January 05, 2023

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - REVISED INTEGRATED INSPECTION REPORT 05000382/2022003

Dear John Ferrick:

On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station, Unit 3. The results of this inspection were originally issued in a report, dated November 1, 2022 (Agencywide Document Access and Management Systems (ADAMS) Accession No. ML22300A103).

The NRC staff subsequently determined that two inspections were recorded in the incorrect subsection of the inspection procedure. This error was due to an administrative oversight; the appropriate inspection was completed in accordance with the respective inspection procedure.

The 71111.01 inspection sample completed on August 31, 2022, was inspecting external flooding, not seasonal extreme weather. The 71114.06 inspection sample completed on September 13, 2022, was inspecting a full site drill, not a limited-scope training exercise for licensed operators. Both inspection samples are now in the correct subsection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Dixon, Jr, Chief Projects Branch D Division of Operating Reactor Safety Docket No. 05000382 License No. NPF-38 Signed by Dixon, John on 01/05/23

Enclosure:

As stated

Inspection Report

Docket Number:

05000382

License Number:

NPF-38

Report Number:

05000382/2022003

Enterprise Identifier:

I-2022-003-0007

Licensee:

Entergy Operations, Inc.

Facility:

Waterford Steam Electric Station, Unit 3

Location:

Killona, LA 70057

Inspection Dates:

July 1, 2022, to September 30, 2022

Inspectors:

D. Childs, Resident Inspector

T. Farina, Senior Operations Engineer

A. Patz, Senior Resident Inspector

Approved By:

John L. Dixon, Jr, Chief

Projects Branch D

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 3 began the inspection period at rated thermal power and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems against external flooding from heavy rains and severe weather due to the potential for hurricane development on August 31, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)emergency feedwater system trains A, B, and AB during and following maintenance on emergency feedwater pump B on July 28, 2022 (2)emergency diesel generator system train B while train A was inoperable during surveillance testing on September 6, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)fire area RAB 2-002, elevation +46.00' reactor auxiliary building main steam isolation valve passage and fire area RAB 3A-003, elevation +21.00' reactor auxiliary building vestibule on July 6, 2022 (2)fire area RAB 32-001, elevation -35.00' auxiliary component cooling water room and pipe penetration area on July 18, 2022 (3)fire area RAB 8B-001, elevation +21.00' reactor auxiliary building switchgear room B on August 12, 2022 (4)fire area RAB 17-001, elevation +21.00' reactor auxiliary building component cooling water pump B room, and fire area RAB 21-001, elevation +21.00' reactor auxiliary building component cooling water heat exchanger B room, on September 1, 2022 (5)fire area RAB 8A-001, elevation +21.00' reactor auxiliary building switchgear room A on September 2, 2022 (6)fire area RAB 25-001, elevation +21.00' reactor auxiliary building decon area on September 27, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) elevation +21.00' component cooling water pump and heat exchanger areas on September 1, 2022

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspector reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exams administered on August 30, 2022.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator simulator training on September 20, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)engineered safety features actuation system train B following auxiliary component cooling water pump B failure to start during testing on September 21, 2022 (2)control room air handling system train B following failure of an electric relay on September 30, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated green risk for motor-driven emergency feedwater pump B outage during the week of July 25, 2022 (2)planned yellow risk due to low-pressure safety injection and containment spray train B outages during the week of August 8, 2022 (3)elevated green risk due to unexpected plant protection system power supply failure during the week of September 6, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)component cooling water system following identification of inleakage on July 28, 2022 (2)reactor trip circuit breakers following surveillance failure on August 5, 2022 (3)feedwater ultrasonic flow meter following erratic indication and repair difficulties on September 8, 2022 (4)containment fan cooler train B following loss of motor control center 317B on September 22, 2022 (5)offsite power following automatic isolation of west switchyard bus on September 29, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1)emergency feedwater pump A after planned maintenance on the motor on July 6, 2022 (2)emergency feedwater pump B after planned maintenance on July 28, 2022 (3)low-pressure safety injection train A header to reactor coolant loop 2A flow control valve SI-139A following planned maintenance on August 9, 2022 (4)containment spray train A header isolation valve CS-125A following planned solenoid replacements on August 11, 2022 (5)component cooling water pump B following corrective maintenance on August 18, 2022 (6)plant stack wide range radiation monitor following identification of incorrect reference values on September 9, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (2 Samples)

(1)dry cooling tower A diesel driven sump pump surveillance testing on August 31, 2022

(2) containment spray pump surveillance testing on September 29, 2022

Inservice Testing (IP Section 03.01) (1 Sample)

(1)steam generator 2 atmospheric dump valve inservice testing on July 21, 2022

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

The inspectors evaluated:

(1)a full site integrated drill for a simulated site area emergency on September 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 3 (July 1, 2021, through June 30, 2022)

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) Unit 3 (July 1, 2021, through June 30, 2022)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 3 (July 1, 2021, through June 30, 2022)

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program and maintenance rule tracking program for potential adverse trends in radiation monitor equipment performance and corrective actions that might be indicative of a more significant safety issue.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On August 30, 2022, the inspectors presented the 71111.11A ARQ exit inspection results to Van Ford, Superintendent, Operations Training, and other members of the licensee staff.

On October 18, 2022, the inspectors presented the integrated inspection results to John Ferrick and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Evaluations

W3F1-2015-0042

Flood Hazard Reevaluation Report

07/21/2015

71111.01

Procedures

OP-901-521

Severe Weather and Flooding

340

OP-009-002

Emergency Diesel Generator

360

71111.04

Procedures

OP-009-003

Emergency Feedwater

2

Calculations

ECF91-010

Combustible Loading Calculation for Fire Area RAB 8

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

22-05705

RAB 17-001

Component Cooling Water Heat Exchanger B Fire Plan

RAB 2-002

Main Steam Isolation Valve Passage

RAB 21-001

Component Cooling Water Pump B Fire Plan

RAB 25-001

RAB +21 Decon Area

RAB 32-001

Auxiliary Component Cooling Water Room & Pipe

Penetration Area

RAB 3A-003

Vestibule

RAB 8A-001

Switchgear Room A

Fire Plans

RAB 8B-001

Reactor Auxiliary Building +21.00' elevation

TCP 22-110

Transient Combustible Permit for Fire Area RAB 8

04/11/2022

Miscellaneous

TCP 22-116

Transient Combustible Permit for Fire Zone RAB 8A

04/18/2022

EN-DC-161

Control of Combustibles

EN-DC-161

Control of Combustibles

Procedures

MM-006-106

Plant Door Maintenance

335

71111.05

Work Orders

2969317

71111.06

Calculations

MNQ3-5

Flooding Analysis Outside Containment

71111.11A

Miscellaneous

N/A

22 Annual NRC Operating Test Results

08/29/2022

EN-TQ-100

Operations Training Program Description

OP-902-000

Standard Post Trip Actions

71111.11Q

Procedures

OP-902-003

Loss of Offsite Power / Loss of Forced Circulation

CR-WF3-YYYY-

NNNN

22-1562, 2022-3627

71111.12

Corrective Action

Documents

WF3-CR-YYYY-

22-04666

06/15/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

XXXX

SD-CC

Component Cooling Water

SD-PPS

Plant Protection System

Miscellaneous

W3-DBD-38

Safety Related HVAC - Control Room

2

EN-FAP-LI-001

Performance Improvement Review Group (PRG) Process

EN-LI-102

Corrective Action Program

EN-LI-118

Causal Evaluation Process

Procedures

OP-903-068

Emergency Diesel Generator and Subgroup Relay

Operability Verification

26

Corrective Action

Documents

CR-WF3-YYYY-

XXXXX

22-06304

09/06/2022

Tagout : 2022-0106-LPSI Pump A

08/09/2022

Tagout: 2022-0107-CS Train A

08/09/2022

Miscellaneous

Tagout: 2022-0108-

0809/2022

Procedures

EN-OP-119

Protected Equipment Postings

2980548, 52988875

71111.13

Work Orders

WO 53000802

09/06/2022

Corrective Action

Documents

CR-WF3-YYYY-

XXXXX

22-5674

08/05/2022

Engineering

Changes

ER-W3-2002-

0519-000

Install Software to Improve Path Reliability on LEFM

10/31/2002

DES-I-018

Feedwater Flow Measurement Instrumentation Specification

for Main Feedwater System

DES-I-018

Feedwater Flow Measurement Instrumentation Specification

for Main Feedwater System

71111.15

Miscellaneous

Technical

Requirements

Manual 0

Technical Requirements Manual - Amendment 17

177

ME-004-330

4kV Induction Motor Maintenance

304

ME-007-008

Motor Operated Valves

MI-004-644

Testing of Solenoid Valves

71111.19

Procedures

OP-903-050

Component Cooling Water and Auxiliary Component Cooling

Water Pump and Valve Operability Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-903-121

Safety Systems Quarterly IST Valve Tests

2988875

WO 2952762, 52980548

Work Orders

WO 2946634, 52953000, 52946634, 53006370

08/17/2022

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2019-3025, 2019-3164, 2020-5920, 2020-6021, 2020-7200,

21-0344, 2022-1819, 2022-4487

EC 88384

Operability Input to CR-WF3-2020-6021

10/25/2020

EC 88921

Rebaseline MS-116B

01/25/2021

Engineering

Changes

ECM97-059

Design Basis Review for Atmospheric Dump Valves MS-

116A and MS-116B

001

CEP-IST-4

Standard on Inservice Testing

311

ECS09-005

Air Operated Valves - Design Basis Accident Times

001

OP-100-014

Technical Specification and Technical Requirements

Compliance

364

OP-903-035

Containment Spray Pump Operability Check

OP-903-120

Containment and Miscellaneous Systems Quarterly IST

Valve Tests

035

SEP-WF3-IST-1

WF3 Inservice Testing Bases Document

010

SEP-WF3-IST-2

WF3 Inservice Testing Plan

011

Procedures

W4-DBD-6

Main Steam System - design basis document

2

71111.22

Work Orders

2894192, 52955201, 52860841, 53002488, 552605,

2715847