ML20150B943

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/87-46,50-260/87-46 & 50-296/87-46 on 871201-31.Violation Noted.Major Areas Inspected:Previous Enforcement matters,multi-plant Action Item,War Room Meeting,Emergency Procedures & Cold Weather Preparations
ML20150B943
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 02/11/1988
From: Brooks C, Christnot E, Ignatonis A, Andrea Johnson, Patterson C, Paulk G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20150B926 List:
References
50-259-87-46, 50-260-87-46, 50-296-87-46, IEIN-86-039, IEIN-86-39, NUDOCS 8803170200
Download: ML20150B943 (28)


See also: IR 05000259/1987046

Text

. . . - - __. . .. .. - . .-

. I

UNITED STATES

i- [p,*Rico o NUCLE R REGULATORY COMMISSION <

y" n REGION 11

g. j 101 M ARIETTA STHEET. N.W.

  • * ATLANTA. GEORGI A 3o323

,

g,

...../

,

I

. Report Nos.: 50-259/87-46, 50-260/87-46, and 50-296/87-46 -

l

'

Licensee: Tennessee Valley Authority

. 6N 38A Lookout Place

i 1101 Market Street'

Chattanooga, TN 37402-2801 ,

Docket Nos.: 50-259, 50-260, & 50-296 License Nos.: DPR-33,

DPR-52,

& DPR-68

Facility Name: Browns Ferry 1, 2, and 3

Inspection Conducted: December 1-31, 1987

'

Inspectors: _ _h)d Nmm ..b (M

Date Signed

T2

G. L. P(ulk, Senior RgidentvInspector

,

GnD&A

C 7 . Pct {erson, Reside 6t 16spector

w Ah/n

Date Signed

-_ 0ld0s ab

C. R. Brogks, Resident Inspegtor'

& '

lb?

Date' Signed

,

i [lb m m,

E. F. 'Chrfstnot, Resid6n1PInspgetor

M3 #/hF

Date~ Signed

,

!

'

Mb ~ h

A. H. Jbhnson, Project Ensineer

'/b7

Date Signed l

l NRC Contractor Assistance:

i David B. Waters, Previous Enforcement Matters  !

Gary W. Bethke, Previous Enforcement Matters

Approved by: (7. /) Mmob

A. J. Ig G tonisl Jection Chief

,1////&

Date S'ign'4d

TVA Projects Division 3

1

j f

SUMMARY  !

i

i

l Scope: This routine inspection was in the areas of previous enforcement  ;

'

I matters, multi plant action item, "war room" meeting, operational safety, j

maintenance observation, informacion notice review, surveillance observation, [

q reportable occurrences, cold weather preparations, restart testing, and emer- [

j gency procedures.  !

i i

1

i

8803170200 880226

PDR

G ADOCK 05000259  !

l ,

PDR -

.

.

2

Results: A violation of Technical Specification 4.7.B.2.a involved failure to

properly test the Standby Gas Treatment System following the fire in the Unit 2

drywell on Novemt:r 2, 1987.

l

1

,

i:

i

- . - - -. . . _ - _. --- - . .- - - -_

b

-

. l

.

REPORT DETAILS

'

.

1. Licensee Employees Contacted

H. C.~Pomrehn, Site Director

  • J. G. Walker, Plant Manager

P. J Speidel, Project Engineer l

-

  • J. D. Martin,-Assistant to the Plant Manager

R. M. McKeon, Superintendent - Unit 2

  • S. Olsen, Superintendent - Units 1 and 3

T. F. Ziegler, Superintendent - Maintenance

,

D. C. Mims, Technical Services Supervisor

l J. G. Turner, Manager - Site Quality Assurance

M. J. May, Manager - Site Licensing

'

  • J. A. Savage, Compliance Supervisor

A. W. Sorrell, Health Physics Supervisor

R. M. Tuttle, Site Security Manager

J. R. Kern, Fire Protection Supervisor

D. A. Pulien, Office of Nuclear Power, Site Representative

Other licens ee employees contacted included licensed reactor operators,  ;

'

auxiliary operators, craftsmen, technicians, public safety officers,

quality assurance, design and engineering personnel.

, * Attended exit interview  ;

2. Exit Interview (30703)  ;

.

The inspection scope and findings were summarized on December 18, 1987,

'

and January 8,1998, with the Plant Manager and/or Superintendents and

other members of his staff. The following new items were identified

during this inspection.

a. Violation 259,260,296/87-46-03. Failure to conduct test per desig- .

nated ANSI standard (Paragraph 11, Section a). .

b. Unresolved Item 260/87-46-04. Licensee's followup on generic

implications of heat tracing CAQR disposition (Paragraph 13).

)*

c. Inspector Followup Item 259,260,296/87-46-01. Independent review

i of substitute material data for RB equipment access door seals

{ (Paragraph 9, Section a).

4

l

i

d. Inspector Followup Item 259,250,296/87-46-02. Review of RHR pump  ;

I wear ring raaterial by specialist (Paragraph 9, Section b). ,

e. Inspector Followup Item 259,260,296/87-46-05. Correction o'

deficiencies in Emergency Plans Manual (Paragraph 15).

,

The licensee acknowledged the findings and took no exceptions,

i

_ _ _ _ _ _ _ , .. ,. __ ,

- - -

. - - _ - , _ _ . . . . , _ , ,_, - , _ , . _ _

. _ _ _. . ~- - . _

.

(

2

The licensee did not identify as proprietary any of the materials provided

to or reviewed by the inspectors during this inspection.

,

3. Licensee Action on Previous Enforcement Matters (92702)

(OPEN) Deviation (259,260,296/87-20-01), This item concerns the anchoring

,

of control room panels in a manner not consistent with the seismic capa-

bility demonstrations described in the FSAR. As opposed to being floor

mounted with 5/8 inch bolts in all mounting holes or a similar fashion as

justified by analysis, the as-constructed panels were tack welded at

intervals to fasten in place atop embedded plates.

This issue was first raised as an unresolved item in Inspection Report

86-25 (URI 259,260,296/86-25-04). The licensee investigated several

2

specific control room panels applying techniques under development by the

Seismic Qualifications Users Group (SQUG) and determined that the weld

attachments were satisfactory. However, further licensee review of other

control room panels found that the method of fastening by welding was not

an adequate means of mounting.

In response to the deviation, TVA has performed a seismic review of the

l main control room vertical bench board panels and freestanding control

panels and has determined an appropriate mounting arrangement. The design ,

consists of an "L" shaped steel bracket secured to the concrete floor with

anchor bolts and running the length of the panels. The panels are then

secured to the brackets at 4 inch intervals by rivets. Tne engineering

calculation number is CD-Q0009-871685 and utilizes standard analytical

techniques. Design Change Notices B00019A, B00020A and B00021A have been ,

issued for modification required for Units 1, 2, and 3 respectively. The

licensee has committed to install the modification by February 27, 1988.

This item remains open pending completion of the modifications.

(OPEN) Violation (259,260,296/86-43-03), This violation resulted from

inspector review of NCRs, SCRs and Problem Identification Reports (PIRs)

for determination of generic applicability, justification for considering

items not generic, adequacy and timeliness of Potential Generic Conditions

Evaluations (PGCEs) and adequacy and timeliness of PGCE replies by the

various TVA sites. At the time of the inspection, the corrective action ,

program had not been updated to the program currently in effect, namely

Nuclear Quality Assurance Manual (NQAM) Part 1, Section 2.16, "Corrective

Action". The inspectors noted several examples of untimely responses as

the basis for the violation.

The current corrective action program differs in several respects from the

the earlier programs. The requirements for the conduct and timir.g of

generic reviews has been made more controlled and centralized by requiring  ;

i

that the organization responsible for determining corrective action

initially review the Condition Adverse to Quality Report (CAQR) for its  ;

potential generic impact on other TVA facilities. Subsequently,  :

significant CAQRs and nonsignificant but potentially generic CAQRs shall

be forwarded to eir.her the Division of Nuclear Safety and Licensing or

,

,


y - , - - - - - - - _ ,.- ,e , - - . , , - - ---.w --.-.

. . . . .= . . .

,

'

'

-

]Y

,

3

'

Division of Nuclear Engineering - Engineering Assurance for further review

as to the potential for generic implications. These organizations will

document justification that the CAQ is not generic or issue a . request to

perform a generic- review by other potentially affected organizations. ,

These organizations in turn are to provide a response which indicates

whether or not they are affected and the justification if they are not

affected.

[ The timing associated with these actions are as follows: (1) Within 30

i calendar days from CAQR origination date, the 7 responsible organization

determines remedial corrective action; root cause and recurrence control,

if required; scheduled completion dates for remedial corrective action and

recurrence control, if required; and whether a review for generic

implications is needed; (2) CAQs reviewed for potential generic implica-

"

tions by DNSL or DNE-EA 40 calendar days from CAQR origination date;

(3) potentially affected organizations shall review CAQRs for generic

j implications - 70 calendar days from CAQR origination date.

,

i In order to asse'ss the effectiveness of the new corrective action prsgram

!

in providing timely reviews of CAQRs for potential generic implications,

the inspector obtained from the licensee a listing of CAQRs generated by ,

i Bellefonte, Saquoyah, and Watts Bar which required a review for potential '

generic implications by Browns Ferry between August 1, 1987, and

November 30, 1987 Out of the 65 items listed, only 5 had been closed

prior to the required due date; 10 were closed between 30 to 60 days after

the due date and 5 were closed greater than 60 days after the due date.

Of greater concern are those which remain unclosed and are substantially

late. In this category, 11 are unclosed and are 30-60 days after the,due

.

date, 14 are unclosed and are 60-90 days af ter the due date, and 2 are -

t

unclosed and greater than 90 days after the due date. The lateness of

these reviews may not totally be the result of Browns Ferry organizations

facility to take timely action; but rather a combination of several other ,

factors including the receipt of timely inputs from other site organiza-

tions. The report reviewed by the inspector does not indicate the date

when assignment was made to a Browns Ferry organization.

The current corrective action program has several mechanisms for reporting

status of CAQRs and informing management of problem areas. While the i

mechanism of CAQR processing by different licensee organizations appears

'

to be acceptable, no noticeable improvement was observed for timely i

,

review and closecut of CAQRs for potential generic implication. The i'

overall corrective action program remains open pending further review to

determine if required action times and organizational support of the l

! program are adequate to make the program truly effective. -l

t

4. Followup of Open Inspection Items (92701)

(CLOSED) Unresolved Item (253,260,296/86-05-01), FSAR Updates Without l

4 Justification. This unresolved item was opened when inspectors determined

that several original FSAR commitments had been deleted or modified in '

Amendment 1 to the FSAR without documented justification or safety

evaluation. TVA reviewed other changes to the FSAR and either provided ,

!

'

l

1

i

!

. . . - - - , - . ., -. . _ . .-

. - . .. .- - = _

-

.

l

l

4

t

safety evaluations or returned the wording to original wording in the 1986  :

FSAR update. This action corrected the specific unresolved item 86-05-01 l

FSAR word change problems. bring an August 1987 NRC inspection, similar i

problems were discovered noting that TVA made changes to the FSAR in

~

Amendment 5 dated July 22, 1987, which were not formally evaluated or

- documented for review. TVA has responded i.o the resulting Deviation

87-30-04 with a letter dated November 17, 1987.

TVA commitments made in_the November 17, 1987 letter are scheduled for

completion by June 22, 1988. The inspectors will followup ~ on this '

concern by reviewing TVA's response to Deviation No. 87-30-04. This

Unresolved Item is closed.

.

(OPEN) Inspector Followup Item (259,260,296/86-25-02),- Control Room

Emergency Ventilation Walkdown Deficiencies. This IFI was opened as a

result of numerous deficiencies discovered during an inspector walkdown of

the CREV system. Most of the deficiencies were hardware oriented and have  ;

been corrected by TVA personnel. The following individual parts of the

IFI are considered closed, with corrective action noted:

l

-

Several FCO-31-150 series dampers were not labeled or were labeled

incorrectly: The completed January 28, 1987, Maintenance Request

'

(MR) to install damper labels was reviewed and found to be

acceptable.

-

The system operating instruction, 01-31 "Air Conditioning System",

1

did not contain dampers FCO-31-150 B, D, E and F in the valve check- i

list: The October 1987 Revision to 01-31 was reviewed to verify that  !

,

these dampers were included.

W.

-

The CREV A Backdraft damper was found stuck open: The initial MR

which fixed the problem in January 1987 was reviewed. TVA has also I

initiated a preventive maintenance, biweekly cleaning of the CREV

Backdraf t dampers effective September 1987. i

-

An air line compression fitting near damper FCO-31-150 0 was found

leaking: The completed March 1,1987 MR which replaced the fitting

was reviewed and found to be acceptable.

-

The CREV B heater control setpoint adjustment knob was found broken:

The completed October 30, 1986, MR which replaced the knob was

j reviewed and found to be acceptable,

i Final closure of this IFI is dependent on two remaining deficiencies which

were not addressed in the TVA closure package. These deficiencies are:

- -

Reactor Operators (R0s) and Senior Reactor Operators (SR0s) took an j

, excessive amount of time to search for and locate the dampers which

must be manually shut, per 01-31, in the event of failure to close )

I  !

,

!

__ -_ __ __. . __ . _ _ _ _ , _ _ - _ . _ , _ . - - - - ~ s .<

_ . _ . _ . . __ = . _ . - _ _ _ . . __ _ ~ _ .

.

5

5

. ,

automatically. The closure package did not address how TVA has

'

upgraded R0 and SR0 knowledge on the'CREV system component locations.

.

- Dampers FC0-31-150 F is one of the dampers which may need to be i

manually shut by operators. The damper is located about 6 feet above  :

the Unit 3 Control Room ceiling panels and is extremely difficult to

access for manual operation. The closure package did not contain any-

,

discussion of an evaluation by TVA to determine if the subject damper  :

needs to have a remote operating aid attached (e.g., a reach rod).  ;

4

As of December 15, 1987, TVA may consider the scope of this IFI reduced to

the two items noted above (operator familiarization with CREV and possible

,

need for a remote operating tid for FCO-31-150 F). These two items will

t

continue to be tracked under IFI 86-25-02.-

i (CLOSED) Inspector Followup Item (259,260,296/86-02-03), Operability -

4 Evaluation due to Froblems Identified During Licensee's Field Inspection

of Anchor Bolt Verification. This IFI was opened as the result _ of a '

l

Seismic Cable Tray Support Anchor Bolt Sampling Program which - was

4

initiated by TVA to resolve Unresolved Item 85-41-01, "Verification of

Installed Concrete Anchor Bolts for Cable Tray Supports". The sampling

program showed that seismic cable tray supports have self-drilling anchor

bolts (Phillips Redhead) installed versus the three unit threaded cinch  ;

anchor bolts specified in some older construction drawings. The sample

i

'

program results closed item 85-41-03, but revealed several new concerns .,

relating to the installation of seismic cable tray supports. Concerns  :

,

included: *

1

-

Two support locations called for six bolt pattern plates and only

i fcsr bolt pattern plates were installed.

-

Poles in she plate were consistently oversized.

.

-

Gaps between the bottom of the plate and the concrete surface were

! excessive.

L

3

-

The recess between the top of the anchor bolt shell and the top of

!

the concrete surface was excessive.

l -

Thread engagement was less than minimum requirement. #

l

! Orawings 48N1100, 48N1104, 48N1101, and 48N1105 have been revised and

! reissued to properly indicate the as-built 4 bolt pattern plates (where

6 bolt patterns were originally indicated). DNE calculation package

'

l 822860213101, sheet ld shows the composite affects of hole oversizing,

base plate gaps, anchor bolt shell recess, and thread engagement for 4 l

l bolt pattern plates, These calculations show that the subject supports  !

'

j are adequate for interim qualification under general design criteria

i BFN-50-795 (I). This interim qualification is the near term resolution of

i anchor bolt questions at BFNP. The long term TVA resolution of anchor .

! bolt questions is planned to be accomplished by the licensee's involvement I

I

. l

i

! ,

l

. . -_ - - _ .- .- - - . - - , _ _

. -_ -. - _ - _ . .

-

.

l

6

with the Seismic Qualification Utility Group (SQUG). TVA intend to i

participate in the walkdown of the Generic Implementation Procedure (GIP) )

at Nine Mile Point during February and March 1988. The GIP has been l

developed as a means for older plants to resolve the seismic - 1

qualification issues raised by IEEE-344, Unresolved Safety Issue A-46, i

Generic Letter 87-02, NUREG 1030, and NUREG 1211. Furthermore, TVAs

overall plan for addressing seismic qualification issues is outlined in i

Volume 3 of the BFNP Nuclear Performance Plan.

(CLOSED) Inspector Followup Item (259,260,296/86-05-10), Protection of

Control Bay Ventilation Towers from Tornad Generated Missiles. This IFI

was closed during inspection 86-14 based upon the submission of undocketed l

PRA data to NRC by TVA. The subject issue was re-opened in inspection l

86-40 because it was determined that the PRA data was an unreviewed draft

'

from which no meaningful conclusions could be drawn. The TVA assessment

of the probability of a tornado missile striking ventilation tower equip-

ment is contained in LER 86-06-02 and is now being tracked by the NRC l

under IFI 86-40-09. l

l

(CLOSED) Unresolved Item (259/85-25-08), Rod Worth Minimizer Program Alarm

Message Table Missing. This item was opened when it was discovered that a

portion of the Unit 3 RWM Alarm Message Table (0CTAL CODE) was missing l

l from the write only portion of the process computer memory. The missing

l section of the code has been loaded into the Unit 3 process computer 1

memory. The octal code sheets have been compared for a match with Units 1 l

l and 2. The revised RWM and RSCS Functional Test for Startup (August 1987)

l

and RWM Program Verification (August 1987) procedures have been reviewed

)

i

j for completeness. The RWM Program Verification Procedure (SI-4.3.B.3.b.3) )

l is a new procedure and requires two man verification of the RWM program j

l

during reactor startup. -

(CLOSED) Inspector Followup Item (259,260,296/86-32-10), This item j

concerns the adequacy of MMI-34, Refueling Platform Inspection and Repair, l

in specifying the correct mechanism for performing corrective maintenance i

when the need is discovered during the performance of other routine

maintenance activities. The licensee had recognized the need for improve-

ments in MMI-34 in order to ensure proper maintenance history records that

can be used to accurately trend recurring defects, and committed to review

and make necessary changes to MMI-34 to satisfy the concerns of this item.

l

The licensee provided Commitment Closure Summary SLT 861087003 which

l included Revision 3 to MMI-34. Revision 2 to IMSI-3014, Troubleshooting

I and Maintenance Instruction (for instrumentation maintenance), Revision 1

to EMI-lob, Troubleshooting, Wirelif ts and/or Reterminations (for elec-

trical maintenance) and new procedure 50SP 7.6, Maintenance Request and

i

Tracking. The revision to MMI-34 includes a statement that requires an

! approved MR per SDSP-7.6 for all corrective maintenance activities such as

repairs o parts replacement. IMSI-3014 and EMI-106 require the use of

MRs to perform troubleshooting, repairs or additional corrective action

outside of the specific requirements of the MR controlling the work

activity. The revision to MMI-34 and the requirements of the other

l

l

\

_ -___ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ - _ _ _ _ _ _ _ _ _ _ .

.- - . .. . _ _ -

'

.

,

r

7

i

-

procedures are adequate to ensure that corrective actions are controlled

by the MR process.  ;

i Discussions were held with the licensee on other MMI procedures where the I

problems encountered in MMI-34 might also potentially exist. The licensee

,

responded that other MMI procedures . did not contain a statement on

'

corrective maintenance activities similar to the one provided in MMI-34,

thus creating the possibility that repairs or parts replacement could be

conducted on other plant equipment without being documented through the MR  !

process. The licensee proposed that a statement be included in SDSP-6.2,

Preventive Maintenance Program, to address the concern on an overall basis

in a controlling document and avoid the need to make revisions to numerous

procedures. The inspector concurred with this approach and with the

proposed revision to SDSP 6.2. PMI-6.2, Conduct of Maintenance, already

contains a satisfactory statement on corrective maintenance activities.

This item is closed. j

(OPEN) NRC Inspection Report (259,260,296/86-35, Sample No. 6), This item ,

addresses reanalysis of high energy lines at Sequoyah where the licensee '

2

requested relief from the requirements of Regulatory Guide 1.46 to

! relocate high energy line break (HELB) protective devices for arbitrary

1

'

intermediate break locations based on the reanalysis being performed.

Based on verbal approval from NRR, the licensee revised plant design

criteria documents to incorporate this exception to RG 1.46, but did not

reflect this exception in the Sequoyah Nuclear Plant updated FSAR. The l

concern was that comparable documentation deficiencies may exist at Browns l

Ferry and should be corrected,

The licensee provided Ccmmitment Closure Summary NCO 870096021 containing

a copy of the TVA response to Sample No. 6, the Sequoyah information

related to the reanalysis issue addressed in Sample No. 6 a copy of

i Generic Letter 87-11, which relaxes arbitrary intermediate pipe rupture l

t

requirements, and an internal memorandum addressing the applicability of i

this item to Browns Ferry.

The licensee stated that they had reviewed the applicable portion of the

Browns Ferry FSAR and concluded that the issue addressed in Sample 6 is

y not specifically addressed. Analyses of high energy lines were conducted

based on NRC requests following issuance of the FSAR and thus requirements

f and results of analyses were never specifically incorporated into the

i

document. There is, therefore, no documentation conflict and no revision

! required to the FSAR f or Browns Ferry. However, since the NRC has

recently relaxed the regulatory requirements for high energy line break

considerations and deleted the requirement for postulation of arbitrary

, intermediate pipe breaks, the licensee plans to update their analytical

proceoures and criteria and prepare FSAR changes to take advantage of this

, relaxation. This item will remain open pending completion of the FSAR

revision.

) (CLOSED) Inspector Followup Item (259,260,296/86-43-01), This item

addresses concerns arising from the review of the licensee's corrective

!

. . . - .. .

. - _ . .. - -- . .. . - -

. . _ . - . - _- . . . - . -

'

.

8

action program as set forth in the Nuclear Quality Assurance Manual, Part

1, Section 2.16, Rev. 1, "Corrective Action". The concerns were: (1) the

procedure does not contain clear requirements on immediate notification of

appropriate personnel upon identification of Conditions Adverse to Quality

(CAQs) which could affect safety in an operating plant, (2) qualification

requirements were not referenced for personnel evaluating CAQs, and 6

(3) provisions were not included to provide for disposition ar.d justifi-

L cation by other units at the same site of CAQs where the issue was -

determined to be generic.

The licensee provided Commitment Closure Summary SLT870051001' which

contains Revision 3 to NAQM Part 1, - Section 2.16; SOSP-3.7, Corrective

Action, Revision 2, which is the Browns- Ferry implementing procedure for

NQAM Part 1, Section 2.16; and a listing of the qualified CAQR management  ;

reviewers.

1

In response to concern (1), the licensee -added a note to the Section on

CAQR processing (Section 7.0 of NQAM Section 2.16 and -Section 6.2 of

SOSP-3.7) that provides guidance for immediate transmittal of CAQRs that ,

potential.y affect plant operability to the PORS section of the affected

plant, immediately notifying the affected nuclear site director of CAQRs

that adversely affect the health and safety of the public and plant

employees, and immediately transmitting to P0RS any CAQR that is poten-

tially reportable for a determination of reportability. This provides

assurance that operability problems can be effectively communicated to the

appropriate personnel during off hours, weekends and holidays.

In response to concern (2), the licensee indicated that training programs

j have been conducted for personnel initiating and processing CAQRs as well

as those personnel designated as management reviewers who are responsible

'

under Paragraph 6.2.2 of 50$P-3.7 for reviewing the CAQR for legibility,

clarity, completeness and validity. Site QA maintains a current list of

qualified management reviewers to ensure that the reviews are only

conducted by designated personnel. ,

In response to concern (3), the licensee revised the corporate and site

corrective action programs to require that if a review for potential

generic implications is not required or an organization determines that it

is not affected by a potentially generic CAQ, then a justification is

j provided and a management supervisor approves the justification. The

, approved justification becomes part of the CAQR package. Additionally, ,

the program requires that an acceptable response to the corrective action J

plan developed by the responsible organization shall consider any possible

'

generic implications of the CAQ within the organization (division or site)

where the CAQ was identified.

l

a If a CAQ is determined to have generic implications, then each potentially l

I affected organization receives a request for generic review, and is l

l required to provide an internally single coordinated response as to l

'

whether or not they are affected. If affected, the identification number '

5

of any resulting CAQR shall be included with the response. If not

1

h

s

_ _.. . , _ - . _ - _ . - . .

._. , - . , , -_ . , . - _ , . , _ . .l

_

.

9

affected, the response shall include a justification which has been

approved by the supervisor of the reviewer. Affected organizations are

directed to communicate with each other in the development of corrective

action plans for generic CAQs to ensure that, when appropriate, such plans

are consistent.

The above program changes satisfactorily address the concerns noted in

this item. This item is closed.

(CLOSED) Inspector Followup Item (50/260/87-30-05), Surveillance Instruc-

tion Upgrade Deficiencies. This IFI was opened following inspector review

of the evaluation documentation and sis associated with the licensee's SI

evaluation program being conducted under SDSP-2.14, "Surveillance

Instruction Evaluation". The IFI consists of three subparts in the *.reas

of (1) Independent verification and special tools (thermometers) relating

to four station battery sis (2-SI-4.9. A.2 series), (2) Qualification and

Certification of NDE Level 1 personnel performing Containment Local Leak

Rate sis (2-SI-4.7. A.2.g series), and (3) Method of Conducting Standby

Liquid Control System flow tests per Technical Specification 4.4.A.2.b

(2-SI-4.4.A.2). Corrective actions taken by TVA in each of these areas

(respectively) is discussed below:

a. The electrical section had realized the lack of independence in

SOSP-2.14 reviews before the date of the inspections which opened

this IFI. Their improved, independent evaluation results were

apparently not available for the inspector. The independent review

and walkdown documentation for the four battery procedures have bsen

reviewed and found satisfactory.

Section 5.0 "Special Tools and Equipment" of each of the four subject

procedures specifies a METTLER/PAAR DMA 35 Specific Gravity Meter,

which incorporates a built-in therraometer.

These findings and reviews resolve subpart 1 of the IFI,

b. The Containment Leak Rate sis reference procedure SDSP 17.1, "Primary

Containment Leak Rate Requirements" for personnel cualifications.

SDSP 17.1 has been revised to state that "qualification is only

achieved by certification under Area Plan 0202.14, Qualification and

Certification Program for Nondestructive Examination". This

procedure modification resolves subpart 2 of the IFI.

c. The BFNP Technical Specifications, section 4.4. A.2.b were in the

process of being modified at the time this IFI was opened. The

August 21, 1987, revision to section 4.4. A.2.b now reads in part,

"Verify minimum pump flow rate of 39 GPM against a system head of

1275 PSIG by pumping demineralized water through the Standby Liquid

Control Test Tank". This Technical Specification revision resolves

subpart 3 of the IFI.

Based on the discussion above, this IFI is closed.

- . _. _ . _ _ _ __ _ __._. _ _ . _ __

-

.

10 f

,

j -

4 (CLOSED) IE Bulletinn 86-01, Minimum Flow Logic Problems That Could _;~

,

Disable RHR Pumps. The licensee's response indicated the condition

,

does not exist at Browns Ferry. This item is closed. .

!'

(CLOSED) Inspector Followup Item (259,260,296/86-32-05), Basis For

Low Scram Air Pressure Trip States That SDIV Instrument Response Time j

May Be Inadequate. This IFI was based on the inspector's concern in  ;

that TS Nendment Number 125, Section 3.1, Bases, provides unclear i

information on the function of low scram pilot air header pressure l

trip. Review of licensee's correspondence, a letter from TVA  :

(L. M. Mills) to NRC (H. R. Denton), dated June 27, 1984, and the -

April 29, 1986 TS amendment request clarified the matter. The

concern that the SDIV instrument response time may be inadequate as

stated in the TS Bases most likely referred to the Magnetrol float

type of detectors which have been operationally observed to actuate

about 20 seconds after the FCI switches as the Instrument Volume

filled during actual scrams. 'The FCI RTD detectors- are a backup to ,

I

the Magnetrol detectors for high water level detection, and are not l

'

mentioned in the subject TS Bases. TVA's real reason for leaving the -,

low pressure switches in service is to provide additional redundancy

and diversity in initiating a scram during the fast fill event. This

item is closed. ,

(OPEN) Inspector Followup Item (87-13-01), Review of Section XI I

,

Surveillance Procedure to Verify SDV Vent and Drain Valve Timing '

Limits are Included. The inspector reviewed copies of the TVA

'

Section XI Surveillance Procedures (ISI Pump and Valve testing

, program). The October 1987 re-submission of this program to NRC does

1 contain all eight SDV vent and drain valves, but does not include

J acceptance criteria such as a stroke time limit. This IFI will

j' remain open until TVA has received approval from NRC on the

Section XI procedure and has developed valve specific acceptance

criteria (i.e., timing limits). I

(CLOSED) Inspection Report (259,260,296/83-15 Item a), This item  !

addresses concerns with management control of commitments and i

,

assurance of compliance. The licensee committed to improving their

4

computerized commitment tracking system to provide a program matrices

j system tnat takes an overall, systematic approach to controlling

i commitments made and implemented in division procedures and instruc-

1 tion, and also provide indicators in plant procedures to identify

steps resulting from NRC commitments and thus preclude the possi-

3

bility of removing commitment items in subsequent revisions. Review

of the computerized commitment tracking system that the licensee

4

currently employs determined that it is adequate to meet the concerns

l raised in Inspection Report 83-15. This item is closed.

5. Unresolved Items *

i One new unresolved item was ident;fied in paragraph 13 relating to cold

weather preparation.

I

j *An Unresolved Item is a matter about which more information is required to

determine whether it is acceptable or may involve a violation or deviation.

i

- --. . - . ~ ..-,___m - - - - . - . _ _ _ - . - _ . - . _ , - ._. - - - - - . - - . - - , ,

-

.

11

6. Multi-Plant Action Item B-58, Scram Discharge Volume Capability (TI

2515/90)

The inspector reviewed licensee's actions in response to the scram

discharge volume capacity concern. Specifically, the inspector audited

licensee compliance with selected criteria taken from the generic Safety

Evaluation Report of December 1, 1980. Eleven items were reviewed and

its status is provided below. The presented information is based on

interviews of cognizant TVA personnel, reviews of drawings, procedures and

Technical Specifications, and reviews of related open items. The status

of related open inspection items 86-32-05 and 87-13-01 is provided in

paragraph 4 of this report. The items are prefixed with 04 number for

NRC tracking purpose only.

04.01 SCRAM OISCHARGE HEADER SIZE

(OPEN) The inspector reviewed all analysis performed by TVA,

discussed the subject with several system engineers, and had several

calls to Knoxville Division of Nuclear Engineering initiated in an

n tempt to verify adequate Scram Discharge Volume (SOV) system sizing

and proper hydraulic coupling of the SOV header to the Instrument

Volumes (IVs). As of December 18, 1987, TVA was unable to provide a

concise statement or calculations to demonstrate that these criterion

of TI 2515/90 have been met by the re-designed SOV system with its

present scram setpoints on IV level. Pending receipt of this

information from TVA this item will remain open. NRC review of this

analysis will need to be completed prior to startup of BFNP Unit 2.

04.02 AUTOMATIC SCRAM ON HIGH SOV LEVEL

(OPEN) Eight high water level instruments are installed, four on

each of the two 50V IVs. Of the four instruments on each IV, two are

magnetrol float type and two are FCI RTO bridge type. These eight

high level instruments are inputs A - H to the RPS logic and function

in the standard G.E. one out of two taken twice logic. Technical

Specifications Tables 3.1. A and 4.1. A document the East and hest

Scram Discharge Volume High Water Level Scrams. Although the

criterion for instrumentation is met, the 50 gallon scram setpcint

may need to be re-evaluated as a result of analysis to be perfoimed

with respect to criterion 04.01 (Sizing and Coupling of the SOV

system). This item will remain open pending re-evaluation of the

scram setpoint.  !

04.03 INSTRUMENT TAPS NOT ON CONNECTED PIPING

(CLOSED) Each of the four high level instruments described in 04.02

1 above on each IV are on a separate standpipe. The standpipes

l

l

l

l

-

.

12

penetrate the IV and do not directly communicate with the SDV to IV

drain lines. The "Rod Block" and "Not Drained" instruments are

served by these same standpipes. This criterion is met.

04.04 DETECTION OF WATER IN THE IV

(CLOSED) This criterion, as written, applies only to the scram

instrumentation, not to the Rod Block and Not Drained

instrumentation. Single line plugging would only preclude 1 of the 8

instruments from providing an input to the 1 out of 2 taken twice RPS

logic. The instrumentation connected to each IV is diverse, with 2

FCI RTD type and 2 magnetrol float type detectors. Power supplies

for the 8 instruments are also diverse. The RPS channel, detector

type and power supplies are show in the matrix below:

WEST SDV

RPS CH POWER SUPPLY DETECTOR TYPE

A Al FCI

C A2 MAGNETROL

B B1 FCI

D B2 MAGNETROL

EAST SDV

RPS CH POWER SUPPLY DETECTOR TYPE

E Al MAGNETRDL

G A2 FCI

F B1 PAGNETROL

H B2 FCI

Loss of one RPS Power Supply (A or B) to the SOV instruments would

give a half scram signal, leaving the surviving instruments in a 1 l

out of 2 logic to initiate a scram. Browns Ferry has the added l

redundancy of 4 scram air header low pressure switches which will

initiate a scram in a 1 out of 2 taken twice logic. These RPS inputs

are actuated at 50 PSIG (or greater) air pressure in the header.

These switches are intended to prevent a single failure of one of the

RTD sensors in conjunction with a fast fill event from causing the

SDV to have inadequate free volume to handle the scram. This

criterion is met.

04.05 VENT AND DRAIN VALVE INTERFACES  ;

(CLOSED) Both of the vent lines on each unit's SDV have high point

vacuum breakers installed. Both the vent and drain lines are routed  !

l

-

.

13

to open sumps on the 519 foot level, precluding a pressurized

backfill of the SOV. The inspector reviewed mechanical drains and

embedded piping drawing 47W481-9 to verify that the vent and drain

lines communicate (converge) in their embedded runs. Therefore the

vacuum breakers serve both the vent and drain lines and preclude

syphoning action from filling the SDV, This criterion is

satisfactorily met.

04.06 VENT AND DRAIN VALVES CLOSE ON LOSS OF AIR

(CLOSED) The vent and drain valves are all air operated. They will

close on loss of air pressure (air to open, spring to close) or loss

of control power. A review of Drawing No. 730E915 shows that vent

and drain valve position indication in the control room is from limit

switches, thereby providing actual position indication (versus demand

signal). This criterion is cet.

04.07 OP9RATOR AID

(CLOSED) Each of the two IVs has one "NOT DRAINED" and one "ROD

BLOCK" instrument which annunciate in the control room. These two

instruments (4 total) provide early indication that the IV is

fill' m. Alarm Response Procedures (BFARPs) Nos. XA-55-6A and

XA-55-Gv necifv operator actions for alarms associated with these

instruments. 'his criterion is met.

1

04.08 ACTIVE FAILURE IN VENT AND DRAIN LINES

(CLOSED) The current BFNP configuration for vent and drain valves is

as follows: Each of the two (West and East) IVs has a drain .ine

with two valves in series; thus there are two drain paths, each

having redundant stop valves. The vent lines tap off the two sides

(east and west) of the SDV (versus off the IV). Each of the two vent

lines has two valves in series. While a failure of a single vent

valve could isolate (remove) the venting capability of a vent line,

it would not interfere with the isolation function.  ;

04.09 PERIODIC TESTING OF VENT AND DRAIN VALVES

(OPEN) The definitinn of "0PERABLE" under TS 4.3.F does not contain

a quantitative closure time of 30 seconds. The OPERABILITY Surveil-

lance test is performed using BF SI-4.3.F.1.b. Step A of this SI

only requires the vent and drain valves to be manually cycled (Steps

A.2 and A.3), with no accompanying timing specification (as

recommended by GE). TVA should consider adding the timing specifi-

cation to the TS (4.3 F' and the SI (BF SI-4.3.F.I.b). This l

criterion is not fully met because of the lack of a quantitative

timing specification in the TS. The TVA submission to NRC on Section l

XI Pump and Valve ISI testing of these valves also contains no l

acceptance criteria, i

1

1

-. -- _ ~ - . -. -. . - - . -

.-. .--

-

.  :;

!

,

14 .

04.10 PERIODIC TESTING OT LEVEL DETECTION' INSTRUMENTATION

(CLC Ttu, Browns terry Surveillance Instructions BF SI 4.1. A ' . 8.FT

(#unctional test) and BF SI 4~.1. A - 8 CAL (calibration) test and

calibrate the high water leve! scram, Rod Block and 'Not Drained

instruments on the IVs. The FT actually tests the float type

switches by filling the float chamber with demineralized water. The-

FT for the RTD type switches injects a test signal to the instrument

loop and does not directly test the sensors. The CAL test for the

float type switches is similer to the FT in that the float chamber is

filled with water and the switch actually cycled. The CAL test for

the RTD type switches includes de-energizing the RTD heater (to  !

verify RTD balance) and filling the standpipe to actually test the.

RTD bridge response. Both the FT and CAL tests have steps to restore

the valve lineups and circuitry to operational mode. The testing

procram for the level instruments is therefore satisfactory. This

criterion is met.

04.11 PERIODIC TESTING OPERABILITY OF THE ENTIRE SYSTEM

(OPEN) Section 4.1.3.1.4 of the BWR Standard Technical

Specifications is where the surveillance requirement relating to this

criterion is addressed. TVA has not included. this surveillance

(observing vent and drain valve operation and timing during a manual scram) in the equivalent section 4.3.F of the BFNP Technical-

Specifications. Observations of the response time during actual past

scrams _has shown that the magnetrol switches respond about 20 seconds

after the RTO switches. Although TVA has not met this criterion,

consideration is being given to the possible conflict between this

criterion and the current attempts by GE owners to reduce manual scrams. The final report has not been issued by the BWR Owner's

Group Committee on the Scram Reduction Program. - This item remains

open pending the receipt of the final report and furthcr review by

the inspector.

7. "War Room" Neeting (30900)

The inspector attended and observed a meeting of Senior Browns Ferry TVA

Managers, Bechtel Managers, Stone and Webster Managers and Ebasco Managers

in what is referred to as the "War Room." The topics of discussion

involved the inputs from the various contractors into the "P2" planning

and scheduling system, the day to day workings of the "War Room" committee

and the preparation and content of the Level One reports to be sent to the

Director, Nuclear Power Office, and TVA. The various planning and

scheduling groups arrived to participate in the meeting midway through the

initial discussions. A free flowing exchange of ideas, information and

questions then took place with each person present being asked by the

Senior Browns Ferry Manager to participate. Numerous items were discussed

as a result of the various topics and comments made by the participants.

Additional War Room committee meetings will be held on a continuous' basis,

and the inspector will attend periodically.

, -

  1. c - .r--. , - - - - ~ , - , - - - - . . ~ , , , -

. _ - - _ - - _ _ _ _

-

.

15

8. Operational Safety (71707,71710)

The . inspectors were kept informed of the overall plant- status and any.

significant safety matters related to plant operations. Daily discussions

were held with plant management and various memoers of the plant operating

staff.

l

i

The inspectors made routine visits to the control rooms when an inspector

I was on site. Observations included instrument readings, setpoints and

( recordings; status of operating systems; . status and alignments of

emergency standby systems; onsite and of fsite emergency power sources

l

I

available for automatic operation; purpose of temporary tags on equipment

controls and switches; annunciator alarm status; adherence to procedures;

adherence to limiting conditions for operations; nuclear instruments

operable; temporary alterations in effect; daily journals and logs; stack

3

monitor recorder traces; and control room manning. This inspection

activity also included numerous informal discussions with operators and

their supervisors.

General plant tours were conducted on at least a weekly basis. Portions of

! the turbine building, each reactor building and outside areas were

l visited. Observations included valve positions and system alignment;

l

'

snubber and hanger enditions; containment isolation alignments; instru-

ment readings; housekeeping; proper power supply and breaker; alignments;

i

radiation area controls; tag controls on equipment; work activities in

progress; and radiation protection controls. Informai discussions were ,

held with selected plant personnel in their functional areas during these l

tours. '

1

In the course of the monthly activities, the inspectors included a review

of the licensee's physical security program. The performance of various l

shif ts of the security force was observed in the conduct of daily

activities to include; protected and vital areas access controls,

searching of personnel, packages and vehicles, badge issuance and

retrieval, escorting of visitors, patrols and compensatory. posts. In

addition, the inspectors observed protected area lighting, potected and

vital areas barrier integrity.

9. Maintenance Observation (62703)

Plant maintenance activities of selected safety-related systems and

components were observed / reviewed to ascertain that they were conducted in

accordance with requirements. The following items were considered during

this review: the limiting conditions for operations were met; activities

were accomplished using approved procedures; functional testing and/or

calibrations were performed prior to returning components or system to I

service; quality control records were maintained; activities were accomp-

lished by qualified personnel; parts and materials used were properly

certified; proper tagout clearance procedures were ed.ared to; Technical

Specification adherence; and radiological controls were implemented as

required.

--

- - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

., . .. . -- - - . - - .

.

16

Maintenance request:, were reviewed to determine status of outstanding jobs

and to assure that priority was assigned to safety-related equipment

maintenance which might affect plant safety. The inspectors observed the

below listed maintenance activities during this report period:

a. Secondary Containment Inflatable Seals

The inspector reviewed activities involved in the replacement of

inflatable seals ' on the reactor building equipment access . doors.

These seals provide a boundary against secondary containment

in-leakage and were discovered inoperable by a restart test performed

several months ago. New seals were drawn from Power Stores and

installed. Procurement documentation was reviewed to assess the

qualification of the seals. The. replacement seals were ordored and

received in late 1985. Since the original vendor was not able to

supply the seals at that time, a substitution was obtained and

evaluated. As part of the evaluation of this substitution, the

design organization evaluated the physical properties and radiation

resistance of the ethylene propylene rubber (EPDM E603) and concluded

that they exceeded the properties of the original neoprene seals.

This conclusion was documented in a memo contained in the contract

files (B22 '85 1213 027). No further data or references could be

found in the file that would allow an independent review of the

properties such that the conclusion could be confirmed. The

inspector learned that no further documentation existed elsewhere in

the licenste's files that would substantiate the conclusion. A

licensee representative stated that they would regenerate the

necessary data and add it to the file. This will be tracked as an

Inspector Followup Item pending independent review of the data

(259,260,296-87-46-01).

b. RHR Pump Wear Ring

The inspector reviewed maintenance activitics associated with removal

and replacement of the Residual Heat Removal (RHR) System pump wear

rings on Unit 1, pump B. Pump failures due to wear ring cracks were

reported in IE Information Notice 86-39. TVA activities associated

with this problem are documented in LER 86-06 and the Browns Ferry

Nuclear Performance Plan, section 111,7.3.S. In summary all of the

wear rings on the four Unit 2 pumps have been inspected and replaced

with the original 410 sta nless steel. Wear ring replacements for

the Units 1 and 3 pumps are being made with materiai having lower

hardness. Mechanical Main'..>. ance Instruction 16-B, Residual Heat

Removal Pump Rotating Asser % Removal and Replacement, contains the

work instructions. This procedure was found to be suitable for the

job; however, it did not contain any references to I.E. Notice 86-39,

LER 86-06 or any special notes or precautions which would focus

special attention on the inspection of wear rings for cracking.

The pump manufacturer recommended replacement of the pump impeller

with one having an integral wear ring (one that has a martensitic

. _

, . _

. . . .

- - - . --

.. _ . - ..- __ __ __ . _ . - . . __ _

-

, ,

!

l

l

17-

stainless steel wear ring cast integral to the impeller) as a long

term solution to the cracking problem. The licensee considers the

softer wear rings being installed on the Units 1 and 3 pumps to be an

acceptable long term solution and-~ asked the. pump manufacturer to

evaluate this approach. The ' manufacturer responded that in their

opinion the. softer wear rings would only be acceptable as an interim

fix. The manuf acturer's response did not change the licensee's

position but plans are being developed to perform a one time

inspection on a single pump after two' operating cycles of operation.

Provided no evidence of cracking is detected on that sample, only

routine pump maintenance would be performed thereafter. Although the

design organization evaluated both the integral wear ring and the

softer wear ring as acceptable alternatives, they pointed out that

several features of the integral wear ring design made it more

desirable than the sof ter ring design. The plant opted for the

softer wear ring due to the cost advantage and ease of installation ~.

An inspector ' followup item will be opened to track review of this

item by a material specialist in the Office of Special Projects

(259,260,296/87-46-02).

No violations or deviations were observed in this area.

10. Information Notice 86-81 Review - Main Steam Isolation Valve Springs

(92701)

The inspectors reviewed the results of the licensee program conducted to

determine generic concerns of Atwood Morrill Main Steam Isolation Valve

(MSIV) Helper Springs as noted in I.E. Information Notice 86-81.

During an inspection of all Unit 1 closing assist springs on main steam

isolation valves, an inner spring on 1-FCV-1-38 (Maintenance Request

A 80817) and 1-FCV-1-52 (Maintenance Request A 808823) were found broken.

General Electric Service Information Letter 422 flagged this problem

occurring at other facilities who had Atwood and Morrill supplied main

steam isolation valves. Nuclear Regulatory Commission Information Notice

86-81 also addressed this problem referencing the General Electric Service

Information Letter 422. Browns Ferry generated a significant condition

report BFN MEB 8606 identifying the problem and committing Browns Ferry to

the visual inspection recommended by General Electric. The inspection

which found the brcken springs was performed to support this commitment.

The spring failure mechanism was quench cracking, which is a brittle

fcilure mechanism expected to occur early in spring life. In all

likelihood, although unable to be verified, these identified spring

failures occurred early in Unit 1 plant life. The Unit 1 main steam

isolation valves have mot required closure times and leak rate testing in

accordance with Browns Ferry Technical Specifications throughout the

Unit 1 operating history. A TVA letter dated July 25, 1987, stated that

the inner springs cumulatively contribute 10% of the closing force. Also,

Engineering Report BFN MEB 8606 notes that it would take all 8 inner-

springs to break to aad 1 second to valve closure times, and that an

_ _ _ _ _ ._. . - , _ . _. _ _ _ , . . _ _ . . _

, _ - . - . . . - - - --. - -- - - - . . .

.

.

1

18

isolated spring failure has a negligible effect on valve leak tightness.

Although an isolated inner spring failure represents a degradation in main

steam isolation valve operation, the magnitude .of the safety degradation

has been indistinguishable over time and analytically appears small. The

General Electric Service Information Letter 422. states if all spring force

was lost, main steam isolation valve closing time .is estimated to- remain

below 10 seconds and for a Mair 3 team Line break unisolated for 10 seconds

offsite radiation doses will still remain below 10 percent of that allowed

by 10 CFR 100.

Unit 2 MS'V inspections have not been conducted to date, but will be

conducted prior to unit startup. Unit 3 MSIV springs were visually

inspected with no deficiencies noted.

11. Surveillance Observation (61726)

The inspectors observed and/or reviewed the below listed surveillance

procedures. The inspection consisted.of a review of the procedures for

technical adequacy, conformance to technical specifications, verification

of test instrument calibration, observation on the conduct of the test,

removal from service and return to service of the system, a review of test

data, limiting condition for operation met, testing accomplished by

qualified personnel, and that the surveillance was completed at the

required frequency.

a. Standby Gas Treatment System (SGTS)

The inspector reviewed the results of Standby Gas Treatment System

(SGTS) testing required by technical specification 4.7.B.2.a

following the Unit 2 drywell fire of November 2, 1987. These tests

involved 00P removal testing of the HEPA filter banks; halogenated

hydrocarbon (freon) removal testing of the charcoal filter banks; and

radioactive methyl iodide removal testing of the charcoal filter

banks. The tests were all conducted and evaluated as satisfactory by

the licensee except for the methyl iodide testing which is to be done

by an of f-site laboratory. The inspector's review of the data

associated with freon testing on SGTS train B conducted on

November 25, 1987, and documented on SI 4.7.B.5, SGTS Charcoal

Halogenated Hydrocarbon Testing, detected several problems which

invalidate the test. Technical specifications require the test to be

performed in accordance with ANSI N510-1975.  ;

l

This standard requires that the upstream freon concentration be

held at 20 percent of the preset value. The test conducted on

November 27, 1987, varied up to +240% of the preset value. The ANSI i

standard further requires that the upstream concentration of freon

tracer gas should be no greater than 20 ppm. During the test of

train B filters the upstream concentration went as high as 34 ppm and

during the test on train C the concentration went up to 40 ppm. The

inability to hold the tracer gas to 120 percent lead to anomalous

data that fit a parabolic curve as opposed to a normal linear

,_ _ - - - . - - . . - - - . .- - -.-,

. . _ .. = _ _ . .. .. . __

-

.

19-

response. Failure to conduct the test per' the designated ANSI

Standard is a violation of Technical Specification 4.7.B.2.a

(259,260,296-87-46-03).

b. As part of the Restart Test Program (RTP) various Surveillance

Instructions (SI) were performed as stipulated in the System Test

Specifications (STS). The inspector observed- the performance and

reviewed portions of these sis when they were performed as part of

the RTP. The STS 2-BFN-STS-057-1, "125 VDC System," Section 5.5.1,

and Section 5.1 of test 2-BFN-RTP-057-1 require that SI-4.9.A.2.c "DG

Battery Discharge Test" be performed; the STS 2-BFN-STS-057-5, "4.16

KV Distribution," Section 5.5.5.1 and Sections 5.27 through 5.36 of

Test 2-BFN-RTP-057-5 requi res . that SI-4.9.A.3.a "Common Accident

Signal Logic" be performed; in addition, the STS/RTP-082 "Standby

Diesel Generators" require that SI-4.9.A.1.d, "Diesel Generator

Annual Inspection", and SI-4.9. A.4.b, "4-KV Shutdown Board Under-

voltage Start of Diesel Generator" be performed. As a part of the

RTP Test Instructions, each completed SI is to be attached as

appendices to their respective t'ests. ,

No violation or deviations were found in this area.

12. Reportable Occurrences (90712,92700)

The below listed licensee events reports (LERs) were reviewed to determine

if the information provided met NRC requirements. The determination

included: adequacy of event description, verification of compliance with

technical specifications and regulatory requirements, corrective action

taken, existence of potential generic problems, reporting requirements

satisfied, and the relative safety significance of each event. Additional

ir-plant reviews and discussion with plant personnel, as appropriate were

conducted. The following licensee event reports are closed:

LER N0. DATE EVENT

259/83-16, Rev. 3 3-9-83 CREV Charcoal

Sample Efficiency Less

Than Required

259/84-12, Rev. 1 and 2 2-14-84 Shutdown Cooling

System Not Available Due

To Valve Failure to Open

259/87-13 7-12-87 Improper

Application of-Radiation

Monitor Detector

Causes Actuation of

Engineered Safety

Features

. , = - - , -- , . - . -

- . .

.

,

L

20

LER NO. DATE EVENT'

259/87-16 7-11-87 Fire Barrier

Breached Without

. Required Compensatory

Measure

259/87-18 - 8-7-87 Spurious Actuation

of Reactor Protection

System Circuit

Protector Causes ESF

Actuation

259/87-19 8-6-87 Incomplete

Surveillance

Results in a Condition

Prohibited by Technical

Specification

260/87-08 8-26-87 Personnel Error

Causes Engineered

. Safety Features (ESF)

Actuation

296/86-11 10-23-86 Technical Specification

Violation From Low

Pressure Coolant

Injection Motor

Generator Set

Coupling Failure

The cause of the CREV charcoal (LER 259/83-16) reduced removal efficiency

was degradation of the stored charcoal prior to use. Replacement charcoal

trays are now filled and sealed by a vendor and come with certification

papers. The charcoal shelf life is now controlled by procedure TI-80,

Charcoal Shelf Life and Inventory Program.

The Electrical Maintenance Instruction 18, limit and Torque Switch Adjust-

ment for CSSC Motor-Operated Valves (LER 259/84-12), was revised to

improve recording and review of acceptance criteria and data recording of

torque switch settings.

",

_ The radiation monitor detector (LER 259/87-13) was replaced and no further

problems have been encountered.

The electrical maintenance foreman (LER 259/87-16) involved was counseled  !

on the proper method and responsibility for initiating the breach,of a

fire barrier. The other maintenance foremen were briefed and trained on )

1

the above. l

l

,

.

-w----r- , ,r-.s -,- , - ,%,- -- %. , ..v , , - .,7 ,, , -- ,-,--4,- -- %- , ,.r-y---

-

- , ,-% , , e ev- , w

- - .-- . _. . .- - - _ _ _

.

21

A review of operational events did not identify any condition that could

have actuated the circuit protector (LER 259/87-18). The event was

attributed to a spurious actuation of the _ circuit protector, and no

further corrective action was planned.

The defective fire hydrant (LER 259/87-19) was replaced and the

surveillance was completed on August 20, 1987.

Personnel error during installation of jumpers (LER 260/87-08) caused a

relay to deenergize and initiate the engineered safety features. The

personnel involved were counseled on using more caution when performing

similar work in the future. Restart test personnel received training to

emphasize the identification of potential system actuations in procedures

and in the pretest briefing.

Improper motor to generator shaft alignments and improper coupling gaps

(LER 296/86-11) resulted in motor generator set coupling problems. Plant

maintenance instruction revisions have been initiated to incorporate the

latest coupling information.

No violations or deviations were found in this area.

13. Cold Weather Preparations (71714)

The inspectors reviewed the licensee program to protect plant safety-

related equipment from cold weather conditions.

l

The intake pumping structure which houses the RHRSW/EECW systems piping is  ;

'

essentially an open structure and therefore subject to the prevailing

weather conditions of the area. Design calculations document that during ,

severe weather, freezing, rupture, and subsequent loss of flow could occur  ;

in the stagnant instrument and vent lines located off the RHRSW/EECW j

system piping. Therefore, some type of protection is required to prevent

this from occurring. As a result, heat tracing and temperature annon- i

ciation in the control room have been installed. '

The RHRSW/EECW systems are safety-related as defined in FSAR Sections ,

10.9.1 and 10.10.1. Heat tracing is installed in accordance with design  !

drawings for the pumping station RHRSW/EECW systems to preclude freezing )

of the EECW strainer instrument lines and pump discharge cross-connect -j

lines. The heat tracing receives its emergency backup power Lfrom the  ;

Class 1E 480V Diesel Auxiliary Boards and its failure is annunciated in

the plant control room. The heat tracing is intended to enhance the

operational reliability of the RHRSW/EECW systens in the sense that the i

function it performs must be provided or other operational actions must be

taken to prevent imminent freezing should the heat tracing fail during

severe weather. i

Additionally, in response to IE Bulletin 79-24 the licensee committe'd to

have the process, instrument, and sampling lines for the EECW/RHRSW

systems at the intake structure and the diesel generator EECW cooling

~

water lines in the diesel generator building cold weather protected by

. . . _ _ _ _ _. . __ _

.

.

1

l

22 l

l

l

l

heat trace systems. An annual maintenance program (Electrical Maintenance '

Instruction 46) has been implemented to verify system operability.

During an Environmental Qualification walkdown by a licensee Performance

Action Team in January 1987, the licensee identified significant

deficiencies Condition Adverse to Quality Report (CAQR) BF 870018 related

to the RHRSW/EECW heat trace systems.

The FSAR safety design basis for the RHRSW system (section 10.9.2, para-

graph 3) and the EECW system (sectio, 10.10.2, paragraph 2) indicates that

this system is safety-related. Additionally, drawing 37W205-60 RA

illustrates the loss of heat trace can render these systems inoperable,

indicating that the heat trace is important to safety.

The CAQR written by the licensee inspection team noted the following

specific heat trace system (eficiencies:

a. Splices were made with wire nuts.

b. Heat trace cables were not terminated.

c. Conductors were cut.

d. Cable and conduit had no identification.

e. Flex conduit had been removed or cut off.

f. Junction boxes were badly rusted and corroded, and had water standing

in them.

g. Terminal blocks were badly corroded.

h. Bend radii of conductors was in question.

1. Ground conductors were left free.

J. Terminations were not supported,

k. Flex conduit was not sealed.

1. Conductors were terminated without lugs and with oversized lugs,

m. TVA Management Review Indicated the heat trace system was installed

as a non-critical system; therefore, there was not enougn quality

requirements specified on the design output documents to maintain the

system. As a result, a general degradation of the system has

occurred over time. EMI - 46, Freeze Protection Program has a lack

of quality acceptance criteria due to the lack of quality standards

in the design output documents resulting in the system being poorly

maintained.

- . . - .- . -- . - .. .. . . - - . ..

.

23

Corrective action on the above CAQR deficiencies have not been fully

evaluated to date by the licensee.

The inspector conducted a walkdown of the "A" RHRSW/EECW pump room at the

intake structure and noted an additional heat trace system deficiency not

previously identified.

Plant drawing 37W205-60 requires that each pump discharge heat trace

circuit shall cover the common piping portions. The inspector's walkdown

revealed that for' the "A" pump room the common discharge RHRSW pipe was

not protected by redundant circuits as required by plant design. Other

pump rom.s could not be assessed due to insulation installed or room

accese not available.

This item will remain unresolved pending completion of the licensee

followup evaluation and generic implications as identified by the

inspector (260/87-46-04).

14. Restart Testing

During this inspection period the inspector attended the 6:30 a.m. Restart

Test Program status meetings on a continuous basis. The inspector closely

monitored the following tests which are currently in progress:

2-BFN-RTP-024 (RTP-024) Raw Cooling Water System 1

2-BFN-RTP-032 (RTP-032) Control Air System

2-BFN-RTP-082 (RTP-082) Standby Diesel Generators

a. RTP-024 Paw Cooling Systems

The test is in the initial stages and several Maintenance Requests

(MRs) are outstanding involving items such as check valve overhauls.

The test director is performing check valve operability tests as the

MRs are completed. No significant problems have been encountered.

b. RTP-032 Control Air System

The test has been in progress for several months and the specific

area being monitored involves sectica 5.4.4 of the System Test

Specification, "Verify that the control air system provides control

air to the large equipment access lock seals at Unit 1." The

licensee continued to have problems with leaks in solenoid valves,

pressure switches not set properly, and air pressure relief valves

malfunctioning. The seven day (162 hour0.00188 days <br />0.045 hours <br />2.678571e-4 weeks <br />6.1641e-5 months <br />) test run, using the air

accumulators to keep the door seals adequately inflated was attempted

on several occasions. However, system leaks other than in the seals

themselves, were preventing a successful run. On December 17, 1987,

'

a successful 162 hour0.00188 days <br />0.045 hours <br />2.678571e-4 weeks <br />6.1641e-5 months <br /> test was completed on the outer doors. The

inner doors continued to have leaks in the system and after repairs

to a solenoid valve a test was attempted starting on December 14,

1987. The seals were maintaining 7 psig or greater at the end of the

o

. _ _ _. _

.

(

24

test; however, the requirement that the seals be deflated and

reinflated at the end of the 162 hours0.00188 days <br />0.045 hours <br />2.678571e-4 weeks <br />6.1641e-5 months <br /> was not successful. The

inspector observed the start of the retest for the inner doors

starting at 2:10 p.m., December 30, 1987. As a result of.the failure

to meet all the test criteria five (5) MRs were written and disposi-

tioned to repair the various leaks in the system. The new seals did

not indicate leakage. The inspector will monitor the progress of the

test on a continuous basis,

c. RTP-082 Standby Diesel Generators (DG)

The inspector observed portions of the air start test of DG 3B.

After the coast down of the DG,~ it was observed that the over-voltage

relays appeared to pickup (energize), a start /stop switch malfunc-

tioned, and a kilo volt ampere reactive (KVAR) meter on shutdown

board 3EB did not indicate properly. Tr.9 test director stopped

further testing of the DG, submitted MRs for the relays, switch, and

KVAR meter. Testing was not resumed on DG 28 until the MRs were

adequately addressed.

A channel on the Measuring and Test Equipment beng used to monitor

the KVAR of _ DG 3A malfunctioned during the origina test and there-

fore the data obtained initially was not adequate for the Department

of Nuclear Engineering (DNE) to evaluate the results cf the test.

This retest was scheduled to be run on Saturday, Decemt.9r 5,1987;

however, operations personnel were not available to suppor' the test,

therefore the test was reschedu'ied and run on Saturday, December 12,

1987.

On December 29, 1987, the inspector observed the shutdown board 2 EB

Emergency Load Acceptance Test and the Full Load Reject Test of DG

38. The load acceptance test involved tripping the normal feeder to

shutdown board 3 EB, allowing the DG 3B to start and feed 3 EB, and

verify that the Residual Heat Removal Service Water (RHRSW) Pump C3

was load shed and auto sequenced back on to the 3 EB board. The DG

output breaker was then tripped af ter the system was allowed to

settle out. The DG output breaker was verified as reclosing with the

RHRSW breaker initially tripping with the DG breaker and reclosing

after the DG output breakers closed. This test was documented on

Data Sheet 7.22, Pages 11 through 21 of 2-BFN-RTP-082. The next

phase of the tests was the load rejection test, which involved

opening the output breaker of DG 3B at 2600 KW. This test was

documented on Data Sheet 7.22, Pages 24 through 26 of RTP-082.

Initial review of all test data indicated that the tests were

satisfactorily conducted.

d. Multiple Testing

On December 18, 1987, the inspector observed the performance of three

simultaneous tests performed by System Engineers, Operations

Personnel, Restart Test Personnel and additional personnel as needed.

. _

. .- ..

-

..

25

The tests involved Surveillance Instruction 0-SI-4.9. A.1.b-4, Diesel  :

Generator "D" Emergency Load Acceptance Test, Restart Test Program

(RTP) Instruction 2-BFN-RTP-082, Standby Diesel Generators, and

2-BFN-RTP-57-4, 480V Distribution System. The specific section of

RTP-057-4 applicable to this testing was the load Shedding function

of Shutdown Board 2B and associated loads, and the section of RTP-082

was the paralleling of "D" Diesel Generator with "30" Diesel

Generator. The perforraance of the SI was observed at "D" DG and

portions of the RTPs were observed from the Unit 1 - 2 and Unit 3 ,

control rooms. A detailed briefing was conducted in the Unit 1 and 2 '

control room attended by all personnel involved with the tc:t

(approximately thirty) four hours prior to the tests with a followup

briefing right before the test. Both briefings were very thorough

and questions were solicited from the attendees. The tests appeared

to be successful and the initial review of the data appeared to

indicate that the test was adequate. Personnel involved displayed a

professional attitude about the test and appeared as a whole to have

a thorough knowledge of the tests and test requirements. While the D

and 30 DGs were operating in parallel / load sharing, an operator noted

that the Control Room Emergency Ventilation System (CREVS) was

running. This was initially reported as an inadvertent actuation.

However, on followup review it was determined that when power to

shutdown Board D was deenergized this should have caused the CREVS to

receive a start signal. It was noted that the CREVS were not part of

the SI or the RTP Tests. During the SI/RTP tests action was not

taken to note the status of the CREVS and this may be more of a

deficiency in test conduct and not one of. test acceptability.

As of the end of November,1987, a total of two RTPs, Standby Liquid

Control, and radiation monitoring have been completed; one test, Raw

Service Water was completed and the results were being prepared for

DNE review; two tests, Standby Diesel Generators and Control Air

System were ongoing; and eight tests were in the initial  :

stages or have been delayed due to equipment modifications, repair or

material availability.

15. Emergency Procedures (82204)

The Browns Ferry Emergency Plans Manual (EPM) was reviewed. This manual l

contains eight events some of which are potential emergencies for which  !

instructions are written per the Nuclear Quality Assurance Manual (NQAM)

Part II, Section 1.1, Plant Operating Instructions, Section 3.2.3.3.

These EPM procedures deal with the following situations:

a. Fire outside the protected area in warehouses.  ;

1

b. Oil and other chemical spills.  !

c. Spill of radioactively contaminated liquids.

d. Flood.

1

!

)

l

__ - -

. .

. _ _ . .

_ . _ _ _ . ._ _

-

.

'

26

e. Control room operators threatened by toxic materials.

.f . Control room abandonment,

g. Breach of downstream dam.

h. Earthquake.

Four.of the procedures have had no review or revision since July 1983.

One of the procedures which has recently been revised and approved (EPM 2,

Oil and other chemical spills) was left with cutdated information after

the revision. Emergency phone numbers contained in EPM 2 were wrong or

disconnected. Responsibilities were assigned to organizational entities

which no longer exist following the rearganization of the Browns Ferry

site several years ago. EPM 5, Control Room Operator Safety Threatened

by Release of Hazardous Chemicals, indicated that one of the methods

available for detection of toxic materials .was chlorine aetector

annunciation. Browns Ferry has never had a chlorine monitoring system

for the control room. EPM 8, Earthquake Emergency Procedure contains

erroneous statements regarding the seismic qualification of reactor

building basement flood switches. This procedure also prematurely

requires that the cooling tower vacuum breakers be opened following a low

level seismic event prior to performing a controlled plant shutdown and

even if no damage is sustained either onsite or offsite. EPM 8 further i

contains a requirement to perform an electrical check (EMI-90) on the

reactor building basement flood switches as part of the initial response

to a seismic event and this action is highlighted as an NRC commitment

made in LER 86-21. This item was not committed to in LER 86-21.

These EPM deficiencies were discussed with site emergency preparedness

personnel who indicated that an immediate, thorough review would be

performed on the EPMs and necessary upgrades would be initiated.

Correction of these deficiencies will be tracked as an Inspector Followup

Item (259,260,296/87-46-05). l

<

l

l

1

. . . -l