Forwards Ssopi Info Request.Nrc Will Perform Ssopi at Plant During Wks of 970428 & 0512
ML20137K297
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 03/24/1997
From: Grant G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Wadley M
NORTHERN STATES POWER CO.
References
NUDOCS 9704070003
Download: ML20137K297 (4)


Text

.

March 24, 1997 i

l 1

Mr. M. D. Wadley j Vice President, Nuclear Generation Northern States Power Company 414 Nicollet Mall Minneapolis, MN 55401 1

SUBJECT:

ANNOUNCEMENT OF SAFETY SYSTEM OPERATIONAL PERFORMANCE INSPECTION

Dear Mr. Wadley:

This is to inform you that the NRC will perform a safety system operational performance l inspection (SSOPI) at the Prairie Island Nuclear Generating Plant. We have chosen the i auxiliary feedwater, the safeguards chilled water, and the control room eentilation systems l as the focus for this SSOPI, which will use NRC inspection Procedure 93801 " Safety '

System Functional Inspection" emphasizing the system operation aspects of the procedure. The inspection's onsite activities era scheduled for the weeks of April 28 and May 12,1997. The details of this inspection, -.wding the systems, were communicated to your staff (Mr. Albrecht of your engineering de rtment) on Friday, March 14,1997.

The details of the inspection were confirmed in a (,Jnversation between the senior resident inspector and Mr. Albrecht on Monday, March 17,1997.

The inspection will assess operation, design, maintenance, surveillance, quality assurance, and corrective actions associated with the selected Prairie Island systems, with a 1 concentration on the operations and design aspects. To accomplish its objectives, the SSOPl team will review a broad range of information and system activities.

)

1 In order to most effectively perform this task, we would appreciate your providing information on the selected systems, as shown on the attached list. We would apfreciate your having this information available for the team the afternoon of April 14,1997.

Members of the team will be at the plant the week of April 14 to prepare for the j inspection, gain some familiarity with your facility and fulfill access requirements. l l

We would also appreciate it if you would arrange for short system overview. presentations I during this week and a general plant tour, including as much of the selected system as is j reasonably accessible.

I i

9704070003 970324 PDR ADOCK 05000282 PDR G [

(

Q

- . - - - - -- ~

. i M. D. Wadley 2 March 24, 1997 If you have any questions regarding the information on the attachment, or on the inspection itself, please contact Joel Guzman at (630) 829-9719.

Sincerely,

/s/ G. E. Grant Geoffrey E. Grant, Director Division of Reactor Safety l

)

Docket Nos. 50-282; 50-306 cc w/ encl: Plant Manager, Prairie Island John W. Ferman, Ph.D.

Nuclear Engineer, MPCA j State Liaison Officer, State  !

of Minnesota State Liaison Officer, State of Wisconsin Tribal Council, Prairie Island Dakota Community Distribution:

Docket File w/enci

~

Rlli PRR w/ encl C. D. Pederson, Rlll w/enct

%IC 15-01M/ encl 3O SRis, Prairie Island, Rlli Enf. Coordinator w/enci OC/LFDCB w/enci Monticello w/ encl TSS w/enci DRP w/enci LPM, NRR w/enci DRS w/ encl A. B. Beach, Rlli w/enci l

l i

DOCUMENT NAME: G:\PRA032_7.DRS To receive a copy of this document, indicate in the box 'C' = Copy w/o attach /enci *E' = Copy w/ attach / encl "N" = No copy 0FFICE RIII:DRS I6 RIII:DRS lf- RlII:DRP lC- Rill:DRS_ l NAME Guzman/kjc /Wv Ring # Jacobson EU A Leach /G M L DATE 03/ 9 /97' " 03/ u /97 03/ao /97

  • 03/Tf//)}(f "

0FFICIAL RECORD COPY

Attachment SSOPI INFORMATION REQUEST Selected systems: Auxiliary feedwater (AF), safeguards chilled water (ZH), and control room ventilation (ZN).

) 1. Auxiliary feedwater (AF), safeguards chilled water (ZH), and control room ventilation (ZN) design basis reconstitution documents.

2. Procurement specification for all major equipment for selected systems. Major equipment would be considered such components as pumps, chillers, air handlers,

, heat exchangers, valves, dampers, and orifices.

3. Analyses supporting single active failure adequacy.
4. The completed preoperational test procedures.
5. Thermal, hydraulic and HVAC calculations and analyses, including a summary of normal and accident heat load inputs to the selected system.
6. A listing of the system components included in the IST program and the results of their IST testing.
7. Certified pump and fan curves (witnessed test curves).
8. Flow data for system components and heat transfer data for heat exchanger and coolers for various modes.
9. Results of any heat exchanger testing, (last three tests on each heat exchanger) if performed.
10. Vendor manuals for the major components of the systems.
11. Cross-sectional drawings of major equipment in the systems.
12. P&lDs of the selected systems and any interconnected or auxiliary systems.
13. Isometrics for the selected system piping.
14. Water hammer or surge pressure suppression information, if any.
15. Electrical schematics and single line drawings showing the power supplies to the major electrical components.
16. Electrical calculations associated with the selected system.
17. System operating procedures for system alignment, normal operation and abnormal condition or emergency response.
18. System response procedures,i.e. those procedures for responding to and evaluating control room or local alarms that may lead into the system operating procedures requested above.
19. Training information for licensed and non-licensed operators including lesson plans, training text, handout material, task performance measures.
20. Training information for. maintenance personnel for activities performed on the 4 selected system.
21. Preventive and corrective maintenance procedures for the selected system,

! components, related instrumentation and power supplies.

1

22. M .;1tenance history for the major components over the last two years.
23. Information on system and component reliability and availability for the last two years.

4

24. A listing of any system maintenance activities scheduled during the inspection, i
25. A listing of the selected systems' scheduled surveillances, including due date, i critical date, and date the surveillance was last performed.
26. Copies of the latest completed system surveillance procedures.
27. Quality Verification activities (surveillance and audits) related to the selected

, systems over the last two years.

28. Onsite and offsite review committee meeting minutes for the past six months.
29. Deviation reports, non-conformance reports, or other deficiency logs pertaining to the selected systems (for the last two years).

} 30. List of modifications, temporary modifications, etc. performed on selected systems.

31. Setpoint calculations for functions for the selected systems.

Additionally, please make available information supporting evaluations of cable trays that did not meet the separation criteria in the USAR as discussed in LER 96-13. Include corrective actions planned or taken and evaluations and analysis in support of SE 371.