ML20205R484

From kanterella
Jump to navigation Jump to search
Forwards Security Insp Repts 50-282/99-03 & 50-306/99-03 on 990322-26.No Violations Noted.Objective of Insp Effort Was to Determine Whether Activities Authorized by License Were Conducted Safely & IAW NRC Requirements
ML20205R484
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 04/16/1999
From: Creed J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Wadley M
NORTHERN STATES POWER CO.
Shared Package
ML20205R488 List:
References
50-282-99-03, 50-282-99-3, 50-306-99-03, 50-306-99-3, NUDOCS 9904230039
Download: ML20205R484 (2)


See also: IR 05000282/1999003

Text

,

.

..-

April 16, 1999

Mr. M. Wadley

President, Nuclear Generation

Northern States Power Company

414 Nicollet Mall

Minneapolis, MN 55401

SUBJECT: NRC SECURITY INSPECTION REPORT 50-282/99003(DRS);

50-306/99003(DRS)'

Dear Mr. Wadley:

On April 7,1999, the NRC completed an inspection of your physical security program at the-

Prairie Island Nuclear Generatin; Plant. The enclosed report presents the results of that

inspection.

Areas examined during the inspection are identified in the report. Within these areas, the

inspection consisted of a selective examination of procedures and representative records,

observations, and interviews with personnel. The objective of the inspection effort was to

determine whether activities authorized by the. license were conducted safely and in accordance

with NRC requirements.

No violations of NRC requirements were noted in the areas that were reviewed. The security

department self-assessment efforts continue to be strong. Although the general performance of

the security force has been effective and consistent recently, we identified two occasions when

the protected area ingress search and access control functions were significantly disrupted. We

also identified that a security implementing procedure included several tasks that could not be

completed during peak protected area ingress periods. Additionally, we identified that you

changed one of your corrective action commitments to security activities without changing your

commitments to the NRC. The significance of the change is still under review.

- 9904230039 990416

PDR ADOCK 05000282

e PDR

!

L

[

1-

,- '

l

M. Wadley -2-

l

!

!

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter and its

enclosure will be placed in the NRC Public Document Room (PDR).

Sincerely,

ames Sajeguards Team Leader

Division of Reactor Safety

Docket Nos.: 50-282;50-306

'

License Nos.: DPR-42; DPR-60

1

!

Enclosure: Inspection Report 50-282/99003(DRS); {

50-306/99003(DRS)

1

'

cc w/ encl: Site General Manager, Prairie Island

Plant Manager, Prairie Island 1

S. Minn, Commissioner, Minnesota

Department of Public Service )

,

State Liaison Officer, State of Wisconsin I

!

Tribal Council, Prairie Island Dakota Community )

Distribution:

CAC (E-Mail)

.

RPC (E-Mail)

! Project Mgr., NRR w/encI f

J. Caldwell, Rlli w/ encl i

B. Clayton, Rlli w/enci l 1

SRI Prairie Island w/enci

DRP w/enci

l DRS w/enci /

Rill PRR w/e el \g

PUBLIC IE- w/ encl

Docket File /enci

GREENS

LEO (E-Mail)

'

DOCDESK (E-Mail)

l

DOCUMENT NAME: G:DRS\PRA99003.WPD

To r.c.w. . copy a mi. ooe-nt, inoic.i. in m. bor c copy -me .n.enen.nuoncio.or. r copy um .u.cnrnonu.ncaur. v wo copy

OFFICE Rlll _

Rill ld Rlli m Rlli l

NAME GPirtle:sd W RLanksbury2Of- JCreeW

DATE 04/t499 04/16/99 046/59 04/ /99

OFFICIAL RECORD COPY

J' 30Mo