ML20135D682
ML20135D682 | |
Person / Time | |
---|---|
Site: | San Onofre |
Issue date: | 12/06/1996 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
To: | |
Shared Package | |
ML20135D674 | List: |
References | |
50-361-96-14, 50-362-96-14, NUDOCS 9612100090 | |
Download: ML20135D682 (41) | |
See also: IR 05000361/1996014
Text
. . . . _ _ _ . _ _ _ . _ _ _ . _ _ . _ . _ . _ . - _ . - . . . _ . _ . _ _ _ . _ _ .-.. _.._._m ._ . _ ___._..m _. _ - _._
i
. I
i
e
L ;
'
ENCLOSURE ,
U.S. NUCLEAR REGULATORY COMMISSION I
REGION IV .;
i
!
Docket Nos.: 50-361 l
50-362
x
Licensa Nos.: NPF-10
Report No.: 50-361/96-14 ,
50-362/96-14
Licensee: Southern California Edison Co.
!
'
Facility: San Onofre Nuclear Generating Station, Units 2 and 3
Location: 5000 S. Pacific Coast Hwy.
,
San Clemente, California
'
Dates: October 20 through November 15,1996 I
Inspectors: C. J. Paulk, Reactor Inspector i
Maintenance Branch
J. E. Whittemore, Reactor Inspector
, Maintenance Branch
j Approved By: Dr. Dale A. Powers, Chief, Maintenance Branch
Division of Reactor Safety
i
i
'
Attachment: SupplementalInformation
i
i
i
l
I
i
l
5
i
!
,
9612100090 961206
PDR ADOCK 05000361
O PDR
_. -. - . . _ _ _ _ . _ _ _ . _ . - - . _ _ _ . - -. . _ , - . - - .
.
-2-
EXECUTIVE SUMMARY
San Onofre Nuclear Generating Station, Units 2 and 3
NRC Inspection Report 50-361/96-14:50 362/96-14 l
During a review of the " Monthly Maintenance Rule Program Performance Update for
Risk-Significant Systems," issued on August 19,1996, the resident inspector identified
approximately 15 structures, systems, or components that had not met the licensee
established performance criteria. An unresolved item was opened for NRC followup on this l
issue. This specialinspection was conducted to evaluate the unresolved item. )
Maintenance
1
The f ailure to set goals and monitoring requirements for 13 structures, systems, or l
components that exhibited performance at levels less than the established i
performance criteria is an apparent violation of 10 CFR 50.65(a)(1)(Section M1.1). l
l
- The failure to establish performance criteria for the control room smoke exhaust '
system is an apparent violation of 10 CFR 50.65(a)(2)(Section M1.1).
l
The f ailure to demorstrate that the use of standard performance criteric of two
functional failures over two fuel cycles for reliability consistent with the
l
assumptions of the probabilistic risk assessment is an apparent violation of 10 CFR
50.65(a)(2). (Section M1.2). .
j An assessment of the Maintenance Rule program and implementation of goal setting
l
'
evaluations was thorough and in-depth for the failure to document goals. However,
the assessment did not address the fact that adequate goals and monitoring
requirements were not established prior to July 10,1996, as required by the
Maintenance Rule (Section M7).
l
l
l
. - - - . . . - . - . _ _ - . - . . . - - . - . - _ - . . . - . . . - . . . _ _ . _ . . - . . - . - -
1 e'
i
i
'
t.
4
-3- l
1'
<
J
i
.l
Report Details I
n ,
' i
j Summary of Plant Status
i ?,oth units were operating at full power during the inspection period. j
i ,
'
1
. II. Maintenance
M1 Conduct of Maintenance (62706 and 92902)
- M 1.1 Maintenance Rule Goal Settina
4
i During a review of the monthly " Maintenance Rule Program Performance Update for
? Risk-Significant Systems," issued on August 19,1996, the resident inspector
l identified approximately 15 structures, systems, or components that had not met
j the licensee established performance criteria. An unresolved item was opened for
- NRC followup on this issue. This specialinspection evaluated the unresolved item.
.
.
a. Insoection Scope
}
The inspectors reviewed the following documents to determine if performance goals
,
and monitoring requirements had been established for those structures, systems,
i and components identified in the licensee's July 10 and August 19,1996, monthly
! status reports as either failing to meet the performance criteria or as having a trend
[ that would result in failure to meet the performance criteria before the next
- evaluation period
l * 10 CFR 50.65, " Requirements for Monitoring the Effectiveness of
Maintenance at Nuclear Power Plants;"
l
- Regulatory Guide 1.160, " Monitoring the Effectiveness of Maintenance at%
.
Nuclear Power Plants," Revision 1;
! l
l * NUMARC 93-01," Industry Guideline for Monitoring the Effectiveness of l
l Maintenance at Nuclear Power Plants," Revision 0;
i
i' * SO123-XV-5.3," Maintenance Rule Program implementation," Revision 0,
TCN 0-3;
i l
j * SO123-XIV-5.3.2," Determination of Maintenance Rule Performance I
l Criteria," Revision 0;
i
,
1
4
k
h
-
. -. . . _ __ _
- . - _ -. - .
.__
".
t
4
SO123-XIV 5.3.6," Goal Setting for the Maintenance Rule," Revision 0; the
San Onofre Nuclear Generation Site's " System Engineer's Notebook for the
Maintenance Rule"; and,
a the action requests listed in the attachment,
b. Observations and Findinas
The inspectors noted that most of the action requests, which were completed after
July 10,1996, contained Maintenance Rule evaluations which determined if
,
performance goals and monitoring requirements should be set for systems,
I structures, and components whose performance was below the licensee established
performance criteria. Within several of the documents reviewed, the inspectors
observed statements that indicated that the performance goals were to regain
satisf actory performance by eventually meeting performance criteria as
4
demonstrated through normal operation, surveillances, and preventive maintenance '
activities. While acknowledging that the ideal was to always have performance at ,
<
levels that met or exceeded the performance criteria, the inspectors noted that, as
, discussed in joint NRC and industry forums, when performance dropped below the
.
performance criteria, corrective actions were to be taken to correct the cause and
prevent recurrence, in order to accomplish that end, performance goals and
'
monitoring requirements were to be established commensurate with safety to
measure the effectiveness of the corrective actions and to demonstrate, within a
certain time period, that the root causes were corrected.
4
-
Through discussion with licensee representatives, the inspectors noted that the
licensee staff considered that the re-achieving performance by meeting the
previously established criteria was a satisfactory goal under 10 CFR 50.65. The
inspectors also determined that performance goals and monitoring requirements
which met the requirements of 10 CFR 50.65 were eventually established, but were
characterized as performance thresholds. The inspectors noted that the licensee
had not documented any performance goals or monitoring requirements in
accordance with 10 CFR 50.65 prior to July 10,1996. The inspectors found that
the only documentation of performance goals and monitoring requirements that met
the requirements of 10 CFR 50.65 were in corrective action documents (action
requests) or in evaluations in support of the action request activities, which were
not established prior to July 10,1996,
'
During a debriefing session on October 25,1996, with licensee management and
supervision having 10 CFR 50.65 responsibilities, the inspectors explained the
requirements for goal setting in accordance with 10 CFR 50.65 and
NUMARC 93-01. The licensee subsequently submitted additionalinformation in the
October 31,1996, letter and attachments (see Section M8.3). The licensee
expressed the opinion that no violations had occurred; they were only untimely in
documenting the goals.
.
- .
-5-
The following discussion addresses those systems and components identified in the
unresolved item.
b.1 Unit 2 Turbine-Driven Auxiliary Feedwater Pumo
On June 25,1996, the licensee representative identified that the Unit 2
steam turbine-drivr;n auxiliary feedwater pump had experienced three
repetitive functioaal failures during the last 3 years. This performance did
not meet the cr8t eria of less than three functional failures or three repetitive
failures within a monitoring period. Because the turbine-driven auxiliary
feedwater pump was included in the scope of 10 CFR 50.65, the licensee
initiated Action Request 960601178to evaluate the failures to determine if
goal setting, in accordance with 10 CFR 50.65(a)(1), was required.
The inspectors noted that the action request was closed on August 28,
1996, on the basis of reaching a determination that goal setting was not
required because only two functional failures were related and the problem
source had been corrected. However, on September 13,1996, after the
resident inspectors identified the unresolved item associated with the f ailure
to establish adequate performance goals and monitoring requirements, the ;
'
failures were reevaluated and the licensee determined that the train would be
placed in goal setting as required by 13 CFR 50.65(a)(1). Subsequently, a
component-specific goal (applicable to the trip and throttle valve) that no
additional f ailures occur within one year of the last f ailure was established.
The inspectors found that the failure to set goals and monitoring l
requirements for the Unit 2 steam turbine-driven auxiliary feedwater system
prior to July 10,1996, was an apparent violation of 10 CFR 50.65(a)(1)
(50-361/9614-01:50-362/9614-01). The inspectors also found that the
licensee established the required goals and monitoring requirements on
September 13,1996.
b.2 Unit 3 Safety Iniection Tanks
On July 23,1996, the licensee identified that the Unit 3 safety injection
tanks had been unavailable for 47.99 hours0.00115 days <br />0.0275 hours <br />1.636905e-4 weeks <br />3.76695e-5 months <br />. This exceeded the availability I
performance criterion, and a Maintenance Rule evaluation was required to be
performed. The licensee initiated Action Request 960700871 to develop a
root cause for the undesirable performance and to develop corrective actions
to return the tanks to an acceptable level of performance. The licensee also
identified the tanks as candidates for goal setting in accordance with
The inspectors noted that the licensee had been calculating availability using
data obtained in an operations procedure for filling the tanks. The calculation
, _ . _ _ _ . . _ . _ _ _
__. _ _ . _ -_.-.___.._._ _ _ ___ _ _ ,
"
, j
t
l in ;
l i
"
i
t
6-
!
included the time required to obtain chemist,y samples. The inspectors ,
noted that the licensee determined that including the time for sampling in the
l calculation was not reasonable. As a result, the licenset recalculated the
! availability and concluded that the Unit 3 safety injection tanks satisfied the
availability performance criterion.
l
'
The inspectors found that the licensee properly evaluated and resolved the
question of the availability of the Unit 3 safety injection tanks.
l b.3 Site Diesel-Driven Fire Water Pumo SA2301MP220 1
J
l On June 26,1996, the licensee identified that Site Diesel-Driven Fire Water )
j Pump SA2301MP220did not meet its reliability performance criterion as a
l
, result of three functional failures during the monitoring period. The separate
events were characterized as failure of the diesel to start on demand for
different reasons. The licensee recognized that the pump may be required to
l be in goal setting, as required by 10 CFR 50.65(a)(1), and initiated Action
- Request 960601201 to evaluate the failures.
l
'
The inspectors noted that, according to the action request, on August 16,
1996, the licensee determined th.at goal setting was not required because
the causes of the failures had been determined and corrected. The
inspectors also noted that, on September 17,1996, the licensee determined
that the fire water pump required monitoring and goal setting in accordance
with 10 CFR 50.65(a)(1). The licensee established a performance threshold
(goal) of zero failures to start for the weekly auto-start test through
December 1996.
l
l The inspectors found that the failure to set goals and monitoring
requirements for the Site Diesel-Driven Fire Water Pump SA2301MP220 prior
to July 10,1996, was an apparent violation of 10 CFH 50.65(a)(1)
(50-361/9614-01:50-362/9614-01). The inspectors also found that the
licensee established the required goals and monitoring requirements on
September 17,1996.
b.4 Site Electric-Driven Fire Water Pumo SA2301MP222
l
On June 28,1996, the licensee determir.ed that the Site Electric-Driven Fire
Water Pump SA2301MP222 failed to meet its availability performance )
criterion of 90 percent. The licensee considered the pump to be in goal
'
setting, in accordance with 10 CFR 50.65(a)(1), and initiated Action
i Request 960601362to determine the cause of the pump not meeting its
, availability performance criterion, develop appropriate L.orrective action to
! return it to an acceptable performance level, to establish a period over which
i the performance would be returned to an acceptable level, and to establish
what monitoring would be done to assure satisfactory recovery.
l
l
._ , , _ . - .._ ,, , __ . _ _ .
. . _ _ _ _ . , -. , m _ ,__, ,,-_
.- -_ -. - . - - - - _ - - - - -. . .- .. .
'
, '.
.
4
b .
-7- !
- The inspectors noted that the failure to meet the availability performance
criterion was due to an extended work scope during the annual work
- window. Specifically, when the pump was removed for an overhaul, the
.1
preventive maintenance activities that the licensee deemed necessary
, resulted in a significantly increased work scope.
t
On August 15,1996, the licensee initiated, and completed, a Maintenance .
Rule evaluation for this component. The inspectors noted that the licensee
established a goal to meet or exceed the performance criterion over
4 quarters. The inspectors also noted that the pump's availability
performance criterion had been met by the time the Maintenance Rule !
j evaluation was written; however, the licensee intended to continue '
'
monitoring the pump's performance in accordance with 10 CFR 50.65(a)(1)
until the next annual maintenance window.
The inspectors found that the f ailure to set goals and monitoring
4
requirements for the Site Electric-Driven Fire Water Pump prior to July 10,
1996, was an apparent violation of 10 CFR 50.65(a)(1)(50-361/9614-01;
, 50-362/9614-01). The inspectors also found that the licensee established
d
the required performance goals and monitoring requirements on August 15,
1996.
1 b5 East Fire Water Pumo S1-FPW-G-11S
On July 10,1996, the " Maintenance Rule Program Performance Update for
.,
Risk-Significant Systems (2096)" indicated that the East Fire Water Pump
9
had an availability of 84.5 percent over a 4-quarter period. This availability
failed to meet the availability performance criterion of 90 percent. On
July 24,1996, the licensee identified the 4-quarter availability of
84.5 percent met the goal setting requirements of 10 CFR 50.65(a)(1), and
'
initiated Action Request 960700894to determine the cause of the
unavailability and to develop a plan to correct the performance.
,
On July 24,1996, the licensee initiated a Maintenance Rule evaluation for
the east fire water pump. On September 25,1996, after the resident ;
inspectors identified the unresolved itern associated with the failure to
establish adequate performance goals and monitoring requirements, the
-
licensee completed the Maintenance Rule evaluation. The licensee
l determined that the cause of the low availability was an extended work
. scope during its annual maintenance window. The licensee established a
4
monitoring goal that the east fire water pump would re-achieve the
availability criterion of 90 percent over 4 quarters after the next annual
maintenance window,
a
- The inspectors found that the failure to set goals and monitoring
- requirements for the east fire water pump prior to July 10,1996, was an
.
.. . _ _ . _ _ _ _ . _ _ _ _ .. _ . _ _ . _ . _ _ . _ _._ _-_ _- _.___
5
i
!
l
l 6
f
'
8-
l
apparent violation of 10 CFR 50.65(a)(1). The inspectors also found that the
j ' licensee established the required performance goals and monitoring
re,quirements on September 25,1996,
i- b.6 Wetoioe Valve for Unit 3 Intake Structure Saltwater Coolina Tunnel
l
l On July 10,1996, the " Maintenance Rule Program Performance Update for
Risk-Significant Systems (2096)" indicated that the wetpipe valve for Unit 3
intake structure saltwater cooling tunnel fire suppression system failed to
meet its availability performance criterion. On July 24,1996, the licensee
, identified the 4-quarter availability of 89 percent potentially met the l
l goal-setting requirements of 10 CFR 50.65(a)(1), and initiated Action '
l Request 960700895 to determine the cause of the unavailability and to
i develop a plan to correct the performance.
On July 25,1996, the licensee initiated a Maintenance Rule evaluation for
l the Unit 3 valve. On September 23,1996, after the resident inspector j
identified the unresolved item associated with the failure to establish
adequate performance goals and monitoring requirements, the licensee
completed the Maintenance Rule evaluation. The licensee determined that
the cause of the low availability was the sprinkler system being impaired
l while work was being performed on Salt Water Cooling Pump 3P-112.
The inspectors found that the inclusion of the time that the sprinkler system
was not required caused the apparent low availability. The inspectors found
that this system was not required to have been in 10 CFR 50.65
l Category (a)(1).
t
l
l b.7 Control Room Comolex Smoke Exhaust System
!
1
On June 26,1996, the licensee determined that the control room complex
l smoke removal system had not met the required reliability performance
l criteria because of three failures of dampers to reposition on receipt of 3
demand (test) signals. The licensee recognized that the system may be l
required to be in goal setting in accordance with 10 CFR 50.65(a)(1) and )
initiated Action Request 960601224to determine if monitoring goel setting )
was necessary.
On July 26,1996, the action request was closed without written
explanation. On September 20,1996, after the resident inspector identified ;
the unresoled item associated with the failure to establish adeq Jate goals
- and monitorina requirements,ihe licensee's expert panel reclassitied the
! control room complex smoke. removal system from a risk-significant
l emergency systern to a nenrisk-significant normal (nonemergency) system.
'
Therefore, the sys;em was categorized as (a)(1) for the perit,d July 10
! through September 20,1996, without the performance goals and monitoring
. --- -
. . _ _ . ___ _. - .- ___. - .-
-- - - . . - - - - - - - . - _ _ _ - - - - - . - - - .-- .
'.-
6
l -9-
4
1
.
requirements required by 10 CFR 50.65(a)(1). Additionally, the performance
! monitoring criteria required by 10 CFR 50.65(a)(2) was not provided for the
- period September 20 through October 25,1996.
2'
The inspectors learned, from the meeting minutes, that the licensee was
considering an option to abandon in-place the control room complex smoke
,
exhaust system and rely on the control room emergency ventilation system
j for smoke removal. The inspectors did not identify smoke removal
capabilities as part of the design features of the control room emergency
, ventilation system during a review of the Updated Safety Analysis Report.
s
1
4
The inspectors found that the failure to set goals and monitoring
requirements for the control room complex smoke exhaust system prior to
'
July 10,1996, was an apparent violation of 10 CFR 50.65(a)(1)
(50-361/9614-01:50-362/9614-01). Additionally, the inspectors found that
i
the failure to provide performance criteria for the control room complex
smoke exhaust system after reclassifying the system as low risk-significant
].
was a violation of 10 CFR 50.65(a)(2)(50-361/9614-02:50-362/9614-02).
i
b.8 Units 2 and 3 Main Steam Safety Relief Valves
- The inspectors observed that the licensee's July 10 and August 19,1996,
- Maintenance Rule Monthly Status Reports identified that the Unit 3 main
] steam safety relief valves had not met their reliability performance criteria
l due to repetitive functional failures. The monthly status reports did not
,
indicate any failures of the Unit 2 main steam safety relief valves for the past
,
12 quarters.
- The inspectors noted that, on July 3,1996, the licensee initiated Action
- Request 960700160,which indicated a total of five functional failures had
occurred on both units over the past 3 years. The failures were all
- characterized as failing to lift within the Technical Specification required
setpoint range. The action request was initiated to determine the cause of
the f ailures and identify appropriate corrective action. l
l
The inspectors noted that, on July 18,1996, the initial Maintenance Rule
i evaluation was closed. This evaluation indicated that the combination of
i expanding the Technical Specification allowed setpoint deviation, and
overhauling or replacing affected valves was considered to be adequate
- corrective action. The inspectors noted that no performance goals or
- monitoring requirements were established. ;
,
l The inspectors noted that, on August 28,1996, the licensee initiated
!
.
another Maintenance Rule evaluation, which was completed on
] September 18,1996. The inspectors observed that the licensee established
} a " goal" to re-achieve the performance criterion for functional failures.
I
'
, . - - . . , ,-- - ._ _
..- .-- - .
.
.
-10-
Additionally, the licensee established a performance threshold (goal) of
zero failures for both units' valves daring the next two refueling outages.
The inspectors found that the failure to set goals and monitoring
requirements for the main steam safety relief valves prior to July 10,1996,
was an apparent violation of 10 CFR 50.65(a)(1)(50-361/9614-01;
50-362/9614-01). The inspectors also found that the licensee established
the required performance goals and monitoring requirements on
September 25,1996.
b.9 Unit 2 Core Protection Calculator / Control Element Assembly Calculator.
Channel A
On July 2,1996, the licensee determined that the Unit 2 Core Protection
Calculator / Control Element Assembly Calculator, Channel A, failed to meet
its performance criteria of less than five functional failures in 36 months and
an availability of 98 percent. The licensee considered the channel to be in
goal setting in accordance with 10 CFR 50.65(a)(1) and initiated Action
Request 960700066to determine the cause of the channel not meeting its
availability performance criterion, develop appropriate corrective action to
return it to an acceptable performance level, to establish a period over which
the performance would be returned to an acceptable level, and to establish l
what monitoring would be done to assure satisf actory recovery.
The inspectors noted that the failure to meet the performance criteria was
due to the intermittent f ailure of one component on a circuit board. The !
intermittent problem was seen by the software as a channel trip which was 1
not recoverable by the software. As a result of the intermittent f ailures, the
required maintenance activities caused the availability to drop to
97.4 percent for the 36 months. The inspectors noted that the licensee
identified the failing circuit board and replaced it on April 2,1996.
l
On August 12,1996, the licensee completed a Maintenance Rule evaluation
which concluded that the channel had "not had intermittent failures [since
April 1996) . . . The performance of the channel has been improved. l
Availability goal > 99% is expected by January,1997."
On September 20,1996, after the resident inspector identified the ,
unresolved item associated with the f ailure to establish adequate l
performance goals and monitoring requirements, the licensee initiated, and
completed, another Maintenance Rule evaluation for this system. The
inspectors noted that the licensee established a goal to meet or exceed the
performance criterion. To meet that goal, the licensee documented that the
Unit 2 Core Protection Calculator / Control Element Assembly Calculator,
Channel A, would not experience any failures, of the type previously
._. _. .
- .
.
-11-
experienced, in the next 24 months. Attaining that goal would result in less
than 5 functional failures and an availability of greater than 98 pe. cent.
The inspectors found that the failure to set goals and monitorir.g l
requirements for the Unit 2 Core Protection Calculator /Contro' Element
.
Assembly Calculator, Channel A, prior to July 10,1996, was an apparent
violation of 10 CFR 50.65(a)(1) (50-361/9614-01:50-362/9614-01). The
inspectors also found that the licensee established the required performance
, goals and monitoring requirements on September 20,1996.
b.10 Unit 2 Core Protection Calculator. Channel D
On June 28,1996, the licensee determined that the Unit 2 Core Protection
Calculator, Channel D, failed to meet its availability performance criterion of
98 percent. The licensee considered the channei to be in goal setting in
accordance with 10 CFR 50.65(a)(1) and initiated Action
Request 960601359to determine the cause cf the channel not meeting its
availability performance criterion, develop appropriate corrective action to
return it to an acceptable performance leve', to establish a period over which
the performance would be returned to an r.cceptable level, and to establish
what monitoring will be done to assure sotisfactory recovery.
The inspectors noted that the failure tr. meet the availability performance
criterion was due to a temperature inreut from a reactor coolant cold leg that
had spiked low. The licensee traced the problem to a resistance temperature
detector that had moisture in the termination head causing low resistance
readings. The inspectors noted that the licensee took actions to correct the
moisture problem.
On July 1,1996, the licensee '.:ompleted a Maintenance Rule evaluation that
concluded that the investigat!on required the channel to be in bypass for a
period of time, effecting the availability of the channel. ' The inspectors noted
that the licensee concluder; that the availability goal was expected to be met
by January 1997. .
On September 16,1993, after the resident inspector identified the
unresolved item assoc.ated with the failure to establish adequate
performance goals ar,d monitoring requirements, the licensee initiated, and
completed, another Maintenance Rule evaluation for this system. The
inspectors noted that the licensee established a goal to meet or exceed the
performance criterion. To meet that goal, the licensee documented that the
Unit 2 Core Prot' action Calculator, Channel D, would not experience any
primary coolant resistance temperature detector failures due to a
low-resistance ground in the termination head for 1 year following the ninth
operating cycle.
' -
- - _ _ ._ _ ._. -- . _ . _ . _ .- - _ _ _.
'.
'.
t
- 12-
The inspectors found that the failure to set goals and monitoring ;
requirements for the Unit 2 Core Protection calculator, Channel D, prior to
July 10,1996, was an apparent violation of 10 CFR 50.65(a)(1)
(50-361/9614-01:50-362/9614-01). The inspectors also found that the
licensee established the required performance goals and monitoring
requirements on September 16,1996.
b.11 Unit 2 Excore Nuclear Instrumentation Loa Power, Channel D
! On June 28,1996, the licensee identified that the Unit 2 Excore Nuclear
Instrumentation Log Power, Channel D, exceeded its performance criteria as !
a result of experiencing seven random functional failures, six repeat l
functional failures, and an availability of 86.2 percent. The licensee j
l considered the channel to be in goal setting in accordance with j
10 CFR 50.65(a)(1) and initiated Action Request 960601337to develop a
l plan to correct the problems with the excore channel, to develop "a
monitoring program (i.e., with documentation) that will demonstrate that
performance is improving over some appropriate time period," to develop a
plan to return the channel to an acceptable performance level, and to
l establish a period over which the performance would be returned to an
l acceptable level.
On September 17,1996, the licensee initiated and completed a Maintenance
Rule evaluation. The licensee documented that the cause of the failures was
most likely the failure of the first-stage amplifier due to a high-energy
transient in the circuit. The inspectors noted that the licensee had
established a goal of no failures of sub-channel linear-gain circuit cards, in
either unit, due to high energy transients over a 12-month period beginning
July 1996. The inspectors considered this " goal" to be ineffective because
there were no means for detecting whether or not the circuit cards had
experienced any high energy transients.
The inspectors found that the f ailure to set goals and monitoring
requirements for the Unit 2 Excore Nuclear Instrumentation Log Power,
Channel D, prior to July 10,1996, was an apparent violation of
t
10 CFR 50.65(a)(1)(50-561/9614 01:50-362/9614-01).
l b.12 Unit 3 Excore Nuclear Instrumentation, Channel A
- On June 28,1996, the licensee identified that Unit 3 Excore Nuclear
4
Instrumentation, Channel A did not meet its availability criterion due
to a detector failure. The licensee considered the char.nel to be in goal
'
setting in accordance with 10 CFR 50.65(a)(1) and initiated Action
Request 960601338to determine the cause of poor performance, develop
necessary corrective actions, and determine the length of an improvement
period.
<
. . - -
_ __
l
-13-
rhe inspectors noted that the root cause was a gas leak into the detector
through the electrical insulator of the mineral-insulated cables. The licenne
took corrective actions to stabilize the detector output and implemehr #
enhanced monitoring. The licensee intended to replace the detector during
- the ninth refueling outage. The inspectors also noted that, on August 15,
1996, the licensee established a goal of zero failures due to the identified
cause of the detector failure for a fuel cycle, or about 20 months.
The inspectors found that the failure to set goals and monitoring
requirements for the Unit 3 Excore Nuclear Instrumentation, Channel A prior
to July 10,1996, was an apparent violation of 10 CFR 50.65(a)(1)
(50-361/9614-01:50-362/9614-01). The inspectors also found that the
licensee established the required performance goals and monitoring
requirements on August 15,1996.
b.13 Unit 3 Containment Purae Isolation Sianal Radiation Monitor. Channel B
On June 28,1996, the licensee determined that the Channel B monitor for
the Unit 3 Containment Purge Isolation Signal was not meeting the
availability performance criterion of 96 percent. The licensee considered the
monitor to be in goal setting in accordance with 10 CFR 50.65(a)(1) and
initiated Action Request 960601351 to determine the cause of the channel
not meeting its availability performance criterion, develop appropriate
corrective action to return it to an acceptable performance level, to establish
a period over which the performance would be returned to an acceptable
level, and to establish what monitoring would be done to assure satisfactory
recovery.
On October 18,1996, the licensee's Maintenance Rule Program Expert Panel
reached a conclusion that the monitors were no longer risk significant on the
basis of not being included in the probabilistic risk assessment model and not
being considered a source of elevated risk for core damage or a large
radiological release. Upon changing the risk-significance classification to
nonrisk-significant, the monitor was placed in 10 CFR 50.65 Category (a)(2).
. The inspectors noted that the licensee gave the Reliability Engineering Group
30 days to review the applicability of plant level performance criteria or to
provide performance criteria capable of verifying the effectiveness of the
preventive maintenance for the components.
The inspectors found that the licensee's failure to set gtals and monitoring
requirements for the Unit 3 Containment Purge Isolation Signal Radiation
Monitor, Channel B, prior to July 10,1996, was an apparent violation of
10 CFR 50.65(a)(1)(50-361/9614-01:50-362/9614-01). Additionally, the
inspectors found that sufficient information was not available to evaluate the
licensee's actions with respect to establishing performance criteria for the
-- . - . - _.- - ._. - - - . . .- - . - .. - .. - - - - - . _ - - . . - .
t
l
't
.
I
! l
-14-
l
4 i
.
Containment Purge Isolation Signal Radiation Monitors; therefore, this is an
j inspection followup item (50-361/9614-03:50-362/9614-03). I
b.14_ Unit 3 Fuel Handlina Buildina isolation Sional Radiation Monitor, ;
'
Trains A'and B
On July 11,1996, the licensee determined that the Unit 3 Fuel Handling
Building Isolation Signal Radiation Monitor, Trains A and B, did not meet the
availability performance criterion of 97 percent for both monitors._ The
licensee considered the monitors to be in goal setting in accordance with
10 CFR 50.65(a)(1) and initiated Action Request 960700430to determine
the reason for the failure to meet the criterion, and initiate corrective action.
The Maintenance Rule evaluation initiated by the corrective action program
stated that goals were established. However, the inspectors did not identify
any specific performance goals or monitoring requirements documented in
the action request, evaluation, or in the licensee's Maintenance Rule
equipment data base. On October 18,1996, the licensee's Maintenance
Rule Program Expert Panel reached a conclusion that the monitors would be
classified as nonrisk-significant except during movement of irradiated fuel in
the fuel building. The inspectors noted, or. the basis of the minutes of a
meeting of the expert panel on October 18,1996, that the panel's
conclusion was reached on the basis that the monitors were not included in
the probabilistic risk assessment model and not considered a source of
elevated risk for core damage or a large radiological release.
Upon changing the risk-significance classification to nonrisk-significant, the
monitors were placed in 10 CFR 50.65 category (a)(2). The inspectors noted
that the licensee maintained an availability monitoring criteria that would
apply only during those times that the monitors were required to be operable
to support fuel movement.
The inspectors found that the failure to set goals and monitoring
requirements for the Unit 3 Fuel Handling Building isolation Signal Radiation
Monitor, Trains A and B, prior to July 10,1996, was an apparent violation of
10 CFR 50.65(a)(1) (50-361/9614-01:50-362/9614-01).
b.15 Common Control Room Comolex Isolation Sianal Radiation Monitor.
Channel B
On June 28,1996, the licensee determined that the Common Control Room
Complex Isolation Signal Radiation Monitor, Channel B was not meeting the
availability performance criterion of 97 percent. The licensee considered the
monitor to be in goal setting in accordance with 10 CFR 50.65(a)(1) and
initiated Action Request 960601352on July 1,1996, to determine the
cause of the channel not meeting its availability performance criterion,
, - -. . - - . - = - . . _ . - - . .
l
-15-
develop appropriate corrective action to return it to an acceptable
performance level, to establish a period over which the performance would
be returned to an acceptable level, and to establish what monitoring would
i
'
be done to assure satisfactory recovery. However, the inspectors noted that
the evaluation for failure to meet the performance criterion was not
performed.
The inspectors noted that, on August 16,1996, the expert panel decided to
lower the availability performance criterion to 93 percent. The licensee's
expert panel made this change on the basis of revised surveillance
requirements and the allowance of appropriate margin for maintenance
activities. However, no performance goals or monitonng requirements were
established.
On October 18,1996, the licensee's Maintenance Rule Program Expert Panel
reached a conclusion that the monitor was no longer risk significant because
it was not included in the probabilistic risk assessment model and not
considered a source of elevated risk for core damage or a large radiological '
release. Upon changing the risk-significance classification to nonrisk-
significant, the monitor was placed in 10 CFR 50.65 Category (a)(2). The
inspectora found that insufficient information was available to evaluate the
licensee's actions with respect to establishing performance criteria for the ,
'
Common Control Room Complex Isolation Signal Radiation Monitor Channel
l B because the expert panel allowed the reliability engineers 30 days to
determine if plant level performance criteria were appropriate. Therefore,
this was identified as an inspection followup item (50-361/9614-03;
50-361/9614-03).
The inspectors found that the f ailure to set goals and monitoring
requirements for the Common Control Room Complex isolation Signal
Radiation Monitor, Channel B, prior to July 10,1996, was an apparent
l violation of 10 CFR 50.65(a)(1)(50-361/9614 01:50-362/9614-01).
i
l
c. Conclusions
l
The f ailure to set performance goals and monitoring requirements for 13 structures,
systems, or components that exhibited performance at levels less than the
established performance criteria is an apparent violation of 10 CFR 50.65(a)(1)
l (50-361/9614-01:50-362/9614-01). The failure to establish performance criteria
for the common control room complex smoke exhaust system is an apparent j
violation of 10 CFR 50.65(a)(2)(50-361/9614-02:50-362/9614-02). The !
evaluation of the licensee's actions for evaluating the applicability of plant level
- criteria for the common control room complex isolation system and the containment
purge isolation system is an inspection followup item (50-361/9614-03:50-
362/9614-03).
.
,
_ _ _.
'
o
.
-16-
M1.2 Reliability Monitorina
a. Inspection Scope
The inspectors used 10 CFR 50.65, " Requirements for Monitoring the Effectiveness
of Maintenance at Nuclear Power Plants"; Regulatory Guide 1.160, " Monitoring the
Effectiveness of Maintenance at Nuclear Power Plants," Revision 1;
NUMARC 93-01, " Industry Guideline for Monitoring the Effectiveness of
Maintenance at Nuclear Power Plants"; SO123-XV-5.3," Maintenance Rule Program
implementation," Revision 0, TCN 0-3; and, SO123-XIV-5.3.2, " Determination of
Maintenance Rule Performance Criteria," Revision 0, to review the performance
criteria that the licensee had established for monitoring structures, systems, and
components,
b. Observations and Findinas
implementation of 10 CFR 50.65 using the guidance contained in NUMARC 93-01
required that safety be taken into account when setting performance criteria and
monitoring under 10 CFR 50.65(a)(2). This safety consideration would then be
used to determine if the structures, systems, and components should be monitored
at the train or plant level.
In addition to determining which structures, systems, and components were within
the scope of 10 CFR 50.65, the licensee's expert panel established the
risk-significance ranking, performance criteria, and goals. The panel also assigned
the structures, systems, and components into categories in accordance with
10 CFR 50.65(a)(1), and (a)(2).
To meet the requirements of 10 CFR 50.65, Section 9.3.2 of NUMARC 93-01
recommended that risk-significant structure, system, and component performance
criteria be set to assure that the availability and reliability assumptions used in the
risk-determining analysis (probabilistic risk assessment) were maintained. The
licensee selected performance criteria, percent availability for risk-significant
functions, that reflected previous successful performance. A performance criterion
for reliability of two functional f ailures in two fuel cycles was selected for most risk-
significant functions, j
The licensee had not performed any studies or analyses that demonstrated the
performance criteria used for reliability preserved the assumptions used in the
probabilistic risk assessment. The inspectors noted that there was no relationship
established between the criteria and any failure probability assumptions in the i
probabilistic risk assessment since the number of function demands or operating j
times were not tracked. Thus, widely different actual function reliability estimates ;
(probability of failure upon demand to start, or, af ter starting, f ailure to run) could i
result from the same number of functional f ailures in a given time period if the
I
-17-
,
t
l
l
number of demands or required run times were different. This is an apparent i
d
v;olation of 10 CFR 50.65(a)(2)(50-361/9614-04:50-362/9614-04).
c. Conclusions
The licensee failed tc demonstrate that their use of a standard performance criteria
of two functional failures over two fuel cycles for reliability preserved the
assumptions of the probabilistic risk assessment. This is an apparent violation of
10 CFR 50.65 (50-361/9614-04:50-362/9614-04).
M7 Quality Assurance in Maintenance Activities (92902 and 62706)
a. Inspection Scope
The inspectors reviewed Action Request 960901036," Maintenance Rule and l
tr.plementation of Goal Setting Evaluations," dated October 30,1996 This action I
request was written by the Nuclear Oversight Division and included as an
attachment to the October 31,1996, letter.
!
b. Observations and Findinas *-
The inspectors noted, during review of Action Request 960901036," Maintenance ;
Rule and Implementation of Goal Setting Evaluations," dated October 30,1996, I
that the licensee's Nuclear Oversight Division concluded that, as the result of
ineffective project management and management oversight, goals were not fully
documented. The inspectors noted that the assessment included contributing
factors for the lack of documentation. One factor was that management redirected
the efforts of the members of the project team. Another was that management
replaced members of the project team and did not include key organizations.
Another was that management did not empower the project team to ensure the
project schedule was met. A fourth was that management was not effective in
communicating with the project team, therefore, management was not aware of the
significance of the scheduling and implementation delays in a timaly manner.
The team found that the ineffectiveness of management oversight contributed to
the failure to adequately establish performance goals and monitoring for those
structures, systems, and components whose performance was less than the criteria
set by the licensee.
Additionally, the inspectors found that, while adequate performance goals and
monitoring were not estab?ished, the licensee did not document those goals that
had been established. Also, the assessment did not address the concerns, as
discussed above, that adaquate goals and monitoring requirements were not
established prior to July 10,1996, as required by 10 CFR 50.65.
i
]
,
I
- '
-18-
c. Conclusions
The inspectors found that the assessment completed by the Nuclear Oversight
Division was in-depth and probing. The assessment was focused on the failure to
document goals. The assessment, however, did not address the fundamental
concern that adequate goals and monitoring requirements were not established prio,
to July 10,1996.
M8 Miscellaneous Maintenance issues (92902)
M8.1 (Closed) Unresolved item 50-361/9609-03:50-362/9609-03: failure to establish
performance goals and monitoring requirements for structures, systems, and
components in acr. olance with 10 CFR 50.65. This item identified approximately
15 structures, syuems, or components that apparently failed to meet the
established performance criteria and the licensee had not established any monitoring
goals on July 10,1996.
l
This report documents the inspection effort to address the unresolved item. The '
specifics are discussed above. The unresolved item is closed.
M8.2 (Closed) Violation 50-361/9501-05: selection of improper maximum interpass
temperatures. The inspectors verified the corrective actions described in the
licensee's response letter, dated May 22,1995, to be reasonable and complete. No
similar problems were identified.
M8.3 In-Office Review of Licensee Submittal
a. Insoection Scope
The inspectors reviewed a docketed letter, and attachments, that Mr. G. T. Gibson,
Manager, Compliance, sent to Mr. Kenneth E. Brockman, Acting Director, Division
of Reactor Safety, Region IV, on October 31,1996.
b. Observations and Findinas
The licensee stated that " Edison believes goals (performance criteria) had been
established and corrective actions were implemented to meet those goals." The
inspectors noted that, while the statements quoted from NUMARC 93-01 were
accurate, the licensee took the quote out of context. The inspectors noted that
Section 2 also stated that a major element in the guidance "[gloal setting and
monitoring of applicable SSCs [ structures, systems, and components] to ensure
plant and system functions are reliably maintained and to demonstrate the
effectiveness of maintenance activities."
The licensee included quotes from Section 9.3.2 of NUMARC 93-01, which did not
apply directly to the concerns related to goals and monitoring requirements.
1
._. __ __ -___ __ _ _ _ _ . _ _ _
- i
'
,
!
- 19- !
Section 9.3.2 is the guidance for establishing performance criteria. Section 9.4 and
its subsections are for goal setting and monitoring.
In the discussion of Sect:on 9.4 and its subsections, the licensee correctly points !
out that "[w] hen selecting a goal, the data should be collected over a sufficient
length of time to minimize the effects of a random event." Subsection 9.4.3
provides additional guidelines for establishing a monitoring period. Additionally,
Sections 6.4.4 and 6.4.6 of Procedure SO123-XIV-5.3.6 provided guidance for ,
establishing a time period for monitoring. The inspectors found that the licensee '
failed to establish a time period in accordance with NUMARC 93-01, Section 9.4.3, l
and Procedure SO123-XIV-5.3.6, Sections 6.4.4 and 6.4.5, to monitor performance ;
in order to ascertain that the corrective actions were effective and to demonstrate
that performance had returned to acceptable levels.
The inspectors found that, while performance criteria had been established, the
licensee provided no objective evidence that goals and monitoring requirements had
been established, or documented, in accordance with 10 CFR 50.65,
NUMARC 93-01, or plant procedures. ;
The inspectors also noted in the review of the October 31,1996, letter and i
attachments, that the licensee discussed Section 13.3 of NUMARC 93-01. The
licensee correctly points out the guidance that states " goals . . . should be
documented." The October 31,1996, letter also stated that responsible managers
approved the deviation from the guidance to allow additional time to prepare a
" thorough product." Also considered in the manager's approval (as indicated in
their letter) to deviate from the guidance was the belief that the goals were
documented in the State of the System Reports. The inspectors reviewed the I
second quarter 1996 report, but did not identify any documented goals.
i
According to the licensee representative, system performance would be given a
grade commensurate with the performance. The licensee representative then stated
that performance at a grade level of "C" or lower would indicate unacceptable
performance. The inspectors noted that the system, structure, or component would
then be considered for monitoring in accordance with 10 CFR 50.65(a)(1). The
licensee representative also stated that the grade assigned to a structure, system, I
or component provided the goal (s). That is, the inspectors understood, the licensee
considered a grade of "C" or less to require goals and that the goals were to
re-establish performance to attain the previously established performance criteria.
The licensee, in the October 31,1996, letter and attachments, also referrSd to
discussions about four systems potentially being considered as standby systems.
While the inspectors considered that the systems (identified in Sections M1.1.b.7,
I
!
-20-
13,14, and 15) may be standby systems, this consideration was not essential to
this inspection.
The inspectors found that the Maintenance Rule Expert Panel appropriately
dispositioned the Fuel Handling Building isolation System. However, the
documented Maintenance Rule Expert Panel decision only stated that the Control
Room Smoke Exhaust System would be monitored at the plant level, without
providing any criteria. The inspectors found that performance' criteria had not been
established for the Control Room Smoke Exhaust System. The licensee
representative stated, to the inspectors, that appropriate plant level monitoring
criteria were being considered for the two remaining subject systems. Additionally,
the Maintenance Rule Expert Panel allowed 30 days to evaluate the appropriateness
of the plant level criteria to measure the efdectiveness of maintenance on the
systems.
The inspectors noted that the licensee's position was that reliability was being
measured in accordance with industry standards. By this, the inspectors noted that
the licensee was measuring reliability on a functional failure per time period,
regardless of the requirement for the system, structure, or component to function.
The licensee also referenced a September 30,1996, letter from the Nuclear Energy
Institute to Mr. F. J. Miraglia, Acting Director, Office of Nuclear Reactor Regulation,
on this topic. On October 22,1996, Mr. Miraglia responded to the September 30
letter. In his response, Mr. Miraglia restated the NRC's position on measuring
reliability. This position is, for normally operating systems or components,
" reliability is the complement of the ratio of the expected number of failures to a
given time of required performance. The ratio of functional failures to a specified
number of operating hours could be shown to describe a reliability level that could
be related to the plant-specific PRA/IPE/IPEEt Probabilistic Risk
Assessment / individual Plant Examination / Individual Plant Examination for External
Events) or other risk-determining analysis." For standby systems, " reliability is the
complement of the ratio of the expected number of failures to a given number of
start demands and, once started, run demands." The inspectors found that the
NRC's position has remained constant; therefore, the licensee was not measuring
reliability properly.
'
c. Conclusions
The licensee's October 31,1996, letter did not provide sufficient information to
demonstrate the position that no violations had occurred. The conclusions
documented previously in this report were still valid.
!
!
l
l
. . -- . . .
-21-
i
lli. Enoineerino
l
E2 Engineering Support of Facilities and Equipment l
l
E2.3 Review of Uodated Safety Analysis Report :
1
A recent discovery of a licensee operating their facility in a manner contrary to the )
Updated Safety Analysis Report description highlighted the need for a special '
i focused review that compares plant practices, procedures, and/or parameters to the
Updated Safety Analysis Report descriptions. While performing the inspections
discussed in this report, the inspectors reviewed the portions of the Updated Safety i
Analysis Report that related to the radiation monitoring isolation signals for the Unit l
3 fuel handling building, the Unit 3 containment purge system, and the common
control room ccn.piex isolation system. The inspectors verified that the Updated
Safety Analysis Report wording was consistent with the observed plant practices, ,
procedures, and/or parameters.
V. Manaaement Meetinas
,
X1 Exit Meeting Summary !
!
,
The inspector presented the inspection results to members of licensee management at the <
- conclusion of the inspection on November 15,1996. The licensee acknowledged the
findings presented. The licensee representatives expressed a position on the inspection
findings. In specific, the licensee representatives stated that they agreed that goals had
not been documented, but they did not agree that they were in violation of any
requirements of 10 CFR 50.65(a)(1) or (a)(2). '
The inspectors asked the licensee whether any materials examined during the inspection
should be considered proprietary. No proprietary information was identified.
1
- I
,
.
i
l
ATTACHMENT f
i
SUPPLEMENTAL INFORMATION l
l
.
'
PARTIAL LIST OF PERSONS CONTACTED
Licensee
D. Breig, Manager, Station Technical
S. Chien, Engineer
R. Clark, Manager, Quality Engineering and Fuels
J. Fee, Manager, Maintenance
K. Franklin, Compliance Engineer
S. Genschaw, Manager, Support Programs
G. Gibson, Manager, Compliance
T. Hook, Supervisor, Nuclear Safety Group
D. Irvine, Manager, Technical Support
R. Kaplan, Compliance Engineer
R. Krieger, Vice President, Nuclear Generation
D. Nunn, Vice President, Engineering and Technical Services
G. Plumlee, Supervisor, Licensing
M. Rodin, Supervisor, Reliability Engineering
R. Sandstrom, Manager, Training
M. Short, Manager, Site Technical
R. Waldo, Manager, Operations
L. Wright, Supervisor, Performance Monitoring and Reliability Engineering
NRC
T. Bergman, Operations Engineer, Quality Assurance and Maintenance Branch
J. Kramer, Resident inspector, Palo Verde Nuclear Generating Station
J. Russell, Resident Inspector, San Onofre Nuclear Generating Station
D. Solorio, Resident inspector, San Onofre Nuclear Generating Station
LIST OF INSPECTION PROCEDURES USED
IP 62706 Maintenance Rule ,
IP 92902 Followup - Maintenance !
LIST OF ITEMS OPENED AND CLOSED
Opened
50-361/9614-01 APV Apparent violation of 10 CFR 50.65(a)(1) for f ailure to
establish and document goals and monitoring requirements for
13 structures, systems, or, or components was opened
(Section M1.1c).
- .- _ -. . . - . . .
t
l
1
2-
50-362/9614-01 APV Apparent violation of 10 CFR 50.65(a)(1) for failure to
establish and document goals and monitoring requirements for
13 structures, systems, or components was opened (Section
M 1.1 c).
{
'
50-361/9614-02 APV Apparert violation of 10 CFR 50.65(a)(2) for failure to
establish performance criteria for four structures, systems, or
components was opened (Section M1.1c).
. 50-362/9614-02 APV Apparent violation of 10 CFR 50.65(a)(2) for failure to
establish performance criteria for four structures, systems, or
components was opened (Section M1.1c).
'
50-361/9614-03 APV Inspection Followup item for evaluation of licensee actions to
determine applicability of plant level monitoring criteria for two
systems.
1 50-362/9614-03 APV inspection Followup Item for evaluation of licensee actions to i
determine applicability of plant level monitoring criteria for two
systems.
I
50-361/9614-04 APV Apparent violation of 10 CFR 50.65(a)(2) for failure to
- demonstrate that the use of standard performance criteria
preserved the reliability of the assumptions of the probabilistic
risk assessment was opened (Section M1.2).
50-362/9614-04 APV Apparent violation of 10 CFR 50.65(a)(2) for failure to
demonstrate that the use of standard performance criteria
preserved the reliability of the assumptions of the probabilistic
risk assessment was opened (Section M1.2).
1
Closed 1
l
50-361/9609-03 URI Failure to Establish Monitoring Goals in Accordance With l
10 CFR 50.65(a)(1)(Section M8.1). {
50-362/9609-03 URI Failure to Establish Monitoring Goals in Accordance With
10 CFR 50.65(a)(1)(Section M8.1).
I
50-361/9501-05 VIO Improper Selection of Maximum interpass Temperatures
'
(Section M8.2). l
!
. . . - - . -. . _ . - _ - - , _ - - . - - ~ . _ - - - . . . - - - . - .. . . _ - . . . - _ ,
a
4
4
3-
LIST OF DOCUMENTS REV EWED
PROCEDUPr.C
PROCEDURE NO. TITLE REVISION NUMBER
.
SO123-XV-5.3 Maintenance Rule Program implementation Revision 0, TCN 0-3
SO123-XIV-5.3.1 Scoping for the Maintenance Rule Revision 0, TCN 0-1
,
SO123-XIV-5.3.2 Determination of Maintenance Rule Revision 0
Performance Criteria
'
SO 123-XIV-5.3.4 Maintenance Rule Expert Panel Revision O
,
'
,
SO123-XIV-5.3.5 Maintenance Rule Risk-Significant SSCs Revision O
SO123-XIV-5.3.6 Goal Setting for the Maintenance Rule Revision 0, TCN 0-1
SO123-XIV-5.3.7 Maintenance Rule Periodic Assessment Revision 0
'
.
ACTION REQUESTS
'
ACTION REQUEST NO. SUBJECT
960700894 Unit 1 Fire Pump Failed Availability Performance Criteria
960700895 Fire Protection Water System in the Unit 3 Salt Water
Pump Room Failed to Meet Availability Performance
Criteria
960601337 Unit 2 Excore Channels B and D Failed to Meet
Performance Criteria
960700871 Unit 3 Safety injection Tank No. 2 Failed to Meet
Performance Criteria
960700430 Unit 3 Radiation Monitors FHIS A & B Failed to Mecc
Performance Criteria
960700066 Unit 2 CPC/CEAC Channel A Failed to Meet Performance
Criteria
960601362 Fire Pump SA2301MP222 Failed to Meet Availability
i
Performance Criteria
960601359 Unit 2 CPC Channel D Failed to meet Availability
Performance Criteria
._. _
_ . _ _ _ _
__
'
-
!
_4
OTHER DOCUMENTS
Technical Specification 3.3.8, Containment Purge isolation Signal
Technical Specification 3.3.9, Control Room isolation Signal
Technical Specification 3.3.10, Fuel Handling isolation Signal l
l
Updated Final Safety Analysis Report Sections 9.2.4,11.1,11.5,15.7 j
!
l
l
I
1
I
1
l
.
ENCLOSURE 2
ENFORCEMENT GUIDANCE MEMORANDUM
INTERIM GUIDANCE FOR 10 CFR 50.65
THE MAINTENANCE RULE
l
l
i
i
!
-- - . .
'
.
arcg
.,.- f*.
- [ W .j UNITED STATES
NUCLEAR REGULATORY COMMISSION
g WASHINGTON, D.C. 20559 0001
%,
/
August 21, 1996
l
t
.
i
!
! MEMORANDUM T0:
i Hubert J. Miller, Regional Administrator
Region I
!
Stewart D. Ebneter, Regional Administrator
Region II
A. Bill Beach, Regional Administrator
Region III
L. Joe Callan, Regional Administrator
Region IV
Roy Zimerman, Associate Director for
Projects, NRR ,
Ashok C. Thadani, Associate Director for ;
'
Inspection and Technical Assessment, NRR
Elizabeth Q. Ten Eyck, Director, Division of
Fuel Cycle Safety and Safeguards, NMSS
Donald A. Cool, Director, Division of
Industrial and Medical Nuclear Safety, NMSS
John T. Greeves, Director, Division of Waste
nagement PgGS
FROM: Jo
'] f. . Vngk
h . G ay,,A trector
0 ic of Enfo nt
SUBJECT:
ENFORCEMENT GUIDANCE MEMORANDUM INTERIM GUIDANCE F
10 CFR 50.65 - THE MAINTENANCE RULE
This Enforcement Guidance Memorandum (EGM) is being issued to provide interim
enforcement guidance for evaluating issues that may be identified during
maintenance rule inspections of licensee facilities. ,
have been developed in close coordination with the Division of ReactorThe enclose
Controls and Human Factors of NRR.
The guidelines in the attachment are intended to provide guidance to the NRC
staff to facilitate consistent categorization of severity levels for failing
~
to comply with the requirements of the maintenance rule. It is important to
note that these guidelines are not currently contained in the Enforcement
Policy and are, therefore, not controlling.
applying the definition in Section IV of the Policy for:They should be used to assist in
significant regulatory concerns (for Severity Level II violations) (2)(1) instances o
significant regulatory concerns (for Severity Level III violations), or (3)
more than of minor concern (for Severity Level IV violations).
It is recognized that maintenance issues can overlap with other issues such as
quality assurance and operability. For some enforcement considerations, other
issues relative to the case may result in another enforcement approach being
taken.
In some cases, the issues can be categorized by either result or the
,
!
root cause. For example, in some instances, the root cause may be more
. -
!
"
Multiple Addressees
-2-
!
significant
hold true. than the result, whereas in other circumstances, the opposite m
In deciding whether to use the enclosed guidance or the existing
Supplement I to the Policy, the selection should normally b
provides the higher severity level and the clearer message.e whichever
The form and philosophy of the rule encourages " maximum flexibility" for
of the rule.in establishing their programs to meet the intent and requirements
licensees
Within these broad requirements, enforcement action would be
rule or whose performance demonstrates a continuing ineffe
maintenance activities.
Escalated enforcement would be appropriate where there was a failure to make
reasonable efforts to implement the requirements of the rule or where
implementation of the maintenance rule.significant degradation of SSCs
The following presents general
guidance that is more fully expanded in the examples in the attachment: l
.
A single violation would be a Severity Level IV violation
NOTE:
In considering whether to make a citation for a violation
involving a relatively isolated, low safety significant SSC,
consider the flexibility in the rule; the risk significance of the
SSC; the reasonableness of the licensee's efforts to implement the
rule, including consideration of its and industry's prior
operating experience; and the licensee's corrective action. If
the licensee has acted reasonably, a citation might not be
warranted.
.
A single violation involving a high safety significant SSC that '
causes a plant transient that would have been prevented by
effective implementation of the maintenance rule would be a
Severity Level III violation. Supplement I, Example C.9, provides !
that equipment failures caused by inadequate or improper
maintenance that substantially complicates recovery from a plant
!
transient is considered a Severity level 111 violation or problem.
Multiple examples of maintenance failures that demonstrate a
" programmatic
Level breakdown," would normally be considered a Severity
III violation. This is consistent with Supplement I,
Example C.7, which provides that a breakdown in the control of
licensed activities involving a number of violations that are
related that collectively represent a potential carelessness
toward licensed responsibilities is considered a Severity Level
til violation or problem.
Multiple examples of maintenance failures of high safety
significant SSCs that cause a plant tratisient or complicate the
recovery from a plant transient, indicate a programmai.ic breakdown
in implementation of the requirements of the rule and would be
considered a very significant regulatory concern and should be
__ .____ __ _ _ __ . . _ _ . .. _ _ . _ _ _
'
s
'
.
.
Multiple Addressees -3-
!
considered for issuance as a Severity Level II violation or
problem.
The maintenance rule does not supersede any existing requirements, such as
.
those contained in 10 CFR Part 50 (including Appendix 8 and other sections) or
a licensee's technical specifications, These requirements remain in effect
!
for ma h tenance activities. When preparing notices of violation for
maintenance activities, the maintenance rule should be used for citations
whenever a licensee has violated a specific requirement of the maintenance
rule. When a set of facts indicates that there are violations of both the
maintenance rule and another NRC regulation, cite both requirements with only
,'
one " contrary to." However, where maintenance violations are caused by
licensee activities not covered by the maintenance rule, cite against the
'
requirements of Appendix B or the plant technical specifications. Also,
i please note that the failure to perform the safety assessment provided for in !
i 10 CFR 50.65 (a)(3) requires special attention. This is addressed in Part A, '
,
Paragraph D in the attachment.
Because the maintenance rule takes a performance based approach to inspecting
licensee maintenance operations (a relatively new technique with limited
i
enforcement experience in these types of performance based inspection
activities), it is anticipated that the guidance provided in the attachment
will require modification as more inspections are completed and further
i experience is gained. It is estimated that a minimum of six months.will be
required until sufficient information can be collected. At that time, the
Office of Enforcement expects to revise the Enforcement Policy by adding
further guidance to the supplements, after consulting with the Commission.
'
Additional enforcement guidance has been provided in EGM 96-001, dated
July 3, 1996, which established a Maintenance Rule Enforcement Review Panel
'
that will meet periodically to review enforcement issues that are disclosed
during the performance of maintenance rule and other routine NRC inspections.
i This should contribute to the consistency of enforcement actions in this area.
.
l e.: J. Milhoan, DEDR
! H. Thompson, DEDS l
W. Russell, NRR
-
J. Goldberg, OGC
F. Gillespie, NRR
!
,
-. .- - -. - .-- -. .- .-
l ,
, 1
3
ATTACHMENT 1: MAINTENANCE RULE VIOLATIONS
'l
I.
Examples of Activities That Would Be Violations of the Maintenance Rule:
A. Failure to include safety related 2
f
or non-safetv related structures,
systems, and components -(SSCs) (as defined in 10 CFR 50.65 (b)(1) and
(2)) within the scope of the program.
1.
Severity Level III - violations involving, for example:
a.
Failure to include one or more SSCs, where they should i
clearly be included within the scope of the rule, that as a
result of the failure to include the SSC: 1) complicates the l
recovery from a plant transient or 2) in the case of high
safety significant SSCs, causes a plant transient )
example applies and indicates programmatic failures (if this i
involving high safety significant SSCs, then a violation at 1
Severity Level 11 should be considered).
b.
Failure to include multiple SSCs within the scope of the
rule which indicates a pro
requirements of the rule. grammatic failure to implement the
2.
Severity Level IV - violations involving, for example:
a.
Failure to include an SSC within the scope of the rule.
l
B.
Failure to establigh goals for SFCs in (a)(1) or performance criteria i
for SSCs in (a)(2) . Establishment of goals that are inconsistent with
4
'All safety related SSCs should be clearly defined in the licensee' s
quality
scope ofassurance the rule. program and should be identified and included within the
,
2
8ecause of the flexibility in the rule, special consideration needs to
be
from given
the to determine
scope of thewhether
rule. a non-safety related SSC was properly excluded
SSCs. In determining whether10 CFR 50.65
a violation (b)
occu(2) governs
rred, non-safety
consider the related
reasonableness of the licensee's actions in evaluating industry-wide and plant
experience and existing analyses (e.g. FSAR, IPE, etc.) to identify events
that would indicate that a particular non-safety related SSC should have been
included within the scope of the rule. Since licensees are not expected to
consider hypothetical scenarios, it is possible that some SSCs (with no
history of ind"stry-wide and plant experience of failures) that were excluded
from the scope of the rule, may fail and cause an event. The failure to
include such an SSC in the scope of the rule prior to the first failure of the
SSC or event would _n_gl be considered a violation. However, the licensee would
be expected to include the SSC within the scope of the rule following the
first failure of the SSC.
3
The licensee has the option under (a)(2) of the rule to demonstrate that
the performance or condition of the SSC is being effectively controlled
through the performance of appropriate preventive maintenance such that the
1
o
- ,
3 ;
-2- l
i
safety significance or industry experience, where practical, are not
considered sufficient goals to meet the rule and would also be j
violations.
'
1.
Severity Level III - violations involving, for example:
a.
A single failure to establish a goal for an SSC under (a)(1)
or a performance criterion under (a)(2) that: 1) complicates
the recovery from a plant transient or 2) in the case of
high safety significant SSCs, causes a plant transient (if
this example applies with more than one failure and
indicates programatic failures involving high safety
significant SSCs, then a violation at Severity Level II
should be considered). )
'
b.
Multiple examples of failures to establish either goals for
SSCs under (a)(1) or performance criteria under (a)(2) that
indicate a programatic failure to implement the maintenance
rule.
c. Multiple examples of the failure to take industry-wide
operating experience into account when establishing goals or
performance criteria, where industry-wide operating
experience was readily available, that indicate a '
programatic failure to meet this requirement of the rule'.
2.
Severity Level IV - violations involving, for example:
a. A single failure to establish a goal for any SSC under
(a)(1) or a performance criterion for any SSC under (a)(2).
C.
Failure to establish a monitoring program (this would include the
failure to take timely and appropriate corrective action in the
evaluation of monitoring activities) that adequately supports the goals
set under 10 CFR 50.65 (a)(1) or the performance criteria set under 10
CFR 50.65(a)(2). The monitoring program must be sufficient in scope and
,
SSC remains capable of performing its intended function. NUMARC 93-01 uses
the establishment of performance criteria to accomplish this. The licensee
also has the option of not establishing goals or performance criteria if a
l
determination is made that low safety significant SSCs are inherently reliable i
or could be allowed to run to failure. However this determination must be
made and documented in advance of the failure.
' Evidence that industry-wide operating experience was taken into
consideration is not required for every goal. However, if multiple examples
of goals and performance criteria are reviewed where industry-wide operating
experiences are readily available and examples are not found where the
licensee can demonstrate that they were taken into consideration, then the
licensee's program indicates a programatic failure.
.. . .-- -. .- _-- .-- - . . ._ -__ --
J
.
3
-3-
meeting their assigned goals or performance criteria. fr
1.
Severity Level III - violations involving, for exagle:
a.
A single failure to establish a monitoring program that
adequately supports a goal set under (a)(1) or a performance
criterion under (a)(2) that: 1) complicates the recovery
from a plant transient or 2
in the case of high safety
significant SSCs, causes a p)lant transient (if this exa
applies with more tF*n one failure and indicates
programmatic failures
involving high safety significant !
SSCs, then a violation at Severity Level II should be
considered). !
b. I
Multiple failures to establish a monitoring program that
adequately supports a goal set under (a)(1 or a performance
criterion under (a)(2) that indicate a prog)rammatic failure
to implement the requirements of the maintenance rule.
c.
A failure to establish a monitoring program that adequately
supports a goal set under (a)(1) or a performance criterion ,
under (a)(2) that results in repetitive maintenance i
preventable functional failures (MPFFs)3
2.
Severity Level IV - violations involving, for example: i
a. !
A single failure to establish a monitoring program that
adequately supports a goal set under (a)(1) or a performance
criterion under (a)(2).
D.
Failure to take timely and appropriate corrective action (this would
include evaluation of monitoring activities) when a goal
or performance criterion is exceeded. Repetitive failures due to
inappropriate or ineffective corrective action could be considered a
violation under this rule for all SSCs within the scope of this rule or
a violation of 10 CFR 50 Appendix B for safety-related SSCs.
1.
Severity Level III - violations involving, for example:
a.
A single failure to take timely and appropriate corrective
action when a goal or performance criterion for an SSC is
exceeded (failed) which 1) complicates the recovery from a
plant transient or 2) in the case of high safety significant
5
Maintenance Preventible Functional Failures (MPFFs) are defined in
NUMARC 93-01, Appendix B, as the failure of an SSC within the scope of the
Maintenance Rule to perform its intended function, where the cause of the
failure of the SSC is attributable to a maintenance-related activity. The
staff has endorsed the use of MPFFs as a tool for monitoring SSC maintenance
performance in Revision 1 of Regulatory Guide 1.160 (January 1995).
_ . . , - - . . - . _-. _ - . - - . ._ - . . . ._
J
ii
, 'I
-4-
SSCs, causes a plant tranc,ient (if this example applies and
indicates programmatic failures involving high safety
significant SSCs, then a violation at Severity Level II
should be considered).
b.
The failure to evaluate the results of monitoring activities
which results in repetitive MPFFs.
c.
Multiple failures to take timely and appropriate corrective
<
action when a goal or performance criterion is exceeded
-
(failed) that indicates a programmatic failure to implement
the requirements of the maintenance rule.
'
2.
Severity Level IV - violations involving, for example:
a.
A single failure to take timely and appropriate corrective
action when a goal or performance criterion is exceeded i
(failed).
E.
Failure to make a reasonable effort to identify and determine the cause
of MPFFs of SSCs covered under (a)(2) would be a violation.Failure to
develop a rationale or justification for continuing to cover an SSC
under (a)(2) after it has experienced a repetitive MPFF would be a
violation.
1.
Severity Level III - violations involving, for example:
a.
Multiple failures to make a reasonable effort to determine
the cause of MPFFs of SSCs covered under (a)(2).
b.
Multiple failures to develop a rationale or justification
for continuing to cover these SSCs under (a)(2) after they
have experienced a repetitive MPFFs that indicate the
programmatic failure to implement the requirements of the
rule.
2.
Severity Level IV - violations involving, for example:
a.
A sincle failure to make a reasonable effort to determine
~
the cause of a MPFF of an SSC covered under (a)(2).
b. The failure to develop a rationale or justification for
continuing to cover that SSC under (a)(2) after it has
experienced a repetitive MPFF.
F.
Failure to perform the required periodic assessment for the activities
described under (a)(3) would be a violation.
J
'
- ,
3
-5-
1.
Severity Level III - violations involving, for example:
a.
The failure to perform any required periodic assessment
w'nich indica.ted a programmatic failure to meet the
requirement of the rule.
2.
Severity Level IV - violations involving, for example:
a.
The failure to include a review of performance and
monitoring activities and associated goals and preventive
maintenance activities (i.e., all (a)(1) and (a)(2)
activities) in the periodic assessment.
b.
Completing this assessment in an untimely manner'.
c.
The failure to take industry-wide operating experience into l
~
consideration when performing the periodic assessment.
<
G.
Failure to periodically (once per refueling cycle, not to exceed 24
months between evaluations) balance reliability and unavailability due
to monitoring / maintenance activities would be a Severity Level IV
violation.
H.
A failure to develop, implement or adhere to any of the procedures
developed by a licensee to implement the rule may be a violation and
could be assessed as a violation of the licensee's technical
specifications or 10 CFR 50 Appendix B. I
1.
Severity level III - violations involving, for example:
- a.
A single failure to develop or follow procedures involving
the maintenance of an SSC that 1) complicates the recovery
from a plant transient or 2 in the case of high safety
significant SSCs, causes a p)lant transient (if this example
applies and indicates programmatic failures involving high
4
safety significant SSCs, then a violation at Severity Level
11 should be considered).
b. The failure tc develop or follow procedures that results in
repetitive MPFFs.
c. Multiple examples of failures to develop or follow
.
procedures that indicate a programmatic failure to implement
the requirements of the maintenance rule.
2. Severity Level IV - violations involving, for example:
a. A single failure to develop or follow procedures.
'At least one assessment during each refueling cycle provided the
interval between assessments does not exceed 24 months.
]
.
.
I
-6-
II.
Examples ofRule:
Maintenance Activities That Would Not Necessarily Be Violations of the l
A.
A failure to meet a licensee developed goal under (a)(1) would not
be subject to enforcement action as long as appropriate corrective
action had been taken when the goal was not met.
8.
It is intended that licensees be allowed flexibility when
establishing goals and not be subject to enforcement on goal
selection as long as these goals are reasonably based on safety
and industry operating experience. The NRC does not intend to
second guess the details of these goals. However the NRC will '
review these goals to ensure that they are reasona,bly based on
safety and industry operating experience.
C.
The details of the monitoring program would not be subject to
enforcement action as long as the monitoring was sufficient to .
!
adequately support the goals and provided for an evaluation
whenever a goal was exceeded (See example of violations C and D
above).
1
D.
Since the rule states that, in performing monitoring and i
preventive maintenance activities, an assessment of the total )
plant equipnent that is out of service should be taken into
account to determine the overall effect on performance of safety
functions, the failure to perform this assessment would not be a
violation of 10 CFR 50.65(a)(3). However, licensees are expected
to perform this assessment.
If the inspector finds that a licensee is not performing this i
i
assessment using the methods detailed in NUMARC 93-01, Section 11,
or equivalent methods, then the inspector should consider this to
be an issue that should be referred for resolution to NRC !
management and the Maintenance Rule Enforcement Review Panel, '
established by EGM 96-001.
In a case where this failure to perform a safety assessment i
contributed to the seve-ity of another violation of the
regulations, or exacerbated the consequences of an event or .
!
transient, the failure to perform a safety assessment could be
taken into account as an escalating factor in any escalated
enforcement action.
In addition,out
equipment theoffailure
servicetothat:
consider the overall impact of taking
(1) exhibits a pattern supporting a
programmatic issue, (2) causes the initiation of a plant trip or a
transient with the potential for a trip, or (3) demonstrates the
potential for a high risk system configuration is of significant
regulatory concern and should be considered for enforcement
action. Depending on the circumstances, the enforcement related
action (enforcement conference, Demand for Information, Order,
etc.) should be utilized to focus the licensee on the need to
__ __ _ . _ . - . . . . _ _ _ _ _ . . _ . _ . - - - _ _ . _ . . _ - _ . _ _ . . - _ _ . . . _ . . _ _ . . _ . . _ . _
_ -
_. _ __.-__
ha
l
- }g I
,
-7-
modify its maintenance activities because of its demonstrated I
failure to consider the overall safety impact of removing
equipment from service. l
l
I
E. Deficiencies in records and documentation would not in themselves J
be subject to enforcement. However, if they contribute to an 1
inappropriate action or inaction to correct the. performance of an
SSC, these record or documentation deficiencies may be cited as -
contributing factors in an enforcement action.
.
i
!'
i
d
i
1
i l
I l
r l
i
i
l
l
4
4
I
$
i
!
!
s
_ . . - . .