NRC Initial Test Program and Operational Programs Integrated Inspection Reports 05200025/2021008, 05200026/2021008
ML22040A213
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/10/2022
From: Bradley Davis
NRC/RGN-II
To: Yox M
Southern Nuclear Operating Co
References
IR 2021008
Download: ML22040A213 (44)


Text

February 10, 2022

Mr. Michael Yox Regulatory Affairs Director Southern Nuclear Operating Company 7825 River Road, BIN 63031 Waynesboro, GA 30830

SUBJECT:

VOGTLE ELECTRIC GENERATING PLANT, UNITS 3 AND 4 - NRC INITIAL TEST PROGRAM AND OPERATIONAL PROGRAMS INTEGRATED INSPECTION REPORTS 05200025/2021008, 05200026/2021008

Dear Mr. Yox:

On December 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Vogtle Electric Generating Plant, Units 3 and 4. The enclosed inspection report documents the inspection results, which the inspectors discussed on January 18, 2022, with Mr.

Glen Chick, Vogtle 3 & 4 Executive Vice President, and other licensee and contractor staff members.

The inspection examined a sample of construction activities conducted under your Combined License (COL) as it relates to safety and compliance with the Commissions rules and regulations, and with the conditions of these documents. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

NRC inspectors documented two findings of very low safety significance (Green) in this report.

All of these findings involved a violation of NRC requirements. The NRC is treating these violations as non-cited violations (NCVs), consistent with Section 2.3.2.a of the Enforcement Policy.

M. Yox 2

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any), will be made available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS) component of NRC's document system ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this letter, please contact us.

Sincerely,

/RA/

Bradley J. Davis, Chief Construction Inspection Branch 2 Division of Construction Oversight

Docket Nos.: 5200025, 5200026 License Nos: NPF-91, NPF-92

Enclosure:

NRC Inspection Report (IR) 05200025/2021008, 05200026/2021008 w/attachment: Supplemental Information

cc w/ encl: Distribution via LISTSERV

ML22040A213 X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available

OFFICE RII/DCO/IB1/VCRO RII/DCO/IB1/VCRO RII/DCO/CIB1 RII/DCO/CIB2 NAME JEargle JParent CEven BDavis DATE 02/01/2022 02/01/2022 02/03/2022 2/10/2022

U.S. NUCLEAR REGULATORY COMMISSION Region II

Docket Numbers: 5200025 and 5200026

License Numbers: NPF-91 andNPF-92

Report Numbers: 05200025/2021008 and 05200026/2021008

Enterprise Identifiers:I-2021-008-002 and I-2021-008-0003

Licensee: Southern Nuclear Operating Company, Inc.

Facility: Vogtle Units 3 & 4 Combined License

Location: Waynesboro, GA

Inspection Dates: October 1, 2021 through December 31, 2021

Inspectors: J. Eargle, Senior Resident Inspector - Testing, Division of Construction Oversight (DCO)

S. Downey, Senior Reactor Inspector, Division of Reactor Safety (DRS)

C. Even, Senior Construction Inspector, DCO B. Griman, Construction Inspector, DCO N. Hansing, Materials Engineer, Nuclear Reactor Regulation B. Kemker, Senior Resident Inspector, DCO T. Morrissey, Senior Resident Inspector, DCO J. Parent, Resident Inspector, DCO R. Patterson, Physical Security Inspector, DRS M. Riley, Senior Construction Inspector, DCO T. Scarbrough, Sr. Mechanical Engineer, Nuclear Reactor Regulation J. Walker, Emergency Preparedness Inspector, DRS

Approved by: Bradley J. Davis, Chief Construction Inspection Branch 2 Division of Construction Oversight

Enclosure

SUMMARY

OF FINDINGS

Inspection Report (IR) 05200025/2021008, 05200026/2021008; October 1-December 31, 2021; Vogtle Units 3 & 4 COL, initial test program and operational programs integrated inspection report.

This report covers a three-month period of announced inspections of Inspections, Tests, Analysis, and Inspection Criteria (ITAAC), preoperational test program, startup test program, and operational program inspections by resident and regional inspectors. Two findings were determined to be of very low safety significance (Green) by the inspectors. The significance of most findings is indicated by their color (Green, White, Yellow, or Red), using Inspection Manual Chapter (IMC) 2519, Construction Significance Determination Process. Cross-cutting aspects are determined using IMC 0613, Appendix F, Construction Cross-Cutting Areas and Aspects.

All violations of NRC requirements are dispositioned in accordance with the NRCs Enforcement Policy and the temporary enforcement guidance outlined in enforcement guidance memorandum 11-006. The NRCs program for overseeing the safe construction of commercial nuclear power reactors is described in IMC 2506, Construction Reactor Oversight Process General Guidance and Basis Document.

A. NRC-Identified and Self Revealed Findings

(Green) NRC inspectors identified a Green ITAAC finding and associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR 50), Appendix B, Criterion V, Instructions, Procedures, and Drawings, and with an associated Severity Level (SL) IV violation of 52.99(c)(1), ITAAC Closure Notification, for the licensees failure to coordinate and collaborate with the ITAAC Project Team (IPT) to identify and collect ITAAC determination basis input documents for ITAAC C.2.6.09.06 (Index Number 647) to demonstrate the vehicle barrier system could protect against the design basis threat vehicle bombs prior to submitting the ITAAC Closure Notification in accordance with procedure ND-RA-001-006, Development and Approval of ITAAC Submittals (ICN, UIN, PCN). The licensee entered this issue into its corrective action program (CAP) as condition report (CR) 50118429.

The performance deficiency was determined to be more than minor because it represented a substantive failure to establish or implement an adequate program, process, procedure, or quality oversight function. The inspectors determined this finding was of very low safety significance (Green) because the vehicle barrier function was not required per 10 CFR 73.55 at that time. The inspectors determined the finding had a cross-cutting aspect of Conservative Bias in the area of Human Performance. Specifically, the licensee failed to use conservative decision making when submitting the ITAAC Closure Notice (ICN) without all the determination basis input documents finalized. [H.14] (Section 1A04)

(Green) NRC inspectors identified a construction finding of very low safety significance and an associated NCV of 10 CFR, Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to accomplish activities associated with local leak rate testing of electrical penetration 4-IDSC-EY-P29Y in accordance with procedure 4-CNS-ITPP-502, Containment Penetration Leak Rate (Type B) Preoperational Test, Version 1.0. Specifically, the licensee failed to wait for flowmeter readings to stabilize prior to recording the leak rate data and inappropriately declaring the test acceptance criteria met. The licensee entered this issue into its CAP as CR 50116481.

2 The performance deficiency was determined to be of more than minor safety significance and thus a finding because it rendered the quality of a structure, system, or component (SSC) unacceptable or indeterminate and required substantial corrective action. The inspectors determined the finding was associated with the containment and was of very low safety significance (Green) because the issue did not affect a design function. The inspectors determined the finding had a cross-cutting aspect of training, in the area of Human Performance. Specifically, the organization failed to ensure that test personnel were trained to perform tests in a consistent manner. [H.9] (Section 1P01)

B. Licensee-Identified Violations

None

3 REPORT DETAILS

Summary of Plant Construction Status

During this report period for Unit 3, the licensee completed various activities to satisfy aspects of the Vogtle Unit 3 operational programs and initial test program. Post work verification was performed on safety-related and non-safety-related SSCs following the completion of repair and remediation of electrical systems. Class 1E direct current and uninterruptible power supply system (IDS), electrical distribution system, and standby onsite power system testing was performed to verify the functional capability of those systems to support electrical loads during normal and off-normal conditions.

During this report period for Unit 4, the licensee continued with integrated flush activities by flushing portions of chemical volume and control, spent fuel cooling, reactor coolant, residual heat removal, and passive core cooling systems. The licensee started open vessel testing activities which included discharging the passive core cooling system accumulators into the reactor vessel through the direct vessel injection line in order to determine actual flow resistance values between the accumulator and reactor vessel. Local leak rate tests were performed to verify the ability of the containment system to perform its safety-related function of providing containment integrity as a barrier against the release of fission products to the atmosphere. The licensee completed the secondary hydrostatic test to verify the integrity of the welds and mechanical connections as required by the ASME code.

1. CONSTRUCTION REACTOR SAFETY

Cornerstones: Design/Engineering, Procurement/Fabrication, Construction/Installation, Inspection/Testing

IMC 2503, Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) - Related Work Inspections

1A01 (Unit 3) ITAAC Number 2.1.02.11a.i (46) / Family 10C

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.1.02.11a.i (46). The inspectors used the following NRC inspection procedures (IPs)/sections to perform this inspection:

65001.C-02.02 - Construction Test Observation 65001.C-A4.10 - Instrumentation & Control Components & Systems

The inspectors used the appropriate portions of the IP to observe the licensee's performance of the following procedures used to partially verify if the controls in the main control room operate to cause a signal at the squib valves', 3-RCS-V004A and 4C, electrical leads which was capable of actuating the squib valves. The test was observed to verify if the test satisfied the applicable quality and technical requirements of the Updated Final Safety Analysis Report (UFSAR) and the ITAAC.

4 B-GEN-ITPCI-039-F126, RCS-PL-V004A-I1-F Component Test 2, Revision (Rev.) 1 B-GEN-ITPCI-039-F124, RCS-PL-V004A-I1-A Component Test 2, Rev. 1 B-GEN-ITPCI-039-F142, RCS-PL-V004C-I1-F Component Test 2, Rev. 1 B-GEN-ITPCI-039-F140, RCS-PL-V004C-I1-A Component Test 2, Rev. 1

b. Findings

No findings were identified.

1A02 (Unit 3) ITAAC Number 2.1.02.11b.i (48) / Family 10C

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.1.02.11b.i (48). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.C-02.02 - Construction Test Observation 65001.C-A4.10 - Instrumentation & Control Components & Systems

The inspectors used the appropriate portions of the IP to observe the licensee's performance of the following procedures used to partially verify if the controls in the main control room operate to cause a signal at the squib valves', 3-RCS-V004A and 4C, electrical leads which was capable of actuating the squib valves. The test was observed to verify if the test satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

B-GEN-ITPCI-039-F126, RCS-PL-V004A-I1-F Component Test 2, Rev. 1 B-GEN-ITPCI-039-F124, RCS-PL-V004A-I1-A Component Test 2, Rev. 1 B-GEN-ITPCI-039-F142, RCS-PL-V004C-I1-F Component Test 2, Rev. 1 B-GEN-ITPCI-039-F140, RCS-PL-V004C-I1-A Component Test 2, Rev. 1

b. Findings

No findings were identified.

1A03 (Unit 3) ITAAC Number 2.6.09.05a (644) / Family 17D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.6.09.05a (644). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.17-02.14 - Intrusion Detection System Console Display 65001.17-02.15 - Intrusion Detection System Recording

5 The inspectors used appropriate portions of the IPs to review documents and observe SNC perform inspections to determine if the security alarm annunciation, video assessment information and the intrusion detection system concurrently provided visual displays and audible annunciation of alarms in both the central and secondary alarm stations. The inspectors observed licensee testing of the alarm systems and reviewed relevant documentation to verify if the applicable quality and technical requirements of the manufactures requirements, Vogtle 3 security plan, and the ITAAC were satisfied.

b. Findings

No findings were identified.

1A04 (Unit 3) ITAAC Number 2.6.09.06 (647) / Family 17A

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.6.09.06 (647). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.17-02.08 - Vehicle Control Measures

The inspectors used appropriate portions of the IPs to review documents and walkdown the vehicle barrier system (VBS) to determine if the VBS was installed and located at the necessary stand-off distance to protect against the design basis threat vehicle bombs. The inspectors performed walkdowns of the vehicle barrier system and reviewed the applicable documentation associated with the ITAAC to verify if the applicable quality and technical requirements of the Vogtle 3 security plan and the ITAAC were satisfied.

b. Findings

Introduction

NRC inspectors identified a Green ITAAC finding and associated NCV of 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, and with an associated SL IV violation of 52.99(c)(1), ITAAC Closure Notification, for the licensees failure to coordinate and collaborate with the IPT to identify and collect ITAAC determination basis input documents for ITAAC C.2.6.09.06 (Index Number 647) to demonstrate the vehicle barrier system could protect against the design basis threat vehicle bombs prior to submitting the ITAAC Closure Notification in accordance with procedure ND-RA-001-006, Development and Approval of ITAAC Submittals (ICN, UIN, PCN).

6 Description

On October 15, 2021, the licensee submitted the ICN for ITAAC 647 to the NRC per the requirements in 10 CFR 52.99. Subsequent to the submittal, the inspectors performed an inspection and identified there was no analysis or supporting inspection that the vehicle barrier system, including the ditch, could protect against the design basis threat vehicle bombs based upon the standoff distance of the system as required by the ITAAC.

The inspectors requested the Westinghouse calculation which was the basis for the adequacy of whether the ditch would protect against the design basis threat vehicle bomb based upon the standoff distance of the system. The calculation was still in draft status because there were construction activities ongoing that could affect the ability of the ditch to protect against the design basis vehicle threat. Without finalization of the design and a supporting inspection verifying adherence to the design, sufficient design basis information was not provided with the ICN to demonstrate that the vehicle barrier system could protect against the design basis threat vehicle bombs.

Subsequent to the NRC inspectors identifying this issue, the licensee entered this issue into its corrective action program as CR 50118429.

Analysis

The inspectors determined that the failure to follow procedure ND-RA-001-006 to coordinate with the IPT to identify and collect ITAAC determination basis input documents to demonstrate the ITAAC acceptance criteria were satisfied prior to submitting the ITAAC Closure Notification was contrary to 10 CFR 50, Appendix B, Criterion V, and was a performance deficiency. Per the guidance in IMC 0613, Appendix E, Examples of Minor Construction Issues, the performance deficiency was determined to be more than minor because it represented a substantive failure to establish or implement an adequate program, process, procedure, or quality oversight function. Specifically, the licensee failed to demonstrate that the ITAAC acceptance criteria was satisfied prior to submitting the ICN.

This finding is an ITAAC finding because the performance deficiency is material to ITAAC 647. Specifically, the VBS is used to protect against the design basis threat vehicle bomb based upon the stand-off distance. Without the design of the protective ditch being complete, the licensee failed to collect and provide the necessary determination basis input documents to demonstrate the VBS could protect against the design basis threat vehicle bombs in accordance with the ITAAC acceptance criteria.

The inspectors determined the finding was associated with the Inspection/Testing Cornerstone and assessed the finding in accordance with IMC 2519, Construction Significance Determination Process, Appendix A, AP1000 Construction Significance Determination Process, Section 4. The inspectors determined this finding was of very low safety significance (Green) because the vehicle barrier function was not required per 10 CFR 73.55 at that time.

7 In accordance with IMC 0613 Appendix F, Construction Cross-Cutting Areas and Aspects, the inspectors determined the finding had a cross-cutting aspect of Conservative Bias in the area of Human Performance. Specifically, the licensee failed to use conservative decision making when submitting the ICN without all the determination basis input documents finalized. [H.14]

In addition, the Construction Reactor Oversight Processs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.

The inspectors determined that the failure to provide sufficient information within the ICN that the prescribed acceptance criteria were met was a violation of 10 CFR 52.99(c)(1). In accordance with Section 6.5 of the NRC Enforcement Policy, the inspectors determined this was a SL IV violation because the licensee failed to establish, maintain, or implement adequate controls over testing processes that were important to safety. Specifically, the licensee failed to finalize the design of the VBS, including the ditch, and perform inspections of the VBS confirming adherence to the final design.

Enforcement

10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings and shall be accomplished in accordance with these instructions, procedures, or drawings.

Procedure ND-RA-001-006, Section 6.1.2, states, For the ITAAC Determination Basis / ITAAC submittal development, the project manager will coordinate and collaborate with the IPT to identify and collect ITAAC determination basis input documents.

Contrary to the above, since October 15, 2021, the licensee failed to follow procedure ND-RA-001-006 to demonstrate that the ITAAC acceptance criteria were satisfied in its ICN. Specifically, the licensee failed to coordinate and collaborate with the IPT to identify that the design of the ditch would need to be completed and collected as an ITAAC determination basis documents to be included with the ICN to demonstrate the ITAAC acceptance criteria were satisfied.

10 CFR 52.99(c)(1), ITAAC Closure Notification, requires, in part, that ITAAC closure notification must contain sufficient information to demonstrate that the prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria are met.

Contrary to the above, since October 15, 2021, the licensee failed to provide sufficient information that demonstrated that the prescribe inspections, tests, and analyses have been performed and that the prescribed acceptance criteria were met. Specifically, without the final design in place, there was no supporting analysis or inspection to demonstrate the ditch could protect against the design basis threat vehicle bombs.

8 The licensee entered this issue into their corrective action program as CR 50118429. Corrective actions are planned and do not represent an immediate safety concern because the licensee is not required to meet 10 CFR 73.55, Requirements for physical protection of licensed activities in nuclear power reactors against radiological sabotage, at this time. The licensee has planned to complete the construction activities and provide the ITAAC determination basis documents to satisfy the ITAAC acceptance criteria.

Because this violation was not repetitive or willful, and was entered into the licensees CAP, this violation is being treated as an NCV, consistent with Section 2.3.2.a of the NRC Enforcement Policy (NCV 05200025/2021008-01, Failure to Follow Procedure for ITAAC Verification).

1A05 (Unit 3) ITAAC Number C.2.6.09.03a (660) / Family 17A

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number C.2.6.09.03a (660). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.17-02.04 - Isolation Zones

The inspectors used appropriate portions of the IP to review documents and observe SNC perform inspections to determine if the isolation zones existed in outdoor areas adjacent to the physical barrier at the perimeter of the protected area that allows 20 feet of observation and assessment of the activities of people on either side of the barrier. The inspectors performed walkdowns of the isolation zones, observed licensee testing of the isolation zones, and reviewed the applicable documentation associated with the ITAAC and Vogtle 3 security plan to verify if the applicable quality and technical requirements were met.

b. Findings

No findings were identified.

1A06 (Unit 3) ITAAC Number C.2.6.09.03b (661) / Family 17A

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number C.2.6.09.03b (661). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.17-02.04 - Isolation Zones

9 The inspectors used appropriate portions of the IPs to review documents and observe SNC perform inspections to determine if the isolation zones were equipped with intrusion detection equipment that provided the capability to detect and assess unauthorized persons, alarm in the Central Alarm Station and Secondary Alarm Station and remain operable from an uninterruptable power supply in the event of the loss of normal power. Specifically, the inspections observed testing and reviewed documentation to verify if they satisfied the applicable quality and technical requirements of the manufactures requirements, Vogtle 3 security plan, and the ITAAC.

b. Findings

No findings were identified.

1A07 (Unit 3) ITAAC Number C.2.6.09.09 (670) / Family 17D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number C.2.6.09.09 (670). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.17-02.11 - Vital Area Access Controls

The inspectors used appropriate portions of the IPs to review documents and observe SNC perform inspections to determine if emergency exits through the protected area perimeter were alarmed and secured by locking devices that allow prompt egress during an emergency and the emergency exits through the vital area boundaries are locked, alarmed, and equipped with a crash bar to allow for emergency egress. The inspectors observed testing and reviewed documentation to verify if they satisfied the applicable quality and technical requirements of the manufactures, Vogtle 3 security plan, and the ITAAC.

b. Findings

No findings were identified.

1A08 (Unit 3) ITAAC Number 2.1.02.11b.i (48) / Family 10C

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.1.02.11b.i (48). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.C-02.01 - Program and Procedure Reviews

10 The inspectors used appropriate portions of the IP to review procedure B-GEN-ITPCI-001-011, which is used to perform PMS Cabinet Diagnostics, to determine if the procedure satisfied the applicable quality and technical requirements of the UFSAR and ITAAC.

b. Findings

No findings were identified.

1A09 (Unit 3) ITAAC Number 2.5.02.06a.ii (530) / Family 10D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.5.02.06a.ii (530). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.C-02.01 - Program and Procedure Reviews

The inspectors used appropriate portions of the IP to review procedure B-GEN-ITPCI-001-011, which is used to perform PMS Cabinet Diagnostics, to determine if the procedure satisfied the applicable quality and technical requirements of the UFSAR and ITAAC.

b. Findings

No findings were identified.

1A10 (Unit 3) ITAAC Number 2.5.02.08a.ii (540) / Family 10D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.5.02.08a.ii (540). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.C-02.01 - Program and Procedure Reviews

The inspectors used appropriate portions of the IP to review procedure B-GEN-ITPCI-001-011, which is used to perform PMS Cabinet Diagnostics, to determine if the procedure satisfied the applicable quality and technical requirements of the UFSAR and ITAAC.

b. Findings

No findings were identified.

11 1A11 (Unit 3) ITAAC Number 2.5.02.08b.ii (543) / Family 10D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.5.02.08b.ii (543). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.C-02.01 - Program and Procedure Reviews

The inspectors used appropriate portions of the IP to review procedure B-GEN-ITPCI-001-011, which is used to perform PMS Cabinet Diagnostics, to determine if the procedure satisfied the applicable quality and technical requirements of the UFSAR and ITAAC.

b. Findings

No findings were identified.

1A12 (Unit 3) ITAAC Number 2.5.02.09d (548) / Family 10D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.5.02.09d (548). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.C-02.01 - Program and Procedure Reviews

The inspectors used appropriate portions of the IP to review procedure B-GEN-ITPCI-001-011, which is used to perform PMS Cabinet Diagnostics, to determine if the procedure satisfied the applicable quality and technical requirements of the UFSAR and ITAAC.

b. Findings

No findings were identified.

1A13 (Unit 4) ITAAC Number C.2.6.09.08a (668) / Family 17A

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number C.2.6.09.08a (668). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.17-02.02 - Vital Areas/Vital Area Barriers

12 The inspectors performed an inspection to determine if the openings in Vogtle Unit 4 vital area barriers for heating, ventilation, and air conditioning (HVAC) system vents were secured to prevent exploitation of the openings to satisfy the ITAAC and 10 CFR 73.55(e)(4).

The inspectors reviewed the design specifications and associated drawings to identify designated HVAC system openings through vital area barriers and the way they would be secured and monitored. The inspectors examined the physical installation of auxiliary building exterior wall 'Q' HVAC penetration SV4-12306-ML-H04 and two HVAC system openings (SV4-VAS-AS-02 and SV4-VAS-AS-03) to the vital areas during this inspection period. The inspectors performed direct observation inspection of the openings to determine if they were secured in a manner that would delay or prevent exploitation. The inspectors directly inspected the barriers, locking mechanisms, welds, and bolts associated with the openings.

b. Findings

No findings were identified.

IMC 2504, Construction Inspection Program - Inspection of Construction and Operational Programs

1P01 Pre-operational Testing

70702-02.04 - Test Witnessing

a. Inspection Scope

The inspectors used appropriate portions of the IP to observe the licensees performance of the following procedure used to test if the containment system was capable of performing its safety-related function to isolate during required design basis events. The tests were observed to verify if they satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

4-CNS-ITPP-502, Attachment 38, 4-IDSC-EY-P29Y (Electrical Penetration E29) Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 15, 4-DAS-EY-P03Z (Electrical Penetration E03)

Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 36, 4-IDSC-EY-P27Z (Electrical Penetration E27) Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 4, 4-CNS-MY-Y04 (Personnel Hatch H03)

Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 1, 4-CNS-MY-Y01 (Equipment Hatch H01)

Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 2, 4-CNS-MY-Y02 (Maintenance Hatch H02)

Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 5, 4-FHS-MY-Y04 (Fuel Transfer Tube Quick Opening Hatch) Type B Test, Rev. 1

13 4-CNS-ITPP-502, Attachment 10, 4-CNS-PY-C01 (Spare Penetration 40)

O-Rings, Type B Test, Rev. 1 4-CNS-ITPP-502, Attachment 12, 4-CNS-PY-C03 (Spare Penetration 42)

O-Rings, Type B Test, Rev. 1 SV4-CNS-T0W-1265323, EPA retaining rings 4-ECS-P17X, -P18X, -P19X,

-P20X, -P21X, -P22X, P23X, -P24X, and -P25X, Rev. 1

b. Findings

Introduction

NRC inspectors identified a construction finding of very low safety significance and an associated NCV of 10 CFR, Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to accomplish activities associated with local leak rate testing of electrical penetration 4-IDSC-EY-P29Y in accordance with procedure 4-CNS-ITPP-502, Containment Penetration Leak Rate (Type B) Preoperational Test, Version 1.0. Specifically, the licensee failed to wait for flowmeter readings to stabilize prior to recording the leak rate data and inappropriately declaring the test acceptance criteria met.

Description

On November 29, 2021, NRC inspectors observed licensee test personnel performing local leak rate testing of electrical penetration assembly 4-IDSC-EY-P29Y per procedure 4-CNS-ITPP-502. Step 3.15 of the procedure states, in part, that, When both of the following conditions are reached: 1) pressure has stabilized between 58.1 psig and 59.0 psig, and 2) flowmeter readings have stabilized for 10 minutes, record the following data for 4-IDSC-EY-P29Y (Electrical Penetration E29) leakage and in Attachment 42, Table 5. The NRC inspectors observed that the test personnel did not allow the flowmeter readings to stabilize, and the measured leak rate fluctuated above and below the acceptance criteria for the 10-minute duration. After the required 10 minutes had passed, the test personnel determined the test to be satisfactory since the leak rate value satisfied the acceptance criteria. Subsequent to the inspectors questioning the licensee whether the procedure was followed and if the test was satisfactory, SNC reviewed the intent of the procedure steps and the data from the test and concluded that the test was unsatisfactory and required to be retested. The licensee entered this issue into its CAP as CR 50116481.

Analysis

The inspectors determined the failure to accomplish local leak rate testing of electrical penetration 4-IDSC-EY-P29Y in accordance with procedure 4-CNS-ITPP-502 was contrary to 10 CFR 50, Appendix B, Criterion V, and a performance deficiency. The performance deficiency was determined to be of more than minor safety significance and thus a finding because it rendered the quality of an SSC unacceptable or indeterminate and required substantial corrective action. Specifically, the performance deficiency resulted in the local leak rate test of containment penetration 4-IDSC-EY-P29Y being declared unsatisfactory, and the test had to be reperformed.

This violation was determined to be a construction finding.

14 The inspectors concluded the finding was associated with the Inspection/Testing Cornerstone and assessed the finding in accordance with IMC 2519, Construction Significance Determination Process, Section 4. The inspectors determined the finding was associated with the containment and was of very low safety significance because the issue did not affect a design function.

In accordance with IMC 0613, Appendix F, Construction Cross-Cutting Areas and Aspects, the inspectors determined the finding had a cross-cutting aspect of training, in the area of Human Performance. Specifically, the organization failed to ensure that test personnel were trained to perform tests in a consistent manner [H.9].

Enforcement

10 CFR 50, Appendix B, Criterion V, states, in part, Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.

Contrary to the above, on November 29, 2021, the licensee failed to accomplish local leak rate testing of electrical penetration 4-IDSC-EY-P29Y in accordance with procedure 4-CNS-ITPP-502. Specifically, the licensee failed to allow flowmeter readings to stabilize prior to recording the leak rate data, resulting in the licensee inappropriately declaring the test acceptance criteria met. This finding did not present an immediate safety concern because the plant was not operating, and the reactor vessel did not have fuel in it. The licensee entered this issue into its CAP as CR 50116481 and retested the electrical penetration assembly. Because this violation was not repetitive or willful, was of very low safety significance, and was entered into the licensees CAP, this violation is being treated as an NCV consistent with Section 2.3.2.a of the NRC Enforcement Policy (NCV 0500026/2021008-02, Failure to Follow Procedure CNS-ITPP-502).

1P02 Pre-operational Testing

70702-02.04 - Test Witnessing

a. Inspection Scope

The inspectors used appropriate portions of the IP to observe the licensees performance of the following procedures used to test if the containment system was capable of performing its safety-related function to isolate during required design basis events. The tests were observed to verify if they satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

4-CNS-ITPP-503, Attachment 6, Type C Testing of 4-CVS-PY-C02 (CVS Letdown CTMT PEN), Rev. 1 4-CNS-ITPP-503, Attachment 8, Type C Testing of 4-CVS-PY-C04 (CVS Zinc Add CTMT PEN), Rev. 1

15

b. Findings

No findings were identified.

3. OPERATIONAL READINESS

Cornerstones: Operational Programs

IMC 2503, ITAAC - Related Work Inspections

3T01 (Unit 3) ITAAC Number 2.1.03.07.i (78) / Family 05D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.1.03.07.i (78). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.05 - Inspection of ITAAC-Related Installation of Reactor Pressure Vessel and Internals 65001.D-02.03 - Test Results Review

The inspectors used appropriate portions of the IP to review the results of the following procedure used to determine if the as-built reactor internals had no observable damage or loose parts following hot functional testing satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC:

3-RXS-ITPP-501, Pre - and Post - Hot Functional Test Inspection of Reactor Vessel Internals, Rev. 3.0

b. Findings

No findings were identified.

3T02 (Unit 3) ITAAC Number 2.2.03.10 (206) / Family 10A

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.2.03.10 (206). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.D-02.02 - Test Witnessing

The inspectors used appropriate portions of the IP to observe the licensees performance of the following procedure used to verify if the valve opens within 20 seconds after receipt of an actuation signal from the protection and monitoring

16 system (PMS). The test was observed to verify if the test satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

3-GEN-OTS-10-002, Division B Quarterly Valve Stroke Test, Rev. 0.1

The inspectors used portions of the IP to observe the licensees performance of the following procedure used to verify if the valve performed its active safety function after a signal is input to the PMS. The test was observed to verify if the test satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

B-GEN-ITPCI-039-F075, PXS-PL-V015A-S1 Component Test, Rev. 2

b. Findings

No findings were identified.

3T03 (Unit 3) ITAAC Number 2.2.03.11b.i (209) / Family 10D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.2.03.11b.i (209). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.D-02.02 - Test Witnessing

The inspectors used appropriate portions of the IP to observe the licensees performance of the following procedure used to partially verify if the squib valves received an electrical signal at the valve electrical leads that was capable of actuating the valve after a signal is input to the PMS. The test was observed to verify if the test satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

B-GEN-ITPCI-039-F098, PXS-PL-V120B-I1-F Component Test 2, Rev. 2 B-GEN-ITPCI-039-F102, PXS-PL-V123A-I1-F Component Test 2, Rev. 2 B-GEN-ITPCI-039-F114, PXS-PL-V125B-I1-F Component Test 2, Rev. 1

b. Findings

No findings were identified.

3T04 (Unit 3) ITAAC Number 2.6.03.04c (603) / Family 08D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 2.6.03.04c (603). The inspectors used the following NRC IPs/sections to perform this inspection:

17 65001.D-02.02 - Test Witnessing

The inspectors used appropriate portions of the IP to observe the licensees performance of the following procedure used to test if Division D and spare IDS 24-hour battery banks could supply their DC switchboard bus loads for a period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without recharging. The inspectors also observed the licensees performance of the following procedure used to test if Division C IDS 72-hour battery bank could supply its DC switchboard bus load for a period of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> without recharging. The tests were observed to verify if they satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

3-IDS-ITPP-501, Class 1E and UPS Preoperational Test, Version 8.0

b. Findings

No findings were identified.

3T05 (Unit 3) ITAAC Number 3.3.00.10.i (815) / Family 06D

a. Inspection Scope

The inspectors performed a direct inspection of construction activities associated with ITAAC Number 3.3.00.10.i (815). The inspectors used the following NRC IPs/sections to perform this inspection:

65001.D-02.02 - Test Witnessing 65001.D-02.03 - Test Results Review

The inspectors used appropriate portions of the IP to observe the licensee's performance of the following procedure used to verify if the leakage from the passive containment cooling system (PCS) storage tank to the leak chase collection system did not exceed 10 gallons per hour. The test was observed to verify if the test satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

3-PCS-ITPP-502, Passive Containment Cooling System Preoperational Test Procedure, Rev. 2

The inspectors used appropriate portions of the IP to review the licensee's test results in the following report to determine if the total water flow from the leak chase collection system did not exceed 10 gal/hr. The test was observed to verify if the test satisfied the applicable quality and technical requirements of the UFSAR and the ITAAC.

SV3-PCS-ITR-800815, Unit 3 Test Results for PCCWST Leakage into the Leak Chase Collection System: ITAAC 3.3.00.10.i, Rev. 0

b. Findings

No findings were identified.

18 IMC 2504, Construction Inspection Program - Inspection of Construction and Operational Programs

3P01 Emergency Preparedness

82002-Att4 - Emergency Preparedness Exercises

a. Inspection Scope

The licensee conducted the first of two full participation exercises on September 23, 2020 (ADAMS Accession Number ML20315A137). The exercise demonstrated the requirements of 10 CFR 50, Appendix E, Section IV.F.2.a.ii, for emergency preparedness. However, the September 2020 exercise assumed a fuel load date within first quarter 2021 that was postponed to 2022. Thus, the requirement that a full participation exercise that tests the licensees onsite emergency plans be conducted within a year before the scheduled date of initial fuel loading had to be re-established. The licensee conducted a second pre-operational full participation exercise on December 14, 2021, to satisfy the requirement.

The inspectors performed direct inspection of the second pre-operational Unit 3 graded exercise. The inspection evaluated the licensees process to determine if the conduct of the exercise supports the finding that the emergency preparedness (EP) program demonstrates reasonable assurance that the licensee can effectively implement its emergency plan (E-Plan) to adequately protect public health and safety in the event of a radiological emergency. The inspection also verified there were no E-Plan changes. The inspectors observed the licensees performance of the drill to verify if the requirements of the E-Plan, 10 CFR Appendix E, and 10 CFR 50.47(b) were satisfied.

b. Findings

No findings were identified.

3P02 Inservice Testing (IST)

73054-02.03 - Program Scope 73054-02.04 - Quality Assurance Program

a. Inspection Scope

The inspectors performed the following activities related to the development of the Vogtle Units 3 & 4 IST Programs for pumps, valves, and dynamic restraints that will perform safety-related functions at Vogtle Units 3 & 4:

The inspectors reviewed the following IST procedures to verify that they met the applicable testing requirements of 10 CFR 50.55a and the American Society of Mechanical Engineers (ASME) Operations and Maintenance (OM)

Code, and support the implementation of the IST program:

19 o 3-CAS-OTS-17-001, Compressed and Instrument Air Systems Check Valve Exercise, Rev. B=0.1 o 3-CCS-OTS-10-001, Component Cooling Water System Valve Stroke Test, Rev. C=0.2 o 3-CCS-OTS-17-002, Component Cooling Water System Check Valve Exercise, Rev. A=0.0 o 3-CNS-OTS-18-001, Containment Isolation Actuation Test, Version B=0.1 o 3-CVS-OTS-10-001, Chemical and Volume Control System Valve Stroke Test, Rev. E=0.4 o 3-CVS-OTS-10-002, Chemical and Volume Control System Check Valve Exercise Test, Rev. B=0.1 o 3-CVS-OTS-17-001, Chemical and Volume Control System Reactor Coolant System Leakage Test, Rev. D=0.3 o 3-MTS-OTS-10-001-V0.2-01, TPC for Main Turbine Inservice Valve Test, Rev. C=0.2 o 3-PXS-OTS-10-004, Passive Core Cooling System Pressure Isolation Valve Leak Test, Rev. A=0.0 o 3-RCS-OTS-10-001, Reactor Coolant System Valve Stroke Test, Rev. C=0.2 o 3-SGS-OTS-10-003, Steam Generating System Valve Stroke Test Train A Modes 3-6, Rev. C=0.2 o 3-SGS-OTS-10-004, Steam Generating System Valve Stroke Test Train B Modes 3-6, Rev. C=0.2 o NMP-ES-017-007, MOV Diagnostic Procedure for QUIKLOOK 3, Rev. 1.1

The inspectors reviewed Technical Evaluations Quality Record 60018184 (4-13-2020) that the licensee prepared to address 10 CFR 50.55a requirements for verifying remote valve position indication. The inspectors also reviewed the licensees check valve condition monitoring program document NMP-ES-013-003 for consistency with the provisions in the ASME OM Code, Appendix II, Check Valve Condition Monitoring Program, as incorporated by reference in 10 CFR 50.55a.

b. Findings

No findings were identified.

3P03 Preservice Testing (PST)

73758-App C - Appendix C. Implementation of PST/IST Program for Pumps, Valves, and Dynamic Restraints 73758-Att2.02.04 - Design-Basis Verification, Preservice Testing and Inservice Testing 73758-Att2.02.06 - Preventive Maintenance

a. Inspection Scope

20 The inspectors performed the following activities related to the development of the Vogtle Units 3 & 4 IST Programs for pumps, valves, and dynamic restraints that perform safety-related functions at Vogtle Units 3 & 4:

The inspectors reviewed the licensees disposition of operating experience (OpE) for Main Steam Isolation Valves (MSIVs) and determined that the licensees actions provided reasonable assurance that the issue identified in the OpE will not adversely impact the plant during operation. Specifically, the inspectors evaluated the licensees procedures for periodic testing and surveillance activities for MSIVs to determine whether degradation in valve performance was occurring over time that might result in the MSIVs being incapable of performing their safety functions. This included as review of APP-GW-GF-105, APOG GC: NRC 2015-13: Main Steam Isolation Valve Failure Events, which describes the licensee review of MSIV OpE up to 2016. The inspectors also reviewed NMP-GM-008, Operating Experience Program, and other documents, that contained the licensees evaluation of more recent OpE.

The inspectors reviewed work packages for static diagnostic testing, PST procedures, and PST results for the following sample of motor-operated valves (MOVs) to verify that the requirements of 10 CFR 50.55a and the ASME OM Code had been met.

o CCS-PL-V200, Cooling Water Supply Containment Isolation Valve o CCS-PL-V208, Cooling Water Return Containment Isolation Valve o CVS-PL-V003, CVS Purification Stop Valve o PXS-PL-V117B, Containment Recirculation Sump B to RCS Isolation Valve o RCS-PL-V002A, ADS Stage 2 Control Valve o RCS-PL-V002B, ADS Stage 2 Control Valve o RCS-PL-V003A, ADS Stage 3 Control Valve o RCS-PL-V003B, ADS Stage 3 Control Valve o RCS-PL-V011A, ADS Stage 1 Isolation Valve o RCS-PL-V012A, ADS Stage 2 Isolation Valve o RCS-PL-V013B, ADS Stage 3 Isolation Valve o RNS-PL-V001B, RNS Suction from RCS Inner Isolation Valve o RNS-PL-V002B, RNS Suction from RCS Outer Isolation /

IC Containment Isolation Valve o SGS-PL-V027A, Steam Generator 1 PORV Isolation Valve o SGS-PL-V027B, Steam Generator 2 PORV Isolation Valve o VBS-PL-V186, MCR Supply Air Isolation Valve o VBS-PL-V188, MCR Return Air Isolation Valve o VFS-PL-800A, Containment Vacuum Relief Valve Isolation Valve A o VFS-PL-800B, Containment Vacuum Relief Isolation Valve B

21 The inspectors reviewed one sample of a test work package for Class 1 Pressurizer Safety Valve RCS-PL-V005A to confirm if the manufacturers testing in advance of the pretesting prior to fuel loading was planned by the licensee. The inspectors confirmed the resolution of the licensees identification of discrepancies in live load packing configuration datasheets for PV01 valves described in AP1000 Nonconformance & Disposition Report SV3-PV01-GNR-000028 (7-3-2020), CR 50054618 (6-29-2020), and Corrective Actions Quality Record (CAR) 80003016 (6-29-2020).

b. Findings

No findings were identified.

4. OTHER INSPECTION RESULTS

4OA6 Meetings, Including Exit

.1 Exit Meeting.

On January 18, 2022, the inspectors presented the inspection results to Mr. G.

Chick, Vogtle 3&4 Executive Vice President, and other licensee and contractor staff members. Proprietary information was reviewed during the inspection period, but was not included in the inspection report.

22 SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensees and Contractor Personnel

A. Nix, NI Manager K. Roberts, ITAAC Manager M. Hickox, Test Support Manager C. Alexander, Milestone Manager S. Boyle, Milestone Manager D. Pagan-Diaz, ITP Turnover. Manager J. Olsen, NI Supervisor N. Kellenberger, SNC Licensing Supervisor C. Castell, SNC Licensing Engineer N. Patel, SNC Licensing Engineer N. Chapman, SNC Licensing Engineer J. Weathersby, SNC Licensing Engineer C. Main, ITAAC Project Manager D. Wade, ITAAC Project Manager B. Macioce, Principle Engineer Digital Testing R. McKay, ITP Test Engineer S. Turner, ITP Test Engineer G. Weaver, ITP Test Engineer R. Nicoletto, ITP Test Engineer W. Pipkins, ITP Test Engineer D. Melton, ITP Test Engineer R. Espara, ITP Test Engineer J. Clark, ITP Test Engineer K. Morgan, ITP Test Engineer

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Item Number Type Status Description

05200025/2021008-01 NCV Open Failure to Prescribe Instructions or Procedures for ITAAC Activities that Affect Quality

05200026/2021008-02 NCV Open/Closed Failure to Follow Procedure CNS-ITPP-502

23 LIST OF DOCUMENTS REVIEWED

Section 1A01 WO 1109896 WO 1237895

Section 1A02 WO 1109896 WO 1237895

Section 1A03 Acceptance Testing documentation for IDS zones 63-71, 84-92, and zones A-F V-SSO-2021 7 Day Testing of the Security Perimeter and Duress Systems, April 30, 2021 3 SES ITAAC-661-UPS01 PA IDS/Assessment-UPS01, Rev. 1.1 3-SES-MIS-001-Site Security System (SES) Perimeter Intrusion Detection Tests, Rev. 4.0 SV3-SES-ITR-800644, Intrusion Detection/Video Assessment Testing: ITAAC 1.6.09.05a, Rev. 0

Section 1A04 3-PCS-ITPP-502, Passive Containment Cooling System Preoperational Test Procedure, Rev. 2.0 WO: 1056002 CR: 50112120, 50112128 SV3-PCS-ITR-800815, Unit 3 Test Results for PCCWST Leakage into the Leak Chase Collection System: ITAAC 3.3.00.10.i, Rev. 0 ITAAC Closure Notification on Completion of Item 3.3.00.10.i [Index Number 815] Letter

Section 1A05 Acceptance Testing documentation for IDS zones 63-71, 84-92, and zones A-F V-SSO-2021 7 Day Testing of the Security Perimeter and Duress Systems, April 30, 2021 3 SES ITAAC-661-UPS01 PA IDS/Assessment-UPS01, Rev. 1.1 3-SES-MIS-001-Site Security System (SES) Perimeter Intrusion Detection Tests, Rev. 4.0

Section 1A06 SV3-SES-ITR-800670, Protected Area Perimeter and Vital Area Boundary Emergency Exit Test, Rev. 0 C.2.6.09.09-U3-CP, ITAAC Completion Package, Rev. 0 VEGP Unit 3 and Unit 4 Physical Security Plan, Rev. 6

Section 1A07 APP-GW-MD-103, HVAC Details Sheet 1, Rev. 1 APP-MD03-V2-850003, DFDAF-330 Damper Schedule, Rev. O 315-FDG-GH-ZZ2875313, Fire Damper Grating Assembly, Rev. 1 APP-VBS-MD-504, HVAC Layout VBS Exh & Ret Duct (CSA) Isometric Annex Building Area 1 El 135'-3", Rev. 3 SV4-12306-GNR-000001, Wall Q Penetration 12306-ML-H04 Specialty Device (ESR 50058583), Rev. 0 APP-GW-MD-103, HVAC Details Sheet 1, Rev. 1 APP-CE01-CE-870514, HVAC Penetration Missile Barrier - Wall Q-Anchorage Option 2, Rev. B

24 SV4-1231-SS-905, Auxiliary Building HVAC Penetration Missile Barrier Wall Q Area 1 El. 100'-0", Rev. 0 APP-MD03-Z0D-004, "VAS Fire, Smoke, Combination Fire/Smoke Damper & Blast Damper Data Sheet Seismic Category II," Rev. 16 APP-VAS-MD-548, "Auxiliary Building Area 4 Elevation 145'-9" VAS Duct Iso View," Rev. 7 Engineering & Design Coordination Report No. APP-SES-GEF-031, "Updates to Barrier Matrix,"

Rev. 0 APP-AS21-A1-001, "AP1000 Security Barrier Design Requirements," Rev. 1

Section 1A08 B-GEN-ITPCI-001-011, PMS-Cabinets - Cabinet Diagnostics, Rev. 1.2

Section 1A09 B-GEN-ITPCI-001-011, PMS-Cabinets - Cabinet Diagnostics, Rev. 1.2

Section 1A10 B-GEN-ITPCI-001-011, PMS-Cabinets - Cabinet Diagnostics, Rev. 1.2

Section 1A11 B-GEN-ITPCI-001-011, PMS-Cabinets - Cabinet Diagnostics, Rev. 1.2

Section 1A12 B-GEN-ITPCI-001-011, PMS-Cabinets - Cabinet Diagnostics, Rev. 1.2

Section 1P01 4-CNS-ITPP-502, Containment Penetration Leak Rate (Type B) Preoperational Test, Rev. 1.0 Work Order SV4-CNS-T0W-1265323, Perform (LLRT) on EPA Retaining Rings Work Order SV4-CNS-T0W-1198235, Perform Pre-op LLRT Test (4-CNS-ITPP-502)

Section 1P02 WO: 1198239

3. OPERATIONAL READINESS

Section 3T01 3-GEN-ITPP-517, Precore Hot Functional Test Procedure, Rev. 5 APP-CVAP-GER-003, Comprehensive Vibration Assessment Program (CVAP) Vibration Analysis Program for the AP1000 Plant, Rev. 0 APP-CVAP-GER-004, Comprehensive Vibration Assessment Program (CVAP) Measurement and Inspection Programs for the AP1000 Plant, Rev. 0 APP-CVAP-T2I-001, AP1000 Comprehensive Vibration Assessment Program (CVAP) Pre and Post Host Functional Test (HFT) Visual Inspection Instructions, Rev. 0 APP-MI01-Z0M-001, AP1000 RVI Installation Requirements Manual CV3-CVAP-T2R-300 (Final Report), Comprehensive Vibration Assessment Program (CVAP)

Final Report for the Southern Vogtle Unit 3 (SV3) AP1000 Plant, Rev. 0 ND-21-0956 ICN Letter, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i

[Index Number 78], 12/21/21 SV0-RCS-VQQ-800060, Vogtle Unit 3 AP1000 Reactor Vessel Internals (RVI) Customization, Installation, Inspection, Testing and Final Cleaning (SV3-RXS-MJR-MI01), Rev. 1

25 SV3-CVAP-T2R-100, Vogtle Unit 3 Pre-Hot Functional Test Visual Report of the AP1000 Reactor Vessel Internals, Rev. 0 SV3-CVAP-T2R-400, Vogtle Unit 3 Post-Hot Functional Test Visual Report of the AP1000 Reactor Vessel Internals, Rev. 0 SV3-MI01-GNR-000041, Neutron Shield Panel Gaps (ESR 50106207), Rev. 0 SV3-MI01-S3R-001, Southern Vogtle Unit 3 Reactor Vessel Internals Summary Design Report, Rev. 1 SV3-RXS-ITR-800078, Unit 3 Reactor Vessel Pre and Post Hot Functional Test Inspection:

ITAAC 2.1.03.07.i, NRC Index Number: 78, Rev. 2 SVP_SV0_006481, Submittal of Inspections, Test, Analyses, and Acceptance Criteria (ITAAC)

Completion Package Documents for Unit 3 ITAAC, 12/10/21 WDI-PJF-1323441-FSR-001, CVAP Pre and Post Hot Functional Test Visual Inspection Field Service Report, Rev. 1 ESRs: 50107475, 50105649, 50105240, 50104641, 50106207, 50105705 NCRs: NCR-915281-028, NCR-915281-028, NCR-915281-027 WO: 1061754

Section 3T02 B-GEN-ITPCI-039-F075, PXS-PL-V015A-S1 Component Test, Rev. 2.0 3-GEN-OTS-10-002, Division B Quarterly Valve Stroke Test, Rev. 0.1 WO 1109882

Section 3T03 WO 1237842

Section 3T04 WO 1124423

Section 3T05 SV3-SES-ITR-800660, Unit 3 ITAAC 660 Walkdown Inspection: ITAAC C.2.6.09.03a, Rev. 0 C.2.6.09.03a-U3-CP, ITAAC Completion Package, Rev. 0 VEGP Unit 3 and Unit 4 Physical Security Plan, Rev. 6

Section 3P01 Procedures NMP-EP-141-004, Vogtle 3 & 4 Emergency Action Levels and Basis (Amendments 77 and 76 (Vogtle Electric Generating Plant Units 3 and 4 LAR 16-002)), Rev. 3.0 NMP-EP-141-004-F01, VEGP 3 & 4 EAL Wall Chart - >200o F, Rev. 2.1 (verified in 2 copies)

NMP-EP-142, Emergency Notification, Rev. 5.0 (verified in 2 binders)

NMP-EP-143, Facility Activation, Rev. 7.0 (verified in 3 binders)

NMP-EP-143-F01, Command and Control Turnover and Transfer, Rev. 3.0 NMP-EP-143-001, Alternative Facility Operation Rev. 3.0 (verified in 1 binder)

NMP-EP-144, Protective Actions Rev. 6.0 (verified in 2 binders)

NMP-EP-145, Termination and Recovery, Rev. 2.0 (verified in 2 binders)

NMP-EP-147, Offsite Dose Assessment Automated MIDAS, Rev. 4.0 (verified in 2 binders)

NMP-EP-147-001, SNC Field Monitoring Team Sampling, Rev. 4.0 (verified in 2 binder)

NMP-EP-147-005, VEGP 3 & 4 MIDAS NU Dose Projections, Rev. 3.0 (verified in 2 binders)

NMP-EP-147-006, SNC-SRS Emergency Response Agreement, Rev. 1.0 (verified in 1 binder)

NMP-EP-147-007, Field Monitoring Team Communication Devices, Rev. 2.0 (verified in 1 binder)

26 NMP-EP-147-008, Field Monitoring Team Environmental Sampling, Rev. 1.0 (verified in 1 binder)

NMP-EP-147-F12, VEGP 3 & 4 AP1000 Plant Schematic, Rev. 1.0 (verified in 1 binder, missing from DAS binder)

NMP-EP-205, Emergency Communications and News Releases, Rev. 9.0 (verified in 1 binder)

NMP-OS-019-001, EOF Support for Beyond Design Based Events, Rev. 4.0 (verified in 2 binders)

NMP-OS-019-002, TSC Support for Beyond Design Based Events, Rev. 4.0 (verified in 1 binder)

NMP-OS-019-003, Security Support for Beyond Design Based Events, Rev. 2.0 (verified in 1 binder)

Emergency Notification Form(s) [NMP-EP-142-F01, Emergency Notification (EN) Form] for ORO Messages 1 thru 8, 12/14/2021.

SNC Dose Assessment Form(s) - WHAT-IF offsite dose calculations (no release in progress). Initial calculation and three (3) follow-up calculations at approximately thirty (30) minute intervals, 12/14/2021.

NMP-EP-146-F06, EOF Dose Analyst Initial Actions, 12/14/2021 NMP-EP-147-F16, VEGP 3 MIDAS Plant Parameters, 12/14/2021 Emergency Plan Annex for Vogtle Electric Generating Plant, Units 3 & 4, Rev. 3 3-AOP-101, Rapid Power Reduction, Rev. 1.0 3-AOP-112, Reactor Coolant Leak, Rev. 1.0 3-AOP-401, Malfunction of DDS, Rev. 1.1 NMP-EP-303-F02, Drill & Exercise Comment & Feedback Form, Rev. 0

Records & Data Emergency Logs, EOF Dose Analyst, 12/14/2021 VEGP Unit 3 NRC Graded Exercise Scenario Package, dated 12/14/2021 2021 US NRC Graded Exercise Management Debrief Presentation Package, 12/16/2021 Control Room Simulator, Operations Support Center, Technical Support Center, and Emergency Operations Facility - documentation packages (logs, event notification forms, protective action recommendations, and radiological dose assessments)

Section 3P02 Corrective Action Documents Preventive Maintenance Change Request PMCR-101353 (10-14-2021), Adjust frequency of 3SGSPM0257 & 0258 based on OE Condition Report Quality Record 50054618 (6-29-2020), PV01 Live Load Packing Configuration Condition Report Quality Record 50093154 (5-19-2021), Non-Safety Time Response Calculation Condition Report Quality Record 50113950 (11-8-2021), Lack of Specificity to Supplemental Data Capture and Acceptance for MSIV Position Verification Condition Report Quality Record 50114114 (10-9-2021), E&DCR Impact to Surveillances Corrective Actions Quality Record 80003016 (6-29-2020), PV01 Live Load Packing Configuration Corrective Actions Quality Record 80005635 (6-12-2021), Use of DDS MTS Atomic Clock instead of M&TE for Testing AP1000 Nonconformance & Disposition Report SV3-PV01-GNR-000028 (Revision 0, 7-03-2020), PV01 Live Load Packing Configuration AP1000 Nonconformance & Disposition Report SV3-PV01-GNR-000038 (Revision 0, 11-02-2020), PV01 MOV Faster Valve Stroke Times During Valve Setup

27 Technical Evaluations Quality Record 60018184 (4-13-2020), 10 CFR 50.55a Condition Requires Procedure Changes

Procedures 3-CAS-OTS-17-001, Compressed and Instrument Air Systems Check Valve Exercise, Version B=0.1 3-CCS-OTS-10-001, Component Cooling Water System Valve Stroke Test, Version C=0.2 3-CCS-OTS-17-002, Component Cooling Water System Check Valve Exercise, Version A=0.0 3-CNS-OTS-18-001, Containment Isolation Actuation Test, Version B=0.1 3-CVS-OTS-10-001, Chemical and Volume Control System Valve Stroke Test, Version E=0.4 3-CVS-OTS-10-002, Chemical and Volume Control System Check Valve Exercise Test, Version B=0.1 3-CVS-OTS-17-001, Chemical and Volume Control System Reactor Coolant System Leakage Test, Version D=0.3 3-MTS-OTS-10-001-V0.2-01, TPC for Main Turbine Inservice Valve Test, Version C=0.2 3-PCS-OTS-10-004, Passive Containment Cooling System Valve Stroke Test (Manual Valve Operability and Exercise), Version D=0.3 3-PXS-OTS-10-004, Passive Core Cooling System Pressure Isolation Valve Leak Test, Version A=0.0 3-RCS-OTS-10-001, Reactor Coolant System Valve Stroke Test, Version C=0.2 3-SGS-OTS-10-003, (Version C=0.2, 12-29-2020), Steam Generating System Valve Stroke Test Train A Modes 3-6, Version C=0.2 3-SGS-OTS-10-004 (Version C=0.2, 12-29-2020), Steam Generating System Valve Stroke Test Train B Modes 3-6 NMP-ES-002 (Version 27.0, 8-13-2021), System Monitoring and Health Reporting NMP-ES-005-001 (Version 11.0, 4-20-2021), Scoping and Importance Determination for Equipment Reliability - Single Point Vulnerability NMP-ES-013-003 (Version 6.0, 10-26-2020), IST Check Valve Condition Monitoring Program Development and Maintenance NMP-ES-017-007 (Version 1.1, 7-21-2021), MOV Diagnostic Procedure for QUIKLOOK 3 NMP-GM-006-002 (Version 4.1, 10-22-2020), Surveillance Program NMP-GM-008 (Version 23.0, 5-9-2021), Operating Experience Program NMP-GM-027 (Version 17.0, 8-26-2021), Plant Health Process NMP-MA-053 (Version 2.2, 5-13-2019), SNC Maintenance Department Measuring and Test Equipment Program (M&TE)

B-GEN-ITPA-004 (Version 11.0, 6-26-2019), Conduct of Test B-GEN-ITPCM-001 (Version 4.0, 7-28-2021), Limitorque SMB/SB Motor Operated Valve Component Testing 3-PMS-OTS-20-002 (Version B=0.1, 8-8-2019), ESFAS 24-Month Trip Actuating Device Operational Test

Work Packages Work Package SV3-CCS-T0W-1100430, Static Diagnostic Testing of MOV SV3-CCS-PL-V200, Rev. 0 Work Package SV3-CCS-T0W-1100440, Static Diagnostic Testing of MOV SV3-CCS-PL-V208, Rev. 0 Work Package SV3-CCS-T0W-1229062, Retest MOV SV3-CCS-PL-V208, Rev. 0 Work Package SV3-CVS-T0W-1054304, Static Diagnostic Testing of MOV SV3-CVS-PL-V003, Rev. 1 Work Package SV3-PXS-T0W-1045343, Static Diagnostic Testing of MOV SV3-PXS-PL-V117B, Rev. 0

28 Work Package SV3-SGS-T0W-1067835, Static Diagnostic Testing of MOV SV3-SGS-PL-V027A Work Package SV3-SGS-T0W-1067844, Static Diagnostic Testing of MOV SV3-SGS-PL-V027B Work Package SV3-RCS-T0W-1054810, Perform Relief Valve Testing on SV3-RCS-PL-V005 PZR Safety A Work Package SV3-RCS-T0W-1235363, Retest 3-RCS-V002B, CWA 3-21-214/238 Work Package SV3-RCS-T0W-1235364, Retest 3-RCS-V003A, CWA 3-21-237 Work Package SV3-RCS-T0W-1237680, Retest 3-RCS-V002A, CWA 3-20-2177 Work Package SV3-RCS-T0W-1067977, Static Diagnostic Testing of MOV SV3-RCS-PL-V003B Work Package SV3-RCS-T0W-1067982, Static Diagnostic Testing of MOV SV3-RCS-PL-V011A Work Package SV3-RCS-T0W-1067988, Static Diagnostic Testing of MOV SV3-RCS-PL-V012A Work Package SV3-RCS-T0W-1067997, Static Diagnostic Testing of MOV SV3-RCS-PL-V013B Work Package SV3-RNS-T0W-1237493, Retest 3-RNS-V002B, CWA 21-0403 Work Package SV3-RNS-T0W-1237500, Retest 3-RNS-V001B, CWA 3-21-0406 Work Package SV3-VBS-T0W-1052705, Static Diagnostic Testing of MOV SV3-VBS-PL-V186, Rev. 1 Work Package SV3-VBS-T0W-1052709, Static Diagnostic Testing of MOV SV3-VBS-PL-V188, Rev. 1 Work Package SV3-VFS-T0W-1049092, Static Diagnostic Testing of MOV SV3-VFS-PL-V800B, Rev. 0 Work Package SV3-VFS-T0W-1049121, Static Diagnostic Testing of MOV SV3-VFS-PL-V800A, Rev. 0

Miscellaneous APP-GW-GF-105 (Revision 0, 6-24-2016), APOG GC: NRC 2015-13: Main Steam Isolation Valve Failure Events SV0-PV64-VMM-001 (Revision 1, 1-9-2020), PV64 Main Steam Isolation Valve (MSIV)

Installation, Operation and Maintenance Manual ND-CO-015 (Version 10.0, 3-4-2020), Nuclear Development Quality Assurance Conduct of Operations Nuclear Development Quality Assurance Manual (Version 20.0, 11-5-2019)

Bechtel 26139-000-4MP-T81C-N7102 (Revision 2, 5-22-2019), Control of Measuring and Test Equipment

CRs Written as a Result of Inspection 50113950 50093154 50114114 CAR 80005635

Section 3P03 Corrective Action Documents Preventive Maintenance Change Request PMCR-101353, Adjust frequency of 3SGSPM0257 &

0258 based on OE, 10/14/2021 Condition Report Quality Record 50054618, PV01 Live Load Packing Configuration, 6/29/2020 Condition Report Quality Record 50093154, Non-Safety Time Response Calculation, 5/19/2021

29 Condition Report Quality Record 50113950, Lack of Specificity to Supplemental Data Capture and Acceptance for MSIV Position Verification, 11/8/2021 Condition Report Quality Record 50114114, E&DCR Impact to Surveillances, 10/9/2021 Corrective Actions Quality Record 80003016, PV01 Live Load Packing Configuration, 6/29/2020 Corrective Actions Quality Record 80005635, Use of DDS MTS Atomic Clock instead of M&TE for Testing, 6/12/2021 AP1000 Nonconformance & Disposition Report SV3-PV01-GNR-000028, PV01 Live Load Packing Configuration, Rev. 0 AP1000 Nonconformance & Disposition Report SV3-PV01-GNR-000038, PV01 MOV Faster Valve Stroke Times During Valve Setup, Rev. 0 Technical Evaluations Quality Record 60018184, 10 CFR 50.55a Condition Requires Procedure Changes, 4/13/2020

Procedures 3-CAS-OTS-17-001, Compressed and Instrument Air Systems Check Valve Exercise, Version B=0.1 3-CCS-OTS-10-001, Component Cooling Water System Valve Stroke Test, Version C=0.2 3-CCS-OTS-17-002, Component Cooling Water System Check Valve Exercise, Version A=0.0 3-CNS-OTS-18-001, Containment Isolation Actuation Test, Version B=0.1 3-CVS-OTS-10-001, Chemical and Volume Control System Valve Stroke Test, Version E=0.4 3-CVS-OTS-10-002, Chemical and Volume Control System Check Valve Exercise Test, Version B=0.1 3-CVS-OTS-17-001, Chemical and Volume Control System Reactor Coolant System Leakage Test, Version D=0.3 3-MTS-OTS-10-001-V0.2-01, TPC for Main Turbine Inservice Valve Test, Version C=0.2 3-PCS-OTS-10-004, Passive Containment Cooling System Valve Stroke Test (Manual Valve Operability and Exercise), Version D=0.3 3-PXS-OTS-10-004, Passive Core Cooling System Pressure Isolation Valve Leak Test, Version A=0.0 3-RCS-OTS-10-001, Reactor Coolant System Valve Stroke Test, Version C=0.2 3-SGS-OTS-10-003, Steam Generating System Valve Stroke Test Train A Modes 3-6, Version C=0.2 3-SGS-OTS-10-004, Steam Generating System Valve Stroke Test Train B Modes 3-6, Rev. C=0.2 NMP-ES-002, System Monitoring and Health Reporting, Rev. 27 NMP-ES-005-001, Scoping and Importance Determination for Equipment Reliability - Single Point Vulnerability, Rev. 11 NMP-ES-013-003, IST Check Valve Condition Monitoring Program Development and Maintenance, Rev. 6 NMP-ES-017-007, MOV Diagnostic Procedure for QUIKLOOK 3, Rev. 1.1 NMP-GM-006-002, Surveillance Program, Rev. 4.1 NMP-GM-008, Operating Experience Program, Rev. 23 NMP-GM-027, Plant Health Process, Rev. 17 NMP-MA-053, SNC Maintenance Department Measuring and Test Equipment Program (M&TE),

Rev. 2.2 B-GEN-ITPA-004, Conduct of Test, Rev. 11 B-GEN-ITPCM-001, Limitorque SMB/SB Motor Operated Valve Component Testing, Rev. 4 3-PMS-OTS-20-002, ESFAS 24-Month Trip Actuating Device Operational Test, Rev. B=0.1

30 Work Packages Work Package SV3-CCS-T0W-1100430, Static Diagnostic Testing of MOV SV3-CCS-PL-V200, Rev. 0 Work Package SV3-CCS-T0W-1100440, Static Diagnostic Testing of MOV SV3-CCS-PL-V208, Rev. 0 Work Package SV3-CCS-T0W-1229062, Retest MOV SV3-CCS-PL-V208, Revision 0 Work Package SV3-CVS-T0W-1054304, Static Diagnostic Testing of MOV SV3-CVS-PL-V003, Rev. 1 Work Package SV3-PXS-T0W-1045343, Static Diagnostic Testing of MOV SV3-PXS-PL-V117B, Rev. 0 Work Package SV3-SGS-T0W-1067835, Static Diagnostic Testing of MOV SV3-SGS-PL-V027A Work Package SV3-SGS-T0W-1067844, Static Diagnostic Testing of MOV SV3-SGS-PL-V027B Work Package SV3-RCS-T0W-1054810, Perform Relief Valve Testing on SV3-RCS-PL-V005 PZR Safety A Work Package SV3-RCS-T0W-1235363, Retest 3-RCS-V002B, CWA 3-21-214/238 Work Package SV3-RCS-T0W-1235364, Retest 3-RCS-V003A, CWA 3-21-237 Work Package SV3-RCS-T0W-1237680, Retest 3-RCS-V002A, CWA 3-20-2177 Work Package SV3-RCS-T0W-1067977, Static Diagnostic Testing of MOV SV3-RCS-PL-V003B Work Package SV3-RCS-T0W-1067982, Static Diagnostic Testing of MOV SV3-RCS-PL-V011A Work Package SV3-RCS-T0W-1067988, Static Diagnostic Testing of MOV SV3-RCS-PL-V012A Work Package SV3-RCS-T0W-1067997, Static Diagnostic Testing of MOV SV3-RCS-PL-V013B Work Package SV3-RNS-T0W-1237493, Retest 3-RNS-V002B, CWA 21-0403 Work Package SV3-RNS-T0W-1237500, Retest 3-RNS-V001B, CWA 3-21-0406 Work Package SV3-VBS-T0W-1052705, Static Diagnostic Testing of MOV SV3-VBS-PL-V186, Rev. 1 Work Package SV3-VBS-T0W-1052709, Static Diagnostic Testing of MOV SV3-VBS-PL-V188, Rev. 1 Work Package SV3-VFS-T0W-1049092, Static Diagnostic Testing of MOV SV3-VFS-PL-V800B, Rev. 0 Work Package SV3-VFS-T0W-1049121, Static Diagnostic Testing of MOV SV3-VFS-PL-V800A, Rev. 0

Miscellaneous APP-GW-GF-105, APOG GC: NRC 2015-13: Main Steam Isolation Valve Failure Events, Rev. 0 SV0-PV64-VMM-001, PV64 Main Steam Isolation Valve (MSIV) Installation, Operation and Maintenance Manual, Rev. 1 ND-CO-015, Nuclear Development Quality Assurance Conduct of Operations, Rev. 10 Nuclear Development Quality Assurance Manual, Rev. 20 Bechtel 26139-000-4MP-T81C-N7102, Control of Measuring and Test Equipment, Rev. 2

CRs Written as a Result of Inspection 50113950

31 LIST OF ACRONYMS

10 CFR Title 10 of the Code of Federal Regulations ASME American Society of Mechanical Engineers CAP corrective action program CAR corrective action quality record COL Combined License CR condition report DCO Division of Construction Oversight DRS Division of Reactor Safety EP emergency preparedness E-Plan emergency plan Green very low safety significance HVAC heating, ventilation, and air conditioning IDS Class 1E direct current and uninterruptible power supply system IMC inspection manual chapter IP inspection procedure IPT ITAAC Project Team IST inservice testing IR inspection report ICN ITAAC Closure Notice ITAAC Inspections, Tests, Analysis, and Acceptance Criteria MOV motor operated valve MSIV main steam isolation valve NCV non-cited violations NRC Nuclear Regulatory Commission OM Operations and Maintenance OpE operating experience PARS Publicly Available Records PCS passive containment cooling system PMS protection and monitoring system PST preservice testing Rev. Revision SL severity level SSC structure, system, or component UFSAR Updated Final Safety Analysis Report VBS vehicle barrier system

32 ITAAC INSPECTED

No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 46 2.1.02.11a.i 11.a) Controls exist in i) Testing will be i) Controls in the the MCR to cause the performed on the MCR operate to cause remotely operated squib valves identified a signal at the squib valves identified in in Table 2.1.2-1 using valve electrical leads Table 2.1.2-1 to controls in the MCR which is capable of perform active without stroking the actuating the squib functions. valve. valve.

48 2.1.02.11b.i 11.b) The valves i) Testing will be i) The squib valves identified in Table performed on the receive a signal at the 2.1.2-1 as having squib valves identified valve electrical leads PMS control perform in Table 2.1.2-1 using that is capable of an active safety real or simulated actuating the squib function after receiving signals into the PMS valve.

a signal from the without stroking the PMS. valve.

78 2.1.03.07.i 7. The reactor i) Not used per i) Not used per internals will withstand Amendment No. 151. Amendment No. 151.

the effects of flow ii) A pre-test ii) The as-built reactor induced vibration. 10. inspection, a flow test internals have no The reactor lower and a post-test observable damage or internals assembly is inspection will be loose parts. At least equipped with holders conducted on the as-eight capsules are in for at least eight built reactor internals. the reactor lower capsules for storing Inspection of the internals assembly.

material surveillance reactor lower internals specimens. assembly for the presence of capsules will be performed.

33 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 206 2.2.03.10 10. Safety-related Inspection will be Safety-related displays of the performed for the displays identified in parameters identified retrievability of the Table 2.2.3-1 can be in Table 2.2.31 can safety-related displays retrieved in the MCR.

be retrieved in the in the MCR. ii) Stroke ii) Controls in the MCR. 11.a) Controls testing will be MCR operate to cause exist in the MCR to performed on remotely remotely operated cause the remotely operated valves other valves other than operated valves than squib valves squib valves to identified in Table identified in Table perform their active 2.2.3-1 to perform 2.2.3-1 using the functions. ii) their active function(s). controls in the MCR. Remotely operated 11.b) The valves ii) Testing will be valves other than identified in Table performed on the squib valves perform 2.2.3-1 as having remotely operated the active function PMS control perform valves other than identified in the table their active function squib valves identified after a signal is input after receiving a signal in Table 2.2.3-1 using to the PMS. iii) from the PMS. 12.b) real or simulated These valves open After loss of motive signals into the PMS. within 20 seconds power, the remotely iii) Testing will be after receipt of an operated valves performed to actuation signal. After identified in Table demonstrate that loss of motive power, 2.2.3-1 assume the remotely operated each remotely indicated loss of PXS isolation valves operated valve motive power position. PXS-V014A/B, identified in Table

13. Displays of the V015A/B, V108A/B 2.2.3-1 assumes the parameters identified open within the indicated loss of in Table 2.2.3-3 can required response motive power position.

be retrieved in the times. Testing of the Displays identified in MCR. remotely operated Table 2.2.3-3 can be valves will be retrieved in the MCR.

performed under the conditions of loss of motive power.

Inspection will be performed for retrievability of the displays identified in Table 2.2.3-3 in the MCR.

209 2.2.03.11b.i 11.b) The valves i) Testing will be i) Squib valves identified in Table performed on the receive an electrical 2.2.3-1 as having squib valves identified signal at the valve PMS control perform in Table 2.2.3-1 using electrical leads that is their active function real or simulated capable of actuating after receiving a signal signals into the PMS the valve after a signal from the PMS. without stroking the is input to the PMS.

valve.

34 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 603 2.6.03.04c 4.c) Each IDS 24-Testing of each 24-The battery terminal hour battery bank hour asbuilt battery voltage is greater than supplies a dc bank will be performed or equal to 210 V after switchboard bus load by applying a a period of no less for a period of 24 simulated or real load, than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with an hours without or a combination of equivalent load that recharging. 4.d) Each simulated or real loads equals or exceeds the IDS 72-hour battery which envelope the battery bank design bank supplies a dc battery bank design duty cycle capacity.

switchboard bus load duty cycle. The test The battery terminal for a period of 72 will be conducted on a voltage is greater than hours without battery bank that has or equal to 210 V after recharging. 4.e) The been fully charged a period of no less IDS spare battery and has been than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> with an bank supplies a dc connected to a battery equivalent load that load equal to or charger maintained at equals or exceeds the greater than the most 270+/-2 V for a period battery bank design severe switchboard of no less than 24 duty cycle capacity.

bus load for the hours prior to the test. The battery terminal required period Testing of each 72-voltage is greater than without recharging. hour as-built battery or equal to 210 V after 4.f) Each IDS 24-hour bank will be performed a period with a load inverter supplies its ac by applying a and duration that load. 4.g) Each IDS simulated or real load, equals or exceeds the 72-hour inverter or a combination of most severe battery supplies its ac load. simulated or real loads bank design duty 4.h) Each IDS 24-hour which envelope the cycle capacity. Each battery charger battery bank design 24-hour inverter provides the PMS with duty cycle. The test supplies a line-to-line two loss-of-ac input will be conducted on a output voltage of 208 voltage signals. 5.a) battery bank that has +/- 2% V at a frequency Each IDS 24-hour been fully charged of 60 +/- 0.5% Hz.

battery charger and has been Each 72-hour inverter supplies a dc connected to a battery supplies a line-to-line switchboard bus load charger maintained at output voltage of 208 while maintaining the 270+/-2 V for a period +/- 2% V at a frequency corresponding battery of no less than 24 of 60 +/- 0.5% Hz. Two charged. 5.b) Each hours prior to the test. PMS input signals IDS 72-hour battery Testing of the as-built exist from each 24-charger supplies a dc spare battery bank will hour battery charger switchboard bus load be performed by indicating loss of ac while maintaining the applying a simulated input voltage when the corresponding battery or real load, or a loss-of-input voltage charged. 5.c) Each combination of condition is simulated.

IDS regulating simulated or real loads Each 24-hour battery transformer supplies which envelope the charger provides an an ac load when most severe of the output current of at powered from the 480 division batteries least 150 A with an V MCC. 6. Safety-design duty cycle. The output voltage in the

35 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis related displays test will be conducted range 210 to 280 V.

identified in Table on a battery bank that Each 72-hour battery 2.6.3-1 can be has been fully charged charger provides an retrieved in the MCR. and has been output current of at

11. Displays of the connected to a battery least 125 A with an parameters identified charger maintained at output voltage in the in Table 2.6.3-2 can 270+/-2 V for a period range 210 to 280 V.

be retrieved in the of no less than 24 Each regulating MCR. hours prior to the test. transformer supplies a Testing of each 24-line-to-line output hour as-built inverter voltage of 208 +/- 2% V.

will be performed by Safety-related applying a simulated displays identified in or real load, or a Table 2.6.3-1 can be combination of retrieved in the MCR.

simulated or real Displays identified in loads, equivalent to a Table 2.6.3-2 can be resistive load greater retrieved in the MCR.

than 12 kW. The inverter input voltage will be no more than 210 Vdc during the test. Testing of each 72-hour as-built inverter will be performed by applying a simulated or real load, or a combination of simulated or real loads, equivalent to a resistive load greater than 7 kW. The inverter input voltage will be no more than 210 Vdc during the test. Testing will be performed by simulating a loss of input voltage to each 24-hour battery charger. Testing of each as-built 24-hour battery charger will be performed by applying a simulated or real load, or a combination of simulated or real loads. Testing of each 72-hour as-built

36 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis battery charger will be performed by applying a simulated or real load, or a combination of simulated or real loads. Testing of each as-built regulating transformer will be performed by applying a simulated or real load, or a combination of simulated or real loads, equivalent to a resistive load greater than 30 kW when powered from the 480 V MCC. Inspection will be performed for retrievability of the safety-related displays in the MCR.

Inspection will be performed for retrievability of the displays identified in Table 2.6.3-2 in the MCR.

37 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 644 2.6.09.05a 5.a) Security alarm Test, inspection, or a Security alarm annunciation and combination of test annunciation and video assessment and inspections of the video assessment information is installed systems will information is displayed concurrently be performed. Tests displayed concurrently in the central alarm will be performed on in the central alarm station and the intrusion detection and station and the secondary alarm assessment secondary alarm station, and the video equipment. station, and the video image recording with image recording with real time playback real time playback capability can provide capability provides assessment of assessment of activities before and activities before and after each alarm after alarm annunciation within annunciation within the perimeter area the perimeter barrier.

barrier. 15.b) The intrusion Intrusion detection detection system and assessment concurrently provides systems concurrently visual displays and provide visual displays audible annunciations and audible of alarms in both the annunciation of alarms central and secondary in the central and alarm stations.

secondary alarm stations.

647 2.6.09.06 6. The vehicle barrier Inspections and The vehicle barrier system is installed and analysis will be system will protect located at the performed for the against the DBT necessary stand-off vehicle barrier system. vehicle bombs based distance to protect upon the stand-off against the DBT distance of the vehicle bombs. system.

38 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 660 C.2.6.09.03a 3.a) Isolation zones Inspections will be Isolation zones exist in exist in outdoor areas performed of the outdoor areas adjacent to the isolation zones in adjacent to the physical barrier at the outdoor areas physical barrier at the perimeter of the adjacent to the perimeter of the protected area that physical barrier at the protected area and allows 20 feet of perimeter of the allow 20 feet of observation on either protected area. observation and side of the barrier. assessment of the Where permanent activities of people on buildings do not allow either side of the a 20foot observation barrier. Where distance on the inside permanent buildings of the protected area, do not allow a 20foot the building walls are observation and immediately adjacent assessment distance to, or an integral part on the inside of the of, the protected area protected area, the barrier. building walls are immediately adjacent to, or an integral part of, the protected area barrier and the 20foot observation and assessment distance does not apply.

39 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 661 C.2.6.09.03b 3.b) The isolation Inspections will be The isolation zones zones are monitored performed of the are equipped with with intrusion intrusion detection intrusion detection detection equipment equipment within the equipment that that provides the isolation zones. provides the capability capability to detect Tests, inspections or a to detect and assess and assess combination of tests unauthorized persons.

unauthorized persons. and inspections of the The intrusion

4. The intrusion intrusion detection and detection and detection and assessment assessment assessment equipment at the equipment at the equipment at the protected area protected area protected area perimeter and its perimeter: a) detects perimeter: a) detects uninterruptible power penetration or penetration or supply will be attempted penetration attempted penetration performed. Tests, of the protected area of the protected area inspections or a barrier and barrier and combination of tests concurrently alarms in concurrently alarms in and inspections of the the Central Alarm both the Central Alarm intrusion detection and Station and Station and assessment Secondary Alarm Secondary Alarm equipment at the Station; b) remains Station; b) remains protected area operable from an operable from an perimeter and its uninterruptible power uninterruptible power uninterruptible power supply in the event of supply in the event of supply will be the loss of normal the loss of normal performed. power.

power.

668 C.2.6.09.08a 8.a) Penetrations Inspections will be Penetrations and through the protected performed of openings through the area barrier are penetrations through protected area barrier secured and the protected area are secured and monitored. 8.b) barrier. Inspections monitored.

Unattended openings will be performed of Unattended openings (such as underground unattended openings (such as underground pathways) that that intersect the pathways) that intersect the protected protected area intersect the protected area boundary or vital boundary or vital area area boundary or vital area boundary will be boundary. area boundary are protected by a protected by a physical barrier and physical barrier and monitored by intrusion monitored by intrusion detection equipment detection equipment or provided or provided surveillance at a surveillance at a frequency sufficient to frequency sufficient to detect exploitation. detect exploitation.

40 No. ITAAC No. Design Commitment Inspections, Tests, Acceptance Criteria Analysis 670 C.2.6.09.09 9. Emergency exits Tests, inspections, or Emergency exits through the protected a combination of tests through the protected area perimeter are and inspections of area perimeter are alarmed and secured emergency exits alarmed and secured with locking devices to through the protected by locking devices that allow for emergency area perimeter will be allow prompt egress egress. 9. Emergency performed. Test, during an emergency.

exits through the vital inspection, or a The emergency exits area boundaries are combination of tests through the vital area locked, alarmed, and and inspections of the boundaries are equipped with a crash emergency exits locked, alarmed, and bar to allow for through the vital area equipped with a crash emergency egress. boundaries will be bar to allow for performed. emergency egress.

815 3.3.00.10.i 10. The shield i) A test will be i) A report exists and building roof and PCS performed to measure concludes that total storage tank support the leakage from the water flow from the and retain the PCS PCS storage tank leak chase collection water sources. The based on measuring system does not PCS storage tank has the water flow out of exceed 10 gal/hr.

a stainless steel liner the leak chase which provides a collection system.

barrier on the inside surfaces of the tank.

Leak chase channels are provided on the tank boundary liner welds.

41