ML20214R963

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/86-31 & 50-446/86-25 on 861101-1231. Violation & Deviations Noted:Unjustified use-as-is Disposition of Nonconformance Rept,Deletion of Insp Attribute from Checklist & Invalidation of Deviation Rept
ML20214R963
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/22/1987
From: Barnes I, Ellershaw L, Hale C, Spessard R, Wagner P
NRC, NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20214R909 List:
References
50-445-86-31, 50-446-86-25, NUDOCS 8706090070
Download: ML20214R963 (40)


See also: IR 05000445/1986031

Text

-

o

APPENDIX C

NRC COMANCHE PEAK RESPONSE TEAM ACTIVITIES INSPECTION REPORT

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-445/86-31 Permits: CPPR-126

50-446/86-25 CPPR-127

Dockets: 50-445 Category: A2

50-446

Construction Permit

Expiration Dates:

Unit 1: August 1, 1988

Unit 2: August 1, 1987

Applicant: Texas Utilities Electric Company

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas 75201

Facility Name: Comanche Peak Steam Electric Station (CPSES), Units 1 & 2

Inspection At: Gle n Rose, Texas

Inspection Conducted: November 1 through December 31, 1986

Inspectors:

_k_

L. E. _1 ershaw,

W

eactor Inspector, Region IV

[DpteAA!77

/

'

CPSES Group

(paragraphs 2.a, 2.b, 2.e g, 4.a-1, 5.a and 5.c)

$ S- ~d S/22/P 7

p C. J. HB e, Reactor Inspector, Region IV bate

CPSES Group

(paragraphs 3.c g, 5.b and 6)

?0. 6 ions

E C Wagner, Reactor Inspector, Region IV

5/zz/ey

Date

~

CPSES Group

(paragraphs 2.c-d and 3.a-b)

0706090070 870601

PDH ADOCK 05000445

0 PDR

, ..

2

Consultants: EG&G - J. Dale (paragraphs 4.d, 4.1 and 5.a)

A. Maughan (paragraphs 2.c and 3.a)

W. Richins (paragraphs 4.e-h)

V. Wenczel (paragraphs 5.b and 6)

Parameter - J. Birmingham (paragraphs 3.c 9)

K. Graham (paragraphs 2.a, 2.e and 4.a-c)

D. Jew (paragraphs 2.b, 2.f g and 5.c)

-

. L. S'pe ard, Deputy Director, Di vision of

5)?i/89

Date

Inspection Programs, Office of In'spection

and Enforcement

Approved: 8e #/22/4'7

1. Barnes, Chief, Region IV CPSES Group Date

Inspection Summary

Inspection Conducted November 1 through December 31, 1986 (Report 50-445/86-31;

50-446/86-25)

Areas Inspected: Nonroutine, unannounced inspection of applicant actions on

previous inspection findings, Comanche Peak Response Team (CPRT) issue-specific

action plans (ISAPs), assessment of allegations, and the ERC collective

evaluation program.

Results: Within the four areas inspected, one violation (use of an incorrect

justification for a "use-as-is" disposition of a nonconformance report (NCR),

paragraph 2.e) and two deviations (incorrect deletion of an inspection

attribute from the inspection checklist by an Evaluation Research

Corporation (ERC) inspector, paragraph 4.h; and invalidation of a deviation

report (DR) by ERC engineering using a basis which was not consistent with

ISAP VII.c criteria, paragraph 4.a) were identified.

r-

-Q eo

3

DETAILS

1. Persons Contacted ,

Texas Utilities Generating Company (TUGCo)

      • R. P. Baker, Regulatory Compliance Manager
    • J. L. Barker,. Engineering Assurance Manager
    • J. Bencivenga, Unit 1 Issue Coordinator
      • T. Braudt, Senior Engineer

T. Brandt, Quality Engineering (QE) Supervisor

R. E. Camp, Project Manager, Unit 1

      • W. G. Counsil, Executive Vice President
    • R. D. Delano
      • P. E. Halstead, Quality Control (QC) Manager
    • T. L. Heatherly, Regulatory Compliance Engineer
      • J. Krechting, Director of Engineering
    • D. McAfee,-Quality Assurance (QA) Manager
      • L. D, Nace, Vice President, Engineering & Construction
      • D. M. Reynerson, Project Manager, Unit 2

P. Stevens, Manager, Electrical Engineering

J. F. Streeter, Director of QA

      • T. G. Tyler, CPRT Program Director
    • D. R. Woodlan, Licensing Supervisor

Comanche Peak Response Team (CPRT)

R. T. Bentley, Technical Assistant

J. Mallanda, Electrical Review Team Leader

Brown and Root (B&R)

D. Johnson, Electrical Training Instructor

K. Thrasher, Training Records Supervisor

Evaluation Research Corporation (ERC)

M. Keathley, Lead Electrical QC Inspector

C. Spinks, QC Supervisor

Impell Corporation

P. Passalugo, Equipment Qualification Engineer

Ebasco

M. Strehlow, Site Engineering Manager

_

.. .

., ,.

4

The NRC inspectors also interviewed other CPRT and applicant employees

during this-inspection period.

  • Denotes personnel present at the December 9, 1986, exit interview.
    • Denotes personnel present at the January 13, 1987, exit interview.
      • Denotes personnel present at both of the above exit interviews.

2. Applicant Actions on Previous Inspection Findings

,

a. (Closed) Open Item (445/8511-04): As a result of CPRT inspection

activities.-12 ASME pipe supports with undersize Type 2 skewed fillet

welds were identified and documented on NCRs.

The NRC inspector performed a review and assessment of NCR

dispositions, all of which have been designated "Use-As-Is." Results

of the NRC review are as follows:

NCR 85-0155 - The NRC inspector confirmed from review of

Drawing SI-1-914-003-S32A that the nonconforming condition had been

correctly found to be invalid. The drawing denoted that the weld

size requirements were not applicable to the weld in question for the

,

identified undersized position.

!

NCRs 85-0179, -180, -181, -182, -183, -184, -185, -186, -187, -202,

and -203 - Calculations were performed by TUGCo pipe support

engineering which substantiated compliance with the pipe support

design loading requirements. These calculations were subsequently

reviewed and approved by Operations Results Engineering and QA in

accordance with applicable procedures.

All pipe support design drawings were revised as required to reflect

the "Use-As-Is" dispositions,

i b. (Closed)OpenItem(445/8511-05): DRs identified by the CPRT during

l reinspection of disassembled valves were to be evaluated and the

! programatic and generic implications were to be reviewed. This has

been completed by the CPRT with their findings contained in the

results report. This item is closed.

'

c. (Closed) Open Item (445/8514-07): Comparison of ERC and NRC review

i

results. The comparison of NRC review findings to the ERC review

findings for ten electrical cable verification packages was discussed

in NRC Inspection Reports 50-445/86-01 and 50-445/86-26. The NRC

inspector reviewed the disposition of the NCR written to resolve the

last portion of this item. The ERC inspector had written

DR R-E-CABLE-035-02 for the failure of an applicant engineer to date

j

! when he. signed an authorization to pull electrical cable through a

cable tray. Subsequent NRC inspector review found no requirement for

l

' a date to be affixed to the pull authorization. In addition, both QC

and installation procedures require checking cable trays to ensure

they are properly prepared prior to cable pulling. ,

, .

- .-- . . - _ - -- - - - - _ - - - - - _ _ - . -_ . -_---

, ..

5

d. (Closed) Violation (445/8601-14; 446/8601-04): Failure to test

electrical cable reels. The requirement to perform field tests on

all electrical cable reels in accordance with the manufacturer

recommendations was removed from the electrical erection

specifications by design change authorization (DCA)-24088. The bases

for removing this from the specification was; (1) the testing

performed by the manufacturer prior to shipping and (2) the

additional onsite testing following cable installation. The NRC

inspector reviewed receiving inspection report (RIR)-10477 for a

shipment of electrical cable reels and verified that the manufacturer

performed tests were appropriately documented in the attached test

reports. The NRC inspector will perform further evaluations of these

manufacturer tests as part of the inspections related to the

ISAP VII.a.9 implementation. In addition, the NRC inspector reviewed

DCA 21,624, dated December 10, 1985, which clarified the requirement

to perform continuity and insulation measurement tests on installed

cables prior to terminating the conductors.

e. (Closed) Open Item (445/8602-09): Review of the disposition of

NCR M-85-101128. The subject NCR was issued to resolve ERC DRs which

addressed excessive undercut, excessive reinforcement, and

suitability of weld surface for nondestructive examination (NDE).

The DRs pertaining to excessive undercut had been identified as an

area-of concern by NRR because of potential noncompliance with Code

requirements (ACI-359-Proposed Section III, Division 2 of the ASME

Code). In order to verify implementation of applicant commitments,

the NRC inspector performed a detailed review of the nonconformance

disposition process. Applicant actions, with respect to the NCR

disposition, were evaluated for the time frame of November 1985

through June 1986.

The Revision 0 disposition of the NCR, use-as-is, was evaluated by

TUGCo Nuclear Engineering (TNE) and reviewed by QE. The technical

evaluation stated, " Radiographic Examinations to the welds in

question indicates that, the shapes and dimensions are not impending

[ sic] the NDT evaluation. Undercuts: By comparing the actual to

nominal yield strengths, it is shown that the remaining thickness of

material is within designed requirements (9.4 percent undercut verses

14.3 percent increased strength)."

NRC review of the disposition revealed that radiographic

examination (RT) had not been performed on the specific weld areas

identified by the NCR. Furthermore, a review of ACI-359 identified

that locations documented as having excessive reinforcement were not

in compliance with NDE requirements; i.e., excessive reinforcement is

not permitted in areas that require RT.

. The TUGCo QE supervisor was notified in regard to the absence of

applicable RT film and the NCR was subsequently reopened to revise

the disposition. The QE supervisor identified the following three

reasons for redispositioning the NCR:

..

6

(1) Structural implications were not adequately addressed.

(2) A DCA was required to be issued for use-as-is dispositions.

(3) No RT film existed for nonconforming weld areas.

The failure to provide sufficient engineering technical justification

to establish that the nonconforming characteristics will result in no

adverse conditions and the fact that a design change document was not

issued as required by TNE-AD-5-2 is a violation (445-8631-V-01).

The NRC inspector examined the Revision 1 disposition of the subject

NCR to determine THE compliance with applicable procedural

requirements. As a result of the technical evaluation performed by

the QE group, which included reinspection / verification of field

identified conditions, it was determined that nonconformances do not

actually exist and the NCR was voided. It is apparent the TUGCo did

not verify the actual field conditions when processing the NCR per

Revision 0. The ERC inspector of record concurs with the

determination by QE that the nonconforming conditions identified do

not exist. The NRC inspector determined that the Revision I

disposition was in compliance with applicable procedural

requirements.

f. (0 pen) Unresolved Item (445/8607-28): CPRT did not completely

address all the ramifications that may result from the fact that the

NPV-1 Data Report- for Valves XSF-179 and 1-7046 are not consistent

with the installed bonnets.

Subsequently, all required vendor supplied documentation for the

as-built condition of Valve 1-7046 has been received onsite. This

included corrected copies of the ITT Grinnell heat code

identificatior, sheet correlating the as-installed valve to the NPV-1

Data Report issued to CPSES. The vendor documentation establishes

that the installed valve body / bonnet is as received from the vendor.

NCR M-23175N, Revision 2, dated October 17, 1986, incorporates this

documentation into RIR 1388.

For Valve XSF-179, a new valve bonnet complete with all necessary

documentation, including the NPV-1 Data Report has been ordered. The

old bonnet will be scrapped per Procedure MCP-10, " Storage and

Storage Maintenance of Mechanical and Electrical Equipment." This

replacement will be dispositioned under NCR M-23178, Revision 1.

This item remains open pending disposition of this NCR.

g. (0 pen) Unresolved Item (445/8622-05): Propriety of utilizing the

NIS-2 form to document as-installed components. This pertains to

Valves 1-7046 and XSF-179 addressed in NCRs M-23175N, Revision 1, and

M-23178N, Revision 0. Subsequent to the identification of this

unresolved item, all required vendor supplied documentation for the

as-built condition of Valve 1-7046 was received onsite. This

included corrected copies of the ITT Grinnell heat code

identification sheet correlating the as-installed valve to the NPV-1

. .,

7

Data Report issued to CPSES. This vendor documentation establishes

that the installed valve body / bonnet is as received from the vendor.

NCR M-23175N, Revision 2, dated October 17, 1986, incorporates this

documentation into RIR 1388.

For Valve XSF-179, a new valve bonnet complete with all necessary

documentation, including the NPV-1 data report has been ordered. The

old bonnet will be scrapped per Procedure MCP-10, " Storage and

Storage Maintenance of Mechanical and Electrical Equipment." This

replacement will be dispositioned under NCR M-23178, Revision 1.

This item remains open pending disposition of the NCR.

3. CPRT ISAPs (excluding VII.c)

a. Heat-Shrinkable Cable Insulation Sleeves (ISAP I.a.1)

Revise Construction Procedure EEI-8 (NRC Reference 01.a.01.01)

The NRC inspector reviewed and made a comparison of the installation

attributes for heat-shrinkable insulation sleeves (HSIs) in

Revisions 4, 5, and 6 of Construction Procedure EEI-8, " Class 1E and

Non-Class 1E Cable Terminations." Revision 6 of Procedure EEI-8,

dated September 23, 1986, was the current revision. All three

revisions contained instructions for craft personnel to read the

manufacturer (Raychem) installation kit instructions prior to

installing HSIs and to install the HSI in accordance with those

instructions. QC hold points for verification and witnessing of the

installation were added in Revision 5.

The NRC inspector also reviewed the Raychem instructions for HSI

installation and compared those instructions to EEI-8, Revision 6; no

requirement differences between the Raychem instructions and EEI-8

were identified.

-

The NRC inspector verified that the ISAP Electrical Review Team (ERT)

reviewed the revised EEI-8 and found no deficiencies. The ERT review

was documented in memorandum CPRT-706.

Since the requirements of this activity have been fulfilled, NRC

inspection of this activity is complete.

No violations or deviations were identified.

Revise Inspection Procedure QI-QP-11.3-28 (NRC Reference 01.a.01.02).

t

l

A review and comparison of Inspection Procedure QI-QP-11.3-28,

l Revisions 23 through 30, was performed by the NRC inspector.

'

Revision 30 was dated May 21, 1986. The procedure was revised to

,

require QC to witness cable preparation, record HSI kit numbers,

j record sleeve numbers, record lot numbers, verify that braided cable

!

I

L

,

..

8

Jacket material was removed, and verify that a minimum of 2 " of

sleeve was on each side of the conductor splice.

The NRC inspector verified that the ERT reviewed Revision 30 of the

procedure and found no deficiencies. This review was also documented

in memorandum CPRT-706.

Since the requirements of this activity have been fulfilled, NRC

inspection of this activity is complete.

No violations or deviations were identified.

Revise Inspection Forms (NRC Reference 01.a.01.03)

The NRC inspector verified that the inspection forms used with

Procedure QI-QP-11.3-28 had been revised to include specific

sign-offs for HSI attributes. The short form used in the past has

been deleted from the procedure. Based on NRC inspector review of

this procedure and inspection forms, the requirements of this

activity have been fulfilled and NRC inspection of this activity is

complete.

No violations or deviations were identified.

Train Craft Personnel (NRC Reference 01.a.01.04)

The NRC inspector reviewed the lesson plan used for training craft

personnel to Procedure eel-8 and held a discussion with the

instructor. The NRC inspector determined that the lesson plan

included the Raychem installation instructions for HSI. The NRC

inspector, in addition to reviewing the lesson plan, reviewed a

sample of 19 electrical terminators' (craft personnel) training

records to verify that all 19 craftsmen had been trained according to

Revision 6 of eel-8. The NRC inspector verified that the ERT had

also reviewed the craft training records and found no deficiencies.

This review is documented in memoranda CPRT-013 and CPRT-366. Based

on the NRC inspector review of the lesson plan and 19 craft training

records, the requirements of this activity have been fulfilled and

NRC inspection of this activity is complete.

No violations or deviations were identified.

Train / Certify Inspection Personnel _(NRC Reference 01.a 01.05)

_

A review was performed by the NRC inspector of the lesson plan used

for training QC inspectors to Procedure QI-QP-11.3-28. No

deficiencies were identified in the lesson plan. A random sample of

nine QC inspector training records was reviewed by the NRC inspector

for verification of training. Of the nine inspectors, seven had

received appropriate training and were certified to the current

revision of Procedure QI-QP-11.3-28. Two of the inspectors

_ _ _ _ _ _ _ _ _ _ _ _ _

e. ..

9

transferred to other departments outside of QC. The requirements of

this activity have been fulfilled; therefore, the NRC inspection of

this activity is complete.

No violations or deviations were identified.

Identify Required Sleeve Locations (NRC Reference 01.a.01.06)

The NRC inspector reviewed the CPRT files to determine the methods

used to identify the sleeve locations as required by the action plan.

The sleeve locations for: (1)penetrationassembliesweredetermined

from penetration connection drawings - 1004 penetrations (2) motors

from power distribution system one-line drawings - 293 motors.

(3) electrical devices in a harsh environment from

drawingsforharshenvironments-48 devices,and(physicallayout4)reductionsp

from drawings for probable locations - 14.

The NRC inspector found these methods to acceptably fulfill the

comitments made by the CPRT. The NRC inspection of this activity is

complete.

No violations or deviations were identified.

Issue Nonconfonnance Reports (NRC Poference 01.a.01.08)

The NRC inspector verified that 22 NCRs were issued for the

deviations identified as a result of the document reviews and

inspections performed for this ISAP. These NCRs are listed in CPRT

memorandum CPRT-739 dated November 5, 1986. The NRC inspector

verified that the project NCR files contained all 22 of these NCRs.

The files indicated that 12 were closed 2 were voided and 8 remained

open. The two voided NCRs were reviewed and found to clarify the

surface preparation requirements for bolted connections. Therefore,

the requirements of this activity have been fulfilled and NRC

inspection of this activity is complete.

No violations or deviations were identified.

Review of Inspection Reports (NRC Reference 01.a.01.09)

The NRC inspector verified, through a review of the CPRT files, that

theappropriateinspectionreports(irs)hadbeenreviewedbythe

ERT. The ERT leader signed each of the 47 irs contained in the

ISAP 1.a.1 files. In addition, the ERT review of the irs was

documented in CPRT memorandum CPRT-731 dated November 4, 1986.

The NRC inspector found the above documentation to acceptably fulfill

the CPRT commitment that the ERT review the irs. Therefore, NRC

inspection of this activity is complete.

No violations or deviations were identified.

_ _ _ _ __ - ____ _ ___-__- . _ _ _ _ - - - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ . _ _-____________ ___ ______ ____.

i

t

<

!

.. ..

10

,

1

l

Visual Hardware Inspection (NRC Reference OI.a.01.10)

, Eleven cables were identified by CpRT inspectors as requiring visual

inspection because the irs did not reflect the installation of a HSI.

Five of these cables were found with no sleeve installed and none was i

required; four of the installed sleeves were found to be  :

unsatisfactory when inspected and were replaced; all other

installations were acceptable.

The NRC inspector reviewed the irs written for these

!

visual inspections, and found that the requirements of this activity

have been fulfilled. NRC inspection of this activity is complete.

,

No violations or deviations were identified.  ;

!

Inspect 7 Cables /26_ Equipment Items (NRC _ Reference 01.a.01.11) l

!

,

The NRC inspector reviewed the irs written for the

CpRT visual inspections of an additional 7 cables and 26 pieces of l

j equipment that could have had installed reduction splices. No

'

reduction splices were found by the CPRT inspectors. Therefore, the

< requirements of this activity have been fulfilled and NRC inspection i

of the activity is complete,

No violations or deviations were identified,

j

j Review irs for 7 Cables /26 Equipment _ Items _(NRC Reference _01.a.01.12}

_  !

l Since no reduction splices were found during the visual reinspections  !

of the 7 cables and 26 pieces of equipment, no IR review was i

i required. Therefore, the requirements of this activity have been

'

fulfilled and NRC inspection of this activity is complete.

I

No violations or deviations were identified.

'

'

I

j Est_ablish_ Root Causes/ Implications /SafetyJ NRC Reference 01.a 01.13) >

l

This activity will be evaluated after the results report has been

j issued.

4

l

j Identify Corrective Action G RC__ Reference 01.a.01.14) l

4

1

) This activity will be evaluated after the results report has been  !

i issued.  !

,

j b NCR$ on Vendo_r installed _ Amp Terminal Lugs _(! SAP 1,a J l

3

The applicant committed to reevaluate and redisposition all NCRs

! which had been written related to vendor-installed terminal lugs in l

i

'

ITE Gould-Brown Bovert switchgear. These actions were to include  ;

consideration of twisted as well as bent terminal lug barrels to

I

!

_ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . . _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ ___.

.. ..

11

confirm the acceptability of the "use-as-is" dispositions which had

been made for the involved NCRs. The applicant actions and NRC

inspector verification consisted of the following.

Disposition of NCRs (NRC Reference 01.a.05.01)

The NRC inspector determined, by CPRT records review, that all of the

involved NCRs had been redispositioned by the applicant; the details

of this inspection were contained in NRC Inspection

Report 50-445/86-01; 50-446/86-01. During this report period, the

NRC inspector verified that the remaining portion of this activity,

ERT approval of final NCR dispositions, had been completed. The

Review Team Leader (RTL) documented the review of the NCR

dispositions by memorandum CPRT-285 dated March 4, 1986. The ERT

review consisted of a visual examination of the involved terminal

lugs. During the ERT examination, a terminal lug, which was to have

been replaced, was determined to have remained installed. (The RTL

assumed that a lug on the same termination point of an adjacent

terminal board had been replaced in lieu of the required lug.) This

deviation was referred to the QA/QC RTL by memorandum CPRT-290 dated

March 6, 1986, in accordance with the CPRT Program Plan, Appendix B,

for inclusion in the collective evaluations. In addition, the NRC

inspector verified that NCR E86-100831 had been written to replace

the terminal lug in question; this rework had not been accomplished

as of the end of this report period.

Based on the above, the NRC inspector determined that the

requirements of this activity have been fulfilled; therefore, NRC

inspection of this activity is complete.

No violations or deviations were identified.

Vendor Analyh(NRC Reference 01.a.05.02)

The submittal and applicant review of the vendor (AMP, Incorporated)

engineering evaluation were also discussed in NRC Inspection

Report 50-445/86-01; 50-446/86-01. The NRC inspector determined, by

review of a memo in CPRT files, that ERT had reviewed the AMP

engineering evaluation report (EER)-136 and the additional

metallurgical analysis recommended by the RTL. These reports

confirmed the terminal lug qualification provided: (1) bending did

not exceed 90', and/or (2) twisting did not exceed 45*. Confirmation

is contained in memorandum CPRT-468 dated June 3, 1986, that the ERT

reviewed these reports.

Based on the above, the NRC inspector determined that the CPRT

commitments for this activity have been fulfilled; therefore, NRC

inspection of this activity is complete.

No violations or deviations were identified.

.. ..

12

,

Use of Results (NRC Reference 01.a.05.03)

The ISAP required a root cause and generic implications evaluation if

deficiencies were identified in the "use-as-is" NCR dispositioning.

Since no deficiencies were identified in the NCR dispositioning, this

requirement is moot. However, the NRC inspector verified that the

applicable installation specification (2323-ES-100), craft

installation procedure (eel-8), and QC inspection

procedure (QI-0P-11.3-28) had all been revised to include instruction

that terminal lugs were to be bent no more than 90* and twisted no

more than 45*.

Based on the above, the NRC inspector determined that the

requirements of this activity have been fulfilled; therefore, NRC

inspection of this activity is complete.

No violations or deviations were identified.

Related Activities (NRC Reference 01.a 05.04)

An evaluation of the disposition of the original NCRs and the

additional NCRs related to terminal lugs that were the subject of

memorandum CPP-19,359 dated February 25, 1986, will be included in

ISAP VII.a.2, "Nonconformance and Corrective Action Systems."

Based on these actions, the NRC inspector determined that the

implementation requirements of this ISAP have been fulfilled;

therefore, NRC inspection of this ISAP is complete.

No violations or deviations were identified.

c. Material Traceability (ISAP VII.a.1)

During this report period, the ISAP activities identified by NRC

Reference 07.a.01.02, and 07.a.01.08 were % nected as follows:

Evaluate Procedures for Material Control 04RC Reference 07.a.01.02)

The ERC evaluation of the site procedures for material control was

reviewed by the NRC inspector to verify implementation of ISAP

paragraph 4.1.2.2. The ERC review checklist was inspected and found

to properly include requirements found in Criterion VIII of

10 CFR 50, Appendix B, and the FSAR, Section 17.1.8, " Identification

and Control of Materials, Parts, and Components." NRC inspection of

the completed procedure reviews found them to properly indicate where

the attributes were incorporated. This was accomplished by the NRC

inspector selecting attributes on the review checklist and verifying

that the attributes were in the procedure. The NRC inspector

determined that using the ERC checklist, the resulting evaluations

would provide the necessary input for the analysis of material

control required by ISAP paragraph 4.1.2.7.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ - _ _ _ _ _

.. ..

13

'

No violations or deviations were identified and no further inspection

is planned for this reference area.

Qualifications of Personnel (NRC Reference 07.a.01.08)

The qualifications of personnel directly involved with gathering or

evaluating data for input to this ISAP were reviewed by the NRC

inspector. The resumes and objectivity questionnaires verified that

the qualifications of ISAP personnel were found to be in accordance

with the requirements of the CPRT Program Plan.

No violations or deviations were found during inspection of this -

activity.

d. Nonconformance and Corrective Action System (ISAP VII.a.2)

During this report period, the ERC VII.a.2 review team added

evaluation of the TNE Design Deficiency Reports (TDDRs) and the

system controlling their issue to the VII.a.2 ISAP. This activity

will be added to the table of activities reported in NRC Inspection

Report 50-445/86-01; 50-446/86-01 as follows:

Activity ISAP NRC

Paragraph Reference

Evaluation of the 4.1.4 07.a.02.14

TODR System

Implementation of this activity (evaluation of the TDDR system) was

inspected by the NRC as follows:

The NRC inspector reviewed the evaluation data sheets developed by

the VII.a.2 review team to perform their review of the TODR system.

The NRC inspection of the evaluation data sheets was performed to

determine if the requirements of Criteria III and XVI of 10 CFR

Part 50, Appendix B; CPSES FSAR, Section 17.1.2.3 and

Section 17.1.2.16, Amendment 55 (Regulatory Guide 1.28 and 1.64); and

TUGCo Procedure TNE-AD-5, all revisions, " Identification of Design

Deficiencies and Errors," were properly incorporated. The NRC

inspector found that the ERC evaluation data sheets included the

regulatory requirements of identifying the nonconformance, evaluating

the nonconformance for reportability, prescribing

corrective / preventive action, and assuring implementation of

corrective / preventive action.

The NRC inspector reviewed the methods that the VII.a.2 review team

used to identify the population of TDDRs and to generate a random

sample of 60 TDDRs. The methods were found to conform to the

'

requirement of the ISAP, paragraph 4.1.4, and to Appendix D of the

CPRT Program Plan. The NRC inspector selected six TDDRs from the ERC

sample to review in detail. These six TDDRs were reviewed for each

r

s

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ -a

.. . - - . - , . -

.

.. ..

I4

of the decision points listed on the VII.a.2 TDDR evaluation data

sheets (I5 items on each TDDR). The results of the NRC review of the

6 TDDRs (total of 90 decision points) was in agreement with the

'

results of the VII.a.2 review team. By inspection of review team

notes and files the NRC inspector also verified that the VII.a.2

review team had performed a review of the TDDR system, had reviewed

applicable TDDR files, and had interviewed key personnel associated

with the TDDR system. These actions were required by the ISAP and

were to familiarize the VII.a.2 review team with the mechanics of the

,

TDDR system.

No violations or deviations were noted for the above activities.

Further activity in this area will be inspected and reported as it is

completed.

e. Document Control (ISAP VII.a.3)

During this report period, the ISAP activities identified by NRC

References 07.a.03.01, 07.a.03.02, 07.a.03.03, and 07.a.03.05 were

inspected as follows:

Identify Other-ISAPs Verifying Document Control (NRC Reference

07.a.03.01)

The issue coordinator for this action plan has identified the ISAPs

that perform activities which verify if plant hardware was installed

and tested in accordance with current design requirements:

ISAP III.d Preoperational Testing

ISAP VII.c Construction Reinspection / Documentation Review Plan

The NRC inspector reviewed ISAP III.d and ISAP VII.c and determined

that these two ISAPs would provide data to assess the impact of past

document control problems on the installation and testing of plant

hardware.

ISAP III.d was developed to determine if site document control

problems had an adverse effect on prerequisite or preoperational

testing.

ISAP VII.c required that a hardware reinspection or documentation

review be performed on selected samples from 32 defined populations.

This resulted in numerous hardware reinspections and documentation

reviews being performed by the CPRT. ISAP VII.c further required

that all valid DRs resulting from these hardware reinspections or

documentation reviews be evaluated by the Safety Significance

Evaluation Group and a root cause analysis be performed for each

safety-significant deviation or adverse trend arising from the

totality of DRs. Thus, VII.c provides data relative to the impact of

document control on safety-significant attributes of installed

hardware.

__

_ _ _ _ . - . - _ _ _ _ _ _ . _ - _ - - _ _ . _ _ _ . - _ ,_ ._

__ ._ . .. _ - _-_ . . .

I' .

-. ..

15

b

-

No violations or deviations were noted and no further NRC inspection

is planned for this reference area.

Evaluate ISAP III.d and ISAP VII.c Document Control Deficiencies

(NRC Reference 07.a.03.02)

The NRC inspector verified the evaluation of ISAP III.d and

ISAP VII.c document control deficiencies performed by the

ISAP VII.a.'3 issue coordinator. inis verification was accomplished

by the NRC inspector interviewirt the ISAP VII.a.3 issue coordinator

and reviewing the notes and data in the ISAP VII.a.3 working file.

Further, the NRC inspector reviewed the ISAP III.d Results Report on

plant testing, all current root cause analyses resulting from

ISAP VII.c, and the current results of 18 ISAP VII.c population

reports for identification of document control problems. The results

of this verification found that the ISAP VII.a.3 working file notes

accurately reflected that.the ISAP III.d Results Report reported no

deficiencies or adverse trends related to document control. The

,

ISAP VII.a.3 working file also accurately reflected that the root

cause analyses from implementation of ISAP VII.c identified no case

where document control deficiencies were identified as the root cause

of any safety significant deficiency, adverse trend, or unidentified

trend.

The NRC inspector's review of the current results from 18 of the

ISAP VII.c population reports found no indication that document

control deficiencies should have been identified as the root cause of

any safety-significant deficiency, adverse trend, or unidentified

trend.

The NRC inspector noted that the current results of the ISAP VII.c

r population reports are not final approved. The issue coordinator has

indicated that if document control deficiencies are subsequently

identified by ISAP VII.c or any other ISAP to'be the root cause of

safety-significant deficiencies, a reassessment of the results of

ISAP VII.a.3 would be conducted by the Collective Evaluation Group.

The NRC inspector verified through review of the above items, that

ISAP VII.a.3 evaluation of ISAP III.d and ISAP VII.c for document

control deficiencies properly reflected the current status of these

ISAPs, and that the ISAPs did not identify document control problems

1

as the root cause of any safety-significant deficiency.

No violations or deviations were noted. The NRC inspector will

continue to monitor ISAP VII.c or other ISAPs for document control

i

problems that may affect this ISAP VII.a.3 evaluation.

- .._ . _ . _ _ _ . - -. ,. , - . . , - . - -- - . - , - - . - - -

_

e. ...

16

Determination of Corrective Action (NRC Reference 07.a.03.03)

ISAP VII.a.3 required that a determination of corrective action be

made if review of ISAP III.d and ISAP VII.c results identified

deficiencies in the document control program.

The NRC inspector verified and reported in this ~ report that

ISAP III.d and ISAP VII.c results did not identify deficiencies in

the document control program, thus no condition requiring corrective

action has been identified.

No violations or deviations were identified in this reference area.

Action on Adverse Trends / Deficiencies (NRC Reference 07.a.03.05)

ISAP VII.a.3 required that remedial action be performed for adverse

trends or safety-significant deficiencies whose root causes were

attributed to document control inadequacies.

The NRC inspector verified and reported in this report that, to date,

ISAPs VII.a.3, III.d, and VII.c results have not identified

deficiencies whose root causes were attributed to document control

inadequacies; thus, no remedial action for such deficiencies have

been required.

No violations or deviations were identified in this reference area.

f. Adequacy of-Purchased Safety-Related Material (ISAP VII.a.9)

ISAP VII.a.9 has been significantly revised by ERC to reflect

comments from the NRC staff. A table of specific activities for

Revision 0 of the ISAP was initially reported in NRC Inspection

Report 50-445/86-03; 50-446/86-02. A revised table to reflect

issuance of Revision 1 dated September 9, 1986, follows:

l' Activity ISAP NRC

Paragraph Reference

Select material / equipment to be 4.1.2 07.a.09.01

reviewed.

Develop reinspection checklists 4.1.3 07.a.09.02

for material and equipment selected.

Perform field inspection of 4.1.3 07.a.09.03

selected material and equipment.

i-

1- Document discrepancies from 4.1.3 07.a.09.04

'

reinspection.

l

l

l

l.

i

  • F ...

17

Develop procurement program review 4.1.3 07.a.09.05

checklists.

Evaluate the current program for 4.1.3 07.a.09.06

adequacy.

Document discrepancies from program 4.1.3 07.a.09.07

evaluation.

Qualifications of personnel. 4.1.3 07.a.09.08

'The ISAP activities identified by NRC Reference 07.a.09.02 and

07.a.09.03 were inspected during this report period as follows:

Develop Reinspection Checklists for Material and Equipment Selected

(NRC Reference 07.a.09.02) and Perform Field Inspection of Selected

Material and Equipment (NRC Reference 07.a.09.03)

The NRC inspector' reviewed the completed reinspection checklists for

two VII.a.09 material / equipment samples. The samples were identified

by the VII.a.09 review team as I-M-VIIA 9-016 and I-M-VIIA 9-052. The

NRC inspector reviewed-these reinspection checklists to determine

that they addressed the criteria of ISAP VII.a.9, paragraph 4.1.3,

and reflected the specific requirements of the applicable procurement

specification and TUGCo/ vendor design drawings which were in effect

at the time of the material being received at CPSES. The

reinspection checklists were found to include inspection of the

chemical and mechanical test results (CMTRs), hydrostatic test

results, RIRs, authorized nuclear inspector review, pressure and

nonpressure boundary welds, functional linear dimensions, compliance

with. shipping requirements, proper nameplate information, proper heat

numbers, and that'the equipment had no visible arc-strikes. The NRC

inspector determined from review of the reinspection checklist and

ERC letter QA/QC-RT-4145, which details the inclusion or exclusion of

inspection attributes, that the reinspection checklist properly

reflected the procurement requirements.

The NRC inspector performed a document review and a field inspection

of the sample items per the ERC reinspection checklist. These

actions yielded the same results as the ERC reinspection includt.1g

discrepancies documented by ERC on DRs. An example of these

discrepancies was the failure to have records documenting that two

air accumulators were shipped and received with desiccant sealed

inside the tanks as required by the purchase order. The lack of

records for the desiccant was documented by ERC on a DR. During NRC

inspection of this DR, it was found that installation records for

these air accumulators had not been properly prepared. The applicant

has shown that the lack of installation records for the air

accumulators had been previously addressed in NCRs I86-103786 and

186-2021795 which resulted from an ISAP VII.c reinspection.

  • .. .,

18

ISAP VII.a.9 is structured such that DRs resulting from reinspection

are not validated until after a review is performed to determine if

changes, authorized since the time of procurement, may_ invalidate the

discrepancy. The NRC inspector will review VII.a.9 DRs, especially

any invalidated DRs, to assure that the DRs are properly processed.

No violations or deviations were noted; further NRC inspection of

these ISAP activities will be reported as they are completed.

g. Onsite Fabrication (ISAP VII.b.1)

During this report period, the ISAP activities identified by NRC

References 07.b.01.02,.07.b.01.03, 07.b.01.04, 07.b.01.05,

07.b.01.06, and 07.b.01.09 were inspected as follows.

Identify and Select Samples from ASME and Non-ASME Fabrications

(NRC Reference 07.b.01.02)

The selection of the ASME safety-related fabricated samples was

previously reported in NRC Inspection Report 50-445/86-03;

50-446/86-02.

During this report period, the NRC inspector inspected the ERC

selection of non-ASME fabricated items (cable tray hangers). The

items selected required at least two of three work activities

(usually cutting and welding) and that they represented a reasonable

cross-section of both ASME and non-ASME fabrication shop activity.

The NRC inspector verified by review of the non-ASME items selected

(18) that the requirements and criteria for sample selection in

paragraph 4.1.2.2 of the ISAP were met. The non-ASME sample was-

found to include three items per-year from 1978-83, which was also an

,

ISAP requirement.

The ASME sample totalled .73 items (as reported previously) while the

'

non-ASME sample totalled 18 items. This total of 91 ASME/non-ASME

items complies with the ISAP commitment (72 item minimum) and is a

representative cross section of fabrication shop activities for the

years of interest (1978-85).

'

No violations or deviations were noted and no further NRC inspection

is planned for this area.

Review Fabrication Packages (NRC Reference 07.b.01.03)

The ERC review of ASME related fabrication packages was previously

inspected and reported in NRC Inspection Report 50-445/86-22;

50-446/86-20. During this report period, non-ASME fabrication

packages were reviewed and inspected by the NRC inspector. The NRC

, inspector selected two of the non-ASME fabrication packages for

review using the criteria listed on the ERC review checklist. The

fabrication packages selected for review were CTH01205 and CTH03254.

.. _ _ _ . _ . _ .

a.= ..

19

The results of these NRC reviews were compared to the documentation

of the same ERC reviews to determine their completeness and accuracy.

The reviews were found to have properly recorded the qualification

status of welders, certification status of QC inspectors, and the

material identity of component material. Other review criteria; such

as, all required inspections completed, required documentation

completed, and legibility were also found to be properly recorded.

No violations or deviations were identified.

'

NRC inspection of this reference activity is complete except for

closing of a deviation identified in NRC Inspection

Report 50-445/86-22; 50-446/86-20.

.

Hardware Reinspection of Fabrication Package Discrepancies (NRC

Reference-07.b.01.04)

During the ERC review of completed fabrication packages, the ERC

document reviewers noted discrepancies in the supporting documents

for the packages,.1.e., missing information on the Bill of Materials

and other documentation problems. These discrepancies were recorded

in DRs as required by procedure. The issue coordinator determined

that these discrepancies were document problems that did not require

a visual reinspection of the installed material to determine that a

deviation existed. In some cases, visual reinspections were

,

performed but only to gather information in support of the DRs.

During the NRC review of the ASME and non-ASME fabrication packages,

the'NRC inspector assessed the documentation discrepancies to

determine that the discrepancies were document problems and that the

I issue coordinator's action of not performing hardware reinspections

to resolve the discrepancies was proper.

No violations or deviations were identified and no further NRC

l inspection is planned for this reference area.

Review of Storage and Surveillance Procedures and Records for

Adequacy (NRC Reference 07.b.01.05)-

The NRC inspected-the ERC review of the storage, fabrication, and

inspection procedures applicable to onsite fabrication. The NRC

1 inspector verified that the attributes listed by ERC as necessary for

! control of material traceability, fabrication processes, and

!. completed item inspection and acceptance reflected the requirements

! of Criteria V, VIII, IX, X, and XIII of Appendix B to 10 CFR Part 50

'

and the Comanche Peak FSAR. The NRC inspector verified that the ERC

l. review results had properly identified where these attributes existed

j

in the current and historical procedures for onsite fabrication.

t No violations or deviations were identified and no further NRC

inspection is planned for this reference area.

(

l

l

r

I

!

t

-_~ , _ .

. . _ _ _ , , . . - - - - _ ,---_.v - _ _ _ , .-

. _ . . _ . _ _ _ _ - ___ . ~ - . - _ __

..E 5

20

Review ISAP VII.a.1 Deviation for Reinspection (NRC

Reference 07.b.01.06)

The commitment to review fabrication shop deviations identified by "

. ISAP VII.a.1 has been excluded from ISAP VII.b.1, Revision 2. The

ISAP VII.b.1 issue' coordinator determined that ISAP VII.a.1 was not

structured to. review fabrication shop packages.

The NRC inspector reviewed ISAP VII.a.1, Revision 1, to verify that

review of fabrication packages was not required in that ISAP. No

such requirement was found.and none appeared warranted. Therefore,

the issue coordinator's determination to exclude this commitment was

correct. No further NRC inspection is planned for this activity.

-No violations or deviations were identified during inspection of

reference item ISAP VII.b.01.06.

i

'

Notify TUGCo of Hardware Deviations (NRC Reference 07.b.01.09)

The NRC inspected a sample of the ASME and non-ASME fabrication

packages. These package inspections have been reported under NRC

Reference 07.b.01.03. During these inspections, the NRC inspector

verified-that deviations were documented on ERC DRs. ERC

Procedure CPP-016, Revision 3, " Safety Significance Evaluations of

-Deviation Reports," requires that a safety-significance

evaluation (SSE) be performed for each valid DR and that the

completed SSE be transmitted to the TUGCo QA coordinator who is

,

responsible to evaluate the SSE/DR in accordance with TUGCo

Procedure CP-QP-16.3, " Processing CPRT Deviation Reports /0bservation

Notices." The NRC inspector determined from the above review that

TUGCo QA is being properly notified of deviations found during

,

implementation of ISAP VII.b.1.

.

No violations or deviations were identified and no further inspection

-is planned for this reference area.

'

'4. Construction / Reinspection (ISAP VII.c)

a. Field Fabricated Tanks

Status of CPRT Activity

ERC has completed four reinspections and eight documentation reviews

of sampled field fabricated tanks. Thirty-six valid deviations have

been issued by ERC.

Status of NRC Inspection Activity

To date, the-NRC inspector has witnessed 10 percent of ERC

reinspections, performed documentation reviews of five Field

Fabricated Tank packages, and performed inspection of approximately

., _ _ , . _ _ _ . .. , . . . _ _ _ _ _ . - - _ _ _ _ _ _ . . . . _ _ _ _ _ _

.- . . -- . _ . . _- - . . -_

-

,

s.. , ,

21

15 percent of'the population sample, of which the following

p documentation review occurred during this inspection period:

Verification Tank I.D. System * Unit

. Package

, R-M-FFTA-001 .CPX-CSATBA-01 CS Common (1)

  • CS - Chemical ~and Volume Control

This review revealed that an ERC inspector had written

DR R-M-FFTA-001-DR6 to document the existence of CBI fabricated

'

material which did not comply with the requirements of ERC Quality

Instruction (QI) QI-042, Revision 0, Attribute 10. This attribute

states, " Verify that the Metal Material Verification Summary Sheet

identifies the correct material and that the 'CTR Checked' space is

signed." The ERC inspector noted ". . . Many of..the items' identified

to the requirements on the certified drawings were entered on a form

identified as a " Supplemental Summary Sheet of Material Verification"

(not noted in procedure QI-042) with no signatures of any kind for

verification." Subsequent review by ERC engineering determined that

the DR was not valid since the intent of QI-042 (that the correct

material was used) had been met.

The NRC inspector reviewed CBI contract requirements; i.e., CBI QA

, Manual and material requirements table MRT 73121/2 to assess the

i technical accuracy of the DR invalidation. The CBI material

requirements table identified that as a minimum requirement for

. Type A, B, and C material, a material verification summary sheet

.

shall be submitted to TUSI (B&R), and did not reference the alternate

, use of the Supplemental Summary Sheet for Material Verification. The

failure of ERC construction sample reinspection engineering to

validate a DR, which correctly identified that CBI did not comply

~

with their program requirements for materials, is a deviation

. -(445/8631-0-03; 446/8625-D-01).

b. Piping Bend Fabrication .

Status of CPRT Activity

ERC has completed all of the required reinspections of the 92 random

( and engineered sample selections. One valid deviation was identified

by ERC. Documentation review was not required for this population.

l

[ Status of NRC Inspection Activity '

!

l The NRC inspector did not witness any ERC reinspections. To date,

the following four inspections have been performed, all of which

i occurred during this report period:

!

I

. .. - - =. ..

..- ..

22

Verification Package Drawing System * Unit

I-M-PB FA-021 BRP-RC-1-RB-010 RC 1

I-M-PBFA-022 BRP-SI-1-RB-022 SI 1

I-M-PBFA-031 BRP-CC-1-RB-035 CC 1

I-M-PB FA-032 BRP-CC-1-RB-068 CC 1

SI - Safety Injection

CC - Component Cooling

No violations or deviations were identified.

c. Fuel Pool Liners

-Status of CPRT Activity

!-

,'

ERC has completed 62 reinspections and 100 documentation reviews of

sampled fuel pool liners. Twenty-nine valid deviations have been

issued by ERC.

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed three ERC reinspections,

performed documentation reviews of five Fuel Pool Liner packages, and

separately performed three inspections, of which the following

documentation review occurred during this inspection period:

Verification Package Weld I.D. Unit

R-S-FPLR-001 #2050 2

R-S-FPLR-004 #969 2

i

R-S-FPLR-025 #865 1

R-S-FPLR-071 #1732 1

R-S-FPLR-162 #2041 1

No violations or deviations were identified.

d. ~ Documentation Review of Category I Conduit Supports

l

Status of CPRT Activity

Documentation review of the 155 Category I conduit supports sample is

complete. As a result, ERC has initiated 616 DRs, of which 176 have

been established as being valid.

Status of NRC Inspection Activity

.

'

To date, the NRC inspector has performed eight inspections and

conducted five documentation reviews of Category I conduit support

!

,._.. .-, -,, ~ . - - . . .-_ _ _.- _ - - - ~. - . . . - . . _ ~ _ . _ - - . . _ _ - - - - - _ _ -.

+. . . . .

23

_ packages. 'All five.of the documentation reviews were conducted

during this report period and are as follows:

Verification Package Conduit Support -Unit

R-S-CSDP-021 C03016387-03 1

R-S-CDSP-072 C14YO9317-02 1

R-S-CDSP-040 EAB11-3 #16 1

R-S-CDSP-001 C12G07866-02 1

R-S-CDSP-039 C16R09450-01 1

No violations or deviations were identified.

e. Reinspection of Small Bore Pipe Supports

Status of CPRT Activity

Reinspection and documentation review of small bore pipe supports is

complete. Sixty-seven valid deviations from reinspection and six

valid deviations from documentation review have been issued. A total-

of 64 valid deviations have been evaluated for safety significance,

resulting in the identification of 2 safety-significant deviations.

Status of NRC Inspection Activity

-To date, the NRC inspector has witnessed 7 ERC reinspections,

performed documentation reviews of 5 small bore pipe support

packages, and performed 11 inspections, of which the following

documentation reviews occurred during this inspection period:

Verification Package Support System * . Unit

-R-S-SBPS-003 CH-1-SB-014-002-3 CH 1

R-S-SBPS-017' CC-1-EC-006-005-3 CC 1

R-S-SBPS-037 - CH-X-FB-003-021-3 CH Common

R-S-SBPS-044 CC-1-RB-003-006-3 CC 1

! R-S-SBPS-051 GH-X-AB-051-004-3 GH Common

  • CC - Component Cooling Water

CH -Ventilated Chilled Water

GH - Gaseous Waste Processing

i No violations or deviations were identified.

4

f. Reinspection of Equipment Supports

,

Status of CPRT Activity

Reinspection and documentation review of equipment supports is

complete. Ninety valid deviations from reinspection and forty eight

valid deviations from documentation review have been issued. A total

.

., . , , - , , - - , , . . , , ..n --.- - - . ,. - ,-. , -

-,-,-,----+--.ee,-e- .w,, ,.w -,, _

.. . .

24

of 129 deviations have been evaluated for safety significance. No

safety-significant deviations have been identified.

Status of NRC Inspection Activity

'To date, the NRC inspector has witnessed-four ERC reinspections,

performed documentation reviews of five equipment support packages,

and performed seven inspections of which the following documentation

reviews occurred during this inspection period:

Verification Package Equipment Unit

R-S-EQSP-008 .CP1-VAFNAV-32 1

-R-S-EQSP-038 ILCS-5691A 1

R-S-EQSP-045 ILCS-5803 1

R-S-EQSP-049 CP2-EPTRET-04 Common

R-S-EQSP-052 CP2-ELDPEC-14 Common

No violations or deviations were identified.

g. Reinspection of Containment Liner and Tank Stainless Steel Liners

Status of CPRT Activity

Reinspection and documentation review of containment liner and tank

stainless steel liner packages is complete with 91 packages

inspected. Eighty-five valid deviations.from reinspection and twelve

valid deviations from documentation' review have been issued. A total

-of 87 deviations have been evaluated for safety significance. No

safety-significant deviations have been identified.

Status of NRC Inspection Activity

To date, the'NRC inspector has witnessed nine ERC reinspections,

performed documentation reviews of five liner packages, and performed

three inspections of which the following documentation reviews

occurred during this inspection period:

Verification Package Joint Unit

R-S-LINR-08 8D 1

i

R-S-LINR-12 P-88 2

R-S-LINR-50 P-366 1

R-S-LINR-60- P-387 1

R-S-LINR-67 B5(A) 2

No violations or deviations were identified.

i

r

1

u*. -. .

25

h. Reinspection of Structural Steel

Status of CPRT Activity

ERC has completed reinspection of 143 of a planned total of 144

structural steel reinspection packages. In addition, ERC has

reviewed 138 of 140 structural steel documentation review packages.

A total of 281 valid deviations from reinspection and 180 valid

deviations from documentation review have been issued resulting in

the identification of four safety-significant deviations.

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed nine ERC reinspections,

performed documentation reviews of ten structural steel packages

(five packages had no documentation, see below), and performed four

inspections.

The NRC inspector-randomly selected ten structur O steel packages for

documentation review. Five of these packages were reviewed in

detail. A thorough inspection of the remaining five verification

packages was not possible because documentation, such as original

construction and inspection records, could not be located by ERC.

The NRC inspector confirmed _this situation. Apparently, no evidence

exists to show that these five packages were originally QC inspected.

The ERC inspector correctly rejected Attribute A.1 (for existence of

an inspection package) and entered NA, not applicable, for all

remaining attributes as required by ERC QI-046, Revision 2. One DR

per package was issued by ERC stating that, " Plant personnel unable

to locate any documentation at the Permanent Plant Records

Vault (PPRV) for this package." The disposition of these deviations

is an open item (445/8631-0-04).

The ten structural steel verification packages reviewed by the NRC

inspector were as follows:

Verification Package Equipment Unit

R-S-STEL-007 Mk A12 (2323-S1-0564) 1

  • R-S-STEL-059 AFC0 Mk F180-1-RB 1
  • R-S-STEL-088 AFC0 Mk C182-7-RB 1

R-S-STEL-117 Mk D2 (2323-51-0564) 1

  • R-S-STEL-120 MRB-0565-DCA, Mk A 1

R-S-STEL-140 Mk C9-22 (MAB-0799-0C5, SH1) 1

R-S-STEL-146 Mk C9-4 (MAB-0799-0C7) 1

. - - . _ _ _=- . .-

t

4. . . < , .

26

  • R-S-STEL-164 DWG 2323-S1-0602 1

Jet Door 4' E of ES

  • R-S-STEL-197 AFC0 Mk B176-1-SA 1

R-S-STEL-236 Mk C7R (2323-SI-0564) 1

'

  • No documentation available for review.

The NRC inspector observed that "N/A" (not applicable) was entered by

the ERC inspector for Attribute B.3.1, structural bolting tightness,

in Verification Package R-S-STEL-117. The ERC inspector listed TUGCo

Instruction QI-QP-11.14-1 in the comment section for this attribute.

Paragraph 5.0.B.3.1 of ERC QI-046, Revision 2, states, in part,

" Verify, by review of the inspection report or Construction Operation

Traveler, that the bolts were tightened in accordance with the design

, drawings. . Record, (if listed) in the comments section of the

"

, checklist . . . the method listed for tightening . . . ."

Drawing 2323-SI-0564, Revision 2, shows eight 3/4" A193, Grade B8,

-Class 1, bolts in bearing connections for member D2. Tightness _of

these bolts is addressed and signed off on construction operation

traveler CE-82-358-4802. Paragraph 3.2.3.2.e of TUGCo

Instruction QI-QP-11.14-1, Revision 25, states, in part, "All

threaded bolts in bearing type connections shall be tightened

snug-tight.as a minimum." Attribute B.3.1, structural bolting

tightness does, in fact, apply to this inspection. This is a

deviation (445/8631-0-02).

1. Reinspection of HVAC Equipment Installation

Status of CPRT Activity

A total of 181 HVAC equipment packages were randomly selected by ERC

from a population of 604 packages representing Units 1, 2, and

common. To date, -331 DRs have been written with 187 determined to be

valid.

' Status of NRC Inspection Activity

To date, the NRC inspector has witnessed four reinspections and

' performed five inspections. No documentation review inspections are

scheduled for HVAC equipment installation. The five inspections were

performed during this report period and are as follows:

..

Verification Package Equipment Unit

.I

I-M-HVIN-032 CPX-VADPOC-64 Common

I-M-HVIN-133 CPX-VADPOC-62 Common

I-M-HVIN-041 CPX-VAFNCB-14 Common

I-M-HVIN-125 CPX-VAERFD-79 Common

I-M-HVIN-185 CPI-VADPFD-023 1

!

-_ _ . __ _ _ _ _ . , - . _. _ _ _ . - . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.l

.. .,

'

27

No violations or deviations were identified.

5. Assessment of Allegations

a. 4-86-A 052: Questionable Entries on Cable Tray Support Packages

An allegation comprised of the following concerns was made by an

individual pertaining to the Unit 1 cable tray hanger walkdown

program:

(1) Cable tray clamp information recorded during a March 1986

walkdown effort had been changed to inaccessible (IA) as a

result of another walkdown team's inspection.

(2) An as-built drawing in package CTH-1-5604 did not have the

required two signatures of both walkdown personnel.

(3) There is a possibility that other packages exist without the

required two signatures.

(4) Package CTH-1-5604 is believed to be missing at this time.

(5) Procedure TNE-FVM-CS-001 was alleged to be only a guide, not a

procedure.

The NRC inspector reviewed Procedure TNE-FVM-CS-001, Revision 3,

which was in effect at the time of.the first walkdown. Section 2.4

states, in part, "If at the time of walkdown any part of a clamp is

inaccessible at the point of walkdown the entire item is to be

-identified as inaccessible (IA) on the drawing."

Section 3.2.3.5 of Revision 5 to TNE-FVM-CS-001 (in effect during the

second walkdown) states, in part, "After the redline process is

. complete, the walkdown team members will sign and date and put their

respective badge number in the available space above the title

block."

The NRC inspector located package CTH-1-5604, which was properly

maintained in Ebasco's document control center. During a review of

this package and an inspection of the support in question, the NRC

inspector identified the following:

Package CTH-1-5604 had been reissued to a second walkdown team

because of changes in the procedure with respect to the documenting

of clamp details. During the course of this second walkdown effort,

the walkdown team found that the entire clamp on each side was not

visible and should have been noted as such on the initial inspection.

The engineer of the second walkdown team lined out, initialed and

dated the original entries for tray clamps, and noted the correct

information on the drawing. The signatures and initials of the

engineer and the craft person performing the first walkdown, along

F'

a..*- c.

28

with the date (March 10,1986), were found in the notes section of

the drawing. The signatures of the engineer and lead engineer

performing the second walkdown, along with the dates _(April 3 and 6,

1986), were observed on the drawing. The NRC inspector was unable to

determine during his review of Revision 4 to the procedure, which

team members were to sign the drawing off but noted that the drawings

were to be signed off. Revision 5 to the procedure clarified the

requirement to be the two individuals performing the walkdown.

During a physical inspection of the support, the NRC inspector found

that approximately 1/3 of each clamp was covered with the tray and

could not be measured according to the procedure, thus an "IA" should

have been entered in the clamp detail block by the first walkdown

team. The second walkdown team.did identify the problem and noted

the correct data on the drawing. A subsequent (third) walkdown was

performed during this investigation and_ included the engineer who

participated in the first walkdown. The engineer concurred with the

decision of the second walkdown team and verified the validity of the

final walkdown package.

The NRC inspector noted that Section 2.1.1 of TNE-FVM-CS-001

identifies the document as a procedure and could find no indication

in any revision of the procedure where it had been_ identified as

anything other than a procedure. Eighty-five additional walkdown

packages were reviewed by the NRC inspector and all were found to be

in accordance with the requirements of the procedure.

In summary, Concern 1 was substantiated; however, the changes were

properly made and documented. Concerns 2, 3, 4, and 5 were not

substantiated. A copy of this inspection report will be provided to

the alleger,

b. 4-86-A-079: Design changes in the Instrumentation and Control Area

(I&C)

It was alleged that TNE drawing revisions incorporating outstanding

changes were not adequately controlled or implemented; for example:

(1) design changes are made without QC inspecting resulting work to

assure configuration agreement, (2) no mechanism was apparent in the

paper flow group (PFG) to notify QC that previous inspections of

hardware had been invalidated, (3) the drawings for level transmitter

supports inspected by QC had been changed since the QC inspections,

and (4) the supervisor of the group reviewing changes to drawings was

discouraging use of NCRs when inconsistencies were suspected to exist

between hardware installation and drawing configuration. The time

frame of this allegation was August 1986.

Based on information provided by the alleger and interviews with

CPSES personnel, it was determined that the above four examples were

related to the safety-related instrumentation and control (I&C)

systems. The above examples are concerns of the methodology TUGCo

o

e' , ' s . . .

29

used in controlling changes to design documents for.the installation

of Unit 1 and Unit 2 instrumentation and control systems, and the

in.pleme.itation of those design changes by field personnel; such as,

the PFGs, construction, and QC. The documents used to convey design

criteria and requirements for the construction and inspection of I&C

systems'were initial design drawings, revised drawings, and DCAs.

.

Each example was assessed by the NRC inspector as separate

concerns / issues and collectively for impact on the adequacy of the

I&C system design, construction and quality.

(1) Design changes were made without QC inspecting resulting work to

assure configuration agreement.

-Criterion X, " Inspection," of 10 CFR Part 50, Appendix B,

requires the inspection of activities affecting quality to

verify conformance with drawings, instructions, and procedures

for accomplishing the activity. This would include conformance

to the design drawings, revised drawings (which incorporate

outstanding design changes), and DCAs which are outstanding.

The NRC inspector reviewed the mechanisms used to implement

design changes in the field for both units. This review covered

the time period from December 1985 to December 1986, which

included the allegation time frame (August 1986). Each unit was

found to have a separate PFG and procedures for the development

of work packages that included design and changes to design

generated by TNE. The work packages identified requirements,

procedures, and instructions for construction, fabrication,

installation, and inspection activities. Unit I construction is

essentially complete and work activity performed in Unit I was

based on either hardware modification and maintenance or design

changes. Accordingly, TUGCo provided to Unit 1 PFG the

requirements for work package preparation as design changes,

maintenance, or modification activities occurred. TUGCo's

procedure-for delineating work package preparation requirements

to PFG was CP-CPM 1.2, " Construction Activities for Systems

and/or Areas Accepted and/or Controlled by TUGCo Plant

Operations." The procedure used by PFG to prepare and control

packages was based on requirements provided by CP-CPM 7.4,

Revision 0, " Unit 1 PFG Package Control," and CP-CPM-7.4A,

Revision 0, " Appendix A Package Preparation." Unit 2 is still

under construction and, as such, when new drawings, revisions,

or changes are issued that impact hardware, B&R reviewed the

design documents to develop the work package. Work package

development and preparation for Unit 2 was governed by

CP-CPM-7.1, Revision 2, " Package Flow Control" with

Appendices CP-CPM-7.1A through CP-CPM-7.1L.

During the review of PFG's function for the preparati9n of work

packages, the NRC found that TUGCo had identified instances in

which QC did not perform required inspections when drawings were

. . - . . .- .. . - . _ ...

%,9 .; .

30

revised. Both Unit 1 and Unit 2 were affected. Unit I

occurrences were in the area of electrical and I&C systems and

Unit 2 was in the mechanical discipline. Corrective Action

Report (CAR) 59, dated March 21, 1986, (Unit 1) and CAR 89,

dated' August 29, 1986, (Unit 2) address this problem. The

methods of identifying design changes on drawings (e.g., clouds,

revision triangles, and circles) were not implemented properly.

For example, Work Order C85-0003233 (PPF-140),

Drawing 2323-El-0049, Sheet 3, Revision CP-1, was initially

issued to govern a work activity related to Revision CP-1.

Prior to completion of the work, Revision CP-2 was issued.which

eliminated the revision clouds shown on CP-1, thus deleting the

identity of the area of the work activity.

As of this NRC inspection, CARS 59 and 89 have not been closed.

Based on reviews of procedural changes, documented responses to

the CARS, and interviews with CPSES personnel (TNE, PFG, and

QC-Corrective Action), the following actions were being taken to

disposition the issues identified in both CARS. When work is.in

progress, changes to design will be restricted to DCAs; drawings

will not be revised until the construction / inspection is

complete and DCA implementation has been verified.

The PFG is now required to notify TUGCo engineering when a DCA

has.been implemented. To assure timely drawing update, the

number of outstanding change documents (DCAs) have been limited

to five or the time limit of three months to incorporate

outstanding DCAs into the next drawing revision.

The Unit 1 and Unit 2 PFGs were consolidated into one PFG,

December 15, 1986. Procedures CP-CPM-7.1 and Appendices A-L

have been designated to govern PFG work package preparation and

control based on issued drawings and design changes identified

on DCAs. In addition, PFG will review in accordance with

CP-CPM 7.1J, " Review of Design Documents," all unincorporated

design changes issued prior to January 1987, to assure that such

design changes have been properly implemented and inspected.

(2) No mechanism was apparent in the PFG to notify QC that

previously accepted inspections were invalidated by design

changes.

The NRC inspector found that the PFG does not have a requirement

to notify QC when the PFG receives a revised drawing or design

change document, which when implemented would invalidate

previous inspections; however, the PFG prepares a work package

when a revised drawing or design change is made and QC

inspection requirements and hold points are identified. Then

during the performance of work prescribed by the work package,

QC involvement is triggered by the inspection requirements and

hold points delineated in the work package. Upon completion of

. - - - . - - - _

- - _. - __ - _ _ _ - . . _

- - -

- -

s e, < ,_ .-

31

craft and inspection activities, the PFG reviews the work

package'to assure completeness and that documentation conforms

to prescribed requirements. With the consolidation of Units 1

and 2 PFGs into one PFG, Revision 3 of CP-CPM 7.1 governs work

package review for completeness.

Even though PFG did not immediately notify QC that affected

inspections were invalidated upon receipt of a' revised drawing

or DCA, QC was required.to inspect modifications to old work

resulting from such changes. As a result of CARS 59 and 89, TNE

Procedure ECE-DC-21, Revision 5, dated October 31, 1986,

" Preparation and Review of Field Design Change," has been

revised to identify on the face of the DCAs when QC reinspection

is required. Futhermore, form ECE-DC-21.3, "QA/QC Notification

for Reinspection," is to be completed by TNE and transmitted to

the QC manager. The form notifies QC that design changes have

rendered the previously accepted installation or hardware as

potentially unacceptable. At the time of this NRC inspection,

QC was maintaining a log of such notifications and was

developing a mechanism to account for required QC involvement

resulting from changes.

(3) Level transmitter supports which QC accepted as being

satisfactory were contrary to the drawing.

In assessing this issue, the NRC inspector found that two NCRs

had been written to report incorrect installation of level

transmitter supports. The NCRs_were I-86-103982 and

I-86-103983; both dated September 11, 1986, subsequent to the

allegation. To date, these NCRs have not been closed. While

reviewing these NCRs and others related to Unit 1 and 2 I&C

nonconformances, the NRC inspector found two_ CARS that were

written against Units 1 and 2 I&C systems. CAR 88 (dated

August 7, 1986) identified problems with Unit 2 instrumentation

systems (within Unit I security boundaries) being installed and

inspected contrary to requirements of design drawings and site

approved construction and inspection procedures. The basis for

the CAR was 67 NCRs which resulted from walkdowns. CAR 105

(dated October 20,1986) reported discrepancies with the

installation of Unit 1 instrumentation; the cause being that

installation and inspection instructions did not contain

j adequate criteria. The CAR resulted when findings and

observations were trended from 23 NCRs associated with I&C

procedural inadequacies. Concurrent with CAR 105 was the

issuance of Stop Work Order 86-05; applicable to both units.

.

Stone & Webster (SWEC) engineering management has estimated

'

completion of action required to resolve both CARS as May 14,

1987.

'

(4) A Gibbs & Hill (G&H) group supervisor in charge of reviewing the

'

incorporation of outstanding design changes into revised

i

i

') ? ..

32

drawings was _ discouraging the writing of NCRs by revieviing

personnel. The supervisor was requesting that any suspected

inconsistencies between the physical installation and the design

drawing be identified to engineering (TNE) via 3 part memorandum

for further action.

Prior to November 7, 1986, G&H performed engineering services

for TUGCo under the direction of TNE. After November 7, SWEC

assumed the responsibility for engineering related to I&C-

systems for both units. Since.the G&H I&C design organization

was disbanded before the NRC inspections, G&H individuals

directly involved in this concern could not be contacted.

Accordingly, this concern was assessed from information provided

by the alleger and interviews of onsite personnel who were

cognizant of the G&H I&C engineering function.

-The subject G&H I&C group performed a design drawing checking

function in accordance with TNE-DC-7, Revision 18, " Preparation

and Review of Design Drawings." This function was to have

individuals not directly involved with the development or

revision of design drawings verify that the drawing was prepared

and reviewed in accordance with TNE-DC-7. In the case of

revised drawings, checkers / reviewers were to review the prepared

revised drawings against design change documents (DCAs) to

assure outstanding design changes had been adequately

incorporated. For this review, design checking experience was

required, not field knowledge of the installed hardware

(as-built condition); however, some'of these reviewers had

previous field experience. Suspected inconsistencies between

the as-built condition and the design drawings were recalled by

some individuals during these reviews. When this occurred,

these individuals were advised by their supervisor that their

responsibility was to verify outstanding design change

incorporation and not generate NCRs against suspected

inconsistencies. The supervisor suggested that suspected

inconsistencies be transmitted to engineering on a 3 part

memorandum for follow up.

During this inspection, the 3 part memorandums identified as

sent to engineering were not retrievable because of the

disbanding of G&H's onsite organization on November 7, 1986.

4

Accordingly, the NRC inspector could not determine if

engineering followed up on the suspected inconsistencies.

The scope of work to be accomplished by SWEC in determining the

design adequacy of the I&C systems is described in general in

the I&C Generic Issue Report. With the assumption by SWEC as

,

the I&C engineer of record, the work previously performed by G&H

design and engineering will no longer be used. From interviews

with SWEC personnel, the following actions have been completed

or are in process: qualification of all I&C equipment will be

,

E'

%

e [. u ,.

33

reverified, new design criteria will be established for I&C

supports, and a walKdown of all I&C systems to verify the

as-constructed constructed condition, which will then be

analyzed against the new criteria and equipment / installation

modifications made as required.

In summary, four concerns were cited as examples of the lack of

adequate I&C design control and implementation. Of the four

concerns, all were substantiated. Based on the documents

reviewed and the interviews by the NRC inspector, it was

apparent that TUGCo had also recognized these inadequacies and

had initiated or taken corrective actions.

Corrective action is being taken by TUGCo to revise methods of

conveying design changes to the craft and QC to assure the

performance of required' inspections. The concern that no

mechanism _is apparent in the PFG to notify QC when previous -

inspections for accepted hardware have been invalidated was

verified. No requirement existed to do so; however, PFG did

have a mechanism in place to notify QC of inspections to be

performed for work resulting from changes to design. As of

November 1, 1986, TNE has instituted a-procedure to directly

notify QC_of design changes which potentially render previous

inspections invalid.

- The concern that I&C-level transmitter supports were incorrectly

inspected by QC was substantiated. This condition was

identified in two NCRs generated by TUGCo. In addition, other

_ )

examples of QC accepting hardware not'in agreement with design

documents were found. These examples provided the basis for

Stop Work Order 86-05 which halted all installation of

safety-related instrumentation for Units 1 and 2. Actions are

t being taken to resolve the~ stop work order and the estimated

schedule for completion of required actions is May 1987.

! The concern that a G&H supervisor for the group reviewing

changes to I&C drawings and discouraging the use of NCRs when

inconsisten'cies were suspected to exist between hardware

installation and drawing configuration was apparently accurate.

The G&H design review group has been eliminated and the NRC

inspector was not able to interview all individuals directly

l

involved in the concern. From information obtained, the G&H

design review group was not verifying the conformance_of

as-built installation for agreement to drawing configuration,

j but performing a design check to verify the incorporation of

l- outstanding design changes by draftsmen into revised drawings.

i The supervisor apparently viewed these inconsistencies as

suspected problems and not factually known, thus his decision to

document them on other than NCRs. In any event, SWEC has become

the engineer of record in this area and has initiated walkdowns

j of all I&C installations to determine the as-constructed

l

c

  • or,

34'

condition. The data obtained from these walkdowns will be

evaluated against new design criteria and modifications to the

as-constructed condition will be made as necessary.

In conclusion, the expressed concerns were recognized by the

applicant as problem areas for which appropriate actions to

correct were either taken or initiated. Based on NRC inspection

of these actions, they appear to have appropriately defined the

problems and their corrective and preventive actions have been

proper. No NRC violations or deviations were identified and no

further action concerning this allegation is planned. A copy of.

this inspection report will be provided to the alleger,

c. 4-86-A-107: Unqualified Walkdown Verification of Conduit

A concern was raised by an anonymous caller that an increasing number

of B&R craft are being used by Ebasco to conduct verification

walkdown inspections of Class 1 (safety-related) conduit. The

alleger, who supplied the identity of one craft, went on to state

that these craft were probably involved in the installation of the

conduit. The alleger inquired as to whether there was a regulation

against an installer conducting verifications.

Based on the identity of the craft supplied by the alleger and by

reviewing Ebasco organization charts, the NRC inspector deterinined

that the allegation was pertinent to the Ebasco Unit 1/ Unit 2

walkdown group. This particular group is responsible for performing

as-built walkdown inspections of Unit 2 safety-related conduits and

supports which are installed in Unit 1 and common areas. With this

as-built walkdown information, the Ebasco design verification

. group (DVG) is to seismically qualify the conduit runs.

r .During August 1986, there were 16 craft people involved with this

Ebasco walkdown group and were identified on the organization chart

as B&R craft and as a separate entity from the individual walkdown

engineers. The NRC inspector interviewed the Ebasco site field

supervisor and found that these craft people were initially brought

,

into the group to assist the Ebasco field walkdown engineers in

l taking measurements, locating and identifying conduit runs and

i supports, and securing support services required to perform the

walkdown. Eventually these craft people were allowed to go out on

their own and generate as-built isometrics of the conduit runs and

redline the conduit support drawings,

i Since no isometric drawings were initially made up for these

conduits, Ebasco generated the as-built isometrics to allow DVG to

get an accurate depiction of the conduit run when seismically

qualifying it and to remain consistent with other Unit 2 conduit

l walkdown programs. The purpose of redlining support drawings was

twofold: (1) to obtain as-built information of the support for DVG

analysis for modified typical and individually engineered supports;

L

r

., c ,

35

-and (2) to' reverify that supports, initially identified as typical

supports by B&R QC during installation, are indeed typical supports.

For typical supports, DVG used generic support load capacities listed

in the 2323-S2-0910 package, which is the design and construction

guideline for conduit routing and support installation in Unit 2.

It was determined that the allegation, as stated, was true. Ebasco

does or has utilized upwards of 16 craft people to perform

verification walkdown inspections. Subsequent NRC inspection

revealed, however, that these craft people received documented

training identical to that received by other Ebasco walkdown

engineers. This training included formal classroom training on the

appropriate walkdown Procedure TNE-FVM-CS-014, "As-built Field

Verification Method," and a B&R training session, including passing a

test, on taking measurements. Ebasco was also required to, by

procedure TNE-FVM-CS-014, independently field verify all isometric

information. Furthermore, it was an Ebasco guideline to field verify

.

the redlined support drawings. Ebasco did, however, stop the

independent field checking of the redlined typical support dr?. wings

by internal memorandum on July 24, 1986. With the issuance of the

memorandum, all redlined typical support drawings which had not been

checked as of that date, were not to be checked and the dates

backdated to the memorandum issuance date. The reasoning behind this

was that the information obtained during the redline process was not

utilized by DVG during their analysis of the conduit. After

redlining a typical support drawing, craft reconfirmed the initial QC

inspection that the support was indeed a typical support. For

typical supports, DVG would review the redline information for

completeness and use the load capacity specified in the 2323-S2-910

'

package. If a typical support should fail the DVG analysis, DVG

would look at the information noted on the redlined support drawing

l only to come up with a-possible fix. Before a final fix was

instituted, the typical support was reinspected and the reinspect _fon

independently field verified.

I At this time, the NRC inspector determined that utilizing craft for

l these walkdown inspections was within procedural guidelines. The NRC

l inspector picked 12 packages walked down by the craft and by tracing

>

documentation back to the initial construction operation traveler,

l determined that in all cases the same craft person was not involved

l in the installation. The possibility, though, does exist that the

same craft person could be involved in installation and walk down of

the same conduit; however, QC inspection and independent field

,

verification of the conduit isometric provide sufficient independence

to the total program.

'

To further assess adequacy of the Ebasco walkdown program and

performance of the craft walkdown inspection, the NRC inspector

inspected six conduit runs and applicable supports which the craft

had walked down. The NRC inspection included all the attributes

necessary to generate an isometric and to redline support drawings

-

%s-- ,

36

per the applicable walkdown Procedure TNE-FVM-CS-014, "As-built Field

Verification Method." No violations or deviations were noted.

In summary, the NRC inspector substantiated the allegation, in that

craft were being utilized by Ebasco:for walkdown inspections and the

potential does exist where the craft would walk down the same conduit

run or support that he had installed. There are, however, no

procedural or regulatory guidelines prohibiting this when there is

also sufficient independent verification involved. This independent

verification is in the form of QC inspection prior to the walkdown

inspection and independent Ebasco field verification of all isometric

and support red lining except for typical supports. In addition, NRC

inspection of six conduit runs which had been "walkdown" inspected by

craft revealed no procedural non-compliance.

6. ERC Collective Evaluation Program

The purpose of this NRC inspection was to determine if ERC has established

and implemented measures to perform collective evaluations of results

obtained from programmatic and construction related ISAPs. In accordance

with the CPRT Program Plan (Section VI), each completed ISAP will produce

a results report. The program plan requires ISAP and DSAP results reports

to be collectively evaluated (i.e., by discipline, population) to

determine if identified deficiencies are isolated occurrences or generic -

weaknesses. These evaluations are to be of sufficient scope to provide

reasonable assurance that there are no remaining undetected safety

significant hardware deficiencies. To implement the collective evaluation

requirements, ERC has developed Procedure CPP-014, " Collective Evaluation

of the Construction QA/QC Program and of The Quality of Construction."

The current version is dated October 30, 1986 (Revision 3).

CPP-014 describes ERC's methodology for collectively evaluating the

results of 39 CPRT ISAPs (excluding testing) and related input from other

applicable investigatory programs. Two separate evaluations are required

to be performed. One evaluation is to assess the adequacy of the

Construction QA/QC Program (programmatic); the other is to determine the

Quality of Construction Program (hardware) for the mechanical, electrical,

civil and structural disciplines. Each evaluation is to summarize

,

'

deficiencies, adverse trends, associated root cause(s), and generic

implications; corrective action to resolve deficiencies and adverse

j trends; and recommendations to preclude recurrence during the remaining

'

work on Unit 2. A summary report will integrate the results of the two

1

collective evaluation reports setting forth CPRT conclusions.

At the time of the NRC inspection, 10 of 39 ISAP results reports were

completed, approved and issued, and therefore, the collective evaluation

, process to evaluate programmatic and hardware results reports has not yet

! been fully implemented. In reviewing CPP-014, it appears to lack specific

detail for collective evaluation performance. The collective

evaluation (CE) personnel stated that the collective evaluation leader in

the programmatic and hardware disciplines would develop controlled working

F'

  • . ** .

37

instructions for given work activities. These work instructions were in

the process of being developed and would provide uniform methodology for

the performance and the documentation of the respective collective

evaluations.

During this inspection period, the NRC inspector was provided the initial

version of the. programmatic and hardware work instructions, dated

November 13 and 18, 1986. These instructions have been approved by the

Collective Evaluation Group Supervisor. Based on NRC review of these work

instructions and interviews with the involved personnel, the collective

evaluation process is described as follows:

a. QA/QC Program Collective Evaluation (programmatic):

(1) CPRT source documents will be used to establish a data base that

includes programmatic deviations, deficiencies, findings and

adverse trends. Source documents generated by activities

described in the CPRT Plan which specifically identify QA/QC

program deviations or address QA/QC problems during the

reinspection / documentation review are:

(a) ISAP results reports.

(b) ISAP VII.c population reports (Appendices).

(c) Program Deviation Reports (PDRs).

(d) Design Appraisal Program (DAP) Memoranda.

(e) Electrical Review Group Memoranda.

(f) Hardware Collective Evaluation Group Problem Forms.

(g) Collective Evaluation Matrix Coordinator Memoranda.

(2) Deviations, deficiencies, adverse trends including associated

root causes, generic implications and corrective actions are

documented on a QA/QC Program Work Sheet.

(3) PDRs are prepared in accordance with CPP-017, Revision 2, for

deviations and findings which are identified during the

collective evaluation process.

(4) Programmatic deviations, deficiencies, and findings will be

classified according to related 10 CFR 50, Appendix B, criteria

and a cause established for trending of programmatic items.

(5) Program items will be reviewed to identify any adverse trends

not previously identified in programmatic results reports in

accordance with CPP-11, Revision 2, " Evaluations of Adverse

Trend Analysis, Construction Deficiencies, and QA/QC Program

Deficiencies." If any new adverse trends are identified, causes

and generic implications will be developed using PAG-04,

Revision 0, " Guide on Root Cause and Generic Implication." As

required, corrective action recommendations will be developed

which may include performance of additional inspections or

document reviews.

c

  • , ..

,

38

(6) Based on steps (1) through (5), a collective evaluation report

will be generated to summarize programmatic findings,

deficiencies, adverse trends and associated root causes and

generic implications. Corrective action to resolve deficiencies

and adverse trends will be identified with recommendations to

preclude recurrence during the remaining work on Unit 2.

Finally, the adequacy of the CPSES QA/QC Program will be

summarized.

Historically, the programmatic evaluation section of the collective

evaluation group was organized in late September 1986 with a staff of

two; by November 1986 staffing was four. Resources for staffing are

CPRT personnel who have completed their related ISAP assignment and

are ready for reassignment. During October and November 1986,

primary work activity of this group was participation in the CPRT

Results Report and Working File Review (RRR) committee meetings to

become acquainted with the subject matter of completed ISAPs, result

reports, and population reports. Secondary work involved development

of working instructions and the review of published and draft results

reports and population reports for preliminary identification of

potential programmatic items.

b. Quality of Construction Collective Evaluation (hardware):

(1) A data base of hardware deviations, deficiencies, and adverse

trends will be developed using applicable CPRT source documents

identified in a.(1) above and data extracted from DRs,

implemented hardware results reports, and ISAP VII.c population

reports. Other related source documents will be reviewed to

identify hardware deficiencies and adverse trends including

associated root causes, generic implications, and corrective

actions. Data from each deviation will be classified by

population, component, work process, and discrepancy type.

Sorting by work process, the data will be reviewed to identify

trends and evaluate for adverse conditions.

(2) After the data base is established, it will be searched for

adverse trends resulting from deviation trending, and for

adverse trends not previously identified in the hardware result

reports or ISAP VII.c population reports. These new trends will

be processed in accordance with CPP-011, Revision 2. Root cause

and generic implications will be developed using PAG-04,

Revision 0.

7

(3) Hardware deficiencies, adverse trends, and associated root

causes with generic implications will be correlated and \

summarized in a collective evaluation report entitled CPSES

Quality of Construction. The report will identify required

'

actions to resolve deficiencies and adverse trends with

recommendations to preclude recurrence in Unit 2 remaining work.

L ,

r

  • .-

,,

39

The adequacy of construction will be summarized including

recommendations for improvements.

The hardware collective evaluation section was organized in late

September 1986. By October 15, 1986, staffing was at five persons

obtained from organizations which have completed specific ISAP

assignments. As with the programmatic section, staffing will be

increased commensurate to the level of work. During October and

November 1986, the hardware section primarily participated in RRR

committee meetings to obtain familiarity with the subject matter of

the ISAP VII.c results report and its associated population reports.

Another major effort was the establishment of the deviation sorting

indexes and data base search methods. Development of the hardware

collective evaluation work instructions included trial testing,

c. Summary Report:

Both the programmatic and hardware collective evaluation reports will

be integrated into one summary report as input into the CPRT overall

Collective Significance Evaluation Report. This report in turn will

summarize the results of all CPRT ISAP and DSAP activities and any

special investigative work not covered by the ISAPs and DSAPs. At

this time, ERC has not finalized the methodology for integrating the

programmatic and hardware collective evaluation into the summary

report.

In summary, the NRC inspector determined that ERC has established and

documented a collective evaluation program to summarize the results of

ISAP activities. The program has not been fully implemented since only 10

out of 39 result reports have been approved and issued. To date, the

collective evaluation group has accomplished preliminary activities; such

as, organizing and staffing hardware and programmatic collective

evaluation sections; participation in RRR committees to become acquainted

with ISAP results report subject matter; and the development of

methodology for the collection and analysis of hardware / programmatic

deviation and deficiency data.

Procedure CPP-014, in general terms, outlines the overall collective

evaluation process. More specific direction for conduct of evaluations is

controlled by documented working instruct. ions. The final stages of the

program for integrating hardware and programmatic collective evaluations

into one summary report have not been formalized. Since the collective

evaluation program is only partially implemented, the NRC will inspect

further program implementation at a later date.

7. Exit Interview

Exit interviews were conducted December 9, 1986, and January 13, 1987,

with the applicant's representatives identified in paragraph 1 of this

appendix. During these interviews, the NRC inspectors summarized the

\ i

e

  • . 2. ,

40

scope and findings of the inspection. The applicant acknowledged the

findings.

l

!

L i