Forwards Unit 1 ISI Summary Rept,Interval 3,Period 2 Refueling Outage Dates 990425-0526,Cycle 19 971212-990526. Rept Identifies Components Examined,Exam Methods Used,Exam Number & Summarizes Results
ML20211C231
Person / Time
Site: Prairie Island 
Issue date: 08/19/1999
From: Sorensen J
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20211C236 List:
References
NUDOCS 9908250183
Download: ML20211C231 (2)


Text

Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Dr. East Welch, Minnesota 55089 August 19,1999 10 CFR 50.55a U S Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Unit 1 Inservice Inspection Summary Report Refueling Outage for Cycle No. 20 During the 1999 Prairie Island Unit 1 refueling outage (Refueling Outage for Cycle No.

20), an inservice inspection (ISI) examination for the first period of the third interval was conducted. Attached for your information are four copies of the ISI examination Summary Report for this period.

The report identifies components examined, the examination methods used, the examination number, and summarizes the results. All anomalies were either corrected or an engineering evaluation was performed to accept "as is" conditions. A description of the corrective work and the corresponding work request numbers are provided in the ASME Section XI Repair / Replacement portion of the report.

This Summary Report is being submitted in accordance with the Prairie Island ASME Code Section XI Inservice inspection Program and is intended to satisfy the inspection j

reporting requirements contained in IWA-6220 of the ASME Boiler and Pressure Vessel Code.

In this letter we have n.9de no new Nuclear Regulatory Commission commitments.

Dh 9908250183 990819 PDR ADOCK 050002G2 G

PDR, L

USNRC NORTHERN STATES POWER COMPANY August 19,1999 Page 2 Please contact Jack Leveille (651-388-1121 Ext. 4142) if you have any questions related to this letter.

Joel P. Sorensen Plant Manager Prairie Island Nuclear Generating Plant c: Regional Administrator-Region Ill, NRC (2 copies of attachment)

Senior Resident inspector, NRC NRR Project Manager, NRC J E Silberg (w/o attachment)

Chief Boiler inspector, State of MN P Fisher, Hartford Insurance

Attachment:

Unit 1 ISI Summary Report, dated August 4,1999 U11SIRPT. DOC