Ack Receipt of 791130 Order Re Interim Operation of Plant. Staff Currently Assembling Info Bearing on Seismic & Other Issues in Proceeding & Will Supplement This Info to ASLB on 791207
ML19211C225
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 12/04/1979
From: Gray J
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Mccollom K, Mark Miller, Paxton H
Atomic Safety and Licensing Board Panel
References
NUDOCS 8001110078
Download: ML19211C225 (1)


Text

a asc f

llNIT ED STATES c

e"

}' 7.

NUCLEAR REGULATORY COMMISSION 5, c;kh/,,E WASmNGTON. D. C. 20555 v w u*

December 4,1979 Marshall E. liiller, Esq., Chaiman Dr. Kenneth A. ficcollom, Dean Atomic Safety and Licensing Board Division of Engineering, U.S. Nuclear Regulatory Commission Architecture & Technology Washington, D.C.

20555 Oklahoma State University Stillwater, Oklahoma 74074 Dr. Hugh C. Paxton 1229 41st Street Los Alamos, llew !!exico 87544 In the !!atter of Portland General Electric Company, et al.

(Trojan Nuclear Plant)

Docket No. 50-344 (Control Building)

Gentlenen:

On November 30, 1979, the Licensing Board in the referenced proceeding issued a "flodification of Order Pemitting Interim Operation of Trojan Nuclear Plant."

This Order was received by the mail room of the Office of the Executive Legal Director on December 3,1979 but Staff counsel did not become aware of the Order until today, December 4.

In the Order at page 4, item (2), the Staff is directed to "immediately infom the Board, explicitely and clearly, what unresolved imoblems remain which might have a bearing upon the seismic and other issues in this proceeding.

This infor-mation should be kept current upon a regular basis." The Staff is now in the process of assembling the infomation required by the Board in this regard.

The Staff will supply this information required immediately by the Board on Friday, December 7,1979.

It should be noted that the same Staff personnel who are involved in the Staff's evaluation of the proposed Control Building modifications have also been involved, in conjunction with the Office of Inspection and Enforcement, in assessing the problem of reaction forces on single and mortared double block walls. These Staff members will be involved in a meeting with the Trojan Licensee and Bechtel personnel on December 5,1979 on the reaction force problem. This meeting must be held as an aid to resolving this problem in a timely manner.

Items (4) and (5) on page 4 of the Board's Order cannot be responded to by the Staff until after this meeting.

In the Staff's submission to the Board on December 7,1979, we will further apprise you as to the timing of our submissions on items (4) and (5) of the Order.

Sincerely, g,t,

10 I

os ph R. Gra i Co sel for I RC S aff cc:

Service List 8 0 01110 0 7f