ML24177A293

From kanterella
Jump to navigation Jump to search
Urenco USA – Inspection Schedule for Calendar Year 2025
ML24177A293
Person / Time
Site: 07003103
Issue date: 06/27/2024
From: Robert Williams
NRC/RGN-II/DFFI
To: Lorskulsint P
Louisiana Energy Services, URENCO USA
References
Download: ML24177A293 (3)


Text

Paul Lorskulsint, Chief Nuclear Officer Louisiana Energy Services dba Urenco USA (UUSA)

P.O. Box 1789 Eunice, NM 88231

SUBJECT:

URENCO USA - INSPECTION SCHEDULE FOR CALENDAR YEAR 2025

Dear Paul Lorskulsint,

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Urenco USA (UUSA) facility in calendar year 2025. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that any regional initiative or reactive inspections are not included in the schedule.

If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Timothy Sippel at (404) 997-4525 with any questions or concerns you may have regarding this letter or the inspection schedule.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room, in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert E. Williams, Jr., Chief Projects Branch 1 Division of Fuel Facility Inspection Docket No. 07003103 License No. SNM-2010

Enclosure:

As stated cc w/ encl: Distribution via LISTSERVJune 27, 2024 Signed by Williams, Robert on 06/27/24

ML24177A183 X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available

OFFICE RII/DFFI RII/DFFI RII/DFFI NAME T. Sippel R. Williams T. Vukovinsky DATE 6/26/2024 6/27/2024 6/26/2024 2025 U.S. NUCLEAR REGULATORY COMMISSION INSPECTION/ACTIVITY PLAN FOR URENCO USA

Dates Number of Description/Inspection Procedures (IPs)

Inspectors March 3 - 7 3 Operational Safety 1 (IP 88020)

Nuclear Criticality Safety 1 (IP 88015)

To Be Determined 3 Emergency Preparedness Exercise (IP 88051)

August 25 - 29 3 Nuclear Criticality Safety 2 (IP 88015)

Operational Safety 2 (IP 88020)

September 22 - 26 2 Information Security (Various IPs)

October 20 - 24 2 Plant Modifications Triennial (IP 88072)

Enclosure