Letter Sequence Other |
|---|
|
Results
Other: 05000344/LER-1979-013, Forwards Confirmatory Info to NRC 791229 Question 1 Re LER 79-13 Concerning Stresses in Walls Due to Thermal Gradients. Masonry Walls Subj to Thermal Gradient Across Thickness Will Undergo Deformation.Certificate of Svc Encl, 05000344/LER-1979-015-01, /01T-0:on 791019,discovered That Piping Restraint on Concrete Block Wall Might Result in Localized Overstress Condition & Degradation of Support Function Under Design Loads.Caused by Inadequate Consideration of Piping Design, 05000344/LER-1980-007, Forwards Suppl 1 to LER 80-007/01T-0,providing Description of Engineering Review,Reportable Noncomformances & Related Evaluation Results, 05000344/LER-1980-007-01, /01T-0:on 800516,masonry Wall in Auxiliary Bldg Was Discovered Not Connected to Interfacing Structures at Top.Caused by Misinterpretation of Design Drawings.Positive Connection Being Made W/Grouted Reinforcing Steel, 05000344/LER-1983-001, Forwards LER 83-001/01T-0.Detailed Event Analysis Encl, 05000344/LER-1983-001-01, /01T-0:on 830106,field Insps & Review of Const Records Revealed as-built Conditions of knock-out Panel & wall-to-roof Connection Different than Those Considered in Previous Analyses for Three Masonry Walls.Mods Underway, ML17208A791, ML19207B551, ML19208A864, ML19209B063, ML19210C870, ML19210D585, ML19211A367, ML19211A374, ML19224D636, ML19225C762, ML19248C628, ML19249B712, ML19250C487, ML19253C727, ML19256B483, ML19256E423, ML19257A197, ML19257A200, ML19257A202, ML19257A780, ML19257A782, ML19257B266, ML19260B505, ML19262A945, ML19262A949, ML19268C263, ML19269D190, ML19274F793, ML19290C026, ML19290C028, ML19294B330, ML19296D746, ML19296D752, ML19296D933, ML19305B776, ML19308A352, ML19309C368, ML19309C371, ML19309G033, ML19309G034, ML19309G035, ML19318D060, ML19320B202, ML19320D055... further results
|
MONTHYEARML19268C2631966-10-31031 October 1966 Compressive & Transverse Strength Tests of 8-Inch Brick Walls. Addl Info Re Masonry Walls & Certificate of Svc Encl Project stage: Other ML19269D1901979-02-28028 February 1979 Forwards Addl Info Provided by Bechtel Re Proposed Control Bldg Mod:Suppl Info on Shear Wall Specimen Test Program & Addl Info Re Lateral Stiffnesses & Response Spectra Determination.Plans Submittal of Design Mod Rept in March Project stage: Other ML19308A3521979-06-20020 June 1979 IE Bulletin 79-02,Revision 1,Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts Project stage: Other ML19256B4831979-06-21021 June 1979 Forwards IE Bulletin 79-02,Revision 1, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts. Action Required Project stage: Other ML19248C6281979-06-29029 June 1979 Forwards Responses to 14 of 50 Questions Submitted in NRC .Will Submit Remaining Responses by 790706. Certificate of Svc Encl Project stage: Other ML19224D6361979-07-0202 July 1979 Forwards IE Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Sys. Action Required Project stage: Other ML19208A8641979-07-13013 July 1979 Forwards Response to IE Bulletin 79-02,Revision 1,re Seismic Category I Piping Sys Support Base Plates Which Use Concrete Expansion Bolts Project stage: Other ML19274F7931979-07-18018 July 1979 Forwards IE Bulletin 79-14,Revision 1, Seismic Analysis for As-Built Safety-Related Piping Sys Project stage: Other ML19225C7621979-07-19019 July 1979 Forwards Corrected Copy of IE Bulletin 79-14,Revision 1, Seismic Analysis for As-Built Safety-Related Piping Sys Project stage: Other ML19207B5511979-08-15015 August 1979 Forwards IE Bulletin 79-14,Suppl 1, Seismic Analysis for As-Built Safety-Related Piping Sys. Action Required Project stage: Other ML19249B7121979-08-20020 August 1979 Forwards IE Bulletin 79-02,Revision 1,Suppl 1,Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts. Action Required Project stage: Other ML19209B0631979-09-0505 September 1979 Forwards Responses to NRC 790817 Questions,Transmitted in NRC to Aslb.Includes Info Re Computer Codes for Evaluation of Mods to Control,Auxiliary,Fuel Bldg Complex & Vertical Natural Frequencies Project stage: Other ML19256E4231979-10-22022 October 1979 Confirms NRC 791022 Telcon W/Wj Lindblad Re Facility Steam Generator Tube Defects & Concrete Block wall-pipe Hanger Structural Problems.Discusses Action to Be Taken by Licensee Project stage: Other ML19210C8701979-10-22022 October 1979 Submits Followup to 791019 Rept of Inadequate Pipe Restraint on Spent Fuel Pool Cooling Sys.Plant Presently in Cold Shutdown.Will Complete Corrective Action Before Mode Change Project stage: Other 05000344/LER-1979-015-01, /01T-0:on 791019,discovered That Piping Restraint on Concrete Block Wall Might Result in Localized Overstress Condition & Degradation of Support Function Under Design Loads.Caused by Inadequate Consideration of Piping Design1979-11-0404 November 1979 /01T-0:on 791019,discovered That Piping Restraint on Concrete Block Wall Might Result in Localized Overstress Condition & Degradation of Support Function Under Design Loads.Caused by Inadequate Consideration of Piping Designs Project stage: Other ML19250C4871979-11-0808 November 1979 Forwards IE Bulletin 79-02,Revision 2, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts. Action Required Project stage: Other ML19260B5051979-11-16016 November 1979 Forwards IE Info Notice 79-28, Overloading of Structural Elements Due to Pipe Support Loads. No Response Required Project stage: Other ML19296D9331979-11-21021 November 1979 Forwards Response to IE Bulletin 79-02,Revision 1,Supp 1. Repairs Completed on Five of 11 Pipe Supports W/Anchor Bolt Safety Factors Less than Two, & Eight of 69 Supports W/Factors Less than Five.Revision 2 Response Forthcoming Project stage: Other ML19210D5851979-11-21021 November 1979 Forwards Suppl 1 to RO 79-015 Re Sample Calculations & Tension & Shear Transfer Project stage: Other ML19262A9491979-11-24024 November 1979 Evaluation of Tests of Tensile Bond Strength of Concrete Block-to-Fill in Trojan Nuclear Power Plant Near Portland, Or. Supporting Documentation Encl Project stage: Other ML19253C7271979-11-30030 November 1979 Modifies ASLB Partial Initial Decision Permitting Interim Operation of Facility.Operation Will Not Resume Pending Further Order.Nrc Shall Inform ASLB of Unresolved Items Re Seismic Issues Project stage: Other ML19262A9451979-11-30030 November 1979 Rept on Testing of Composite Masonry Walls Project stage: Other ML19253C7691979-12-0101 December 1979 Notification of 791205-06 Meeting W/Util in Bethesda,Md to Discuss LER 79-15 Re Masonry Block Wall & Support Reaction Problem Project stage: Meeting ML19211C2251979-12-0404 December 1979 Ack Receipt of 791130 Order Re Interim Operation of Plant. Staff Currently Assembling Info Bearing on Seismic & Other Issues in Proceeding & Will Supplement This Info to ASLB on 791207 Project stage: Request ML19211A3741979-12-0707 December 1979 Affidavit by President of Util Explaining Unique Circumstances Facing Region & Affecting Public Need Project stage: Other ML19211A3671979-12-0808 December 1979 Forwards Affidavits of Rh Short & Dj Broehl,President & Vice President of Util,Respectively,In Response to ASLB 791130 Order.Certificate of Svc Encl Project stage: Other ML19294B3301979-12-0808 December 1979 Forwards Response to IE Bulletin 79-02,Revision 2,Items 5, 6 & 7 Project stage: Other ML20125C1751979-12-19019 December 1979 Summary of 791205-06 Meeting W/Util & Bechtel Re Discussion of LER 79-15 Wherein Certain Problems W/Masonry Block Walls & Support Reactions of Equipment/Piping Attached Thereto Were Identified Project stage: Meeting ML19290C0281979-12-20020 December 1979 Supplements Re Concrete Block Wall/Pipe Hanger Structural Problems,Subj of 791220 Discussions.States NRC Understanding That Util Will Resolve re-evaluations Per LER 79-15 Project stage: Other ML19290C0261979-12-21021 December 1979 Joint Affidavit Re Review & Evaluation of as-built Control Bldg Interim Operation.Block Wall Reaction Force Problem Must Be Satisfactorily Resolved Before Resumption of Operation.Problem Chronology Encl Project stage: Other ML19257A1971979-12-27027 December 1979 Forwards Class III Fee Re 791224 License Change Application 56 Project stage: Other ML19257A2021979-12-27027 December 1979 Forwards Util to NRC Region 5 Summarizing All Mods to Pipe Supports & Restraints.W/O Encl.Certificate of Svc Encl Project stage: Other ML19257A2001979-12-27027 December 1979 Submits Followup to RO-79-15.All Analyses & Evaluations Completed.Summary of Corrective Actions on Pipe Supports & Restraints Provided.Power Operation Will Not Resume Until Further ASLB Order Project stage: Other ML19257A7801979-12-31031 December 1979 Advises That Schedule for Implementation & Documentation of Confirmatory Testing Program Will Be Submitted Following NRC Review.Certificate of Svc Encl Project stage: Other ML19257A7821979-12-31031 December 1979 Advises of Resolution of Problems Re Steam Generators & single-wythe,mortared double-wythe & Composite Block/ Concrete Walls,As Described in LER 79-15.NRC Questions & Util Responses Encl Project stage: Other 05000344/LER-1979-015, Responds to NRC Request for Addl Info Re LER 79-15.Forwards Info Re Confirmatory Testing Program on Model double-block Masonry & Composite Walls.Schedule Will Be Established for Completion & Documentation of Results & Conclusio1979-12-31031 December 1979 Responds to NRC Request for Addl Info Re LER 79-15.Forwards Info Re Confirmatory Testing Program on Model double-block Masonry & Composite Walls.Schedule Will Be Established for Completion & Documentation of Results & Conclusions Project stage: Request ML19257B2661980-01-0909 January 1980 Forwards NRC Sample Calculation Comparing Use of Transverse Shear Force Directly from Stardyne Output W/Calculations from Displacement & Rotation Output from Same Analysis. Certificate of Svc Encl Project stage: Other 05000344/LER-1979-013, Forwards Confirmatory Info to NRC 791229 Question 1 Re LER 79-13 Concerning Stresses in Walls Due to Thermal Gradients. Masonry Walls Subj to Thermal Gradient Across Thickness Will Undergo Deformation.Certificate of Svc Encl1980-01-18018 January 1980 Forwards Confirmatory Info to NRC 791229 Question 1 Re LER 79-13 Concerning Stresses in Walls Due to Thermal Gradients. Masonry Walls Subj to Thermal Gradient Across Thickness Will Undergo Deformation.Certificate of Svc Encl Project stage: Other ML19296D7521980-02-13013 February 1980 Rept on Design Criteria for Masonry Walls Project stage: Other ML19296D7461980-02-13013 February 1980 Forwards Rept on Design Criteria for Masonry Walls Project stage: Other ML19296D7381980-02-22022 February 1980 Forwards Safety Evaluation Re Concrete Masonry Wall Design Criteria for Transverse Loadings & Rept on Design Criteria for Masonry Walls. Discussion Will Take Place During Wk of 800225 Project stage: Approval ML19296D7431980-02-22022 February 1980 Safety Evaluation Re Concrete Masonry Wall Design Criteria for Transverse Loadings Project stage: Approval ML19344D2271980-03-0505 March 1980 Informs That Testing & Grouting Program Completed 800213. Estimates 86% Fill in Collar Joint.No Wall Areas Contain Continuous Collar Joint Voids Project stage: Other ML19344D2681980-03-0606 March 1980 Forwards Info Re Values for Ultimate Compressive Strength of Masonry Assemblies.No Violation of Tech Specs Occurred as Result of Values Used in Accordance W/Uniform Bldg Code Project stage: Other ML19305B7761980-03-15015 March 1980 Forwards Comments Re App B of J Colville 800213 Rept Concerning Design Criteria of Plant Masonry Walls.Analysis Indicates That Wall 46 Has Capacity to Resist Out of Plane Loads During SSE Event.Certificate of Svc Encl Project stage: Other ML19305C3161980-03-17017 March 1980 Forwards Response to NRC Questions Presented at 800307 Meeting Re Structural Considerations for Proposed Mods to Control Bldg.Overall Modified Complex Has Available Capacity to Satisfy 1.4 Load Factor OBE Criteria Project stage: Meeting ML19309C3711980-04-0101 April 1980 Addendum 1 to Rept on Testing of Composite Masonry Walls Project stage: Other ML19309C3681980-04-0101 April 1980 Forwards Mar 1980 Addendum 1 to Rept on Testing of Composite Masonry Walls,Nov 1979. Test Results Described in Addendum Indicate That 40 Psi Is Appropriate Principle Tensile Stress Value at block-core Interface of Wall Project stage: Other ML19309G0341980-04-0808 April 1980 Response to Comments on App B of Coleville Rept of 800213 on Trojan Masonry Walls Project stage: Other ML19309G0351980-04-0808 April 1980 Comments on Review by Professor B Bresler of Evaluation of Tensile Bond & Shear Bond of Masonry by Means of Centrifugal Force,By M Hatzinikolas,J Longworth & J Warwaruk,Alberta Masonry Institute,Undated (1978-1979) Project stage: Other 1979-06-20
[Table View] |
Text
. -.
=
TROJAN NUCLEAR PLANT ADDENDUM 1, MARCH 1980 TO REPORT ON TESTING OF COMPOSITE MASONRY WALLS In accordance with the request of the NRC staff, twelve additional tests of the tension espacity at the interf ace between masonry block and concrete core of composite walls were performed during the period between January 31 and February 5, 1980. These tests were conducted to supplement the data obtained in the thirteen initial tests, reported in November 1979, and further quantify P
the ultimate tensile bond stress between the concrete masonry units and the concrete core in representative composite walls at the Trojan Plant.
Locations
]
for the supplemental tests were preselected from architectural drawings to represent a random sample of wall thicknesses, wall locations, and building These locations were then field verified for such considerations elevations.
as accessibility, shielding requirements, structural conditions, and interferences.
The design properties for the supplemental test composite walls were the same I
as those for the initial test composite walls.
4 As described below, the tests were performed in accordance with the initial test procedure with only minor variations therefrom. Two tests were performed at each of six locations. The first test at each location was performed with the load applied to the block side of the interface, after which a second 3
test was performed by pulling the concrete core from the block at the back side of the composite wall. To prepare the test sample, a 1-in. diameter wedge anchor was pre-set at the centerline of the test sample, then a-12-in.
diameter (11-1/2 in.1D) core was drilled 'to approximately 1 in. 'beyond the interf ace between' the masonry and core concrete. The test setup utilized a-jacking frame which was bolted to the wall and a hand pressurized hydraulic 8064080 h Ci A-1
1 ram to provide the specified loads to a 1-in. diameter rod connected to the 1-in. diameter wedge anchor. The preselected test loads were cycled five times each at intervals ranging between 2500 lbs and 5000 lbs up through 15,000 lbs, at which point if no failure had occurred, the hydraulic ram pressure was increased up to a value initiating a failure in the specimen.
e Some variations to the written test procedure were approved by the Engineer-In-Charge. These variations included reduction of the load cycle time from 60 seconds to 15 seconds, deletion of deflection measurements after the first phase of tests, and the use of a single pressure gauge for some portions of the tests.
1 Only four of the 12 test specimens failed at the interface between the core concrete and mesonry block. Seven of the 12 test specimens experienced failure primarily in the block and at the cell fill to block interface. One test specimen failed due to splitting at the anchor bolt. Of the four specimens that failed at the block-core interface, a visual inspection of the-failure surfaces indicated that, in general, no obvious areas of separation at the block-core interface were evident, except at mortar joints where the block-core interface was interrupted. All failures were sudden, clear-break type failures. No measurable deflection prior to the break was detected for the five tests performed with dial gauge instrumentation.
The ultimate load 4
and general failure mode of each of the tests are summarized in Table 1.
Due to difficulties involved in orienting the hand-held impact drill-used for the anchor bolts, there was some eccentricity between the center of applied load and the center of resistance. This was evident in the majority of the tests.
This eccentricity was measured where possible and included on the data sheets.
A-2
Calculated tension stresses at failure for each of the tests are presented.in Table 2.
The average load at failure for the four samples that' failed at the block-core interface was 11,800 lbs and the average failure load for all tests was 11,600 lbs. The corresponding nominal tensile stresses on the interface at failure are approximately 114 psi and 112 psi, respectively.
However, if the eccentricity is included in terms of bending stress, these average maximum stresses become approximately 139 psi for the block-core failures and 137 psi for all sample failures.
The lowest block-core failure occurred at 7400 lbs (Test S-7A), and the highest failed at 19,800 lbs (Test S-1B).
This lower test may have actually been cycled ten times at 5000 lbs and may possibly have reached 10,000 lbs during an initial test which was considered invalid due to equipment malfunc-tion.
An additional contributing factor to this lower failure load was the eccentricity of the anchor bolt with respect to the jacking rod.
When the data from the five initial and four supplemental tests, which were considered to be representative of block-core tensile bond capacity, are lumped together, the average nominal tensile bond capacity, excluding bending effects, becomes 158 psi. This average val'se from the tests is a factor of 3.95 times the value of 40 psi selected as a design limit. Therefore, based on our evaluation of these supplemental test data together with the initial test data, the value of 40 psi is still considered to be an appropriate t
principal tensile stress value at the block-core interface for use in analysis of composite walls for factored load conditions.
A-3
TABLE 1 SUPPLEMENTAL COMPOSITE WALL BOND TESTS
SUMMARY
Test Thickness Location Ultimate Load Failure Mode S-1A 24 Fuel Building 10,000 lbs Block-Core El 45 Ft S-1B 24 Fuel Building 19,800 lbs Block-Cote El 45 Ft S-2A 27 Auxiliary Building 4,950 lbs cell-Block El 77 FT S-2B 27 Auxiliary Building 10,000 lbs Block-Core El 77 Ft S-3A 27 Fuel Building 11,700 lb, Cell-Block El 77 Ft S-3B 27 Fuel Building 15,000 lbs Cell-Block El 77 Ft S-4A 34 Control / Auxiliary 7,500 lbs Cell-Block Building El 93 Ft S-4B 34 Control / Auxiliary 10,000 lbs Cell-Block Building El 93 Ft S-5A 24 Control Building 10,000 lbs Cell-Block El 93 Ft S-5B 24 Control Building 18,000 lbs cell-Block El 93 Ft S-6A NOT APPLICABLE S-7A 21 Control Building 7,400 lbs Block-Core El 45 Ft S-75 21 Control Building 14,600 lbs Anchor Bolt El 45 Ft A-4
TABLE 2 SUPPLEMENTAL COMPOSITE WALL BOND TESTS
SUMMARY
I
/
'"' ' 'E#
Test p, Ult e, Eccentricity No.
Load, Ibs In.
Nominal I/
Bending 2/ Total S-1A*
10,000 1/8 96.3 8.4 104.6 S-1B*
19,800 1/4 190.6 33.2 223.8 S-2A 4,950 3/8 47.7 12.4 60.1 S-2B*
10,000 1/2 96.3 33.5 129.8 S-3A 11,700 1/4 112.6 19.6 132.2 S-3B 15,000 1/2 144.4 50.2 194.6 S-4A 7,500 1/2 72.2 25.1 97.3 S-4B 10,000 3/P 96.3 25.1 121.4 S-SA 10,000 1/16 96.3 4.2 100.5 S-5B 18,000 1/16 173.3 7.5 180.8 S-7A*
7,400 1/2 71.2 24.8 96.0 S-7B 14,600 5/8 140.6 61.6 202.2
- Block-core failure 1/ Nominal tensile stress = failure load f gross area 2,/ Bending tensile stress = f ailure load x eccentricity' + gross section modulus i
A-5
_