:

l e Restart Issues File includes the documentation which the Responsible Person is  ;

required to forward to the Restart Issues Coordinator (see immediately above).  ;

e Duty Shift Supervisor's signature and date is on the " Equipment Return to 1 I

Service" section on page 2 of the associated work order.

e Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

131

-- -a , - _ - -I a-n-A--- -,-,

  • A 4- - -

214 -- ~ --- -- w~^ + - - ---B M =m--J - &h Q- A W-4 4

Status:

Verified closed. The associated documentation was provided to the NRC on February 6 and 10,1997.

t 1

J

]

I i

5 i

s e

i 1

4 I

i E

4 1

4 i

1 132 4

7

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 66 Commitment

Description:

The work and testing associated with this work order will be completed prior to the associated component / system being declared operable: Work Order 9611052 - replace the 2P-10B handswitch, the "B" RilR Pump control switch.

This handswitch has a history of not operating smoothly, and this was addressed in the past through the use oflubricants. A change in maintenance philosophy prompted the replacement of this component.

Completion Timingt This should be completed prior to the Unit 2 core loading.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work order.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the closed work order.

  • A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system NUTRK U2R22 RESTART Action #66).
3. The Restart issues Coordinator has verified that the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.

  • Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

Status:

This is in the closecut verification process.

133

4e4-4 r.d.-*4#4 -.a - +- aA4-s444-, - -.m2-4A%--- e h m_, -, 2+J44s-un-. u m mA 4W..-F3mhs-- ,4m-aF..h4J JJ1 444-s4W+-U_waA4-d%4._. 41444J4 m2 Am 44 A N . 3.a-.J24 _

e h.

i 1

1 a

T 4

4 i

4 J

i i

d 4

f

, i J-4 i

i 134

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 67 Commitment

Description:

The work and testing associated with these work orders will be completed prior to the associated component / system being declared operable: Work Orders 9611198 and 9611199 - repair the body-to-bonnet boric acid leak on CV-307 B (lowside tap for "B" RCP #1 seal d/p) and CV-308B (!:p seal d/p for "B" RCP).

This is a housekeeping issue, not an operability issue. Resolution will bring this into compliance with Maintenance Department housekeeping standards.

Completion Timing: This should be completed prior to the Unit 2 approach to criticality.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work orders.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the closed work orders.
  • A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #67).
3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the " Equipment Return to ,

Service" section on page 2 of the associated work orders. ]

  • Significant items / issues identified during conduct of the work orders are being l tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

1 1

i-135

t

' SL111111

The physical work is complete, and the work order is awaiting PMT (a s isual leak check to atmosphere during the conduct ofIT-235).

The scheduled completion date is May 12,1997, 1

i l l

.i l l

i 1

i 4

] I 1

}

s 1

i i

j 136

a 1

- Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l l

l Commitment IDR1 68 ,

j Commitment Descriptiom Repair valve AR-3511 per Work Order 9513340. The Unit 2 priming air ejector is blank flanged due to air in-leakage through the condenser air l removal isolation valve, AR-3511. This resolves a workaround issue.

i Completion Timing: This should be completed prior to the Unit 2 approach to

criticality.

t Criteria to Closcout This item:

a J

1. Completion of the work associated with the listed work order.

I

2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the closed work order.

j e A summary of the significant items / issues identified during conduct of the work s order and how they were resolved (can simply reference Condition Report numbers j or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #68).

, 3. The Restart Issues Coordinator has verified that the:

4.

e Restart Issues File includes the documentation which the Responsible Person is
required to forward to the Restart issues Coordinator (see immediately abos e t j e Duty Shift Supervisor's signature and date is on the " Equipment Return to j Service" section on page 2 of the associated work order.
  • Significant items / issues identified during conduct of the work order are being
tracked in a tracking system which is being reviewed per Restart Commitment #22.

1

4. Completion of an independent verification.

i Status The physical work associated with this work order is complete, and it is awaiting PMT (a general leak test during the conduct of OP-13A). The scheduled completion date is May 15,1997.

l n

, 137

J..a.S+- 46 .TeJ weM- A... *0 se 6. A M.Pe3L44 Je # ,

- - 654--f4aS=OSS de , , ,44e4b=ma*G-. h- 5444 4 ,ah24b4h44--4 4 4 e.

  • 4e WA -44e&&Jidev64,..-M4e, 4,@e ee.J e.,44M444-hw->J 7 J 6-4 & 4 a auM4 i

I 4

1

.e j d i I.

l 4

i 4

h B

4 i

4 i

I l

- 1 7

1 Il 1

I I

1 I

l i

i .

138

Point Beach Nuclear Plant Unit 2 Restart Commitment l Summary (March 12,1997) i Commitment ID#: 69 Commitment

Description:

Repair the drain valve for the heating steam moisture separator per Work Order 9613451.

l The Unit 2 heating steam moisture separator level has 'seen difficult to maintain during normal operations. Frequent Main Control Board alarms have been receised due to loa level, countering the station's attempt to maintain a black board policy. This will be tested followirig Unit 2 startup.

4 Completion Timine This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

)

! 1. Completion of the work associated with the listed work order. I

2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the closed work order.

. A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numl ers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #69).

3. The Restart Issues Coordinator has verified that the:
  • Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.

. Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

i 139 I

l l

l Stalin I

The physical work associated with this work order is scheduled.

The scheduled completion date is April 7,1997.

I l

1 1

1 l

l l

i 140

1 l

1

]

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Comn11tinent_UM2 70

! Ginmitment Descrintinin Install a new lesel control system for the brine tank fi-l IL

+

per Modification 92-008*Q.

1 j The tank overflows because the installed automatic level control system is not efleenve. t and there is no high-high level alarm for the tank. This has been a recurring human l

performance issue exasperated by design. This modification will minimize the human

) performam challenges.

)

Cntnpletion Timing: This should be in an accepted status prior to the Unit 2 approach to l

criticality. l I

Criteria to Closcout This Itenu

1. The modification is in an accepted status.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator- i 1

. A copy of the completed Installation Work Package.

. A summary of the significant items / issues identified during conduct of the l

modification and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there wtre none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action

  1. 70).
3. The Restart Issues Coordinator has verified that the: I e Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issnes Coordinator (see immediately at>ove).
  • Duty Shift Supervisor's signature and date is on the copy of the Installation Work Package page.
  • Significant items / issues identified during conduct of the modification are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

141

i l

Status I

This is in the closecut verification precess.

l l

I I

I l

142

I Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 71 Commitment

Description:

Repair MS 749, the Unit 2 steam line sample vah e. per Work Order 9603128.

This valve had a packing leak, which required steam h ader sampling to be shifled to the B steam header. This repair will restore the ability to sample normally and resolves a workaround issue.

Completion Timine: This should be completed prior to the Unit 2 approach to l criticality. I Criteria to Closcout This Item:

1. Completion of the work associated with the listed work order.

l

2. The Responsible Person has forwarded the following documentation to the Restart l Issues Coordinator.

l

  • A copy of the closed work order. l
  • A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #71).

1

3. The Restart Issues Coordinator has verified that the: i

+ Restart issues File includes the documentation which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.
  • Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment It22.
4. . Completion of an independent verification.

143

)

Status:

The physical work is complete, and the work order is awaiting PMT (general leak test during OP-13 A). 1 The scheduled completion date is May 15,1997.

l l

l 1

l l

l l

l I

1 144

.sM... - -4+D4e P a 14 e 414 - m e :q--,m_

g --& .1.4 - a a _J. 42am._e .a6a .s A-* _ .w_

1 l

l l

Point Beach Nuclear Plant Unit 2 Restart Commitment l Summary (March 12,1997) l Commitment ID#: 72 Commitment

Description:

Repair alarm switch 21.S-2511 per Work Order 9605711.

The Unit 2 D MSR level was being maintained low in the band due to level oscillations and a steam leak from the alarm switch.

Completion Timine The physical work should be completed prior to Unit 2 leaving cold shutdown. PMT needs to be conducted at 75% reactor power.

Crittria to Closeout This Item:

1. Completion of the work associated with the listed work order.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A copy of the closed work order.
  • A summary of the significant items / issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #72).
3. The Restart Issues Coordinator has verified that the:
  • Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).
  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.

. Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Stattm The physical work is complete, and the work order is awaiting PMT (leak test at 75%

power). The scheduled completion date is May 17.1997.

145

~* M &MM4 44 48*,.4.4.4 3 4w, e A, A . e 4.qs.g.4_O .de,4_g4_g g,4y g g ,,,,4 g 44 g ,gj g__

r i

i l

l I

i 1

i i

I

)

r 146

Point Beach Nuclear Plant Unit 2 Restart Commitment Sum mary (March 12,1997)

Commitment ID#: 73 Commitment

Description:

Repair 2P116. the Unit 2 Boric Acid Recirculation Pump.

per Work Order 9603130.

There have been recurrent, significant seal leaks due to the pump's design and application. This work order replaces the current pump with a seal-less pump.

Completion Timine: This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. Completion of the work associated with the listed work order.
2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:

. A copy of the closed work order.

. A summary of the significant items! issues identified during conduct of the work order and how they were resolved (can simply reference Condition Report nunibers or other tracking mechanisms) M a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #73).

3. The Restart Issues Coordinator has verified . hat the:

. Restart Issues File includes the documentation which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above).

  • Duty Shift Supervisor's signature and date is on the " Equipment Return to Service" section on page 2 of the associated work order.

. Significant items / issues identified during conduct of the work order are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status:

The physical work is scheduled to begin on March 17.1997.

The scheduled completion date is March 21.1997.

147

,Ja.ma-meAma. me e a w w e.4-F,. 4<a Ne85d-JA.-a*+=68alddf6a A.4 e e l a65. m.mp ee. h4 a.4NM AEL ;dd fodae h-W_ eda .p e d a4biM ,"aq5 M e.B d F_ J45 ship 4 p .MMg4 m #r,m a ge AM A.L.m p.4MA. HAM Jipf4h M4(4- 4 # 4dh.4,MdehMt.de. 4MA haMed M MM A&4hd4a.4MMW.,

E 4

4 e

f~

4' 4-1 d

3

}'

I I

A i

I' e

j :-

i r

1 d

I' f

4 4-I l

I t

I e

6 k

l e

4 I

a i

l' 8

e 1

e t-i 4

1 1

l i

9 I

t

  • e I.

! I48 s

d i'

W I

x- -... ,- . ..-... _ . ...,., . . - . . ... - - - - . . - , - . -.-, .. ..-.. ,_ . ..,- . . -.- .

Point lleach Nuclear Plant Unit 2 Restart Commitment Snm mary (Mareli 12,1997)

Commitment ID#: 74 Commitment Descrintion: Each operating crew will receive simulator training to gain proficiency in casualty response, the expected response of the newly installed steam generators and reactor core, and placing the turbine on-line.

This simulator training will consist of :

. Bringing the turbine on-line (from no load on the turning gear to about 15% power).

. Reviewing the differences in steam generator response between Units 1 and 2.

  • Conducting normal trips and identifying the differences in response between Units 1 and 2.
  • Addressing instrument failure response differences between Units 1 and 2.

. Conducting casualty response dynamic scenarios.

Completion Timine: This will be completed prior to the Unit 2 approach to criticality .

l 1

Criteria to Closcout This Item:  :

1

1. Completion of the training defined in the " Commitment Description" section.
2. The Responsible Person haa forwarded the following documentation to the Restart Issues Coordinator:

. A summary / document describing what was covered in the simulator training 1 (report using the NUTRK system - NUTRK U2R22 RESTART Action # 74). l

. Copies of the attendance sheets for the simulator training.

. Significant items / issues identified during conduct of this task and how they were

resolved (can simply reference Condition Report numbers or other tracking mechanisms) DE a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action #74).
3. The Restart issues Coordina;or has verified that the:
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

e Significant items / issues identified during conduct of the review are being tracked l in a tracking system which is being reviewed per Restart Commitment #22.

, 4. Completion of an independent verification.

I 149

a Status:

The crew training commenced on January 13,1997 as part of LOR training cycle 97-1.

The operating crews will be trained during their normal requalification weeks. One Operator remains to be trained. The scheduled completion date fbr this is March 15.

I997.

i I50

1 l

i Point Beach Nuclear Plant Unit 2 Restart Commitment 3 Summary (March 12,1997) i Commitment ID#: 75 l i

Commitment

Description:

Revise the initial and requalification operator training plans to include a review of the administrative procedures identified as significant to daily operation of the plant during each two year operations training plan.

This commitment is also Enforcement Conference Commitment Item # 20.

Completion Timing 1 This should be completed prior to the Unit 2 approach to  !

criticality.

)

l Criteria to Closcout This Item:

1. Completion of the task defined in the " Commitment Description" section.  !
2. The Responsible Person has forwarded the following to the Enforcemem Conference Commitments Coordinator:

. A copy of the initial and requalification operator training plans which includes a review of the administrative procedures identified as significant to daily operation of the plant during each two year operations training plan.

. When the actions described in the " Commitments Description" section were completed (report using the NUTRK system).

. Significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system);

3. The Restart issues Coordinator or the Enforcement Conference Commitments Coordinator have verified that the:
  • Restart Issues File includes the documents which the Responsible Person is required to forward to the Enforcement Conference Commitments Coordinator (see immediately above).
  • Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
4. Completion of an independent verification.

151

Status:

Verified closed by the Enforcement Conference Conunitments Coordinator. The independent verification is in progress.

The associated documentation was provided to the NRC in the January 24,1997 weekly management meeting.

i l

i 152 l i

l

1 1

1 l

l Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 76 1

Commitment

Description:

Conduct roundtable discussions with all MSS \SS\DTA  !

personnel regarding conservative decisionmaking, Technical Specification interpretations, and lessons learned from recent regulatory communications and perspectives. Review outlier Tculmical Specification interpretations for interim 1 applications.

Completion Timing: This should be completed prior to the Unit 2 fuel loading.

Criteria to Closcout This Item:

1. Completion of the roundtable discussions defined in the " Commitment Description" section.
2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator: '

. A summary / document describing what was covered in the roundtable discussions (report using the NUTRK system - NUTRE U2R22 RESTART Action # 76).

. Copies of the attendance sheets for the roundtable discussions.

Significant item 3/ issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) GR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 76).

3. The Restart issues Coordinator has verified that the:

Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment u22.

4. Completion of an independent verification.

153

l l

l Status: I i

This is in progress. I 1

  • The first round table discussion was held on February 6.1997. where 10 of i 1 DTAs I l

attended,9 of 13 Operations management personnel attended. and 7 of 38 MSS l members attended. I e The session was videotaped. I 1

Personnel who did not attend the February 6,1997 meeting will be provided the l opportunity to view the videotape (twice offered the week of March 3 and once offered the week of March 10) and afterwards participate in a discussion regarding conservative decisionmaking, Technical Specification interpretations, and lessons learned from recent regulatory communications and perspectives. Outher Technical Specification I interpretations for interim applications will be revic wed.

This is scheduled to be completed by March 14,1997. l l

l 1

l l

i i

I I

154

l Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 77 Commitment

Description:

Complete the procedure changes and training associated with the new Technical Specification on ECCS regarding the new Containment Integrity Analysis.

This involves the implementation of Technical Specification Change Request 192.

Completion Timing This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This Item:

1. Completion of the procedure changes and training defined in the "Conunitment Description" section.
2. The Responsible Person has forwarded the following documentation to the Restart issues Coordinator:
  • A copy of the revised procedures.

. A summary / document describing what was covered in the training (report using the NUTRK system - NUTRK U2R22 RESTART Action # 77).

  • Copies of the attendance sheets for the training.
  • Significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 77).

I

3. The Restart Issues Coordinator has verified that the:

. Restart issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

l l

4. Completion of an independent verification.

155

1 i

i 1

1 Stallis {

^

This is in progress. Training and procedure work have commenced. Further training (as )

needed) will be conducted when the final content of the Technical Specificanon Change is known and the procedure changes have been finalized. )

The scheduled completion date is March 28.1997. l l

l 1

l l

l l

l l

l 156

Point Beach Nuclear Plant Unit 2 Restart Commitment i Summary (March 12,1997)

Commitment ID#: 78 Commitment

Description:

Communicate specific expectations regarding AFW and EDG status control to Operators. I When the P-29 TDAFP should be declared operable has caused confusion since the )

ability to FULLY test it for flow is not available until after reactor criticality. That delas )

in achieving a full flow test has been a confusing point. The Technical Specifications and procedures are adequate.

The AFW status control issue involves AFW pumps tripping on overcurrent when the EDG's are lightly loaded and in an overfrequency condition.

Completion Timine: This should be completed prior to Unit 2 leaving cold shutdown.

Criteria to Closcout This item:

1. Completion of the communication of specific expectations defined in the

" Commitment Description" section.

2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A summary / document describing what was covered in the communications (report i using the NUTRK system - NUTRK U2R22 RESTART Action # 78). )

. Significant items / issues identified during conduct of this task and how they were I resolved (can simply reference Condition Report numbers or other tracking mechanisms) QR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 78).

3. The Restart Issues Coordinator has:

. Verified that the Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart issues Coordinator (see immediately above). l

  • Verified that the significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.
  • Determined that all Operators were informed of these expectations.

IS7

4. Completion of an independent verification. I Suttiin This is in progress.

. The AFW status control expectations have been disseminated via E-Mail.

. It has been found that keeping the AFW pump flowrates less than 250 gpm will prevent the overcurrent condition. This will be disseminated to operators through classroom training (as part of the SOER 96-01 training), as an Operations Notebook entry to explain the controls, and the EOPs will be revised to reflect this.

. An entry into the Operations Notebook regarding AFW status control expectations has been made.

The Operations Notebook entry needs to be reviewed by members of the Operations stafY prior to this being closed-out.

The scheduled completion date is March 15,1997.

158

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitment ID#: 79 l

Commitment

Description:

Restore a proceduralized capability to operate the Containment Spray Pumps in the recirculation mode of the ECCS. This will be included j procedurally in the EOP package.  ;

i Completion Timingt This should be completed prior to Unit 2 leaving cold shutdim o Criteria to Closcout This Itenu j 1

1. Completion of the task defined in the " Commitment Description" section.

I

2. The Responsible Person has forwarded the following documentation to the Restart Issues Coordinator:
  • A summary addressing when the actions described in the " Commitments Description" section were completed and what specifically was done to accomplish l the task (report using the NUTRK system - NUTRK U2R22 RESTART Action #

l 79). l

. Documents initiated or changed as a result of this task. The identification number for each of these must be included in this summary, and a copy sent to the Restart issues Coordinator for inclusion in the Restart issues File. l

. Significant items / issues identified during conduct of this task and how they were I resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 79).

3. The Restart issues Coordinator has verified that the:

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above).

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

159

Stalits Procedure CSPZ.1 is being drafted to address an RiiR pump supplying CS and core deluge alone.

This is scheduled to be completed by April 1,1997.

l l

I 160

4 Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997)

Commitnient ID#: 80 Gommitment Descrintinn; Obtain amendments requested by Change Requests ISS anJ l89 related to Steam Generator replacement; 192 related to Sen ice Water operabihty.

and 194 related to Low Temperature Overpressurization limits. This will include resolution ofissues related to Control Room and offsite dose evaluations for the analyzed ,

events. l Completion Timingt This should be completed prior to Unit 2 leaving cold shutdown.

l Criteria to Closcout This Itemi

1. Completion of the task defined in the " Commitment Description" section.

j

2. The Responsible Person has fonvarded the following documentation to the Restart issues Coordinator:

. When the actions described in the " Commitments Description" section were completed (report using the ~NI'TRK system - NUTRK U2R22 RESTART Action

  1. 80).

. A copy of the amendments.

. Significant items / issues identified during conduct of this task and how they were resolved (can simply reference Condition Report numbers or other tracking mechanisms) OR a statement that there were none identified (report using the NUTRK system - NUTRK U2R22 RESTART Action # 80). I

3. The Restart Issues Coordinator has verilled that the:

. Restart Issues File includes the documents which the Responsible Person is required to forward to the Restart Issues Coordinator (see immediately above). 1

. Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

1 161

1 Status This is in progress.

. Technical Specification Change Request 194 was approved by the NRC on February l 20,1997 and has been implemented as Amendment Number 172 (Unit 1) and  ;

Amendment Number 176 (Unit 2).

. LOCA dose calculations to support Technical Specification Change Requests 188, i 189, and 192 have been provided to the NRC. l

. A team has been formed to address control room ventilation dose concerns with the Operators. l l

This is scheduled to be completed by March 25.1997.

1 i

l 1

l l

l I

l l

l 162

Point Beach Nuclear Plant Unit 2 Restart Commitment Summary (March 12,1997) l Commitment ID#: 81 Commitment Descrintion: Submit the following requests for license amendments resulting from the review of existing Technical Specification interpretations:

i Revise the maximum acceptable power level when crossover steam dumps are ,

inoperable (TS 15.3.4.E). l Revise requirements for offsite power lines availability to address adequacy (TS 15.3.7. A. l .a).

Remove allowances in TS 15.3.1.A.l.a for single reactor coolant pump operation.

Appropriately modify the minimum required boron concentration in the Refueling Water Storage Tanks.

Completion Timing: This should be completed prior to the Unit 2 approach to criticality.

Criteria to Closcout This Item:

1. Completion of the task defined in the " Commitment Description" section.
2. The Responsible Person has forwarded to the Restart issues Coordinator a copy of the requests for the license amendments. l
3. The Restart Issues Coordinator has verified that the:

Restart Issues File includes the documents which the Responsible Person is l required to forward to the Restart issues Coordinator (see immediately above).

Significant items / issues identified during conduct of the review are being tracked in a tracking system which is being reviewed per Restart Commitment #22.

4. Completion of an independent verification.

Status: I This is in progress:

. The crossover steam dump / turbine overspeed request, Technical Specification Change Request 196, has been submitted to the NRC.

. The request to eliminate single RCP operation has been drafted and is being reviewed.

163

l l

+ Offsite power availability changes are being discussed with analysis personnel since the present study does not support an amendment request.

  • The RWST boron concentration request was submitted to the NRC.

This is scheduled to be completed by March 25,1997.

I i

)

L 164