Forwards SER on Util 801023,810619,820624 & 1222 & 830120 & 0422 Submittals in Response to Items 2b & 3 of IE Bulletin 80-11, Masonry Wall Design. Operational Level of 0.15g OBE May Be Reinstated,Per Review & 860514 Meeting
ML20211A112
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 05/27/1986
From: Varga S
Office of Nuclear Reactor Regulation
To: Withers B
PORTLAND GENERAL ELECTRIC CO.
Shared Package
ML20211A118 List:
References
IEB-80-11, TAC-12369, NUDOCS 8606110060
Download: ML20211A112 (3)


Text

.

May 27, 1986 Docket No. 50-344 D}6TRIBUTION focketFile NRC PDR L PDR Gray File PAD-3 H. Thompson Mr. Bart D. Withers OELD E. Jordan Vice President Nuclear J. Partlow B. Grimes Portland General Electric Company ACRS 10 T. Chan 121 S.W. Salmon Street C. Vogan Portland, Oregon 97204

Dear Mr. Withers:

SUBJECT:

TROJAN NUCLEAR PLANT - MASONRY WALL DESIGN; IE BULLETIN 80-11 We have completed our review of Items 2b and 3 of your October 23, 1980, June 19, 1981, June 24 and December 22, 1982, and January 20 and April 22, 1983 submittals in response to IE Bulletin 80-11, Masonry Wall Design.

Based on our review, we conclude that Items 2b and 3 of IE Bulletin 80-11 have been fully implemented at Trojan, and that there is reasonable assurance that the safety-related masonry walls will withstand the specified design load conditions, including the original OBE design level of 0.15g. Our Safety Evaluation is enclosed.

In a meeting with your staff on May 14, 1986, it was confirmed that the nonconforming and deficient conditions which were previously identified have been completed, and that procedures are currently in place to resolve future identification of potential nonconforming conditions. As such, we conclude that PGE's December 10, 1980 commitment to maintain the 0.08g OBE operational condition until the completion of the necessary wall improvements, following the expiration of License Condition 2.c.(10), has been fulfilled, and that the operational level of 0.15g may be reinstated.

Sincerely,

/s/SVarga Steven A. Varga, Director PWR Project Directorate No. 3 Division of PWR Licensing-A, NRR

Enclosure:

As stated cc w/ enclosure:

See next page

  • SEE PREVIOUS P_ AGE FOR CONCURRJNCE OFC : PAD #3 *
PAD #3
D/ PAD V :

, 4. -

8606110060 860527 NAME :CVogan

TChan;

_____.:....{DR ADOCK 0500 4

DATE :5/21/86

5/47 /86

/86 0FFICIAL RECORD COPY

Docket No. 50-344 DISTRIBUTION Docket File NRC PDR L PDR Gray File PAD-3 H. Thompson Mr. Bart D. Withers OELD E. Jordan Vice President Nuclear J. Partlow B. Grimes Portland General Electric Company ACRS 10 T. Chan 121 S.W. Salmon Street C. Vogan Portland, Oregon 97204

Dear Mr. Withers:

SUBJECT:

TROJAN NUCLEAR PLANT - MASONRY WALL DESIGN; IE BULLETIN 80-11 We have completed our review of Items 2b and 3 of your October 23, 1980, June 19,1981, June 24 and December 22, 1982, and January 20 and April 22, 1983 submittals in response to IE Bulletin 80-11, Masonry Wall Design.

Based on our review, we conclude that Items 2b and 3 of IE Bulletin 80-11 have been fully implemented at Trojan, and that there is reasonable assurance that the safety-related masonry walls will withstand the specified design load conditions, including the original OBE design level of 0.15g. Our Safety Evaluation is enclosed.

In a meeting with your staff on May 14, 1986, it was confirmed that the nonconforming and deficient conditions which were previously identified have been completed, and that procedures are currently in place to resolve future identification of potential nonconforming conditions. As such, we conclude that PGE's December 10, 1980 commitment to maintain the 0.08g OBE operational condition until the completion of the necessary wall improvements, following the expiration of License Condition 2.c.(10), has been fulfilled.

Steven A. Varga, Director PWR Project Directorate No. 3 Division of PWR Licensing-A, NRR

Enclosure:

As stated cc w/ enclosure:

See next page OFC : PAD #3

PAD #3
D/ PAD #3 i

NAME :CVogan

CThan;ps
SVarga

..___:7_\\/86 DATE :3/.

4/ /86
4/ /86 4

0FFICIAL RECORD COPY l

t

S Mr. Bart D. Withers Portland General Eletric Company Trojan Nuclear Plant cc:

Senior Resident Inspector U.S. Nuclear Regulatory Commission i

Trojan Nuclear Plant Post Office Box 0 Rainier, Oregon 97048 Robert M. Hunt, Chairman Board of County Commissioners Columbia County St. Helens, Oregon 97501 William T. Dixon Oregon Department of Energy Labor and Industries Building Room 111 Salem, Oregon 97310 Regional Administrator, Region V U.S. Nuclear Regulatory Commission Office of Executive Director for Operations 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 l